Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:16 PM · 5237 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL07.INT.ENDC.07120 RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (P Restrooms Not Started 11/13/26 11/19/26 6.2 6.2
0%
173.8
RPL07.INT.SSB.01900 RPL07.Interior.SSB - Final Finishes & Fixtures - Casework Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 11/13/26 11/23/26 8.8 8.8
0%
210.0
RPL07.INT.SSB.06000 RPL07.Interior.SSB LO #16 - Close Exterior LO #16 (SSB - North of Loading Dock) WBS Summary Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 11/13/26 02/08/27 71.2 71.2
0%
67.5
RPL07.INT.SSB.06020 RPL07.Interior.SSB LO #16 - IMP In Wall MEP Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 11/13/26 11/16/26 2.5 2.5
0%
67.5
RPL07.INT.SSBC.3600 RPL07.Interior.SSBC LO #06 - Install Asset Tags Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 11/13/26 11/13/26 1.2 1.2
0%
95.0
GCD.RPL07.1116 RPL07 EY Ready for Energization Construction Milestones Not Started 11/16/26 11/16/26 0.0 0.0
0%
212.5
GCD.RPL07.2001 Cx Power Available (Temp) CX Milestones Not Started 11/16/26 11/16/26 0.0 0.0
0%
23.8
GCD.RPL07.5765 RMU Loop Ready for Energization - DHB Loop EY Not Started 11/16/26 11/16/26 0.0 0.0
0%
23.8
ICM.B7.2530 [SSDCB2] L3/L4 Start EY Commissioning Not Started 11/16/26 11/16/26 0.0 0.0
0%
178.8
RPL07.CX.DHB.01000 RPL07.CX.DHB - L3, L4, IST - WBS Summary DHB Not Started 11/16/26 07/09/27 201.2 201.2
0%
153.8
RPL07.CX.DHB.01010 RPL07.CX.DHB - L3 - WBS Summary (Electrical) DHB ELECTRICAL Not Started 11/16/26 03/19/27 105.0 105.0
0%
73.8
RPL07.CX.DHB.01020 RPL07.CX.DHB - L3/L4 - MV Skids (10) Loop 1 DHB ELECTRICAL Not Started 11/16/26 12/01/26 12.5 12.5
0%
23.8
RPL07.EY.DHA.01300 RPL07.EY.DHA - Install Sleeves MEPL Hardscape and Landscape Not Started 11/16/26 11/20/26 6.2 6.2
0%
181.2
RPL07.EY.DHA.01320 RPL07.EY.DHA - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 11/16/26 01/22/27 56.2 56.2
0%
298.8
RPL07.EY.DHB.01340 RPL07.EY.DHB - Install Lighting Hardscape and Landscape Not Started 11/16/26 12/01/26 12.5 12.5
0%
181.2
RPL07.INT.ENDC.01250 RPL07.Interior.End-Corridor - Set Equipment / Interior ?? Fit out Not Started 11/16/26 11/20/26 6.2 6.2
0%
161.2
RPL07.INT.ENDC.01270 RPL07.Interior.End-Corridor - Install Tile Fit out Not Started 11/16/26 11/24/26 8.8 8.8
0%
173.8
RPL07.INT.ENDC.01420 RPL07.Interior.End-Corridor - Install Remaining Refrigerant Line Fit out Not Started 11/16/26 11/20/26 6.2 6.2
0%
216.2
RPL07.INT.SSB.14220 RPL07.Interior.SSB LO #01 to #05 - Fire Safing OH and In-wall Finishes Not Started 11/16/26 11/16/26 1.2 1.2
0%
87.5
RPL07.INT.SSBC.3520 RPL07.Interior.SSBC LO #06 - Plumbing Trim Out Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 11/16/26 11/17/26 2.5 2.5
0%
93.8
RPL07.INT.SSBC.3620 RPL07.Interior.SSBC LO #06 - Install Door (Verify with Trades before installation) Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 11/16/26 11/16/26 1.2 1.2
0%
95.0
