Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.INT.CTRC.1540 |
RPL07.Interior.Center-Corridor - BoW - QC - Backings/Walls | Balance of Walls & Overhead | Not Started | 11/24/26 | 12/02/26 | 6.2 | 6.2 |
|
68.8 |
RPL07.INT.SBC.03920 |
RPL07.Interior.SSB-Corridor - BoW - Install Asset Tags | Balance of Walls & Overhead | Not Started | 11/24/26 | 12/04/26 | 8.8 | 8.8 |
|
100.0 |
RPL07.INT.SSB.02420 |
RPL07.Interior.SSB - Final Finishes & Fixtures - Fixture Install | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 11/24/26 | 12/04/26 | 8.8 | 8.8 |
|
237.5 |
RPL07.INT.SSB.06740 |
RPL07.Interior.SSB - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (Post Drywall) | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 11/24/26 | 12/02/26 | 6.2 | 6.2 |
|
210.0 |
RPL07.INT.SSBC.01230 |
RPL07.Interior.SSB-Corridor - Install Remaining Refrigerant Line | Fit out | Not Started | 11/24/26 | 12/02/26 | 6.2 | 6.2 |
|
125.0 |
RPL07.INT.SSBC.4540 |
RPL07.Interior.SSBC LO #07 - Fire Life Safety Trim Out | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/24/26 | 11/24/26 | 1.2 | 1.2 |
|
87.5 |
RPL.GF.D.N7240.XR |
GS IDF Huts Innerduct Complete for RPL 7 | Receive Milestones (XREFs) | Not Started | 11/25/26 | 11/25/26 | 0.0 | 0.0 |
|
326.2 |
RPL07.CON.WP3B.01000 |
RPL07.Conn WP#3B - ISP - WBS Summary | WP#3B ISP - UPDATED | Not Started | 11/25/26 | 06/14/27 | 170.0 | 170.0 |
|
107.5 |
RPL07.CON.WP3B.01020 |
RPL07.Conn WP#3B - ISP DHB - WBS Summary | DHB | Not Started | 11/25/26 | 04/14/27 | 117.5 | 117.5 |
|
58.8 |
RPL07.CON.WP4.01000 |
RPL07.Conn - DH B Network - WBS Summary | DH B | Not Started | 11/25/26 | 05/26/27 | 155.0 | 155.0 |
|
31.2 |
RPL07.CON.WP4.01020 |
RPL07.Conn WP4 FENW DHB CFD1 Infrastructure | Infrastructure | Not Started | 11/25/26 | 12/24/26 | 25.0 | 25.0 |
|
161.2 |
RPL07.CX.DHA.01000 |
RPL07.CX.DHA - L3, L4, IST - WBS Summary | DHA | Not Started | 11/25/26 | 08/05/27 | 216.2 | 216.2 |
|
130.0 |
RPL07.CX.DHA.01090 |
RPL07.CX.DHA - L4 - WBS Summary (Mechanical) | DHA MECHANICAL | Not Started | 11/25/26 | 05/24/27 | 152.5 | 152.5 |
|
30.0 |
RPL07.CX.DHA.01260 |
RPL07.CX.DHA - L3/L4 - Control Fault Domain 01 - FW Flush and Fill | Control Fault Domain 1 | Not Started | 11/25/26 | 12/07/26 | 8.8 | 8.8 |
|
77.5 |
RPL07.EY.DHC.01250 |
RPL07.EY.DHC - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 11/25/26 | 12/10/26 | 12.5 | 12.5 |
|
138.8 |
RPL07.EY.DHC.01260 |
RPL07.EY.DHC - Tie-ins - WBS Summary | Tie-ins | Not Started | 11/25/26 | 06/10/27 | 167.5 | 167.5 |
|
101.2 |
RPL07.INT.DHA.01260 |
RPL07.Interior.DHA - Control Fault Domain 2 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/25/26 | 12/24/26 | 25.0 | 25.0 |
|
40.0 |
RPL07.INT.DHA.01270 |
RPL07.Interior.DHA - Control Fault Domain 2 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/25/26 | 12/24/26 | 25.0 | 25.0 |
|
52.5 |
RPL07.INT.DHA.01280 |
RPL07.Interior.DHA - Control Fault Domain 2 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/25/26 | 12/24/26 | 25.0 | 25.0 |
|
40.0 |
RPL07.INT.DHA.01290 |
RPL07.Interior.DHA - Control Fault Domain 1 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/25/26 | 12/24/26 | 25.0 | 25.0 |
