Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:16 PM · 5237 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL07.INT.CTRC.1540 RPL07.Interior.Center-Corridor - BoW - QC - Backings/Walls Balance of Walls & Overhead Not Started 11/24/26 12/02/26 6.2 6.2
0%
68.8
RPL07.INT.SBC.03920 RPL07.Interior.SSB-Corridor - BoW - Install Asset Tags Balance of Walls & Overhead Not Started 11/24/26 12/04/26 8.8 8.8
0%
100.0
RPL07.INT.SSB.02420 RPL07.Interior.SSB - Final Finishes & Fixtures - Fixture Install Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 11/24/26 12/04/26 8.8 8.8
0%
237.5
RPL07.INT.SSB.06740 RPL07.Interior.SSB - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (Post Drywall) Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 11/24/26 12/02/26 6.2 6.2
0%
210.0
RPL07.INT.SSBC.01230 RPL07.Interior.SSB-Corridor - Install Remaining Refrigerant Line Fit out Not Started 11/24/26 12/02/26 6.2 6.2
0%
125.0
RPL07.INT.SSBC.4540 RPL07.Interior.SSBC LO #07 - Fire Life Safety Trim Out Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 11/24/26 11/24/26 1.2 1.2
0%
87.5
RPL.GF.D.N7240.XR GS IDF Huts Innerduct Complete for RPL 7 Receive Milestones (XREFs) Not Started 11/25/26 11/25/26 0.0 0.0
0%
326.2
RPL07.CON.WP3B.01000 RPL07.Conn WP#3B - ISP - WBS Summary WP#3B ISP - UPDATED Not Started 11/25/26 06/14/27 170.0 170.0
0%
107.5
RPL07.CON.WP3B.01020 RPL07.Conn WP#3B - ISP DHB - WBS Summary DHB Not Started 11/25/26 04/14/27 117.5 117.5
0%
58.8
RPL07.CON.WP4.01000 RPL07.Conn - DH B Network - WBS Summary DH B Not Started 11/25/26 05/26/27 155.0 155.0
0%
31.2
RPL07.CON.WP4.01020 RPL07.Conn WP4 FENW DHB CFD1 Infrastructure Infrastructure Not Started 11/25/26 12/24/26 25.0 25.0
0%
161.2
RPL07.CX.DHA.01000 RPL07.CX.DHA - L3, L4, IST - WBS Summary DHA Not Started 11/25/26 08/05/27 216.2 216.2
0%
130.0
RPL07.CX.DHA.01090 RPL07.CX.DHA - L4 - WBS Summary (Mechanical) DHA MECHANICAL Not Started 11/25/26 05/24/27 152.5 152.5
0%
30.0
RPL07.CX.DHA.01260 RPL07.CX.DHA - L3/L4 - Control Fault Domain 01 - FW Flush and Fill Control Fault Domain 1 Not Started 11/25/26 12/07/26 8.8 8.8
0%
77.5
RPL07.EY.DHC.01250 RPL07.EY.DHC - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 11/25/26 12/10/26 12.5 12.5
0%
138.8
RPL07.EY.DHC.01260 RPL07.EY.DHC - Tie-ins - WBS Summary Tie-ins Not Started 11/25/26 06/10/27 167.5 167.5
0%
101.2
RPL07.INT.DHA.01260 RPL07.Interior.DHA - Control Fault Domain 2 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 11/25/26 12/24/26 25.0 25.0
0%
40.0
RPL07.INT.DHA.01270 RPL07.Interior.DHA - Control Fault Domain 2 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 11/25/26 12/24/26 25.0 25.0
0%
52.5
RPL07.INT.DHA.01280 RPL07.Interior.DHA - Control Fault Domain 2 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 11/25/26 12/24/26 25.0 25.0
0%
40.0
