Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.WP4.013100 |
RPL07.Conn DHA.01.04<>03 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Jumpers | Not Started | 01/04/27 | 01/07/27 | 5.0 | 5.0 |
|
158.8 |
RPL07.WP4.013120 |
RPL07.Conn DHA.02.08<>07 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 01/04/27 | 01/07/27 | 5.0 | 5.0 |
|
158.8 |
RPL07.CON.WP3B.01140 |
RPL07.Conn EF2<>DHB.14 - WBS Summary | EF2<>DHB.14 | Not Started | 01/05/27 | 01/20/27 | 13.8 | 13.8 |
|
128.8 |
RPL07.CX.DHB.01380 |
RPL07.CX.DHB - L3/L4 - Control Fault Domain 03 - FW Flush and Fill | Control Fault Domain 3 | Not Started | 01/05/27 | 01/13/27 | 8.8 | 8.8 |
|
73.8 |
RPL07.INT.DHA.01500 |
RPL07.Interior.DHA - Control Fault Domain 3 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/05/27 | 02/02/27 | 25.0 | 25.0 |
|
86.2 |
RPL07.INT.DHA.01530 |
RPL07.Interior.DHA - Control Fault Domain 3 - Install copper from GS.IDF to BMS and EPMS panels (UG from Center IDF) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/05/27 | 02/02/27 | 25.0 | 25.0 |
|
47.5 |
RPL07.INT.DHB.01670 |
RPL07.Interior.DHB - Control Fault Domain 4 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/05/27 | 02/02/27 | 25.0 | 25.0 |
|
55.0 |
RPL07.INT.DHB.01680 |
RPL07.Interior.DHB - Control Fault Domain 4 - Pull EMPS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/05/27 | 02/02/27 | 25.0 | 25.0 |
|
55.0 |
RPL07.INT.DHB.01690 |
RPL07.Interior.DHB - Control Fault Domain 4 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/05/27 | 02/02/27 | 25.0 | 25.0 |
|
48.8 |
RPL07.INT.ENDC.06980 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Final Punch Walk | Restrooms | Not Started | 01/05/27 | 01/06/27 | 2.5 | 2.5 |
|
173.8 |
RPL07.WP3B.012080 |
RPL07.Conn EF2<>DHB.14 Pull Pigtails (384F) P2&3 (LV) | EF2<>DHB.14 | Not Started | 01/05/27 | 01/06/27 | 2.5 | 2.5 |
|
118.8 |
RPL07.WP3B.013500 |
RPL07.Conn EF2<>DHB.13 Install (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.13 | Not Started | 01/05/27 | 01/05/27 | 1.2 | 1.2 |
|
131.2 |
RPL07.WP4.011980 |
RPL07.Conn DHB.13 Pull Trunk (384F) [RSW<>FSW] | Trunks | Not Started | 01/05/27 | 01/05/27 | 1.2 | 1.2 |
|
143.8 |
RPL07.WP4.012000 |
RPL07.Conn DHB.14 Pull Trunk (384F) [RSW<>FSW] | Trunks | Not Started | 01/05/27 | 01/05/27 | 1.2 | 1.2 |
|
143.8 |
RPL07.EY.DHA.01470 |
RPL07.EY.DHA - Remaining L2 Checklist Completion | Tie-ins | Not Started | 01/06/27 | 01/12/27 | 6.2 | 6.2 |
|
137.5 |
RPL07.INT.SBC.04020 |
RPL07.Interior.SSB-Corridor - BoW - Mechanical L2 Checklist Completion | Balance of Walls & Overhead | Not Started | 01/06/27 | 01/20/27 | 12.5 | 12.5 |
|
90.0 |
RPL07.INT.SSB.14660 |
RPL07.Interior.SSB LO #01 to #05 - Mechanical L2 Checklist Completion | Finishes | Not Started | 01/06/27 | 01/20/27 | 12.5 | 12.5 |
|
87.5 |
RPL07.WP3B.014940 |
RPL07.Conn EF2<>DHB.13 Splice (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.13 | Not Started | 01/06/27 | 01/13/27 | 7.5 | 7.5 |
|
131.2 |
RPL07.WP3B.016380 |
RPL07.Conn EF2<>DHB.13 Install (Z-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.13 | Not Started | 01/06/27 | 01/06/27 | 1.2 | 1.2 |
|
131.2 |
RPL07.CX.DHA.01340 |
