Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
37
Activities Shown
0
Completed
0
In Progress
6
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.CX.ENDC.01020 |
RPL07.CX.END COR - L4 | End Corridor | Not Started | 08/26/27 | 09/09/27 | 12.5 | 12.5 |
|
30.0 |
RPL07.PR.DHC.BE.0025 |
RPL07.PR.DHC BENW PZ1 (Row 01-16) - Remaining Provisioning with PZ2 (FSW, SSW) | BENW | Not Started | 09/01/27 | 09/08/27 | 6.2 | 6.2 |
|
76.2 |
RPL07.PR.DHC.FE.0025 |
RPL07.PR.DHC FENW PZ1 (Row 01-16) - Remaining Provisioning with PZ2 (FSW, SSW) | FENW | Not Started | 09/01/27 | 09/08/27 | 6.2 | 6.2 |
|
76.2 |
GCD.RPL07.4905 |
IST Finish - DHD | DH | Not Started | 09/07/27 | 09/07/27 | 0.0 | 0.0 |
|
46.2 |
ICM.B7.2710.D |
[SSDCB2] IST Start - DHD | Commissioning | Not Started | 09/07/27 | 09/07/27 | 0.0 | 0.0 |
|
46.2 |
ICM.B7.2710.C |
[SSDCB2] IST Start - DHC | Commissioning | Not Started | 09/09/27 | 09/09/27 | 0.0 | 0.0 |
|
52.5 |
RPL07.CX.DHC.01240 |
RPL07.CX.DHC - L5 IST [Includes Issues Resolution, Migration & FUL] | DHC DATA HALL LEVEL TESTING | Not Started | 09/09/27 | 09/20/27 | 10.0 | 10.0 |
|
42.5 |
RPL07.CX.ENDC.01030 |
RPL07.CX.END COR - IST | End Corridor | Not Started | 09/10/27 | 09/23/27 | 12.5 | 12.5 |
|
30.0 |
GCD.RPL07.5265 |
IST Finish - DHC | DH | Not Started | 09/20/27 | 09/20/27 | 0.0 | 0.0 |
|
42.5 |
RPL07.WA.DHC.01000 |
RPL07.WA - Weather Allowance - OFE to FE.AC - DHC | Weather Allowance | Not Started | 09/24/27 | 10/06/27 | 16.2 | 16.2 |
|
55.0 |
RPL07.WA.DHD.01000 |
RPL07.WA - Weather Allowance - OFE to FE.AC - DHD | Weather Allowance | Not Started | 09/24/27 | 10/06/27 | 16.2 | 16.2 |
|
42.5 |
ICM.B7.1080 |
[SSDCB2] FE Network Complete (ENS Handover) [DHC,D] - Contractual | FENW | Not Started | 10/06/27 | 10/06/27 | 0.0 | 0.0 |
|
51.2 |
ICM.B7.8040.C.ET |
[SSDCB2] FE Area Complete (ENS Ready) [DHC] - Early Target | FENW | Not Started | 10/06/27 | 10/06/27 | 0.0 | 0.0 |
|
38.8 |
ICM.B7.8040.D.ET |
[SSDCB2] FE Area Complete (ENS Ready) [DHD] - Early Target | FENW | Not Started | 10/06/27 | 10/06/27 | 0.0 | 0.0 |
|
30.0 |
RPL07.CX.DHC.01250 |
RPL07.CX.DHC - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - ET | DHC DATA HALL LEVEL TESTING | Not Started | 10/07/27 | 10/20/27 | 12.5 | 12.5 |
|
38.8 |
RPL07.CX.DHD.01250 |
RPL07.CX.DHD - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - ET | DHD DATA HALL LEVEL TESTING | Not Started | 10/07/27 | 10/20/27 | 12.5 | 12.5 |
|
38.8 |
ICM.B7.8040.D |
[SSDCB2] FE Area Complete (ENS Ready) [DHD] - Incentivised (11/09/27) | FENW | Not Started | 10/12/27 | 10/12/27 | 0.0 | 0.0 |
|
46.2 |
RPL07.CX.DHD.01600 |
RPL07.CX.DHD - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - Contractual | DHD DATA HALL LEVEL TESTING | Not Started | 10/13/27 | 10/26/27 | 12.5 | 12.5 |
|
58.8 |
ICM.B7.1080.ET |