RPL07.INT.DHA.01290 RPL07.Interior.DHA - Control Fault Domain 1 - L2 Checklist Completion Remaining Tie-ins post Mech Side Aisle install Not Started 11/25/26 12/24/26 25.0 25.0
0%
33.8
RPL07.INT.DHA.02200 RPL07.Interior.DHA - Control Fault Domain 2 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 11/25/26 12/24/26 25.0 25.0
0%
40.0
RPL07.INT.DHB.01290 RPL07.Conn DHB - CFD1 - Set Passive Racks for WP#3b (16) Infrastructure Not Started 11/25/26 12/01/26 3.8 3.8
0%
130.0
RPL07.INT.DHB.01450 RPL07.Interior.DHB - Control Fault Domain 2 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 11/25/26 12/24/26 25.0 25.0
0%
40.0
RPL07.INT.DHB.02800 RPL07.Conn DHB - CFD1 - Set Passive Racks for PON (16) Infrastructure Not Started 11/25/26 12/01/26 3.8 3.8
0%
145.0
RPL07.INT.DHC.01490 RPL07.Interior.DHC - OFE - Control Fault Domain 4 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 4 Not Started 11/25/26 04/13/27 116.2 116.2
0%
46.2
RPL07.INT.DHC.01510 RPL07.Interior.DHC - Control Fault Domain 3 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 11/25/26 12/02/26 5.0 5.0
0%
217.5
RPL07.INT.DHC.02450 RPL07.Interior.DHC - OFE - Control Fault Domain 4 (LV Side Aisle) Control Fault Domain 4 Not Started 11/25/26 12/02/26 5.0 5.0
0%
147.5
RPL07.INT.ENDC.01320 RPL07.Interior.End-Corridor - Install Toilet Accessories Fit out Not Started 11/25/26 12/07/26 8.8 8.8
0%
173.8
RPL07.INT.SSB.14200 RPL07.Interior.SSB LO #01 to #05 - Mechanical Tie-In Finishes Not Started 11/25/26 11/25/26 1.2 1.2
0%
107.5
RPL07.INT.SSB.14300 RPL07.Interior.SSB LO #01 to #05 - Electrical Tie-In Finishes Not Started 11/25/26 12/03/26 6.2 6.2
0%
107.5
RPL07.INT.SSB.14760 RPL07.Interior.SSB LO #01 to #05 - Install Remaining Refrigerant Line Finishes Not Started 11/25/26 12/03/26 6.2 6.2
0%
113.8
RPL07.INT.SSBC.3660 RPL07.Interior.SSBC LO #06 - Mechanical L2 Checklist Completion Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 11/25/26 12/10/26 12.5 12.5
0%
93.8
RPL07.INT.SSBC.4640 RPL07.Interior.SSBC LO #07 - Electrical L2 Checklist Completion Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 11/25/26 12/10/26 12.5 12.5
0%
87.5
DCC.B7.3300 [SSDCB2] Cabling Start : OSP Pathways - Primary GS Connectivity Not Started 11/30/26 11/30/26 0.0 0.0
0%
345.0
DCC.B7.3707 [SSDCB2] Cabling Start : General Services (GS) Connectivity Not Started 11/30/26 11/30/26 0.0 0.0
0%
345.0
RPL.GF.D.N7140.XR Fiber Pulls, Test & Term to Prod EF1 Complete RPL 10 to RPL07 Receive Milestones (XREFs) Not Started 11/30/26 11/30/26 0.0 0.0
0%
266.2
RPL.GF.D.N7150.XR Fiber Pulls, Test & Term to Prod EF2 Complete RPL 10 to RPL07 Receive Milestones (XREFs) Not Started 11/30/26 11/30/26 0.0 0.0
0%
266.2
RPL07.CON.WP2.02400 RPL07.Conn - GS EF2 (North) Install Cabling (Pull, Splice & Terminate) Cabling Not Started 11/30/26 12/03/26 5.0 5.0
0%
266.2
RPL07.CON.WP2.07240 RPL07.Conn - Ext. GSIDF7X01 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 11/30/26 12/07/26 7.5 7.5