|
33.8 |
RPL07.INT.DHA.02200 |
RPL07.Interior.DHA - Control Fault Domain 2 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/25/26 | 12/24/26 | 25.0 | 25.0 |
|
40.0 |
RPL07.INT.DHB.01290 |
RPL07.Conn DHB - CFD1 - Set Passive Racks for WP#3b (16) | Infrastructure | Not Started | 11/25/26 | 12/01/26 | 3.8 | 3.8 |
|
130.0 |
RPL07.INT.DHB.01450 |
RPL07.Interior.DHB - Control Fault Domain 2 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 11/25/26 | 12/24/26 | 25.0 | 25.0 |
|
40.0 |
RPL07.INT.DHB.02800 |
RPL07.Conn DHB - CFD1 - Set Passive Racks for PON (16) | Infrastructure | Not Started | 11/25/26 | 12/01/26 | 3.8 | 3.8 |
|
145.0 |
RPL07.INT.DHC.01490 |
RPL07.Interior.DHC - OFE - Control Fault Domain 4 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 4 | Not Started | 11/25/26 | 04/13/27 | 116.2 | 116.2 |
|
46.2 |
RPL07.INT.DHC.01510 |
RPL07.Interior.DHC - Control Fault Domain 3 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 11/25/26 | 12/02/26 | 5.0 | 5.0 |
|
217.5 |
RPL07.INT.DHC.02450 |
RPL07.Interior.DHC - OFE - Control Fault Domain 4 (LV Side Aisle) | Control Fault Domain 4 | Not Started | 11/25/26 | 12/02/26 | 5.0 | 5.0 |
|
147.5 |
RPL07.INT.ENDC.01320 |
RPL07.Interior.End-Corridor - Install Toilet Accessories | Fit out | Not Started | 11/25/26 | 12/07/26 | 8.8 | 8.8 |
|
173.8 |
RPL07.INT.SSB.14200 |
RPL07.Interior.SSB LO #01 to #05 - Mechanical Tie-In | Finishes | Not Started | 11/25/26 | 11/25/26 | 1.2 | 1.2 |
|
107.5 |
RPL07.INT.SSB.14300 |
RPL07.Interior.SSB LO #01 to #05 - Electrical Tie-In | Finishes | Not Started | 11/25/26 | 12/03/26 | 6.2 | 6.2 |
|
107.5 |
RPL07.INT.SSB.14760 |
RPL07.Interior.SSB LO #01 to #05 - Install Remaining Refrigerant Line | Finishes | Not Started | 11/25/26 | 12/03/26 | 6.2 | 6.2 |
|
113.8 |
RPL07.INT.SSBC.3660 |
RPL07.Interior.SSBC LO #06 - Mechanical L2 Checklist Completion | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 11/25/26 | 12/10/26 | 12.5 | 12.5 |
|
93.8 |
RPL07.INT.SSBC.4640 |
RPL07.Interior.SSBC LO #07 - Electrical L2 Checklist Completion | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 11/25/26 | 12/10/26 | 12.5 | 12.5 |
|
87.5 |
DCC.B7.3300 |
[SSDCB2] Cabling Start : OSP Pathways - Primary GS | Connectivity | Not Started | 11/30/26 | 11/30/26 | 0.0 | 0.0 |
|
345.0 |
DCC.B7.3707 |
[SSDCB2] Cabling Start : General Services (GS) | Connectivity | Not Started | 11/30/26 | 11/30/26 | 0.0 | 0.0 |
|
345.0 |
RPL.GF.D.N7140.XR |
Fiber Pulls, Test & Term to Prod EF1 Complete RPL 10 to RPL07 | Receive Milestones (XREFs) | Not Started | 11/30/26 | 11/30/26 | 0.0 | 0.0 |
|
266.2 |
RPL.GF.D.N7150.XR |
Fiber Pulls, Test & Term to Prod EF2 Complete RPL 10 to RPL07 | Receive Milestones (XREFs) | Not Started | 11/30/26 | 11/30/26 | 0.0 | 0.0 |
|
266.2 |
RPL07.CON.WP2.02400 |
RPL07.Conn - GS EF2 (North) Install Cabling (Pull, Splice & Terminate) | Cabling | Not Started | 11/30/26 | 12/03/26 | 5.0 | 5.0 |
|
266.2 |
RPL07.CON.WP2.07240 |
RPL07.Conn - Ext. GSIDF7X01 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 11/30/26 | 12/07/26 | 7.5 | 7.5 |
|
333.8 |
RPL07.CON.WP2.07440 |
