Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:16 PM · 5237 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL07.WP4.010560 RPL07.Conn DHB.11.01<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 12/03/26 12/07/26 3.8 3.8
0%
158.8
RPL07.WP4.010580 RPL07.Conn DHB.12.05<>05 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 12/03/26 12/07/26 3.8 3.8
0%
158.8
RPL07.WP4.010600 RPL07.Conn DHB.11 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] In-Rack Not Started 12/03/26 12/07/26 3.8 3.8
0%
177.5
RPL07.WP4.010620 RPL07.Conn DHB.12 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] In-Rack Not Started 12/03/26 12/07/26 3.8 3.8
0%
177.5
RPL07.CON.WP2.07920 RPL07.Conn - EF1<>MDF1 Install Cabling (Pull, Splice & Terminate) OSP (MDF RPL10 <> MDF RPL07) Not Started 12/04/26 12/11/26 7.5 7.5
0%
266.2
RPL07.CON.WP2.08000 RPL07.Conn - EF2<>MDF1 (South) Install Cabling (Pull, Splice & Terminate) OSP (MDF RPL10 <> MDF RPL07) Not Started 12/04/26 12/11/26 7.5 7.5
0%
266.2
RPL07.CON.WP3B.01060 RPL07.Conn EF2<>DHB.12 - WBS Summary EF2<>DHB.12 Not Started 12/04/26 12/18/26 13.8 13.8
0%
153.8
RPL07.INT.CC.9040 RPL07.Interior.CC Ext. LO #17 - Tape Finish Paint Exterior Leave Out Wall #17 (CC - South) Not Started 12/04/26 12/10/26 6.2 6.2
0%
77.5
RPL07.INT.DHA.01310 RPL07.Interior.DHA - Control Fault Domain 2 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 12/04/26 01/04/27 25.0 25.0
0%
52.5
RPL07.INT.DHA.01320 RPL07.Interior.DHA - Control Fault Domain 2 - Pull EMPS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 12/04/26 01/04/27 25.0 25.0
0%
52.5
RPL07.INT.DHA.01330 RPL07.Interior.DHA - Control Fault Domain 2 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 12/04/26 01/04/27 25.0 25.0
0%
40.0
RPL07.INT.DHA.03640 RPL07.Interior.DHA - OFE - Control Fault Domain 3 (Mech Side Aisle) Control Fault Domain 3 Not Started 12/04/26 12/22/26 16.2 16.2
0%
47.5
RPL07.INT.DHB.01480 RPL07.Interior.DHB - Control Fault Domain 2 - Install copper from GS.IDF to BMS and EPMS panels Remaining Tie-ins post Mech Side Aisle install Not Started 12/04/26 01/04/27 25.0 25.0
0%
40.0
RPL07.INT.DHB.01490 RPL07.Interior.DHB - Control Fault Domain 3 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 12/04/26 01/04/27 25.0 25.0
0%
47.5
RPL07.INT.DHB.01500 RPL07.Interior.DHB - Control Fault Domain 3 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 12/04/26 01/04/27 25.0 25.0
0%
53.8
RPL07.INT.DHB.01510 RPL07.Interior.DHB - Control Fault Domain 3 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 12/04/26 01/04/27 25.0 25.0
0%
47.5
RPL07.INT.DHB.02240 RPL07.Interior.DHB - Control Fault Domain 3 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 12/04/26 01/04/27 25.0 25.0
0%
47.5
RPL07.INT.DHC.01670 RPL07.Interior.DHC - Control Fault Domain 4 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 12/04/26 12/09/26 5.0 5.0
0%
238.8