0%
333.8
RPL07.CON.WP2.07440 RPL07.Conn - Ext. GSIDF7X02 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 11/30/26 12/07/26 7.5 7.5
0%
333.8
RPL07.CON.WP2.07840 RPL07.Conn - GS EF1 (South) Install Cabling (Pull, Splice & Terminate) Cabling Not Started 11/30/26 12/03/26 5.0 5.0
0%
266.2
RPL07.CON.WP2.08420 RPL07.Conn - Ext. GSIDF7X03 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 11/30/26 12/07/26 7.5 7.5
0%
333.8
RPL07.CON.WP2.08480 RPL07.Conn - Ext. GSIDF7X04 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 11/30/26 12/15/26 15.0 15.0
0%
326.2
RPL07.INT.CC.9540 RPL07.Interior.CC Ext. LO #17 - QC - Backings/Walls Exterior Leave Out Wall #17 (CC - South) Not Started 11/30/26 11/30/26 1.2 1.2
0%
77.5
RPL07.INT.DHC.01530 RPL07.Interior.DHC - Control Fault Domain 3 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 11/30/26 12/03/26 5.0 5.0
0%
241.2
GCD.RPL07.2251 L3/L4 Finish EY - DHB EY Not Started 12/01/26 12/01/26 0.0 0.0
0%
166.2
RPL07.EY.DHC.01280 RPL07.EY.DHC - Install BMS/EPMS Tie-ins Tie-ins Not Started 12/01/26 12/14/26 12.5 12.5
0%
138.8
RPL07.EY.DHD.01300 RPL07.EY.DHD - Install Sleeves MEPL Hardscape and Landscape Not Started 12/01/26 12/07/26 6.2 6.2
0%
253.8
RPL07.EY.DHD.01310 RPL07.EY.DHD - MV Loop - L2 Checklist Completion Tie-ins Not Started 12/01/26 12/14/26 12.5 12.5
0%
135.0
RPL07.EY.DHD.01320 RPL07.EY.DHD - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 12/01/26 06/16/27 170.0 170.0
0%
173.8
RPL07.INT.CC.9020 RPL07.Interior.CC Ext. LO #17 - Hang Drywall Exterior Leave Out Wall #17 (CC - South) Not Started 12/01/26 12/03/26 3.8 3.8
0%
77.5
RPL07.INT.CTRC.01260 RPL07.Interior.Center-Corridor (N) - Remaining Electrical OFE Tie In Fit out (North) Not Started 12/01/26 12/07/26 6.2 6.2
0%
111.2
RPL07.INT.CTRC.01850 RPL07.Interior.Center-Corridor (S) - Remaining Electrical OFE Tie In Fit out (South) Not Started 12/01/26 12/07/26 6.2 6.2
0%
102.5
RPL07.INT.DHA.03620 RPL07.Interior.DHA - OFE - Control Fault Domain 3 (HAC) Control Fault Domain 3 Not Started 12/01/26 12/21/26 18.8 18.8
0%
12.5
RPL07.INT.DHC.01580 RPL07.Interior.DHC - Tie-ins - Control Fault Domain 4 - WBS Summary Control Fault Domain 4 Not Started 12/01/26 06/02/27 157.5 157.5
0%
90.0
RPL07.INT.DHC.02570 RPL07.Interior.DHC - Control Fault Domain 4 - Install Duct (LV Side) LV Side Tie-ins Not Started 12/01/26 12/04/26 5.0 5.0
0%
202.5
RPL07.INT.SSB.01260 RPL07.Interior.SSB - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls and OverHead Not Started 12/01/26 12/09/26 8.8 8.8
0%
83.8
RPL07.INT.SSB.01800 RPL07.Interior.SSB - BoW - Install Plumbing Lowside OH and In-wall Balance of Walls and OverHead Not Started 12/01/26 12/09/26 8.8 8.8
0%
77.5
RPL07.INT.SSB.06100 RPL07.Interior.SSB LO #16 - Install Mechanical Piping/ Refrigerant Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 12/01/26 12/07/26 6.2 6.2