RPL07.CX.DHA - L3/L4 - Control Fault Domain 02 - TW Flush and Fill | Control Fault Domain 2 | Not Started | 01/07/27 | 01/19/27 | 10.0 | 10.0 |
|
72.5 |
RPL07.INT.DHB.02680 |
RPL07.Interior.DHB - OFE - Control Fault Domain 5 (Mech Side Aisle) | Control Fault Domain 5 | Not Started | 01/07/27 | 01/26/27 | 16.2 | 16.2 |
|
37.5 |
RPL07.INT.ENDC.06880 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Electrical L2 Checklist Completion | Restrooms | Not Started | 01/07/27 | 01/21/27 | 12.5 | 12.5 |
|
173.8 |
RPL07.WP3B.013520 |
RPL07.Conn EF2<>DHB.14 Install (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.14 | Not Started | 01/07/27 | 01/07/27 | 1.2 | 1.2 |
|
128.8 |
RPL07.WP4.012540 |
RPL07.Conn DHB.13.11<>11 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 01/07/27 | 01/11/27 | 3.8 | 3.8 |
|
133.8 |
RPL07.WP4.012560 |
RPL07.Conn DHB.14.15<>15 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Across-Row | Not Started | 01/07/27 | 01/11/27 | 3.8 | 3.8 |
|
133.8 |
GCD.RPL07.5285 |
L3/L4 Finish EY - DHC | EY | Not Started | 01/08/27 | 01/08/27 | 0.0 | 0.0 |
|
238.8 |
RPL07.EY.DHA.01480 |
RPL07.EY.DHA - Install Landscaping | Hardscape and Landscape | Not Started | 01/08/27 | 01/22/27 | 12.5 | 12.5 |
|
298.8 |
RPL07.INT.ENDC.1560 |
RPL07.Interior.End-Corridor - BoW - Hang Drywall | Balance of Walls & Overhead | Not Started | 01/08/27 | 01/19/27 | 8.8 | 8.8 |
|
125.0 |
RPL07.INT.SSB.02400 |
RPL07.Interior.SSB - Final Finishes & Fixtures - Final Clean | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 01/08/27 | 01/13/27 | 5.0 | 5.0 |
|
210.0 |
RPL07.WP3B.014960 |
RPL07.Conn EF2<>DHB.14 Splice (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.14 | Not Started | 01/08/27 | 01/15/27 | 7.5 | 7.5 |
|
128.8 |
RPL07.WP3B.016400 |
RPL07.Conn EF2<>DHB.14 Install (Z-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.14 | Not Started | 01/08/27 | 01/08/27 | 1.2 | 1.2 |
|
128.8 |
RPL07.WP4.012420 |
RPL07.Conn DHB.13.09<>09 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 01/08/27 | 01/08/27 | 1.2 | 1.2 |
|
147.5 |
RPL07.WP4.012440 |
RPL07.Conn DHB.14.13<>13 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Across-Row | Not Started | 01/08/27 | 01/08/27 | 1.2 | 1.2 |
|
147.5 |
RPL07.WP4.013600 |
RPL07.Conn DHA.01.04<>03 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Jumpers | Not Started | 01/08/27 | 01/08/27 | 1.2 | 1.2 |
|
158.8 |
RPL07.WP4.013620 |
RPL07.Conn DHA.02.08<>07 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 01/08/27 | 01/08/27 | 1.2 | 1.2 |
|
158.8 |
GCD.RPL07.5305 |
L3 Finish - DHC | DH | Not Started | 01/11/27 | 01/11/27 | 0.0 | 0.0 |
|
238.8 |
ICM.B7.2510.C |
[SSDCB2] L3/4 Start - DHC | Commissioning | Not Started | 01/11/27 | 01/11/27 | 0.0 | 0.0 |
|
238.8 |
RPL07.CX.DHC.01030 |
RPL07.CX.DHC - L3/L4 - House Power (for electrical) | DHC HOUSE POWER | Not Started | 01/11/27 | 01/25/27 | 12.5 | 12.5 |
|
133.8 |
RPL07.INT.CTRC.06900 |
RPL07.Interior.Center-Corridor - Final Finishes & Fixtures - Casework | Restrooms | Not Started | 01/11/27 | 01/20/27 | 8.8 | 8.8 |
|
36.2 |
RPL07.INT.SSB.01570 |
RPL07.Interior.SSB - Loading Dock and Storage - Electrical L2 Checklist Completion | Loading Dock and Storage | Not Started | 01/11/27 | 01/25/27 | 12.5 | 12.5 |
|
127.5 |