[SSDCB2] FE Network Complete (ENS Handover) [DHC,D] - Early Target | FENW | Not Started | 10/20/27 | 10/20/27 | 0.0 | 0.0 |
|
38.8 |
ICM.B7.1080.ET20 |
[SSDCB2] BE Network Complete (ENS Handover) [DHC,D] - Early Target | BENW | Not Started | 10/20/27 | 10/20/27 | 0.0 | 0.0 |
|
38.8 |
ICM.B7.1110.ET |
[SSDCB2] Partial Occupancy (FACOPS Handover) - DHC&D - Early Target | Construction | Not Started | 10/20/27 | 10/20/27 | 0.0 | 0.0 |
|
38.8 |
RPL07.PR.DHDC.ACT.20 |
RPL07.PR.DHD&C FENW Activation - DH D & C | DH C&D - Activation, Undraining | Not Started | 10/21/27 | 11/03/27 | 12.5 | 12.5 |
|
38.8 |
RPL07.SC.020020 |
RPL07 Punch List for SC - Early Target | Punch List | Not Started | 10/21/27 | 11/03/27 | 12.5 | 12.5 |
|
51.2 |
ICM.B7.8040.C |
[SSDCB2] FE Area Complete (ENS Ready) [DHC] - Incentivised (11/23/27) | FENW | Not Started | 10/26/27 | 10/26/27 | 0.0 | 0.0 |
|
33.8 |
RPL07.CX.DHC.01600 |
RPL07.CX.DHC - Punch List Remediation, Site Acceptance, and AHJ Approval of TCO - Contractual | DHC DATA HALL LEVEL TESTING | Not Started | 10/27/27 | 11/09/27 | 12.5 | 12.5 |
|
46.2 |
ICM.G.9000.2.ET |
RPL07 Substantial Completion - Early Target | IMS P0 Milestones | Not Started | 11/03/27 | 11/03/27 | 0.0 | 0.0 |
|
51.2 |
RPL07.PR.DHDC.ACT.40 |
RPL07.PR.DHD&C FENW Undraining - DH D & C | DH C&D - Activation, Undraining | Not Started | 11/04/27 | 11/18/27 | 12.5 | 12.5 |
|
38.8 |
ICM.B7.8050.D |
[SSDCB2] BE Area Complete (ENS Ready) [DHD] - Incentivised (11/09/27) | BENW | Not Started | 11/09/27 | 11/09/27 | 0.0 | 0.0 |
|
46.2 |
ICM.B7.8050.C |
[SSDCB2] BE Area Complete (ENS Ready) [DHC] - Incentivised (11/23/27) | BENW | Not Started | 11/23/27 | 11/23/27 | 0.0 | 0.0 |
|
35.0 |
ICM.B7.1110 |
[SSDCB2] Partial Occupancy (FACOPS Handover) - DHC&D - Contractual | Contractual | Not Started | 12/07/27 | 12/07/27 | 0.0 | 0.0 |
|
0.0 |
ICM.B7.3395 |
[SSDCB2] BE Network Complete (ENS Handover) [DHC,D] - Contractual | BENW | Not Started | 12/07/27 | 12/07/27 | 0.0 | 0.0 |
|
0.0 |
RPL07.PR.DHDC.ACT.60 |
RPL07.PR.DHD&C BENW Activation - DH D & C | DH C&D - Activation, Undraining | Not Started | 12/08/27 | 12/21/27 | 12.5 | 12.5 |
|
0.0 |
RPL07.SC.020040 |
RPL07 Punch List for SC - Contractual | Punch List | Not Started | 12/08/27 | 12/21/27 | 12.5 | 12.5 |
|
12.5 |
ICM.G.9000.2 |
RPL07 Substantial Completion - Contractual | IMS P0 Milestones | Not Started | 12/21/27 | 12/21/27 | 0.0 | 0.0 |
|
12.5 |
RPL07.PR.DHDC.ACT.80 |
RPL07.PR.DHD&C BENW Undraining - DH D & C | DH C&D - Activation, Undraining | Not Started | 12/22/27 | 01/07/28 | 12.5 | 12.5 |
|
0.0 |
RPL.07.D.N6240.XG |
RPL07 Activation Complete for 1st GW Crew Flow | Internal Milestones (XREFs) | Not Started | 01/07/28 | 01/07/28 | 0.0 | 0.0 |
|
0.0 |
RPL07.SUCC |
SUCC | Obsolete | Not Started | 01/07/28 | 01/07/28 | 0.0 | 0.0 |
|
0.0 |