Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
93
Completed
6
In Progress
93
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
PRE.MIR.1100 |
Roofing SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 10/30/25 | 11/11/25 | 12.5 | 0.0 |
|
0.0 |
PRE.TPBD.1060 |
Steel SA Package | Trade Partner Bid Development | Complete | 10/30/25 | 10/30/25 | 12.5 | 0.0 |
|
0.0 |
PRE.MIR.1040 |
Steel SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 10/31/25 | 11/14/25 | 12.5 | 0.0 |
|
0.0 |
RPL07.CFCI.6210 |
RPL07 - SOG Mock-up | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 10/31/25 | 10/31/25 | 6.2 | 0.0 |
|
0.0 |
RPL07.VDC.1140 |
T1 (Center EF to End Corridor) - BIM Model & Coordination | TIER 1 - Center of EF to End Corridor | Complete | 11/03/25 | 01/23/26 | 17.5 | 0.0 |
|
0.0 |
PRE.TPBD.1040 |
Turnkey Concrete (Foundations Only) - Submit for Meta Review | Trade Partner Bid Development | Complete | 11/06/25 | 11/06/25 | 1.2 | 0.0 |
|
0.0 |
PRE.MIR.1060 |
Turnkey Concrete SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 11/07/25 | 11/18/25 | 12.5 | 0.0 |
|
0.0 |
RPL07.VDC.1100 |
T1 (SSB to Center EF) - BIM Model & Coordination | TIER 1 - SSB to Center of EF | Complete | 11/17/25 | 01/23/26 | 17.5 | 0.0 |
|
0.0 |
RPL07.VDC.1180 |
T2-4 (mCUP Yard / Ext.) - BIM Model & Coordination | TIER 2 - 4 - mCUP Yard / Exterior | Complete | 11/17/25 | 01/21/26 | 15.0 | 0.0 |
|
0.0 |
RPL.07.D.73910.XG |
Production Cabling Start - SS-1 Entry to SS-1 DH-A - Obsolete | Obsolete | Not Started | 11/24/25 | 11/24/25 | 0.0 | 0.0 |
|
644.0 |
RPL07.CFCI.3660 |
RPL07 - Submittals Prep & Submit for Review - Strut | (CFCI) Div. 05 - Slotted Channel Framing (Strut) | Complete | 12/04/25 | 01/06/26 | 25.0 | 0.0 |
|
0.0 |
PRE.TPBD.1180 |
Waterproofing / Caulking / Expansion Joints - Submit for Meta Review | Trade Partner Bid Development | Complete | 12/11/25 | 12/12/25 | 37.5 | 0.0 |
|
0.0 |
PRE.MIR.1160 |
Waterproofing / Caulking / Expansion Joints SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 12/12/25 | 01/07/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.VDC.1080 |
T0 (mCUP Yard/Ext.) - Prepare & Submit BIM Shops | TIER 0 - mCUP Yard / Exterior | Complete | 12/15/25 | 03/16/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.VDC.1360 |
T2-4 (SSB) - BIM Model & Coordination | TIER 2 - 4 - SSB | Complete | 12/15/25 | 03/27/26 | 22.5 | 0.0 |
|
0.0 |
PRE.TPA.1120 |
Fire Suppression - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 12/16/25 | 12/16/25 | 10.0 | 0.0 |
|
0.0 |
PRE.FA.1000 |
Electrical - LOI Issued to Start Coordination | Trade Partner Final Agreement | Complete | 12/22/25 | 12/22/25 | 10.0 | 0.0 |
|
0.0 |
PRE.FA.1100 |
Mechanical / Plumbing - Final Agreement | Trade Partner Final Agreement | Complete | 12/22/25 | 12/22/25 | 0.0 | 0.0 |
|
0.0 |
PRE.FA.1120 |
Fire Suppression - Final Agreement | Trade Partner Final Agreement | Complete | 12/22/25 | 12/22/25 | 0.0 | 0.0 |
|
0.0 |
RPL07.CFCI.6220 |
RPL07 - Submittals Prep & Submit for Review - AHUs | (CFCI) Div. 23 - Air Handler Units (AHUs) | Complete | 12/29/25 | 01/08/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.VDC.1120 |
T0 (Bldg07) - Prepare & Submit BIM Shops | TIER 0 - Building 07 | Complete | 12/29/25 | 03/16/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CFCI.6040 |
Submittal Review & Approval - Technical Water (Assume HDPE Pipe) | (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) | Complete | 12/30/25 | 01/22/26 | 18.8 | 0.0 |
|
0.0 |
RPL07.CFCI.3040 |
RPL07 - Submittals Prep & Submit for Review - Structural Steel (Joists) | (CFCI) Div. 05 - Structural Steel (Joists) | Complete | 01/05/26 | 02/04/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.5460 |