RPL07.CON.WP2.08720 |
RPL07.Conn - GSIDF/DH B1 - WBS Summary | Int. IDF Stick Build - GSIDF7B1 | Not Started | 01/12/27 | 02/04/27 | 21.2 | 21.2 |
|
287.5 |
RPL07.CON.WP2.08740 |
RPL07.Conn - GSIDF/DH B1 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 01/12/27 | 01/19/27 | 6.2 | 6.2 |
|
123.8 |
RPL07.CON.WP4.03200 |
RPL07.Conn WP4 FENW DHA CFD2 Infrastructure | Infrastructure | Not Started | 01/12/27 | 02/09/27 | 25.0 | 25.0 |
|
136.2 |
RPL07.INT.DHA.01340 |
RPL07.Conn DHA - CFD2 - Set Passive Racks for WP#3b (16) | Infrastructure | Not Started | 01/12/27 | 01/14/27 | 3.8 | 3.8 |
|
105.0 |
RPL07.INT.DHA.01540 |
RPL07.Interior.DHA - Control Fault Domain 4 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/12/27 | 02/09/27 | 25.0 | 25.0 |
|
48.8 |
RPL07.INT.DHA.01550 |
RPL07.Interior.DHA - Control Fault Domain 4 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/12/27 | 02/09/27 | 25.0 | 25.0 |
|
55.0 |
RPL07.INT.DHA.01560 |
RPL07.Interior.DHA - Control Fault Domain 4 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/12/27 | 02/09/27 | 25.0 | 25.0 |
|
48.8 |
RPL07.INT.DHA.01620 |
RPL07.Interior.DHA - Control Fault Domain 3 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/12/27 | 02/09/27 | 25.0 | 25.0 |
|
47.5 |
RPL07.INT.DHA.02240 |
RPL07.Interior.DHA - Control Fault Domain 4 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/12/27 | 02/09/27 | 25.0 | 25.0 |
|
48.8 |
RPL07.INT.DHA.03900 |
RPL07.Conn DHA - CFD2 - Set Passive Racks for PON (16) | Infrastructure | Not Started | 01/12/27 | 01/14/27 | 3.8 | 3.8 |
|
126.2 |
RPL07.INT.DHB.01730 |
RPL07.Interior.DHB - Control Fault Domain 4 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/12/27 | 02/09/27 | 25.0 | 25.0 |
|
67.5 |
RPL07.INT.DHB.01760 |
RPL07.Interior.DHB - Control Fault Domain 4 - Install copper from GS.IDF to BMS and EPMS panels (UG from Center IDF) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 01/12/27 | 02/09/27 | 25.0 | 25.0 |
|
48.8 |
RPL07.WP4.012860 |
RPL07.Conn DHB.13.11<>11 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 01/12/27 | 01/12/27 | 1.2 | 1.2 |
|
146.2 |
RPL07.WP4.012880 |
RPL07.Conn DHB.14.15<>15 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Across-Row | Not Started | 01/12/27 | 01/12/27 | 1.2 | 1.2 |
|
146.2 |
RPL07.WP4.012940 |
RPL07.Conn DHB.13.10<>09 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 01/12/27 | 01/15/27 | 5.0 | 5.0 |
|
133.8 |
RPL07.WP4.012960 |
RPL07.Conn DHB.14.14<>13 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Jumpers | Not Started | 01/12/27 | 01/15/27 | 5.0 | 5.0 |
|
133.8 |
GCD.RPL07.2606 |
L3/L4 Start - DHB Rows 09-16 | DH | Not Started | 01/13/27 | 01/13/27 | 0.0 | 0.0 |
|
131.2 |
RPL07.CX.DHA.01220 |
RPL07.CX.DHA - L3/L4 - Remaining Electrical Equipment | DHA ELECTRICAL | Not Started | 01/13/27 | 01/20/27 | 6.2 | 6.2 |
|
137.5 |
RPL07.CX.DHB.01080 |
RPL07.CX.DHB - L3/L4 - Elec. Domain 03/04 | DHB ELECTRICAL | Not Started | 01/13/27 | 01/19/27 | 5.0 | 5.0 |
|
40.0 |
RPL07.CX.DHD.01050 |
RPL07.CX.DHD - L3/L4 - House Power (for mechainical) | DHD HOUSE POWER | Not Started | 01/13/27 | 01/27/27 | 12.5 | 12.5 |
|
135.0 |
RPL07.INT.CTRC.1800 |
