Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:16 PM · 5237 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL07.CON.WP4.010760 RPL07.Conn C CFD4 - Deliver & Assemble - PON OFE- Passive In-row Racks, Racks (ORv3Ns, MCRs) & PON Not Started 07/21/27 07/30/27 10.0 10.0
0%
61.2
RPL07.WP4.045000 RPL07.Conn DHC.25.18<>17 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 07/21/27 07/21/27 1.2 1.2
0%
71.2
RPL07.WP4.045020 RPL07.Conn DHC.26.22<>21 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 07/21/27 07/21/27 1.2 1.2
0%
71.2
RPL07.WP4.045040 RPL07.Conn DHD.35.26<>25 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 07/21/27 07/21/27 1.2 1.2
0%
71.2
RPL07.WP4.045060 RPL07.Conn DHD.36.30<>29 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 07/21/27 07/21/27 1.2 1.2
0%
71.2
RPL07.WP4.045240 RPL07.Conn DHC.25 Install (Z-End) Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 07/21/27 07/22/27 2.5 2.5
0%
66.2
RPL07.WP4.045260 RPL07.Conn DHC.26 Install (Z-End) Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 07/21/27 07/22/27 2.5 2.5
0%
66.2
RPL07.WP4.045280 RPL07.Conn DHD.35 Install (Z-End) Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 07/21/27 07/22/27 2.5 2.5
0%
66.2
RPL07.WP4.045300 RPL07.Conn DHD.36 Install (Z-End) Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 07/21/27 07/22/27 2.5 2.5
0%
66.2
ICM.B7.1070 [SSDCB2] FE Network Complete (ENS Handover) [DHA,B] - Contractual FENW Not Started 07/22/27 07/22/27 0.0 0.0
0%
117.5
ICM.B7.1070.ET [SSDCB2] FE Network Complete (ENS Handover) [DHA,B] - Early Target FENW Not Started 07/22/27 07/22/27 0.0 0.0
0%
117.5
ICM.B7.8040.A [SSDCB2] FE Area Complete (ENS Ready) [DHA] - Incentivised (08/05/27) FENW Not Started 07/22/27 07/22/27 0.0 0.0
0%
105.0
ICM.B7.8040.A.ET [SSDCB2] FE Area Complete (ENS Ready) [DHA] - Early Target FENW Not Started 07/22/27 07/22/27 0.0 0.0
0%
12.5
ICM.B7.8050.B [SSDCB2] BE Area Complete (ENS Ready) [DHB] - Incentivised (07/22/27) BENW Not Started 07/22/27 07/22/27 0.0 0.0
0%
142.5
RPL07.Conn.FIM.01580 RPL07.Conn FIM - DH C - Control Fault Domain C.4 DH C Not Started 07/22/27 08/18/27 25.0 25.0
0%
56.2
RPL07.EY.ENDC.01210 RPL07.EY.End - Install Landscaping Hardscape and Landscape Not Started 07/22/27 08/11/27 18.8 18.8
0%
125.0
RPL07.INT.ENDC.5440 RPL07.Interior.EC Ext. Leave Out #19 - Final Clean Exterior Leave Out Wall #19 EC - South for DHA&C HACs Not Started 07/22/27 07/27/27 5.0 5.0
0%
53.8
RPL07.WP4.045320 RPL07.Conn DHC.25.20<>19 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 07/22/27 07/22/27 1.2 1.2
0%
71.2
RPL07.WP4.045340 RPL07.Conn DHC.26.24<>23 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 07/22/27 07/22/27 1.2 1.2
0%
71.2
RPL07.WP4.045360 RPL07.Conn DHD.35.28<>27 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 07/22/27 07/22/27 1.2 1.2