RPL07 - Submittals Prep & Submit for Review - Foundation Struc. Conc. (Rebar) | (CFCI) Div. 03 - (Foundation) Struc. Concrete | Complete | 01/05/26 | 01/05/26 | 18.8 | 0.0 |
|
0.0 |
RPL07.CFCI.6540 |
RPL07 - (DBC) Submittals Prep & Submit for Review - IWP | Exterior Metal Panels | Complete | 01/05/26 | 01/09/26 | 1.2 | 0.0 |
|
0.0 |
PRE.TPA.1080 |
Steel - Trade Partner Process Mill Order | DPR issue Trade Parter Agreements | Complete | 01/06/26 | 01/15/26 | 10.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3020 |
RPL07 - Submittals Prep & Submit for Review - Structural Steel | (CFCI) Div. 05 - Structural Steel | Complete | 01/06/26 | 02/04/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.5470 |
RPL07 - Submittals Review & Approval - Foundation Struc. Conc. (Rebar) | (CFCI) Div. 03 - (Foundation) Struc. Concrete | Complete | 01/06/26 | 02/05/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CFCI.5210 |
RPL07 - Submittals Review & Approval - Strut | (CFCI) Div. 05 - Slotted Channel Framing (Strut) | Complete | 01/07/26 | 01/28/26 | 18.8 | 0.0 |
|
0.0 |
PRE.BNS.1380 |
GMP Review and Final Submission (fGMP) * Obsolete | Obsolete | Complete | 01/09/26 | 01/09/26 | 18.8 | 0.0 |
|
0.0 |
PRE.BNS.1400 |
GMP Review by Legal (fGMP) * Obsolete | Obsolete | Complete | 01/09/26 | 01/09/26 | 6.2 | 0.0 |
|
0.0 |
PRE.BNS.1420 |
GMP Approved by Meta Legal (fGMP) * Obsolete | Obsolete | Complete | 01/09/26 | 01/09/26 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1440 |
fGMP Issuance * Obsolete | Obsolete | Complete | 01/09/26 | 01/09/26 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1460 |
fGMP Review Cycle * Obsolete | Obsolete | Complete | 01/09/26 | 01/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL.GF.D.N7210.XG |
Circut Audit Start RPL07 DHB/A *OBSOLETE | Obsolete | Complete | 01/09/26 | 01/09/26 | 0.0 | 0.0 |
|
0.0 |
RPL.GF.D.N7220.XG |
Circut Audit Start RPL07 DHD/C *OBSOLETE | Obsolete | Complete | 01/09/26 | 01/09/26 | 0.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3650 |
RPL07 - Submittals Prep & Submit for Review - Cold Formed Metal Framing | (CFCI) Div. 05 - Cold Formed Metal Framing | Complete | 01/09/26 | 01/30/26 | 18.8 | 0.0 |
|
0.0 |
RPL07.CFCI.5650 |
RPL07 - Submittals Prep & Submit for Review - SOG/SOMD/Pads Struc. Conc. (Rebar) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 01/09/26 | 02/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.CFCI.6230 |
RPL07 - Submittals Review & Approval - AHUs | (CFCI) Div. 23 - Air Handler Units (AHUs) | Complete | 01/09/26 | 01/22/26 | 11.2 | 0.0 |
|
0.0 |
RPL07.CON.WP3B.01780 |
RPL07.Connectivity.WP3B Pull/Install/Test Universal Fabric EF21 (North) <> DHB.10 P1&4 (LVSA) - **OBSOLETE** | Obsolete | Complete | 01/09/26 | 01/09/26 | 5.0 | 0.0 |
|
0.0 |
PRE.TPA.1000 |
Electrical - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 01/12/26 | 01/12/26 | 10.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3700 |
RPL07 - Submittals Prep & Submit for Review - Below Grade Waterproofing (SPW - Div 07) | Waterproofing | Complete | 01/12/26 | 01/30/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.6560 |
RPL07 - (DBC) Submittals Review & Approval - IWP | Exterior Metal Panels | Complete | 01/12/26 | 01/23/26 | 12.5 | 0.0 |
|
0.0 |
PRE.TPA.1140 |
Steel Mill Order Placed | DPR issue Trade Parter Agreements | Complete | 01/15/26 | 01/15/26 | 0.0 | 0.0 |
|
0.0 |
RPL07.CFCI.6240 |
RPL07 - Fabricate / Deliver - AHUs (EY.SSBC, EY.DHA) | (CFCI) Div. 23 - Air Handler Units (AHUs) | Active | 01/16/26 | 06/15/26 | 86.2 | 56.2 |