RPL07.Interior.Center-Corridor - BoW - Install Door (Verify with Trades before installation) | Balance of Walls & Overhead | Not Started | 01/13/27 | 01/22/27 | 8.8 | 8.8 |
|
68.8 |
RPL07.INT.SSB.01340 |
RPL07.Interior.SSB - BoW - Tape Finish Paint | Balance of Walls and OverHead | Not Started | 01/13/27 | 01/15/27 | 3.8 | 3.8 |
|
77.5 |
RPL07.CX.DHB.01400 |
RPL07.CX.DHB - L3/L4 - Control Fault Domain 03 - TW Flush and Fill | Control Fault Domain 3 | Not Started | 01/14/27 | 01/26/27 | 10.0 | 10.0 |
|
73.8 |
RPL07.EY.ENDC.1950 |
RPL07.EY.DHD.T1 - HAC Prefab prior to install for DH D | Tent 1 | Not Started | 01/14/27 | 01/21/27 | 6.2 | 6.2 |
|
30.0 |
RPL07.INT.DHA.03740 |
RPL07.Interior.DHA - OFE - Control Fault Domain 5 (HAC) | Control Fault Domain 5 | Not Started | 01/14/27 | 02/04/27 | 18.8 | 18.8 |
|
12.5 |
RPL07.INT.ENDC.06900 |
RPL07.Interior.End-Corridor - Final Finishes & Fixtures - Mechanical L2 Checklist Completion | Restrooms | Not Started | 01/14/27 | 01/28/27 | 12.5 | 12.5 |
|
173.8 |
RPL07.INT.SSB.02380 |
RPL07.Interior.SSB - Final Finishes & Fixtures - Final Punch Walk | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 01/14/27 | 01/15/27 | 2.5 | 2.5 |
|
210.0 |
RPL07.INT.SSB.02960 |
RPL07.Interior.SSB - Loading Dock and Storage - Install Flooring | Loading Dock and Storage | Not Started | 01/14/27 | 01/21/27 | 6.2 | 6.2 |
|
131.2 |
RPL07.WP3B.017820 |
RPL07.Conn EF2<>DHB.13 Test Pigtails (384F) P2&3 (LV) | EF2<>DHB.13 | Not Started | 01/14/27 | 01/15/27 | 2.5 | 2.5 |
|
131.2 |
GCD.RPL07.4105 |
[RPL07] TC-C Ready : Production Cabling Start [DHA Rows 09-16] | TC-C Ready: Production Cabling - DHA | Not Started | 01/15/27 | 01/15/27 | 0.0 | 0.0 |
|
305.0 |
RPL07.CON.WP2.13040 |
RPL07.Conn - GSMDF1(South)<>DH A - CFD2 Rack #50 Pull, Install & Patch PON Trunks | MDF1 <> DH A - Rack#50 LV side | Not Started | 01/15/27 | 01/22/27 | 6.2 | 6.2 |
|
126.2 |
RPL07.CON.WP2.14040 |
RPL07.Conn - GSMDF2(North)<>DH A - CFD2 Rack #01 Pull, Install & Test PON Trunks | MDF2 <> DH A - Rack#01 MES side | Not Started | 01/15/27 | 01/20/27 | 3.8 | 3.8 |
|
136.2 |
RPL07.CON.WP3B.02000 |
RPL07.Conn EF1<>DHA.03 - WBS Summary | EF1<>DHA.03 | Not Started | 01/15/27 | 02/01/27 | 13.8 | 13.8 |
|
131.2 |
RPL07.CX.DHA.01100 |
RPL07.CX.DHA - L3/L4 - Control Fault Domain 01 | Control Fault Domain 1 | Not Started | 01/15/27 | 02/22/27 | 31.2 | 31.2 |
|
23.8 |
RPL07.INT.SSB.06440 |
RPL07.Interior.SSB LO #16 - Final Paint | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 01/15/27 | 01/26/27 | 8.8 | 8.8 |
|
67.5 |
RPL07.WP3B.011140 |
RPL07.Conn EF1<>DHA.01 Pull Pigtails (384F) P1&4 (LV) | EF1<>DHA.03 | Not Started | 01/15/27 | 01/19/27 | 2.5 | 2.5 |
|
120.0 |
RPL07.WP4.013140 |
RPL07.Conn DHB.14.14 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 01/15/27 | 01/29/27 | 12.5 | 12.5 |
|
105.0 |
RPL07.WP4.013160 |
RPL07.Conn DHA.03 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 01/15/27 | 01/15/27 | 1.2 | 1.2 |
|
142.5 |
RPL07.WP4.013180 |
RPL07.Conn DHA.04 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 01/15/27 | 01/15/27 | 1.2 | 1.2 |
|
142.5 |
RPL07.WP4.013280 |
RPL07.Conn DHA.03.09 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 01/15/27 | 01/29/27 | 12.5 | 12.5 |
|
105.0 |
RPL07.WP4.013300 |