RPL07.Conn - Ext. GSIDF7X02 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 11/30/26 | 12/07/26 | 7.5 | 7.5 |
|
333.8 |
RPL07.CON.WP2.07840 |
RPL07.Conn - GS EF1 (South) Install Cabling (Pull, Splice & Terminate) | Cabling | Not Started | 11/30/26 | 12/03/26 | 5.0 | 5.0 |
|
266.2 |
RPL07.CON.WP2.08420 |
RPL07.Conn - Ext. GSIDF7X03 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 11/30/26 | 12/07/26 | 7.5 | 7.5 |
|
333.8 |
RPL07.CON.WP2.08480 |
RPL07.Conn - Ext. GSIDF7X04 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 11/30/26 | 12/15/26 | 15.0 | 15.0 |
|
326.2 |
RPL07.INT.CC.9540 |
RPL07.Interior.CC Ext. LO #17 - QC - Backings/Walls | Exterior Leave Out Wall #17 (CC - South) | Not Started | 11/30/26 | 11/30/26 | 1.2 | 1.2 |
|
77.5 |
RPL07.INT.DHC.01530 |
RPL07.Interior.DHC - Control Fault Domain 3 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 11/30/26 | 12/03/26 | 5.0 | 5.0 |
|
241.2 |
GCD.RPL07.2251 |
L3/L4 Finish EY - DHB | EY | Not Started | 12/01/26 | 12/01/26 | 0.0 | 0.0 |
|
166.2 |
RPL07.EY.DHC.01280 |
RPL07.EY.DHC - Install BMS/EPMS Tie-ins | Tie-ins | Not Started | 12/01/26 | 12/14/26 | 12.5 | 12.5 |
|
138.8 |
RPL07.EY.DHD.01300 |
RPL07.EY.DHD - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 12/01/26 | 12/07/26 | 6.2 | 6.2 |
|
253.8 |
RPL07.EY.DHD.01310 |
RPL07.EY.DHD - MV Loop - L2 Checklist Completion | Tie-ins | Not Started | 12/01/26 | 12/14/26 | 12.5 | 12.5 |
|
135.0 |
RPL07.EY.DHD.01320 |
RPL07.EY.DHD - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 12/01/26 | 06/16/27 | 170.0 | 170.0 |
|
173.8 |
RPL07.INT.CC.9020 |
RPL07.Interior.CC Ext. LO #17 - Hang Drywall | Exterior Leave Out Wall #17 (CC - South) | Not Started | 12/01/26 | 12/03/26 | 3.8 | 3.8 |
|
77.5 |
RPL07.INT.CTRC.01260 |
RPL07.Interior.Center-Corridor (N) - Remaining Electrical OFE Tie In | Fit out (North) | Not Started | 12/01/26 | 12/07/26 | 6.2 | 6.2 |
|
111.2 |
RPL07.INT.CTRC.01850 |
RPL07.Interior.Center-Corridor (S) - Remaining Electrical OFE Tie In | Fit out (South) | Not Started | 12/01/26 | 12/07/26 | 6.2 | 6.2 |
|
102.5 |
RPL07.INT.DHA.03620 |
RPL07.Interior.DHA - OFE - Control Fault Domain 3 (HAC) | Control Fault Domain 3 | Not Started | 12/01/26 | 12/21/26 | 18.8 | 18.8 |
|
12.5 |
RPL07.INT.DHC.01580 |
RPL07.Interior.DHC - Tie-ins - Control Fault Domain 4 - WBS Summary | Control Fault Domain 4 | Not Started | 12/01/26 | 06/02/27 | 157.5 | 157.5 |
|
90.0 |
RPL07.INT.DHC.02570 |
RPL07.Interior.DHC - Control Fault Domain 4 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 12/01/26 | 12/04/26 | 5.0 | 5.0 |
|
202.5 |
RPL07.INT.SSB.01260 |
RPL07.Interior.SSB - BoW - Install Fire Life Safety Lowside OH and In-wall | Balance of Walls and OverHead | Not Started | 12/01/26 | 12/09/26 | 8.8 | 8.8 |
|
83.8 |
RPL07.INT.SSB.01800 |
RPL07.Interior.SSB - BoW - Install Plumbing Lowside OH and In-wall | Balance of Walls and OverHead | Not Started | 12/01/26 | 12/09/26 | 8.8 | 8.8 |
|
77.5 |
RPL07.INT.SSB.06100 |
RPL07.Interior.SSB LO #16 - Install Mechanical Piping/ Refrigerant Lowside OH | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 12/01/26 | 12/07/26 | 6.2 | 6.2 |
|
70.0 |
RPL07.INT.SSB.06120 |