RPL07.INT.SSBC.4660 RPL07.Interior.SSBC LO #07 - Mechanical L2 Checklist Completion Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 12/04/26 12/17/26 12.5 12.5
0%
87.5
RPL07.WP3B.012040 RPL07.Conn EF2<>DHB.12 Pull Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 12/04/26 12/07/26 2.5 2.5
0%
138.8
RPL07.WP3B.013460 RPL07.Conn EF2<>DHB.11 Install (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.11 Not Started 12/04/26 12/04/26 1.2 1.2
0%
155.0
RPL07.WP4.010400 RPL07.Conn DHB.11 Pull Trunk (384F) [RSW<>FSW] Trunks Not Started 12/04/26 12/04/26 1.2 1.2
0%
168.8
RPL07.WP4.010420 RPL07.Conn DHB.12 Pull Trunk (384F) [RSW<>FSW] Trunks Not Started 12/04/26 12/04/26 1.2 1.2
0%
168.8
RPL07.CX.DHB.01280 RPL07.CX.DHB - L3/L4 - Control Fault Domain 01 - TW Flush and Fill Control Fault Domain 1 Not Started 12/07/26 12/16/26 10.0 10.0
0%
66.2
RPL07.EY.DHA.01590 RPL07.EY.DHA - Install Mechanical/ refrigerantTie-ins Build back Exterior Leave Out #17 (South) Not Started 12/07/26 12/11/26 6.2 6.2
0%
137.5
RPL07.EY.DHA.02000 RPL07.EY.DHA - Exterior Leave Out #17 (CC - South) WBS Summary Build back Exterior Leave Out #17 (South) Not Started 12/07/26 01/05/27 25.0 25.0
0%
137.5
RPL07.INT.CTRC.1900 RPL07.Interior.Center-Corridor - BoW - F/R/P Pads Balance of Walls & Overhead Not Started 12/07/26 12/11/26 6.2 6.2
0%
68.8
RPL07.INT.SBC.03680 RPL07.Interior.SSB-Corridor - BoW - Install Door (Verify with Trades before installation) Balance of Walls & Overhead Not Started 12/07/26 12/15/26 8.8 8.8
0%
100.0
RPL07.INT.SSBC.01400 RPL07.Interior.SSB-Corridor - Install Grounding Fit out Not Started 12/07/26 12/09/26 3.8 3.8
0%
101.2
RPL07.WP3B.016340 RPL07.Conn EF2<>DHB.11 Install (Z-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.11 Not Started 12/07/26 12/14/26 7.5 7.5
0%
155.0
RPL07.CON.WP2.07280 RPL07.Conn - Ext. GSIDF7X01 - Install & Test Network (FIM) Network Not Started 12/08/26 12/10/26 3.8 3.8
0%
333.8
RPL07.CON.WP2.07480 RPL07.Conn - Ext. GSIDF7X02 - Install & Test Network (FIM) Network Not Started 12/08/26 12/10/26 3.8 3.8
0%
333.8
RPL07.CON.WP2.08440 RPL07.Conn - Ext. GSIDF7X03 - Install & Test Network (FIM) Network Not Started 12/08/26 12/10/26 3.8 3.8
0%
333.8
RPL07.CX.DHA.01280 RPL07.CX.DHA - L3/L4 - Control Fault Domain 01 - TW Flush and Fill Control Fault Domain 1 Not Started 12/08/26 12/17/26 10.0 10.0
0%
77.5
RPL07.EY.DHC.01290 RPL07.EY.DHC - MV Loop - L2 Checklist Completion Tie-ins Not Started 12/08/26 12/21/26 12.5 12.5
0%
138.8
RPL07.EY.DHD.01330 RPL07.EY.DHD - Install Early EY Paving Hardscape and Landscape Not Started 12/08/26 12/14/26 6.2 6.2
0%
253.8
RPL07.INT.CTRC.01290 RPL07.Interior.Center-Corridor (N) - Remaining Mechanical OFE Tie In Fit out (North) Not Started 12/08/26 12/10/26 3.8 3.8
0%
111.2
RPL07.INT.CTRC.01870 RPL07.Interior.Center-Corridor (S) - Remaining Mechanical OFE Tie In Fit out (South) Not Started 12/08/26 12/10/26 3.8 3.8
0%
102.5