0%
71.2
RPL07.WP4.045380 RPL07.Conn DHD.36.32<>31 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 07/22/27 07/22/27 1.2 1.2
0%
71.2
RPL07.CX.DHA.01250 RPL07.CX.DHA - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - ET DHA DATA HALL LEVEL TESTING Not Started 07/23/27 08/05/27 12.5 12.5
0%
105.0
RPL07.CX.DHA.01600 RPL07.CX.DHA - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - Contractual DHA DATA HALL LEVEL TESTING Not Started 07/23/27 08/05/27 12.5 12.5
0%
130.0
RPL07.INT.ENDC.6020 RPL07.Interior.EC Ext. Leave Out #18 - Final Clean Exterior Leave Out Wall #18 EC - North for DHB&D HACs Not Started 07/23/27 07/28/27 5.0 5.0
0%
52.5
RPL07.PR.DHBA.ACT.20 RPL07.PR.DHB&A FENW Activation - DH B & A DH B&A - Activation, Undraining Not Started 07/23/27 08/05/27 12.5 12.5
0%
117.5
RPL07.WP4.045400 RPL07.Conn DHC.25.17<>17 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 07/23/27 07/23/27 1.2 1.2
0%
71.2
RPL07.WP4.045420 RPL07.Conn DHC.26.21<>21 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 07/23/27 07/23/27 1.2 1.2
0%
71.2
RPL07.WP4.045440 RPL07.Conn DHD.35.25<>25 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 07/23/27 07/23/27 1.2 1.2
0%
71.2
RPL07.WP4.045460 RPL07.Conn DHD.36.29<>29 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 07/23/27 07/23/27 1.2 1.2
0%
71.2
RPL07.WP4.045640 RPL07.Conn DHC.25 Install (Z-End) Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 07/23/27 07/26/27 2.5 2.5
0%
66.2
RPL07.WP4.045660 RPL07.Conn DHC.26 Install (Z-End) Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 07/23/27 07/26/27 2.5 2.5
0%
66.2
RPL07.WP4.045680 RPL07.Conn DHD.35 Install (Z-End) Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 07/23/27 07/26/27 2.5 2.5
0%
66.2
RPL07.WP4.045700 RPL07.Conn DHD.36 Install (Z-End) Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 07/23/27 07/26/27 2.5 2.5
0%
66.2
RPL07.WP4.048500 RPL07.Conn BE ISP DHC.CFD2 (RSL) FTSW > STSW EX384f [Across-Row] Across-Row Not Started 07/23/27 07/27/27 3.8 3.8
0%
131.2
RPL07.WP4.048540 RPL07.Conn BE ISP DHC.CFD3 (RSL) FTSW > STSW EX384f [In-Row] In-Row Not Started 07/23/27 07/27/27 3.8 3.8
0%
131.2
RPL07.WP4.048580 RPL07.Conn BE ISP DHC.CFD4 (RSL) FTSW > STSW - TR288f (DHB NC>DHC Passive Racks) CFD4 (Control Fault Domain C.4; Rows 25-32) Not Started 07/23/27 07/27/27 3.8 3.8
0%
127.5
RPL07.WP4.045720 RPL07.Conn DHC.25.19<>19 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 07/26/27 07/26/27 1.2 1.2
0%
71.2
RPL07.WP4.045740 RPL07.Conn DHC.26.23<>23 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 07/26/27 07/26/27 1.2 1.2
0%
71.2
RPL07.WP4.045760 RPL07.Conn DHD.35.27<>27 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 07/26/27 07/26/27 1.2 1.2
0%
71.2