0%
70.0
RPL07.INT.SSB.06120 RPL07.Interior.SSB LO #16 - Install Electrical Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 12/01/26 12/09/26 8.8 8.8
0%
71.2
RPL07.INT.SSB.06140 RPL07.Interior.SSB LO #16 - Install Plumbing Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 12/01/26 12/09/26 8.8 8.8
0%
67.5
RPL07.INT.SSB.06160 RPL07.Interior.SSB LO #16 - Install Fire Life Safety Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 12/01/26 12/03/26 3.8 3.8
0%
72.5
RPL07.INT.SSB.06180 RPL07.Interior.SSB LO #16 - Install Security Lowside OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 12/01/26 12/04/26 5.0 5.0
0%
71.2
RPL07.INT.SSB.06200 RPL07.Interior.SSB LO #16 - Install Controls / EPMS / BMS OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 12/01/26 12/03/26 3.8 3.8
0%
72.5
RPL07.INT.SSB.06220 RPL07.Interior.SSB LO #16 - Fire Safing OH Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 12/01/26 12/07/26 6.2 6.2
0%
70.0
RPL07.INT.SSB.14420 RPL07.Interior.SSB LO #01 to #05 - Electrical Trim Out Finishes Not Started 12/01/26 12/09/26 8.8 8.8
0%
118.8
RPL07.INT.SSB.14440 RPL07.Interior.SSB LO #01 to #05 - Security Trim Out Finishes Not Started 12/01/26 12/09/26 8.8 8.8
0%
118.8
DCC.B7.3527 [SSDCB2] Cabling Start : Front End Production Cabling [DHB] Connectivity Not Started 12/02/26 12/02/26 0.0 0.0
0%
342.5
GCD.RPL07.3527 [RPL07] TC-C Ready : Production Cabling Start [DHB Rows 01-08] TC-C Ready: Production Cabling - DHB Not Started 12/02/26 12/02/26 0.0 0.0
0%
342.5
GCD.RPL07.4605 L3/L4 Start EY - DHA EY Not Started 12/02/26 12/02/26 0.0 0.0
0%
178.8
ICM.B7.2510.B [SSDCB2] L3/4 Start - DHB Commissioning Not Started 12/02/26 12/02/26 0.0 0.0
0%
166.2
RPL07.CON.WP3B.01080 RPL07.Conn EF2<>DHB.11 - WBS Summary EF2<>DHB.11 Not Started 12/02/26 12/17/26 15.0 15.0
0%
155.0
RPL07.CX.DHA.01010 RPL07.CX.DHA - L3 - WBS Summary (Electrical) DHA ELECTRICAL Not Started 12/02/26 04/05/27 105.0 105.0
0%
73.8
RPL07.CX.DHA.01020 RPL07.CX.DHA - L3/L4 - MV Skids (10) Loop 1 DHA ELECTRICAL Not Started 12/02/26 12/15/26 12.5 12.5
0%
23.8
RPL07.CX.DHB.01030 RPL07.CX.DHB - L3/L4 - House Power (for electrical) DHB HOUSE POWER Not Started 12/02/26 12/15/26 12.5 12.5
0%
23.8
RPL07.EY.DHA.01340 RPL07.EY.DHA - Install Lighting Hardscape and Landscape Not Started 12/02/26 12/15/26 12.5 12.5
0%
181.2
RPL07.EY.DHB.01390 RPL07.EY.DHB - Install Remaining EY Paving Hardscape and Landscape Not Started 12/02/26 12/08/26 6.2 6.2
0%
181.2
RPL07.INT.ENDC.1380 RPL07.Interior.End-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall Balance of Walls & Overhead Not Started 12/02/26 12/08/26 6.2 6.2
0%
196.2
RPL07.INT.ENDC.1440 RPL07.Interior.End-Corridor - BoW - Mechanical Tie-In Balance of Walls & Overhead Not Started 12/02/26 12/08/26 6.2 6.2
0%
125.0