RPL07.INT.DHB.02600 RPL07.Interior.DHB - OFE - Control Fault Domain 4 (HAC) Control Fault Domain 4 Not Started 12/08/26 12/29/26 18.8 18.8
0%
30.0
RPL07.INT.ENDC.06920 RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Flooring Restrooms Not Started 12/08/26 12/16/26 8.8 8.8
0%
182.5
RPL07.INT.SBC.03960 RPL07.Interior.SSB-Corridor - BoW - Final Paint and Tube Steel Paint (IFP Add) Balance of Walls & Overhead Not Started 12/08/26 12/16/26 8.8 8.8
0%
90.0
RPL07.INT.SSB.14600 RPL07.Interior.SSB LO #01 to #05 - Install Asset Tags Finishes Not Started 12/08/26 12/16/26 8.8 8.8
0%
87.5
RPL07.INT.SSBC.01290 RPL07.Interior.SSB-Corridor - Install Cable Tray Fit out Not Started 12/08/26 12/14/26 6.2 6.2
0%
93.8
RPL07.WP3B.013480 RPL07.Conn EF2<>DHB.12 Install (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 12/08/26 12/08/26 1.2 1.2
0%
153.8
RPL07.WP4.010720 RPL07.Conn DHB.11.03<>03 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 12/08/26 12/10/26 3.8 3.8
0%
158.8
RPL07.WP4.010740 RPL07.Conn DHB.12.06<>05 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 12/08/26 12/11/26 5.0 5.0
0%
158.8
GCD.RPL07.2605 L3/L4 Start - DHB Rows 01-08 DH Not Started 12/09/26 12/09/26 0.0 0.0
0%
160.0
RPL07.CX.DHB.01050 RPL07.CX.DHB - L3/L4 - Elec. Domain 01/02 DHB ELECTRICAL Not Started 12/09/26 12/17/26 8.8 8.8
0%
33.8
RPL07.CX.MCUP.01370 RPL07.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - DHD & DHC - Loop 2 (Phase 4) Fill and Flush Not Started 12/09/26 12/15/26 6.2 6.2
0%
171.2
RPL07.EY.DHB.01430 RPL07.EY.DHB - Install Irrigation Hardscape and Landscape Not Started 12/09/26 12/22/26 12.5 12.5
0%
311.2
RPL07.EY.DHB.01440 RPL07.EY.DHB - Install Exterior Signage Hardscape and Landscape Not Started 12/09/26 12/22/26 12.5 12.5
0%
181.2
RPL07.INT.ENDC.01330 RPL07.Interior.End-Corridor - Electrical Trim Fit out Not Started 12/09/26 12/14/26 5.0 5.0
0%
167.5
RPL07.INT.ENDC.01340 RPL07.Interior.End-Corridor - Install Grounding Fit out Not Started 12/09/26 12/22/26 12.5 12.5
0%
161.2
RPL07.INT.ENDC.1460 RPL07.Interior.End-Corridor - BoW - Frame Hard Lid Balance of Walls & Overhead Not Started 12/09/26 12/15/26 6.2 6.2
0%
125.0
RPL07.WP3B.014920 RPL07.Conn EF2<>DHB.12 Splice (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 12/09/26 12/16/26 7.5 7.5
0%
153.8
RPL07.WP3B.016360 RPL07.Conn EF2<>DHB.12 Install (Z-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 12/09/26 12/09/26 1.2 1.2
0%
153.8
RPL07.Conn.MS.01220 CorpNet FacNet Available (mCUP) Connectivity Milestones Not Started 12/10/26 12/10/26 0.0 0.0
0%
333.8
RPL07.INT.CTRC.06800 RPL07.Interior.Center-Corridor - Final Finishes & Fixtures - MEP Rough-In Restrooms Not Started 12/10/26 12/16/26 6.2 6.2
0%
36.2
RPL07.INT.SSB.01220 RPL07.Interior.SSB - BoW - Install Security Lowside OH and In-wall Balance of Walls and OverHead Not Started 12/10/26 12/18/26 8.8 8.8
0%
146.2
RPL07.INT.SSB.01240 RPL07.Interior.SSB - BoW - Install VAV's/Duct Branches Balance of Walls and OverHead Not Started 12/10/26 12/23/26 12.5 12.5