RPL07.WP4.045780 RPL07.Conn DHD.36.31<>31 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 07/26/27 07/26/27 1.2 1.2
0%
71.2
RPL07.WP4.045960 RPL07.Conn DHC.25 Install (Z-End) Trunk (384F) [RSW<>FSW] Trunks Not Started 07/27/27 07/30/27 5.0 5.0
0%
66.2
RPL07.WP4.045980 RPL07.Conn DHC.26 Install (Z-End) Trunk (384F) [RSW<>FSW] Trunks Not Started 07/27/27 07/30/27 5.0 5.0
0%
66.2
RPL07.WP4.046000 RPL07.Conn DHD.35 Install (Z-End) Trunk (384F) [RSW<>FSW] Trunks Not Started 07/27/27 07/30/27 5.0 5.0
0%
66.2
RPL07.WP4.046020 RPL07.Conn DHD.36 Install (Z-End) Trunk (384F) [RSW<>FSW] Trunks Not Started 07/27/27 07/30/27 5.0 5.0
0%
66.2
RPL07.INT.ENDC.5460 RPL07.Interior.EC Ext. Leave Out #19 - Final Punch Walk Exterior Leave Out Wall #19 EC - South for DHA&C HACs Not Started 07/28/27 07/29/27 2.5 2.5
0%
53.8
RPL07.PR.DHC.BE.0010 RPL07.PR.DHC BENW Data Hall C - Provisioning - WBS Summary BENW Not Started 07/28/27 09/30/27 57.5 57.5
0%
56.2
RPL07.PR.DHC.BE.0015 RPL07.PR.DHC BENW PZ1 (Row 01-16) - ENS Ready for PZ1 BENW Not Started 07/28/27 07/28/27 0.0 0.0
0%
76.2
RPL07.PR.DHC.BE.0020 RPL07.PR.DHC BENW PZ3 (Row 01-16) - Provisioning, Auditing, Issue Remediation (FSW, SSW) BENW Not Started 07/28/27 08/31/27 31.2 31.2
0%
76.2
RPL07.PR.DHC.FE.0010 RPL07.PR.DHC FENW Data Hall C - Provisioning - WBS Summary FENW Not Started 07/28/27 10/06/27 62.5 62.5
0%
51.2
RPL07.PR.DHC.FE.0015 RPL07.PR.DHC FENW PZ1 (Row 01-16) - ENS Ready for PZ1 FENW Not Started 07/28/27 07/28/27 0.0 0.0
0%
76.2
RPL07.PR.DHC.FE.0020 RPL07.PR.DHC FENW PZ3 (Row 01-16) - Provisioning, Auditing, Issue Remediation (FSW, SSW) FENW Not Started 07/28/27 08/31/27 31.2 31.2
0%
76.2
RPL07.WP4.048560 RPL07.Conn BE ISP DHC.CFD3 (RSL) FTSW > STSW EX384f [Across-Row] Across-Row Not Started 07/28/27 07/30/27 3.8 3.8
0%
131.2
RPL07.WP4.048640 RPL07.Conn BE ISP DHC.CFD4 Pull/Splice/Test ESL Bag Pigtails 384f CFD4 (Control Fault Domain C.4; Rows 25-32) Not Started 07/28/27 07/30/27 3.8 3.8
0%
127.5
RPL07.INT.ENDC.6040 RPL07.Interior.EC Ext. Leave Out #18 - Final Punch Walk Exterior Leave Out Wall #18 EC - North for DHB&D HACs Not Started 07/29/27 07/30/27 2.5 2.5
0%
52.5
GCD.RPL07.5465 L3/L4 Finish - DHC Rows 17-24 DH Not Started 08/02/27 08/02/27 0.0 0.0
0%
62.5
RPL07.WP4.046200 RPL07.Conn DHC.27.26<>25 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 08/02/27 08/02/27 1.2 1.2
0%
61.2
RPL07.WP4.046220 RPL07.Conn DHC.28.30<>29 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 08/02/27 08/02/27 1.2 1.2
0%
61.2
RPL07.WP4.046320 RPL07.Conn DHC.27 Install (Z-End) Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 08/02/27 08/03/27 2.5 2.5
0%
56.2
RPL07.WP4.046340 RPL07.Conn DHC.28 Install (Z-End) Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 08/02/27 08/03/27 2.5 2.5
0%
56.2