RPL07.INT.SBC.03660 RPL07.Interior.SSB-Corridor - BoW - Install Horizontal Steel Supports for Cable Tray (IFP Add) Balance of Walls & Overhead Not Started 12/02/26 12/07/26 5.0 5.0
0%
90.0
RPL07.WP3B.012020 RPL07.Conn EF2<>DHB.11 Pull Pigtails (384F) P2&3 (LV) EF2<>DHB.11 Not Started 12/02/26 12/03/26 2.5 2.5
0%
138.8
RPL07.WP4.010080 RPL07.Conn DHB.11 Pull Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 12/02/26 12/02/26 1.2 1.2
0%
168.8
RPL07.WP4.010100 RPL07.Conn DHB.12 Pull Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 12/02/26 12/02/26 1.2 1.2
0%
168.8
RPL07.WP4.010200 RPL07.Conn DHB.11.01 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 12/02/26 12/15/26 12.5 12.5
0%
130.0
RPL07.WP4.010220 RPL07.Conn DHB.12.05 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 12/02/26 12/15/26 12.5 12.5
0%
130.0
RPL07.WP4.010440 RPL07.Conn DHB.11 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] In-Rack Not Started 12/02/26 12/02/26 1.2 1.2
0%
158.8
RPL07.WP4.010460 RPL07.Conn DHB.12 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] In-Rack Not Started 12/02/26 12/02/26 1.2 1.2
0%
158.8
RPL.GF.D.N7100.XG Both GSEF Room Complete RPL 7 Give Milestones (XREFs) Not Started 12/03/26 12/03/26 0.0 0.0
0%
340.0
RPL07.EY.DHB.01470 RPL07.EY.DHB - Remaining L2 Checklist Completion Tie-ins Not Started 12/03/26 12/09/26 6.2 6.2
0%
152.5
RPL07.INT.CTRC.1560 RPL07.Interior.Center-Corridor - BoW - Hang Drywall Balance of Walls & Overhead Not Started 12/03/26 12/11/26 8.8 8.8
0%
68.8
RPL07.INT.DHC.01650 RPL07.Interior.DHC - Control Fault Domain 4 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 12/03/26 12/08/26 5.0 5.0
0%
232.5
RPL07.INT.ENDC.01310 RPL07.Interior.End-Corridor - Fire Life Safe Trim Fit out Not Started 12/03/26 12/08/26 5.0 5.0
0%
167.5
RPL07.INT.ENDC.06800 RPL07.Interior.End-Corridor - Final Finishes & Fixtures - MEP Trims Restrooms Not Started 12/03/26 12/11/26 8.8 8.8
0%
173.8
RPL07.INT.SSB.06720 RPL07.Interior.SSB - Final Finishes & Fixtures - Install Tile/ Grout Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 12/03/26 12/16/26 12.5 12.5
0%
218.8
RPL07.INT.SSB.06760 RPL07.Interior.SSB - Final Finishes & Fixtures - Install Fixtures, Partitions & Accessories Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 12/03/26 12/11/26 8.8 8.8
0%
210.0
RPL07.INT.SSB.14520 RPL07.Interior.SSB LO #01 to #05 - Plumbing Trim Out Finishes Not Started 12/03/26 12/09/26 6.2 6.2
0%
118.8
RPL07.INT.SSB.14540 RPL07.Interior.SSB LO #01 to #05 - Fire Life Safety Trim Out Finishes Not Started 12/03/26 12/11/26 8.8 8.8
0%
118.8
RPL07.INT.SSBC.01410 RPL07.Interior.SSB-Corridor - Battery Connection Fit out Not Started 12/03/26 12/09/26 6.2 6.2
0%
95.0
RPL07.WP4.010240 RPL07.Conn DHB.11 Pull Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 12/03/26 12/03/26 1.2 1.2
0%
168.8
RPL07.WP4.010260 RPL07.Conn DHB.12 Pull Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 12/03/26 12/03/26 1.2 1.2
0%
168.8