0%
133.8
RPL07.INT.SSB.01820 RPL07.Interior.SSB - BoW - Mechanical Tie-In Balance of Walls and OverHead Not Started 12/10/26 12/16/26 6.2 6.2
0%
77.5
RPL07.INT.SSB.06240 RPL07.Interior.SSB LO #16 - Install Remaining Lights Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 12/10/26 12/18/26 8.8 8.8
0%
67.5
DCC.B7.3025 [SSDCB2] Production Gear Delivered [DHA] Front End (SSW &FSW) Connectivity Not Started 12/11/26 12/11/26 0.0 0.0
0%
161.2
RPL07.CON.WP3B.01040 RPL07.Conn WP#3B - ISP DHA - WBS Summary DHA Not Started 12/11/26 04/23/27 113.8 113.8
0%
60.0
RPL07.CON.WP4.03000 RPL07.Conn - DH A Network - WBS Summary DH A Not Started 12/11/26 06/02/27 147.5 147.5
0%
38.8
RPL07.CON.WP4.03020 RPL07.Conn WP4 FENW DHA CFD1 Infrastructure Infrastructure Not Started 12/11/26 01/11/27 25.0 25.0
0%
161.2
RPL07.CX.DHB.01060 RPL07.CX.DHB - L3/L4 - UPS Start-up DHB ELECTRICAL Not Started 12/11/26 12/24/26 12.5 12.5
0%
98.8
RPL07.CX.DHB.01320 RPL07.CX.DHB - L3/L4 - Control Fault Domain 02 - FW Flush and Fill Control Fault Domain 2 Not Started 12/11/26 12/21/26 8.8 8.8
0%
72.5
RPL07.INT.CC.9060 RPL07.Interior.CC Ext. LO #17 - Duct Drops / Trim out Exterior Leave Out Wall #17 (CC - South) Not Started 12/11/26 12/14/26 2.5 2.5
0%
80.0
RPL07.INT.CC.9080 RPL07.Interior.CC Ext. LO #17 - Install Remaining Refrigerant Line Exterior Leave Out Wall #17 (CC - South) Not Started 12/11/26 12/11/26 1.2 1.2
0%
108.8
RPL07.INT.CC.9100 RPL07.Interior.CC Ext. LO #17 - Install Remaining Lights Exterior Leave Out Wall #17 (CC - South) Not Started 12/11/26 12/16/26 5.0 5.0
0%
80.0
RPL07.INT.CC.9120 RPL07.Interior.CC Ext. LO #17 - Fire Safing / Wall Finishes Exterior Leave Out Wall #17 (CC - South) Not Started 12/11/26 12/15/26 3.8 3.8
0%
77.5
RPL07.INT.CC.9220 RPL07.Interior.CC Ext. LO #17 - Install Flooring Tiles/Resinous Flooring in specific rooms **?? Exterior Leave Out Wall #17 (CC - South) Not Started 12/11/26 12/15/26 3.8 3.8
0%
81.2
RPL07.INT.DHA.01200 RPL07.Conn DHA - CFD1 - Set Passive Racks for WP#3b (16) Infrastructure Not Started 12/11/26 12/15/26 3.8 3.8
0%
130.0
RPL07.INT.DHA.01360 RPL07.Interior.DHA - Control Fault Domain 2 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 12/11/26 01/11/27 25.0 25.0
0%
40.0
RPL07.INT.DHA.03880 RPL07.Conn DHA - CFD1 - Set Passive Racks for PON (16) Infrastructure Not Started 12/11/26 12/15/26 3.8 3.8
0%
145.0
RPL07.INT.DHB.01530 RPL07.Interior.DHB - Control Fault Domain 3 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 12/11/26 01/11/27 25.0 25.0
0%
53.8
RPL07.INT.DHB.01540 RPL07.Interior.DHB - Control Fault Domain 3 - Pull EMPS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 12/11/26 01/11/27 25.0 25.0
0%
53.8
RPL07.INT.DHB.01550 RPL07.Interior.DHB - Control Fault Domain 3 - Set UPS and Panel (2) and GS.IDF B1 (Stick Built) Remaining Tie-ins post Mech Side Aisle install Not Started 12/11/26 01/11/27 25.0 25.0
0%
47.5