RPL07.CON.WP2.06680 RPL07.Conn - GSIDF/DH D2 - Install & Test Network (FIM) Network Not Started 11/17/26 11/19/26 3.8 3.8
0%
350.0
RPL07.CX.MCUP.01070 RPL07.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - DHB & DHA (Phase2) Fill and Flush Not Started 11/17/26 11/23/26 6.2 6.2
0%
66.2
RPL07.EY.DHA.02080 RPL07.EY.DHA - Install reminder of CSUs post LO buildback (Qty1) OFE Not Started 11/17/26 11/18/26 2.5 2.5
0%
162.5
RPL07.EY.DHB.01450 RPL07.EY.DHB - Install Remaining Remaining Electrical Tie-ins Tie-ins Not Started 11/17/26 11/30/26 10.0 10.0
0%
155.0
RPL07.EY.DHB.01460 RPL07.EY.DHB - Install Remaining Mechanical/refrigerantTie-ins Tie-ins Not Started 11/17/26 12/02/26 12.5 12.5
0%
152.5
RPL07.INT.CC.9380 RPL07.Interior.CC Ext. LO #17 - Install Security Lowside OH and In-wall Exterior Leave Out Wall #17 (CC - South) Not Started 11/17/26 11/18/26 2.5 2.5
0%
93.8
RPL07.INT.CC.9400 RPL07.Interior.CC Ext. LO #17 - Install Controls / EPMS / BMS OH and In-wall Exterior Leave Out Wall #17 (CC - South) Not Started 11/17/26 11/18/26 2.5 2.5
0%
78.8
RPL07.INT.CC.9420 RPL07.Interior.CC Ext. LO #17 - Mechanical Tie-In Exterior Leave Out Wall #17 (CC - South) Not Started 11/17/26 11/19/26 3.8 3.8
0%
77.5
RPL07.INT.CC.9440 RPL07.Interior.CC Ext. LO #17 - Electrical Tie-In Exterior Leave Out Wall #17 (CC - South) Not Started 11/17/26 11/19/26 3.8 3.8
0%
77.5
RPL07.INT.CTRC.1520 RPL07.Interior.Center-Corridor - BoW - Install Backing at Exterior Wall Balance of Walls & Overhead Not Started 11/17/26 11/23/26 6.2 6.2
0%
36.2
RPL07.INT.DHC.01300 RPL07.Interior.DHC - Tie-ins - Control Fault Domain 2 - WBS Summary Control Fault Domain 2 Not Started 11/17/26 05/13/27 151.2 151.2
0%
71.2
RPL07.INT.DHC.02530 RPL07.Interior.DHC - Control Fault Domain 2 - Install Duct (LV Side) LV Side Tie-ins Not Started 11/17/26 11/20/26 5.0 5.0
0%
172.5
RPL07.INT.DHD.01650 RPL07.Interior.DHD - Control Fault Domain 4 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 11/17/26 11/20/26 5.0 5.0
0%
236.2
RPL07.INT.ENDC.01440 RPL07.Interior.End-Corridor - OFE - UPS Gallery (2x) OFE/MOFE & CFCI Not Started 11/17/26 12/02/26 12.5 12.5
0%
181.2
RPL07.INT.SSB.06040 RPL07.Interior.SSB LO #16 - QC - Backings/Walls Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 11/17/26 11/17/26 1.2 1.2
0%
67.5
RPL07.INT.SSB.14400 RPL07.Interior.SSB LO #01 to #05 - Tape Finish Paint Finishes Not Started 11/17/26 11/19/26 3.8 3.8
0%
87.5
RPL07.INT.SSBC.01180 RPL07.Interior.SSB-Corridor - Install Fitout (GS.MDF Mech & Elec2x, Riser Room, GS Fiber Entry Room, Carrier MDF) - WBS Fit out Not Started 11/17/26 02/24/27 82.5 82.5
0%
115.0
RPL07.INT.SSBC.01210 RPL07.Interior.SSB-Corridor - Install Split Systems/Humidifiers Fit out Not Started 11/17/26 11/23/26 6.2 6.2
0%
125.0
RPL07.INT.SSBC.01390 RPL07.Interior.SSB-Corridor - Install Battery **?? Fit out Not Started 11/17/26 12/02/26 12.5 12.5
0%
95.0
RPL07.INT.SSBC.01590 RPL07.Interior.SSB-Corridor - Install Mechanical Tie-Ins (needs to micro plan) Fit out Not Started 11/17/26 11/23/26 6.2 6.2
0%
131.2