RPL07.Conn DHA.04.13 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 01/15/27 | 01/29/27 | 12.5 | 12.5 |
|
105.0 |
RPL07.WP4.013560 |
RPL07.Conn DHA.03 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 01/15/27 | 01/15/27 | 1.2 | 1.2 |
|
133.8 |
RPL07.WP4.013580 |
RPL07.Conn DHA.04 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 01/15/27 | 01/15/27 | 1.2 | 1.2 |
|
133.8 |
RPL07.WP4.014600 |
RPL07.Conn DHA.01.03 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 01/15/27 | 01/29/27 | 12.5 | 12.5 |
|
130.0 |
RPL07.WP4.014620 |
RPL07.Conn DHA.02.07 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 01/15/27 | 01/29/27 | 12.5 | 12.5 |
|
130.0 |
RPL07.WP4.014960 |
RPL07.Conn DHB.11.04 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 01/15/27 | 01/29/27 | 12.5 | 12.5 |
|
130.0 |
RPL07.WP4.014980 |
RPL07.Conn DHB.12.08 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 01/15/27 | 01/29/27 | 12.5 | 12.5 |
|
130.0 |
RPL07.WP4.015020 |
RPL07.Conn DHB.13.10 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 01/15/27 | 01/29/27 | 12.5 | 12.5 |
|
105.0 |
RPL07.INT.SSB.01280 |
RPL07.Interior.SSB - BoW - Duct Drops / Trim out | Balance of Walls and OverHead | Not Started | 01/19/27 | 01/25/27 | 6.2 | 6.2 |
|
123.8 |
RPL07.INT.SSB.01360 |
RPL07.Interior.SSB - BoW - Electrical Trim Out | Balance of Walls and OverHead | Not Started | 01/19/27 | 01/27/27 | 8.8 | 8.8 |
|
128.8 |
RPL07.INT.SSB.01380 |
RPL07.Interior.SSB - BoW - Security Trim Out | Balance of Walls and OverHead | Not Started | 01/19/27 | 01/27/27 | 8.8 | 8.8 |
|
128.8 |
RPL07.INT.SSB.01490 |
RPL07.Interior.SSB - BoW - Install Lights (**Work with FTI to coordinate flow map light Install & duration) | Balance of Walls and OverHead | Not Started | 01/19/27 | 02/01/27 | 12.5 | 12.5 |
|
77.5 |
RPL07.INT.SSB.01500 |
RPL07.Interior.SSB - BoW - Install Bathroom Fixtures | Balance of Walls and OverHead | Not Started | 01/19/27 | 01/27/27 | 8.8 | 8.8 |
|
77.5 |
RPL07.INT.SSB.01600 |
RPL07.Interior.SSB - Loading Dock and Storage - Mechanical L2 Checklist Completion | Loading Dock and Storage | Not Started | 01/19/27 | 02/01/27 | 12.5 | 12.5 |
|
127.5 |
RPL07.INT.SSB.01700 |
RPL07.Interior.SSB - BoW - Install Balance Of Refrigerant Line | Balance of Walls and OverHead | Not Started | 01/19/27 | 01/25/27 | 6.2 | 6.2 |
|
123.8 |
RPL07.INT.SSB.01840 |
RPL07.Interior.SSB - Install Split Systems/Humidifiers | OFE/MOFE & CFCI | Not Started | 01/19/27 | 01/25/27 | 6.2 | 6.2 |
|
123.8 |
RPL07.INT.SSB.02180 |
RPL07.Interior.SSB - Final Finishes & Fixtures - Electrical L2 Checklist Completion | Final Finishes & Fixtures (Includes Restrooms, Kitchen, TFW, etc.) | Not Started | 01/19/27 | 02/01/27 | 12.5 | 12.5 |
|
210.0 |
RPL07.INT.SSB.02520 |
RPL07.Interior.SSB - BoW - ACT - Set Wall Angle & Shoot Ceiling Wire | Balance of Walls and OverHead | Not Started | 01/19/27 | 01/27/27 | 8.8 | 8.8 |
|
77.5 |
RPL07.INT.SSBC.01470 |
RPL07.Interior.SSB-Corridor - Mechanical L2 Checklist Completion | Fit out | Not Started | 01/19/27 | 02/01/27 | 12.5 | 12.5 |
|
87.5 |
RPL07.WP3B.017840 |
RPL07.Conn EF2<>DHB.14 Test Pigtails (384F) P2&3 (LV) | EF2<>DHB.14 | Not Started | 01/19/27 | 01/20/27 | 2.5 | 2.5 |
|
128.8 |