RPL07.Interior.SSB LO #16 - Install Electrical Lowside OH | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 12/01/26 | 12/09/26 | 8.8 | 8.8 |
|
71.2 |
RPL07.INT.SSB.06140 |
RPL07.Interior.SSB LO #16 - Install Plumbing Lowside OH | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 12/01/26 | 12/09/26 | 8.8 | 8.8 |
|
67.5 |
RPL07.INT.SSB.06160 |
RPL07.Interior.SSB LO #16 - Install Fire Life Safety Lowside OH | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 12/01/26 | 12/03/26 | 3.8 | 3.8 |
|
72.5 |
RPL07.INT.SSB.06180 |
RPL07.Interior.SSB LO #16 - Install Security Lowside OH | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 12/01/26 | 12/04/26 | 5.0 | 5.0 |
|
71.2 |
RPL07.INT.SSB.06200 |
RPL07.Interior.SSB LO #16 - Install Controls / EPMS / BMS OH | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 12/01/26 | 12/03/26 | 3.8 | 3.8 |
|
72.5 |
RPL07.INT.SSB.06220 |
RPL07.Interior.SSB LO #16 - Fire Safing OH | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 12/01/26 | 12/07/26 | 6.2 | 6.2 |
|
70.0 |
RPL07.INT.SSB.14420 |
RPL07.Interior.SSB LO #01 to #05 - Electrical Trim Out | Finishes | Not Started | 12/01/26 | 12/09/26 | 8.8 | 8.8 |
|
118.8 |
RPL07.INT.SSB.14440 |
RPL07.Interior.SSB LO #01 to #05 - Security Trim Out | Finishes | Not Started | 12/01/26 | 12/09/26 | 8.8 | 8.8 |
|
118.8 |
DCC.B7.3527 |
[SSDCB2] Cabling Start : Front End Production Cabling [DHB] | Connectivity | Not Started | 12/02/26 | 12/02/26 | 0.0 | 0.0 |
|
342.5 |
GCD.RPL07.3527 |
[RPL07] TC-C Ready : Production Cabling Start [DHB Rows 01-08] | TC-C Ready: Production Cabling - DHB | Not Started | 12/02/26 | 12/02/26 | 0.0 | 0.0 |
|
342.5 |
GCD.RPL07.4605 |
L3/L4 Start EY - DHA | EY | Not Started | 12/02/26 | 12/02/26 | 0.0 | 0.0 |
|
178.8 |
ICM.B7.2510.B |
[SSDCB2] L3/4 Start - DHB | Commissioning | Not Started | 12/02/26 | 12/02/26 | 0.0 | 0.0 |
|
166.2 |
RPL07.CON.WP3B.01080 |
RPL07.Conn EF2<>DHB.11 - WBS Summary | EF2<>DHB.11 | Not Started | 12/02/26 | 12/17/26 | 15.0 | 15.0 |
|
155.0 |
RPL07.CX.DHA.01010 |
RPL07.CX.DHA - L3 - WBS Summary (Electrical) | DHA ELECTRICAL | Not Started | 12/02/26 | 04/05/27 | 105.0 | 105.0 |
|
73.8 |
RPL07.CX.DHA.01020 |
RPL07.CX.DHA - L3/L4 - MV Skids (10) Loop 1 | DHA ELECTRICAL | Not Started | 12/02/26 | 12/15/26 | 12.5 | 12.5 |
|
23.8 |
RPL07.CX.DHB.01030 |
RPL07.CX.DHB - L3/L4 - House Power (for electrical) | DHB HOUSE POWER | Not Started | 12/02/26 | 12/15/26 | 12.5 | 12.5 |
|
23.8 |
RPL07.EY.DHA.01340 |
RPL07.EY.DHA - Install Lighting | Hardscape and Landscape | Not Started | 12/02/26 | 12/15/26 | 12.5 | 12.5 |
|
181.2 |
RPL07.EY.DHB.01390 |
RPL07.EY.DHB - Install Remaining EY Paving | Hardscape and Landscape | Not Started | 12/02/26 | 12/08/26 | 6.2 | 6.2 |
|
181.2 |
RPL07.INT.ENDC.1380 |
RPL07.Interior.End-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall | Balance of Walls & Overhead | Not Started | 12/02/26 | 12/08/26 | 6.2 | 6.2 |
|
196.2 |
RPL07.INT.ENDC.1440 |
RPL07.Interior.End-Corridor - BoW - Mechanical Tie-In | Balance of Walls & Overhead | Not Started | 12/02/26 | 12/08/26 | 6.2 | 6.2 |
|
125.0 |
RPL07.INT.SBC.03660 |
