Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.INT.ENDC.07120 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (P | Restrooms | Not Started | 11/13/26 | 11/19/26 | 6.2 | 6.2 |
|
173.8 |
RPL07.INT.SSB.01900 |
RPL07.Interior.SSB - Final Finishes & Fixtures - Casework | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 11/13/26 | 11/23/26 | 8.8 | 8.8 |
|
210.0 |
RPL07.INT.SSB.06000 |
RPL07.Interior.SSB LO #16 - Close Exterior LO #16 (SSB - North of Loading Dock) WBS Summary | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 11/13/26 | 02/08/27 | 71.2 | 71.2 |
|
67.5 |
RPL07.INT.SSB.06020 |
RPL07.Interior.SSB LO #16 - IMP In Wall MEP | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 11/13/26 | 11/16/26 | 2.5 | 2.5 |
|
67.5 |
RPL07.INT.SSBC.3600 |
RPL07.Interior.SSBC LO #06 - Install Asset Tags | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 11/13/26 | 11/13/26 | 1.2 | 1.2 |
|
95.0 |
GCD.RPL07.1116 |
RPL07 EY Ready for Energization | Construction Milestones | Not Started | 11/16/26 | 11/16/26 | 0.0 | 0.0 |
|
212.5 |
GCD.RPL07.2001 |
Cx Power Available (Temp) | CX Milestones | Not Started | 11/16/26 | 11/16/26 | 0.0 | 0.0 |
|
23.8 |
GCD.RPL07.5765 |
RMU Loop Ready for Energization - DHB Loop | EY | Not Started | 11/16/26 | 11/16/26 | 0.0 | 0.0 |
|
23.8 |
ICM.B7.2530 |
[SSDCB2] L3/L4 Start EY | Commissioning | Not Started | 11/16/26 | 11/16/26 | 0.0 | 0.0 |
|
178.8 |
RPL07.CX.DHB.01000 |
RPL07.CX.DHB - L3, L4, IST - WBS Summary | DHB | Not Started | 11/16/26 | 07/09/27 | 201.2 | 201.2 |
|
153.8 |
RPL07.CX.DHB.01010 |
RPL07.CX.DHB - L3 - WBS Summary (Electrical) | DHB ELECTRICAL | Not Started | 11/16/26 | 03/19/27 | 105.0 | 105.0 |
|
73.8 |
RPL07.CX.DHB.01020 |
RPL07.CX.DHB - L3/L4 - MV Skids (10) Loop 1 | DHB ELECTRICAL | Not Started | 11/16/26 | 12/01/26 | 12.5 | 12.5 |
|
23.8 |
RPL07.EY.DHA.01300 |
RPL07.EY.DHA - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 11/16/26 | 11/20/26 | 6.2 | 6.2 |
|
181.2 |
RPL07.EY.DHA.01320 |
RPL07.EY.DHA - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 11/16/26 | 01/22/27 | 56.2 | 56.2 |
|
298.8 |
RPL07.EY.DHB.01340 |
RPL07.EY.DHB - Install Lighting | Hardscape and Landscape | Not Started | 11/16/26 | 12/01/26 | 12.5 | 12.5 |
|
181.2 |
RPL07.INT.ENDC.01250 |
RPL07.Interior.End-Corridor - Set Equipment / Interior ?? | Fit out | Not Started | 11/16/26 | 11/20/26 | 6.2 | 6.2 |
|
161.2 |
RPL07.INT.ENDC.01270 |
RPL07.Interior.End-Corridor - Install Tile | Fit out | Not Started | 11/16/26 | 11/24/26 | 8.8 | 8.8 |
|
173.8 |
RPL07.INT.ENDC.01420 |
RPL07.Interior.End-Corridor - Install Remaining Refrigerant Line | Fit out | Not Started | 11/16/26 | 11/20/26 | 6.2 | 6.2 |
|
216.2 |
RPL07.INT.SSB.14220 |
RPL07.Interior.SSB LO #01 to #05 - Fire Safing OH and In-wall | Finishes | Not Started | 11/16/26 | 11/16/26 | 1.2 | 1.2 |
|
87.5 |
RPL07.INT.SSBC.3520 |
RPL07.Interior.SSBC LO #06 - Plumbing Trim Out | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 11/16/26 | 11/17/26 | 2.5 | 2.5 |
|
93.8 |
RPL07.INT.SSBC.3620 |
RPL07.Interior.SSBC LO #06 - Install Door (Verify with Trades before installation) | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 11/16/26 | 11/16/26 | 1.2 | 1.2 |
|
95.0 |
RPL07.CON.WP2.06680 |