RPL07.WP4.048600 RPL07.Conn BE ISP DHC.CFD4 (RSL) FTSW > STSW EX384f [In-Row] In-Row Not Started 08/02/27 08/04/27 3.8 3.8
0%
127.5
RPL07.CX.DHC.01150 RPL07.CX.DHC - L3/L4 - Control Fault Domain 04 Control Fault Domain 4 Not Started 08/03/27 08/24/27 20.0 20.0
0%
42.5
RPL07.WP4.046360 RPL07.Conn DHC.27.28<>27 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 08/03/27 08/03/27 1.2 1.2
0%
61.2
RPL07.WP4.046380 RPL07.Conn DHC.28.32<>31 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 08/03/27 08/03/27 1.2 1.2
0%
61.2
RPL07.WP4.046400 RPL07.Conn DHC.27.25<>25 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 08/04/27 08/04/27 1.2 1.2
0%
61.2
RPL07.WP4.046420 RPL07.Conn DHC.28.29<>29 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 08/04/27 08/04/27 1.2 1.2
0%
61.2
RPL07.WP4.046520 RPL07.Conn DHC.27 Install (Z-End) Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 08/04/27 08/05/27 2.5 2.5
0%
56.2
RPL07.WP4.046540 RPL07.Conn DHC.28 Install (Z-End) Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 08/04/27 08/05/27 2.5 2.5
0%
56.2
ICM.B7.1070.ET20 [SSDCB2] BE Network Complete (ENS Handover) [DHA,B] - Early Target BENW Not Started 08/05/27 08/05/27 0.0 0.0
0%
105.0
ICM.B7.1075 [SSDCB2] Partial Occupancy (FACOPS Handover) - DHA&B - Contractual Contractual Not Started 08/05/27 08/05/27 0.0 0.0
0%
105.0
ICM.B7.1075.ET [SSDCB2] Partial Occupancy (FACOPS Handover) - DHA&B - Early Target Construction Not Started 08/05/27 08/05/27 0.0 0.0
0%
105.0
ICM.B7.3375 [SSDCB2] BE Network Complete (ENS Handover) [DHA,B] - Contractual BENW Not Started 08/05/27 08/05/27 0.0 0.0
0%
105.0
ICM.B7.8050.A [SSDCB2] BE Area Complete (ENS Ready) [DHA] - Incentivised (08/05/27) BENW Not Started 08/05/27 08/05/27 0.0 0.0
0%
130.0
RPL07.WP4.046560 RPL07.Conn DHC.27.27<>27 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 08/05/27 08/05/27 1.2 1.2
0%
61.2
RPL07.WP4.046580 RPL07.Conn DHC.28.31<>31 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 08/05/27 08/05/27 1.2 1.2
0%
61.2
RPL07.WP4.048620 RPL07.Conn BE ISP DHC.CFD4 (RSL) FTSW > STSW EX384f [Across-Row] Across-Row Not Started 08/05/27 08/09/27 3.8 3.8
0%
127.5
RPL07.PR.DHBA.ACT.40 RPL07.PR.DHB&A FENW Undraining - DH B & A DH B&A - Activation, Undraining Not Started 08/06/27 08/19/27 12.5 12.5
0%
117.5
RPL07.PR.DHBA.ACT.60 RPL07.PR.DHB&A BENW Activation - DH B & A DH B&A - Activation, Undraining Not Started 08/06/27 08/19/27 12.5 12.5
0%
105.0
RPL07.WP4.046680 RPL07.Conn DHC.27 Install (Z-End) Trunk (384F) [RSW<>FSW] Trunks Not Started 08/06/27 08/11/27 5.0 5.0
0%
56.2
RPL07.WP4.046700 RPL07.Conn DHC.28 Install (Z-End) Trunk (384F) [RSW<>FSW] Trunks Not Started 08/06/27 08/11/27 5.0 5.0
0%
56.2
ICM.B7.8050.D.ET [SSDCB2] BE Area Complete (ENS Ready) [DHD] - Early Target BENW Not Started 08/09/27 08/09/27 0.0 0.0