RPL07.Interior.SSB-Corridor - BoW - Install Horizontal Steel Supports for Cable Tray (IFP Add) | Balance of Walls & Overhead | Not Started | 12/02/26 | 12/07/26 | 5.0 | 5.0 |
|
90.0 |
RPL07.WP3B.012020 |
RPL07.Conn EF2<>DHB.11 Pull Pigtails (384F) P2&3 (LV) | EF2<>DHB.11 | Not Started | 12/02/26 | 12/03/26 | 2.5 | 2.5 |
|
138.8 |
RPL07.WP4.010080 |
RPL07.Conn DHB.11 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 12/02/26 | 12/02/26 | 1.2 | 1.2 |
|
168.8 |
RPL07.WP4.010100 |
RPL07.Conn DHB.12 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 12/02/26 | 12/02/26 | 1.2 | 1.2 |
|
168.8 |
RPL07.WP4.010200 |
RPL07.Conn DHB.11.01 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 12/02/26 | 12/15/26 | 12.5 | 12.5 |
|
130.0 |
RPL07.WP4.010220 |
RPL07.Conn DHB.12.05 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 12/02/26 | 12/15/26 | 12.5 | 12.5 |
|
130.0 |
RPL07.WP4.010440 |
RPL07.Conn DHB.11 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 12/02/26 | 12/02/26 | 1.2 | 1.2 |
|
158.8 |
RPL07.WP4.010460 |
RPL07.Conn DHB.12 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 12/02/26 | 12/02/26 | 1.2 | 1.2 |
|
158.8 |
RPL.GF.D.N7100.XG |
Both GSEF Room Complete RPL 7 | Give Milestones (XREFs) | Not Started | 12/03/26 | 12/03/26 | 0.0 | 0.0 |
|
340.0 |
RPL07.EY.DHB.01470 |
RPL07.EY.DHB - Remaining L2 Checklist Completion | Tie-ins | Not Started | 12/03/26 | 12/09/26 | 6.2 | 6.2 |
|
152.5 |
RPL07.INT.CTRC.1560 |
RPL07.Interior.Center-Corridor - BoW - Hang Drywall | Balance of Walls & Overhead | Not Started | 12/03/26 | 12/11/26 | 8.8 | 8.8 |
|
68.8 |
RPL07.INT.DHC.01650 |
RPL07.Interior.DHC - Control Fault Domain 4 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 12/03/26 | 12/08/26 | 5.0 | 5.0 |
|
232.5 |
RPL07.INT.ENDC.01310 |
RPL07.Interior.End-Corridor - Fire Life Safe Trim | Fit out | Not Started | 12/03/26 | 12/08/26 | 5.0 | 5.0 |
|
167.5 |
RPL07.INT.ENDC.06800 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - MEP Trims | Restrooms | Not Started | 12/03/26 | 12/11/26 | 8.8 | 8.8 |
|
173.8 |
RPL07.INT.SSB.06720 |
RPL07.Interior.SSB - Final Finishes & Fixtures - Install Tile/ Grout | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 12/03/26 | 12/16/26 | 12.5 | 12.5 |
|
218.8 |
RPL07.INT.SSB.06760 |
RPL07.Interior.SSB - Final Finishes & Fixtures - Install Fixtures, Partitions & Accessories | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 12/03/26 | 12/11/26 | 8.8 | 8.8 |
|
210.0 |
RPL07.INT.SSB.14520 |
RPL07.Interior.SSB LO #01 to #05 - Plumbing Trim Out | Finishes | Not Started | 12/03/26 | 12/09/26 | 6.2 | 6.2 |
|
118.8 |
RPL07.INT.SSB.14540 |
RPL07.Interior.SSB LO #01 to #05 - Fire Life Safety Trim Out | Finishes | Not Started | 12/03/26 | 12/11/26 | 8.8 | 8.8 |
|
118.8 |
RPL07.INT.SSBC.01410 |
RPL07.Interior.SSB-Corridor - Battery Connection | Fit out | Not Started | 12/03/26 | 12/09/26 | 6.2 | 6.2 |
|
95.0 |
RPL07.WP4.010240 |
RPL07.Conn DHB.11 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 12/03/26 | 12/03/26 | 1.2 | 1.2 |
|
168.8 |
RPL07.WP4.010260 |
RPL07.Conn DHB.12 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 12/03/26 | 12/03/26 | 1.2 | 1.2 |
|
168.8 |