RPL07.Conn - GSIDF/DH D2 - Install & Test Network (FIM) | Network | Not Started | 11/17/26 | 11/19/26 | 3.8 | 3.8 |
|
350.0 |
RPL07.CX.MCUP.01070 |
RPL07.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - DHB & DHA (Phase2) | Fill and Flush | Not Started | 11/17/26 | 11/23/26 | 6.2 | 6.2 |
|
66.2 |
RPL07.EY.DHA.02080 |
RPL07.EY.DHA - Install reminder of CSUs post LO buildback (Qty1) | OFE | Not Started | 11/17/26 | 11/18/26 | 2.5 | 2.5 |
|
162.5 |
RPL07.EY.DHB.01450 |
RPL07.EY.DHB - Install Remaining Remaining Electrical Tie-ins | Tie-ins | Not Started | 11/17/26 | 11/30/26 | 10.0 | 10.0 |
|
155.0 |
RPL07.EY.DHB.01460 |
RPL07.EY.DHB - Install Remaining Mechanical/refrigerantTie-ins | Tie-ins | Not Started | 11/17/26 | 12/02/26 | 12.5 | 12.5 |
|
152.5 |
RPL07.INT.CC.9380 |
RPL07.Interior.CC Ext. LO #17 - Install Security Lowside OH and In-wall | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/17/26 | 11/18/26 | 2.5 | 2.5 |
|
93.8 |
RPL07.INT.CC.9400 |
RPL07.Interior.CC Ext. LO #17 - Install Controls / EPMS / BMS OH and In-wall | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/17/26 | 11/18/26 | 2.5 | 2.5 |
|
78.8 |
RPL07.INT.CC.9420 |
RPL07.Interior.CC Ext. LO #17 - Mechanical Tie-In | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/17/26 | 11/19/26 | 3.8 | 3.8 |
|
77.5 |
RPL07.INT.CC.9440 |
RPL07.Interior.CC Ext. LO #17 - Electrical Tie-In | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/17/26 | 11/19/26 | 3.8 | 3.8 |
|
77.5 |
RPL07.INT.CTRC.1520 |
RPL07.Interior.Center-Corridor - BoW - Install Backing at Exterior Wall | Balance of Walls & Overhead | Not Started | 11/17/26 | 11/23/26 | 6.2 | 6.2 |
|
36.2 |
RPL07.INT.DHC.01300 |
RPL07.Interior.DHC - Tie-ins - Control Fault Domain 2 - WBS Summary | Control Fault Domain 2 | Not Started | 11/17/26 | 05/13/27 | 151.2 | 151.2 |
|
71.2 |
RPL07.INT.DHC.02530 |
RPL07.Interior.DHC - Control Fault Domain 2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 11/17/26 | 11/20/26 | 5.0 | 5.0 |
|
172.5 |
RPL07.INT.DHD.01650 |
RPL07.Interior.DHD - Control Fault Domain 4 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 11/17/26 | 11/20/26 | 5.0 | 5.0 |
|
236.2 |
RPL07.INT.ENDC.01440 |
RPL07.Interior.End-Corridor - OFE - UPS Gallery (2x) | OFE/MOFE & CFCI | Not Started | 11/17/26 | 12/02/26 | 12.5 | 12.5 |
|
181.2 |
RPL07.INT.SSB.06040 |
RPL07.Interior.SSB LO #16 - QC - Backings/Walls | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 11/17/26 | 11/17/26 | 1.2 | 1.2 |
|
67.5 |
RPL07.INT.SSB.14400 |
RPL07.Interior.SSB LO #01 to #05 - Tape Finish Paint | Finishes | Not Started | 11/17/26 | 11/19/26 | 3.8 | 3.8 |
|
87.5 |
RPL07.INT.SSBC.01180 |
RPL07.Interior.SSB-Corridor - Install Fitout (GS.MDF Mech & Elec2x, Riser Room, GS Fiber Entry Room, Carrier MDF) - WBS | Fit out | Not Started | 11/17/26 | 02/24/27 | 82.5 | 82.5 |
|
115.0 |
RPL07.INT.SSBC.01210 |
RPL07.Interior.SSB-Corridor - Install Split Systems/Humidifiers | Fit out | Not Started | 11/17/26 | 11/23/26 | 6.2 | 6.2 |
|
125.0 |
RPL07.INT.SSBC.01390 |
RPL07.Interior.SSB-Corridor - Install Battery **?? | Fit out | Not Started | 11/17/26 | 12/02/26 | 12.5 | 12.5 |
|
95.0 |
RPL07.INT.SSBC.01590 |
RPL07.Interior.SSB-Corridor - Install Mechanical Tie-Ins (needs to micro plan) | Fit out | Not Started | 11/17/26 | 11/23/26 | 6.2 | 6.2 |
|
131.2 |