0%
82.5
RPL07.PR.DHD.BE.0035 RPL07.PR.DHD BENW PZ2 (Row 17-32) - ENS Ready for PZ2 BENW Not Started 08/09/27 08/09/27 0.0 0.0
0%
66.2
RPL07.PR.DHD.BE.0040 RPL07.PR.DHD BENW PZ2 (Row 17-32) - Provisioning, Auditing, Issue Remediation (FSW, SSW) BENW Not Started 08/09/27 09/20/27 37.5 37.5
0%
66.2
RPL07.WA.DHD.01020 RPL07.WA - Weather Allowance - OFE to BE.AC - DHD Weather Allowance Not Started 08/09/27 08/21/27 16.2 16.2
0%
173.8
GCD.RPL07.5125 L3/L4 Finish - DHD Rows 25-32 DH Not Started 08/10/27 08/10/27 0.0 0.0
0%
46.2
RPL07.CX.DHD.01220 RPL07.CX.DHD - L4 - Data Hall Level Testing DHD DATA HALL LEVEL TESTING Not Started 08/11/27 08/24/27 12.5 12.5
0%
46.2
RPL07.PR.DHD.FE.0035 RPL07.PR.DHD FENW PZ2 (Row 17-32) - ENS Ready for PZ2 FENW Not Started 08/11/27 08/11/27 0.0 0.0
0%
63.8
RPL07.PR.DHD.FE.0040 RPL07.PR.DHD FENW PZ2 (Row 17-32) - Provisioning, Auditing, Issue Remediation (FSW, SSW) FENW Not Started 08/11/27 09/22/27 37.5 37.5
0%
63.8
RPL.07.D.74090.XG Laydown Area 13 - RPL07 handover Give Milestones (XREFs) Not Started 08/18/27 08/18/27 0.0 0.0
0%
118.8
ICM.B7.8050.C.ET [SSDCB2] BE Area Complete (ENS Ready) [DHC] - Early Target BENW Not Started 08/19/27 08/19/27 0.0 0.0
0%
83.8
RPL07.PR.DHC.BE.0035 RPL07.PR.DHC BENW PZ2 (Row 17-32) - ENS Ready for PZ2 BENW Not Started 08/19/27 08/19/27 0.0 0.0
0%
56.2
RPL07.PR.DHC.BE.0040 RPL07.PR.DHC BENW PZ2 (Row 17-32) - Provisioning, Auditing, Issue Remediation (FSW, SSW) BENW Not Started 08/19/27 09/30/27 37.5 37.5
0%
56.2
RPL07.WA.DHC.01020 RPL07.WA - Weather Allowance - OFE to BE.AC - DHC Weather Allowance Not Started 08/19/27 08/31/27 16.2 16.2
0%
161.2
RPL07.PR.DHBA.ACT.80 RPL07.PR.DHB&A BENW Undraining - DH B & A DH B&A - Activation, Undraining Not Started 08/20/27 09/02/27 12.5 12.5
0%
105.0
RPL07.PR.DHD.BE.0025 RPL07.PR.DHD BENW PZ1 (Row 01-16) - Remaining Provisioning with PZ2 (FSW, SSW) BENW Not Started 08/20/27 08/26/27 6.2 6.2
0%
86.2
RPL07.PR.DHD.FE.0025 RPL07.PR.DHD FENW PZ1 (Row 01-16) - Remaining Provisioning with PZ2 (FSW, SSW) FENW Not Started 08/20/27 08/26/27 6.2 6.2
0%
86.2
GCD.RPL07.5485 L3/L4 Finish - DHC Rows 25-32 DH Not Started 08/24/27 08/24/27 0.0 0.0
0%
42.5
RPL07.CX.DHC.01230 RPL07.CX.DHC - L4 - Data Hall Level Testing DHC DATA HALL LEVEL TESTING Not Started 08/25/27 09/08/27 12.5 12.5
0%
42.5
RPL07.CX.DHD.01230 RPL07.CX.DHD - L5 IST [Includes Issues Resolution, Migration & FUL] DHD DATA HALL LEVEL TESTING Not Started 08/25/27 09/03/27 10.0 10.0
0%
46.2
RPL07.PR.DHC.FE.0035 RPL07.PR.DHC FENW PZ2 (Row 17-32) - ENS Ready for PZ2 FENW Not Started 08/25/27 08/25/27 0.0 0.0
0%
51.2
RPL07.PR.DHC.FE.0040 RPL07.PR.DHC FENW PZ2 (Row 17-32) - Provisioning, Auditing, Issue Remediation (FSW, SSW) FENW Not Started 08/25/27 10/06/27 37.5 37.5
0%
51.2