RPL07.INT.SSBC.3540 RPL07.Interior.SSBC LO #06 - Fire Life Safety Trim Out Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 11/17/26 11/17/26 1.2 1.2
0%
93.8
RPL07.INT.SSBC.4560 RPL07.Interior.SSBC LO #07 - Install Remaining Lights Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 11/17/26 11/19/26 3.8 3.8
0%
88.8
RPL07.INT.SSBC.4580 RPL07.Interior.SSBC LO #07 - Install Flooring Tiles/Resinous Flooring in specific rooms Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 11/17/26 11/19/26 3.8 3.8
0%
91.2
RPL07.INT.SSBC.4720 RPL07.Interior.SSBC LO #07 - Fire Safing / Wall Finishes Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 11/17/26 11/18/26 2.5 2.5
0%
87.5
RPL07.INT.DHA.01250 RPL07.Interior.DHA - Control Fault Domain 1 - Install Copper from GS.IDF to BMS and EPMS panels Remaining Tie-ins post Mech Side Aisle install Not Started 11/18/26 12/17/26 25.0 25.0
0%
33.8
RPL07.INT.DHB.01390 RPL07.Interior.DHB - Control Fault Domain 2 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 11/18/26 12/17/26 25.0 25.0
0%
52.5
RPL07.INT.DHB.01400 RPL07.Interior.DHB - Control Fault Domain 2 - Pull EMPS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 11/18/26 12/17/26 25.0 25.0
0%
52.5
RPL07.INT.DHB.01410 RPL07.Interior.DHB - Control Fault Domain 2 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 11/18/26 12/17/26 25.0 25.0
0%
40.0
RPL07.INT.DHB.02560 RPL07.Interior.DHB - OFE - Control Fault Domain 3 (Mech Side Aisle) Control Fault Domain 3 Not Started 11/18/26 12/08/26 16.2 16.2
0%
45.0
RPL07.INT.DHD.01670 RPL07.Interior.DHD - Control Fault Domain 4 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 11/18/26 11/23/26 5.0 5.0
0%
250.0
RPL07.INT.SSB.06060 RPL07.Interior.SSB LO #16 - Hang Exterior Wall Drywall Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 11/18/26 11/19/26 2.5 2.5
0%
67.5
RPL07.INT.SSBC.3640 RPL07.Interior.SSBC LO #06 - Electrical L2 Checklist Completion Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 11/18/26 12/03/26 12.5 12.5
0%
93.8
RPL07.EY.DHA.01450 RPL07.EY.DHA - Install Remaining Electrical Tie-ins Tie-ins Not Started 11/19/26 12/02/26 10.0 10.0
0%
165.0
RPL07.INT.CC.9500 RPL07.Interior.CC Ext. LO #17 - Install Electrical Lowside OH and In-wall Exterior Leave Out Wall #17 (CC - South) Not Started 11/19/26 11/20/26 2.5 2.5
0%
78.8
RPL07.INT.DHC.01350 RPL07.Interior.DHC - OFE - Control Fault Domain 3 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 3 Not Started 11/19/26 03/30/27 108.8 108.8
0%
48.8
RPL07.INT.DHC.01370 RPL07.Interior.DHC - Control Fault Domain 2 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 11/19/26 11/24/26 5.0 5.0
0%
181.2
RPL07.INT.DHC.02390 RPL07.Interior.DHC - OFE - Control Fault Domain 3 (LV Side Aisle) Control Fault Domain 3 Not Started 11/19/26 11/24/26 5.0 5.0
0%
140.0
RPL07.INT.SSBC.4420 RPL07.Interior.SSBC LO #07 - Electrical Trim Out Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 11/19/26 11/20/26 2.5 2.5
0%
87.5