RPL07.INT.SSBC.3540 |
RPL07.Interior.SSBC LO #06 - Fire Life Safety Trim Out | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 11/17/26 | 11/17/26 | 1.2 | 1.2 |
|
93.8 |
RPL07.INT.SSBC.4560 |
RPL07.Interior.SSBC LO #07 - Install Remaining Lights | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/17/26 | 11/19/26 | 3.8 | 3.8 |
|
88.8 |
RPL07.INT.SSBC.4580 |
RPL07.Interior.SSBC LO #07 - Install Flooring Tiles/Resinous Flooring in specific rooms | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/17/26 | 11/19/26 | 3.8 | 3.8 |
|
91.2 |
RPL07.INT.SSBC.4720 |
RPL07.Interior.SSBC LO #07 - Fire Safing / Wall Finishes | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/17/26 | 11/18/26 | 2.5 | 2.5 |
|
87.5 |
RPL07.INT.DHA.01250 |
RPL07.Interior.DHA - Control Fault Domain 1 - Install Copper from GS.IDF to BMS and EPMS panels | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/18/26 | 12/17/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.DHB.01390 |
RPL07.Interior.DHB - Control Fault Domain 2 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/18/26 | 12/17/26 | 25.0 | 25.0 |
|
52.5 |
RPL07.INT.DHB.01400 |
RPL07.Interior.DHB - Control Fault Domain 2 - Pull EMPS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/18/26 | 12/17/26 | 25.0 | 25.0 |
|
52.5 |
RPL07.INT.DHB.01410 |
RPL07.Interior.DHB - Control Fault Domain 2 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/18/26 | 12/17/26 | 25.0 | 25.0 |
|
40.0 |
RPL07.INT.DHB.02560 |
RPL07.Interior.DHB - OFE - Control Fault Domain 3 (Mech Side Aisle) | Control Fault Domain 3 | Not Started | 11/18/26 | 12/08/26 | 16.2 | 16.2 |
|
45.0 |
RPL07.INT.DHD.01670 |
RPL07.Interior.DHD - Control Fault Domain 4 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 11/18/26 | 11/23/26 | 5.0 | 5.0 |
|
250.0 |
RPL07.INT.SSB.06060 |
RPL07.Interior.SSB LO #16 - Hang Exterior Wall Drywall | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 11/18/26 | 11/19/26 | 2.5 | 2.5 |
|
67.5 |
RPL07.INT.SSBC.3640 |
RPL07.Interior.SSBC LO #06 - Electrical L2 Checklist Completion | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 11/18/26 | 12/03/26 | 12.5 | 12.5 |
|
93.8 |
RPL07.EY.DHA.01450 |
RPL07.EY.DHA - Install Remaining Electrical Tie-ins | Tie-ins | Not Started | 11/19/26 | 12/02/26 | 10.0 | 10.0 |
|
165.0 |
RPL07.INT.CC.9500 |
RPL07.Interior.CC Ext. LO #17 - Install Electrical Lowside OH and In-wall | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/19/26 | 11/20/26 | 2.5 | 2.5 |
|
78.8 |
RPL07.INT.DHC.01350 |
RPL07.Interior.DHC - OFE - Control Fault Domain 3 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 3 | Not Started | 11/19/26 | 03/30/27 | 108.8 | 108.8 |
|
48.8 |
RPL07.INT.DHC.01370 |
RPL07.Interior.DHC - Control Fault Domain 2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 11/19/26 | 11/24/26 | 5.0 | 5.0 |
|
181.2 |
RPL07.INT.DHC.02390 |
RPL07.Interior.DHC - OFE - Control Fault Domain 3 (LV Side Aisle) | Control Fault Domain 3 | Not Started | 11/19/26 | 11/24/26 | 5.0 | 5.0 |
|
140.0 |
RPL07.INT.SSBC.4420 |
RPL07.Interior.SSBC LO #07 - Electrical Trim Out | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/19/26 | 11/20/26 | 2.5 | 2.5 |
|
87.5 |
RPL07.INT.SSBC.4440 |
RPL07.Interior.SSBC LO #07 - Security Trim Out | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/19/26 | 11/20/26 | 2.5 | 2.5 |