RPL07.INT.DHB.01570 RPL07.Interior.DHB - Control Fault Domain 2 - L2 Checklist Completion Remaining Tie-ins post Mech Side Aisle install Not Started 12/11/26 01/11/27 25.0 25.0
0%
40.0
RPL07.INT.DHB.02620 RPL07.Interior.DHB - OFE - Control Fault Domain 4 (Mech Side Aisle) Control Fault Domain 4 Not Started 12/11/26 12/30/26 16.2 16.2
0%
42.5
RPL07.WP4.010900 RPL07.Conn DHB.11.02<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 12/11/26 12/16/26 5.0 5.0
0%
158.8
RPL07.CON.WP2.07940 RPL07.Conn - GSMDF2 (North) Test Network (FIM) Network Not Started 12/14/26 12/16/26 3.8 3.8
0%
266.2
RPL07.CON.WP2.08020 RPL07.Conn - GSMDF1 (South) Test Network (FIM) Network Not Started 12/14/26 12/16/26 3.8 3.8
0%
266.2
RPL07.EY.DHA.01610 RPL07.EY.DHA - Install Electrical Tie-ins Build back Exterior Leave Out #17 (South) Not Started 12/14/26 12/18/26 6.2 6.2
0%
137.5
RPL07.INT.CTRC.1580 RPL07.Interior.Center-Corridor - BoW - Tape Finish Paint Balance of Walls & Overhead Not Started 12/14/26 12/16/26 3.8 3.8
0%
68.8
RPL07.INT.ENDC.06840 RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Install Acoustical Ceiling Restrooms Not Started 12/14/26 12/16/26 3.8 3.8
0%
173.8
RPL07.INT.SSB.02480 RPL07.Interior.SSB - Final Finishes & Fixtures - MEP Trims Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) Not Started 12/14/26 12/22/26 8.8 8.8
0%
210.0
RPL07.WP4.011220 RPL07.Conn DHB.12.07<>07 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 12/14/26 12/16/26 3.8 3.8
0%
158.8
GCD.RPL07.4565 L3/L4 Finish EY - DHA EY Not Started 12/15/26 12/15/26 0.0 0.0
0%
166.2
GCD.RPL07.5845 RMU Loop Ready for Energization - DHD Loop EY Not Started 12/15/26 12/15/26 0.0 0.0
0%
135.0
RPL.07.D.73330.XR Pull and Term MV Skids - RPL07 DHC Receive Milestones (XREFs) Not Started 12/15/26 12/15/26 0.0 0.0
0%
145.0
RPL.07.D.73830.XR 100MW Cx Temp Power to MV Skids RPL07 DHC Available Receive Milestones (XREFs) Not Started 12/15/26 12/15/26 0.0 0.0
0%
145.0
RPL07.CON.WP2.11020 RPL07.Conn - GSMDF1(South)<>DH B - CFD1 Rack #01 Pull, Install & Test PON Trunks MDF1 <> DH B - Rack#01 MES side Not Started 12/15/26 12/17/26 3.8 3.8
0%
146.2
RPL07.CON.WP2.12020 RPL07.Conn - GSMDF2(North)<>DH B - CFD1 Rack #50 Pull, Install & Patch PON Trunks MDF2 <> DH B - Rack#50 LV side Not Started 12/15/26 12/21/26 6.2 6.2
0%
133.8
RPL07.EY.DHC.01300 RPL07.EY.DHC - Install Sleeves MEPL Hardscape and Landscape Not Started 12/15/26 12/21/26 6.2 6.2
0%
250.0
RPL07.EY.DHC.01320 RPL07.EY.DHC - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 12/15/26 06/18/27 160.0 160.0
0%
171.2
RPL07.EY.DHD.01340 RPL07.EY.DHD - Install Lighting Hardscape and Landscape Not Started 12/15/26 12/29/26 12.5 12.5
0%
253.8
RPL07.INT.ENDC.01350 RPL07.Interior.End-Corridor - Plumbing Trim Fit out Not Started 12/15/26 12/18/26 5.0 5.0
0%
167.5
RPL07.INT.ENDC.01430 RPL07.Interior.End-Corridor - MOFE - Ancillary Skids Qty2 (DH D) OFE/MOFE & CFCI Not Started 12/15/26 12/29/26 12.5 12.5
0%
172.5