RPL07.INT.SSBC.4440 RPL07.Interior.SSBC LO #07 - Security Trim Out Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 11/19/26 11/20/26 2.5 2.5
0%
87.5
RPL.07.D.73340.XR Pull and Term MV Skids - RPL07 DHD Receive Milestones (XREFs) Not Started 11/20/26 11/20/26 0.0 0.0
0%
153.8
RPL.07.D.73840.XR 100MW Cx Temp Power to MV Skids RPL07 DHD Available Receive Milestones (XREFs) Not Started 11/20/26 11/20/26 0.0 0.0
0%
153.8
RPL07.INT.CC.9480 RPL07.Interior.CC Ext. LO #17 - Fire Safing OH and In-wall Exterior Leave Out Wall #17 (CC - South) Not Started 11/20/26 11/23/26 2.5 2.5
0%
77.5
RPL07.INT.DHC.01390 RPL07.Interior.DHC - Control Fault Domain 2 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 11/20/26 11/25/26 5.0 5.0
0%
181.2
RPL07.INT.ENDC.07100 RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Install Tile/ Grout Restrooms Not Started 11/20/26 12/07/26 12.5 12.5
0%
182.5
RPL07.INT.ENDC.07140 RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Install Fixtures, Partitions & Accessories Restrooms Not Started 11/20/26 12/02/26 8.8 8.8
0%
173.8
RPL07.INT.SSB.05860 RPL07.Interior.SSB - BoW - BoW - Install Mechanical Piping/ Refrigerant (Lowside OH space) Balance of Walls and OverHead Not Started 11/20/26 11/30/26 6.2 6.2
0%
77.5
RPL07.INT.SSB.06080 RPL07.Interior.SSB LO #16 - Tape Finish Paint Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 11/20/26 11/30/26 6.2 6.2
0%
67.5
RPL07.INT.SSB.14460 RPL07.Interior.SSB LO #01 to #05 - Mechanical Trim out Finishes Not Started 11/20/26 11/30/26 6.2 6.2
0%
102.5
RPL07.INT.SSB.14480 RPL07.Interior.SSB LO #01 to #05 - Final Paint Finishes Not Started 11/20/26 12/02/26 8.8 8.8
0%
127.5
RPL07.INT.SSB.14560 RPL07.Interior.SSB LO #01 to #05 - Install Remaining Lights Finishes Not Started 11/20/26 12/07/26 12.5 12.5
0%
87.5
RPL07.INT.SSB.14580 RPL07.Interior.SSB LO #01 to #05 - Install Flooring Tiles/Resinous Flooring in specific rooms Finishes Not Started 11/20/26 12/02/26 8.8 8.8
0%
108.8
RPL07.INT.SSB.14720 RPL07.Interior.SSB LO #01 to #05 - Fire Safing / Wall Finishes Finishes Not Started 11/20/26 11/30/26 6.2 6.2
0%
118.8
RPL07.INT.SSB.14740 RPL07.Interior.SSB LO #01 to #05 - Install Split Systems Finishes Not Started 11/20/26 11/24/26 3.8 3.8
0%
107.5
RPL07.INT.SSBC.4600 RPL07.Interior.SSBC LO #07 - Install Asset Tags Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 11/20/26 11/20/26 1.2 1.2
0%
88.8
GCD.RPL07.5805 RMU Loop Ready for Energization - DHA Loop EY Not Started 11/23/26 11/23/26 0.0 0.0
0%
30.0
RPL07.CON.WP2.02000 RPL07.Conn - GS EF2 (North) - WBS Summary GS.EF2 (North) Not Started 11/23/26 12/03/26 8.8 8.8
0%
266.2
RPL07.CON.WP2.02200 RPL07.Conn - GS EF2 (North) Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Not Started 11/23/26 11/25/26 3.8 3.8
0%
266.2
RPL07.CON.WP2.03000 RPL07.Conn - GS EF1 (South) - WBS Summary GS.EF1 (South) Not Started 11/23/26 12/03/26 8.8 8.8
0%
266.2
RPL07.CON.WP2.07820 RPL07.Conn - GS EF1 (South) Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Not Started 11/23/26 11/25/26 3.8 3.8
0%
266.2