|
87.5 |
RPL.07.D.73340.XR |
Pull and Term MV Skids - RPL07 DHD | Receive Milestones (XREFs) | Not Started | 11/20/26 | 11/20/26 | 0.0 | 0.0 |
|
153.8 |
RPL.07.D.73840.XR |
100MW Cx Temp Power to MV Skids RPL07 DHD Available | Receive Milestones (XREFs) | Not Started | 11/20/26 | 11/20/26 | 0.0 | 0.0 |
|
153.8 |
RPL07.INT.CC.9480 |
RPL07.Interior.CC Ext. LO #17 - Fire Safing OH and In-wall | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/20/26 | 11/23/26 | 2.5 | 2.5 |
|
77.5 |
RPL07.INT.DHC.01390 |
RPL07.Interior.DHC - Control Fault Domain 2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 11/20/26 | 11/25/26 | 5.0 | 5.0 |
|
181.2 |
RPL07.INT.ENDC.07100 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Install Tile/ Grout | Restrooms | Not Started | 11/20/26 | 12/07/26 | 12.5 | 12.5 |
|
182.5 |
RPL07.INT.ENDC.07140 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Install Fixtures, Partitions & Accessories | Restrooms | Not Started | 11/20/26 | 12/02/26 | 8.8 | 8.8 |
|
173.8 |
RPL07.INT.SSB.05860 |
RPL07.Interior.SSB - BoW - BoW - Install Mechanical Piping/ Refrigerant (Lowside OH space) | Balance of Walls and OverHead | Not Started | 11/20/26 | 11/30/26 | 6.2 | 6.2 |
|
77.5 |
RPL07.INT.SSB.06080 |
RPL07.Interior.SSB LO #16 - Tape Finish Paint | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 11/20/26 | 11/30/26 | 6.2 | 6.2 |
|
67.5 |
RPL07.INT.SSB.14460 |
RPL07.Interior.SSB LO #01 to #05 - Mechanical Trim out | Finishes | Not Started | 11/20/26 | 11/30/26 | 6.2 | 6.2 |
|
102.5 |
RPL07.INT.SSB.14480 |
RPL07.Interior.SSB LO #01 to #05 - Final Paint | Finishes | Not Started | 11/20/26 | 12/02/26 | 8.8 | 8.8 |
|
127.5 |
RPL07.INT.SSB.14560 |
RPL07.Interior.SSB LO #01 to #05 - Install Remaining Lights | Finishes | Not Started | 11/20/26 | 12/07/26 | 12.5 | 12.5 |
|
87.5 |
RPL07.INT.SSB.14580 |
RPL07.Interior.SSB LO #01 to #05 - Install Flooring Tiles/Resinous Flooring in specific rooms | Finishes | Not Started | 11/20/26 | 12/02/26 | 8.8 | 8.8 |
|
108.8 |
RPL07.INT.SSB.14720 |
RPL07.Interior.SSB LO #01 to #05 - Fire Safing / Wall Finishes | Finishes | Not Started | 11/20/26 | 11/30/26 | 6.2 | 6.2 |
|
118.8 |
RPL07.INT.SSB.14740 |
RPL07.Interior.SSB LO #01 to #05 - Install Split Systems | Finishes | Not Started | 11/20/26 | 11/24/26 | 3.8 | 3.8 |
|
107.5 |
RPL07.INT.SSBC.4600 |
RPL07.Interior.SSBC LO #07 - Install Asset Tags | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/20/26 | 11/20/26 | 1.2 | 1.2 |
|
88.8 |
GCD.RPL07.5805 |
RMU Loop Ready for Energization - DHA Loop | EY | Not Started | 11/23/26 | 11/23/26 | 0.0 | 0.0 |
|
30.0 |
RPL07.CON.WP2.02000 |
RPL07.Conn - GS EF2 (North) - WBS Summary | GS.EF2 (North) | Not Started | 11/23/26 | 12/03/26 | 8.8 | 8.8 |
|
266.2 |
RPL07.CON.WP2.02200 |
RPL07.Conn - GS EF2 (North) Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 11/23/26 | 11/25/26 | 3.8 | 3.8 |
|
266.2 |
RPL07.CON.WP2.03000 |
RPL07.Conn - GS EF1 (South) - WBS Summary | GS.EF1 (South) | Not Started | 11/23/26 | 12/03/26 | 8.8 | 8.8 |
|
266.2 |
RPL07.CON.WP2.07820 |
RPL07.Conn - GS EF1 (South) Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 11/23/26 | 11/25/26 | 3.8 | 3.8 |
|
266.2 |
RPL07.EY.DHA.01330 |
RPL07.EY.DHA - Install Early EY Paving | Hardscape and Landscape | Not Started | 11/23/26 | 12/01/26 | 6.2 | 6.2 |
|
181.2 |
RPL07.EY.DHA.01460 |
RPL07.EY.DHA - Install Remaining Mechanical Tie-ins | Tie-ins | Not Started | 11/23/26 | 12/08/26 | 12.5 | 12.5 |
|
160.0 |
RPL07.EY.DHA.01520 |
RPL07.EY.DHA - Install Floor Mounted Outdoor Split AC Units (Qty 4) | OFE | Not Started | 11/23/26 | 12/04/26 | 10.0 | 10.0 |
|
137.5 |
RPL07.INT.CC.9580 |
RPL07.Interior.CC Ext. LO #17 - Install Door Frame Hardware | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/23/26 | 11/30/26 | 5.0 | 5.0 |
|
91.2 |
RPL07.INT.DHC.01440 |
RPL07.Interior.DHC - Tie-ins - Control Fault Domain 3 (including IDF) - WBS Summary | Control Fault Domain 3 | Not Started | 11/23/26 | 05/20/27 | 152.5 | 152.5 |
|
97.5 |
RPL07.INT.DHC.02550 |
RPL07.Interior.DHC - Control Fault Domain 3 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 11/23/26 | 11/30/26 | 5.0 | 5.0 |
|
187.5 |
RPL07.INT.ENDC.01280 |
RPL07.Interior.End-Corridor - Duct Drops / Trim out | Fit out | Not Started | 11/23/26 | 12/02/26 | 7.5 | 7.5 |
|
167.5 |
RPL07.INT.ENDC.01290 |
RPL07.Interior.End-Corridor - Install Battery | Fit out | Not Started | 11/23/26 | 12/08/26 | 12.5 | 12.5 |
|
161.2 |
RPL07.INT.ENDC.01590 |
RPL07.Interior.End-Corridor - Install Electrical - DHD/DHC UPS Gallery | Fit out | Not Started | 11/23/26 | 12/01/26 | 6.2 | 6.2 |
|
173.8 |
RPL07.INT.ENDC.1340 |
RPL07.Interior.End-Corridor - BoW - Install VAV's/Duct Branches | Balance of Walls & Overhead | Not Started | 11/23/26 | 12/01/26 | 6.2 | 6.2 |
|
125.0 |
RPL07.INT.ENDC.1360 |
RPL07.Interior.End-Corridor - BoW - Install Split Systems/Humidifiers | Balance of Walls & Overhead | Not Started | 11/23/26 | 12/01/26 | 6.2 | 6.2 |
|
125.0 |
RPL07.INT.SBC.03640 |
RPL07.Interior.SSB-Corridor - BoW - Install Vertical Tube Steel Support for Cable Tray (IFP Add) | Balance of Walls & Overhead | Not Started | 11/23/26 | 12/01/26 | 6.2 | 6.2 |
|
90.0 |
RPL07.INT.SSBC.4520 |
RPL07.Interior.SSBC LO #07 - Plumbing Trim Out | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/23/26 | 11/24/26 | 2.5 | 2.5 |
|
87.5 |
RPL07.INT.SSBC.4620 |
RPL07.Interior.SSBC LO #07 - Install Door (Verify with Trades before installation) | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/23/26 | 11/23/26 | 1.2 | 1.2 |
|
88.8 |
RPL.07.D.73730.XG |
RMUs/MV Skids Set (Ready for Longhorn Pulls) - DHC | Give Milestones (XREFs) | Not Started | 11/24/26 | 11/24/26 | 0.0 | 0.0 |
|
346.2 |
RPL.07.D.74080.XG |
Ready for MV Cable Pull DH C (MVs - Qty 8)* | Give Milestones (XREFs) | Not Started | 11/24/26 | 11/24/26 | 0.0 | 0.0 |
|
346.2 |
RPL07.CX.DHB.01090 |
RPL07.CX.DHB - L4 - WBS Summary (Mechanical) | DHB MECHANICAL | Not Started | 11/24/26 | 05/10/27 | 141.2 | 141.2 |
|
30.0 |
RPL07.CX.DHB.01260 |
RPL07.CX.DHB - L3/L4 - Control Fault Domain 01 - FW Flush and Fill | Control Fault Domain 1 | Not Started | 11/24/26 | 12/04/26 | 8.8 | 8.8 |
|
66.2 |
RPL07.INT.CC.9520 |
RPL07.Interior.CC Ext. LO #17 - Install Backing | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/24/26 | 11/25/26 | 2.5 | 2.5 |
|
77.5 |
RPL07.INT.CTRC.06780 |
RPL07.Interior.Center-Corridor - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings | Restrooms | Not Started | 11/24/26 | 12/09/26 | 12.5 | 12.5 |
|
36.2 |