RPL07.EY.DHA.01330 RPL07.EY.DHA - Install Early EY Paving Hardscape and Landscape Not Started 11/23/26 12/01/26 6.2 6.2
0%
181.2
RPL07.EY.DHA.01460 RPL07.EY.DHA - Install Remaining Mechanical Tie-ins Tie-ins Not Started 11/23/26 12/08/26 12.5 12.5
0%
160.0
RPL07.EY.DHA.01520 RPL07.EY.DHA - Install Floor Mounted Outdoor Split AC Units (Qty 4) OFE Not Started 11/23/26 12/04/26 10.0 10.0
0%
137.5
RPL07.INT.CC.9580 RPL07.Interior.CC Ext. LO #17 - Install Door Frame Hardware Exterior Leave Out Wall #17 (CC - South) Not Started 11/23/26 11/30/26 5.0 5.0
0%
91.2
RPL07.INT.DHC.01440 RPL07.Interior.DHC - Tie-ins - Control Fault Domain 3 (including IDF) - WBS Summary Control Fault Domain 3 Not Started 11/23/26 05/20/27 152.5 152.5
0%
97.5
RPL07.INT.DHC.02550 RPL07.Interior.DHC - Control Fault Domain 3 - Install Duct (LV Side) LV Side Tie-ins Not Started 11/23/26 11/30/26 5.0 5.0
0%
187.5
RPL07.INT.ENDC.01280 RPL07.Interior.End-Corridor - Duct Drops / Trim out Fit out Not Started 11/23/26 12/02/26 7.5 7.5
0%
167.5
RPL07.INT.ENDC.01290 RPL07.Interior.End-Corridor - Install Battery Fit out Not Started 11/23/26 12/08/26 12.5 12.5
0%
161.2
RPL07.INT.ENDC.01590 RPL07.Interior.End-Corridor - Install Electrical - DHD/DHC UPS Gallery Fit out Not Started 11/23/26 12/01/26 6.2 6.2
0%
173.8
RPL07.INT.ENDC.1340 RPL07.Interior.End-Corridor - BoW - Install VAV's/Duct Branches Balance of Walls & Overhead Not Started 11/23/26 12/01/26 6.2 6.2
0%
125.0
RPL07.INT.ENDC.1360 RPL07.Interior.End-Corridor - BoW - Install Split Systems/Humidifiers Balance of Walls & Overhead Not Started 11/23/26 12/01/26 6.2 6.2
0%
125.0
RPL07.INT.SBC.03640 RPL07.Interior.SSB-Corridor - BoW - Install Vertical Tube Steel Support for Cable Tray (IFP Add) Balance of Walls & Overhead Not Started 11/23/26 12/01/26 6.2 6.2
0%
90.0
RPL07.INT.SSBC.4520 RPL07.Interior.SSBC LO #07 - Plumbing Trim Out Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 11/23/26 11/24/26 2.5 2.5
0%
87.5
RPL07.INT.SSBC.4620 RPL07.Interior.SSBC LO #07 - Install Door (Verify with Trades before installation) Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 11/23/26 11/23/26 1.2 1.2
0%
88.8
RPL.07.D.73730.XG RMUs/MV Skids Set (Ready for Longhorn Pulls) - DHC Give Milestones (XREFs) Not Started 11/24/26 11/24/26 0.0 0.0
0%
346.2
RPL.07.D.74080.XG Ready for MV Cable Pull DH C (MVs - Qty 8)* Give Milestones (XREFs) Not Started 11/24/26 11/24/26 0.0 0.0
0%
346.2
RPL07.CX.DHB.01090 RPL07.CX.DHB - L4 - WBS Summary (Mechanical) DHB MECHANICAL Not Started 11/24/26 05/10/27 141.2 141.2
0%
30.0
RPL07.CX.DHB.01260 RPL07.CX.DHB - L3/L4 - Control Fault Domain 01 - FW Flush and Fill Control Fault Domain 1 Not Started 11/24/26 12/04/26 8.8 8.8
0%
66.2
RPL07.INT.CC.9520 RPL07.Interior.CC Ext. LO #17 - Install Backing Exterior Leave Out Wall #17 (CC - South) Not Started 11/24/26 11/25/26 2.5 2.5
0%
77.5
RPL07.INT.CTRC.06780 RPL07.Interior.Center-Corridor - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings Restrooms Not Started 11/24/26 12/09/26 12.5 12.5
0%
36.2