|
125.0 |
RPL07.MR.1020 |
RPL07.MR - Trailer Complete Ready for Move-In **(Update Description & Date) | Make Ready | Complete | 01/16/26 | 01/16/26 | 0.0 | 0.0 |
|
0.0 |
RPL07.MR.1160 |
RPL07.MR - Trailer Setup & Tie-Ins | Make Ready | Complete | 01/16/26 | 01/16/26 | 28.8 | 0.0 |
|
0.0 |
RPL07.MR.1220 |
RPL07.MR - Parking Areas Buildout | Make Ready | Complete | 01/16/26 | 01/16/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.CFCI.4310 |
RPL07 - Fabricate / Deliver - CMU - Storm Shelter | (CFCI) Div. 04 - Concrete Masonry Units | Complete | 01/19/26 | 03/24/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.CFCI.6140 |
RPL07 - Submittals Prep & Submit for Review - CMU - Storm Shelter | (CFCI) Div. 04 - Concrete Masonry Units | Complete | 01/19/26 | 02/20/26 | 18.8 | 0.0 |
|
0.0 |
PRE.FA.1080 |
Steel - Final Agreement | Trade Partner Final Agreement | Complete | 01/20/26 | 01/20/26 | 0.0 | 0.0 |
|
0.0 |
PRE.TPA.1060 |
Steel - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 01/20/26 | 01/20/26 | 10.0 | 0.0 |
|
0.0 |
RPL.07.D.70000.XR |
External Tie from RPL06 - Bldg Concrete Foundations Crew Flow (RPL06.SUB.DHCD.01030) | Internal Milestones (XREFs) | Complete | 01/20/26 | 01/20/26 | 0.0 | 0.0 |
|
0.0 |
RPL07.CFCI.6050 |
Submittals Review & Approval - Technical Water (Assume HDPE Pipe) | (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) | Complete | 01/23/26 | 02/20/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CFCI.6060 |
Fabricate / Deliver - Technical Water (Assume HDPE Pipe) | (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) | Complete | 01/23/26 | 03/20/26 | 50.0 | 0.0 |
|
0.0 |
RPL07.CFCI.6920 |
RPL07 - Fabricate / Deliver - AHUs (EY.EC) | (CFCI) Div. 23 - Air Handler Units (AHUs) | Active | 01/23/26 | 05/07/27 | 355.0 | 336.2 |
|
41.2 |
RPL07.CFCI.6580 |
RPL07 - (DBC) Fabricate / Deliver - IWP | Exterior Metal Panels | Active | 01/26/26 | 05/12/26 | 43.8 | 27.5 |
|
36.2 |
RPL07.VDC.1240 |
T1 (SSB to Center EF) - Prepare & Submit BIM Shops (ext IMP shops by 1/9/26) | TIER 1 - SSB to Center of EF | Complete | 01/26/26 | 02/13/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.VDC.1280 |
T1 (Center EF to End Corridor) - Prepare & Submit BIM Shops | TIER 1 - Center of EF to End Corridor | Complete | 01/26/26 | 02/13/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CFCI.3680 |
RPL07 - Submittals Prep & Submit for Review - FSC -Rough Carpentry (In Wall Backing / Blocking) | Rough Carpentry - FSC Wood | Complete | 01/28/26 | 02/25/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.5340 |
RPL07 - Fabricate / Deliver - Strut | (CFCI) Div. 05 - Slotted Channel Framing (Strut) | Complete | 01/29/26 | 03/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3810 |
RPL07 - Submittals Review & Approval - Exterior Louvers (w Ext Metal Panel Trade) | Fixed Louvers | Complete | 02/02/26 | 02/12/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CFCI.4340 |
RPL07 - Submittals Review & Approval - Below Grade Waterproofing | Waterproofing | Complete | 02/02/26 | 02/18/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CFCI.4530 |
RPL07 - Submittals Review & Approval - Cold Formed Metal Framing | (CFCI) Div. 05 - Cold Formed Metal Framing | Complete | 02/02/26 | 02/18/26 | 12.5 | 0.0 |
|
0.0 |
PRE.TPA.1160 |
Roofing - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 02/03/26 | 02/05/26 | 10.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3930 |
RPL07 - Submittals Review & Approval - Structural Steel (Joists) | (CFCI) Div. 05 - Structural Steel (Joists) | Complete | 02/04/26 | 02/12/26 | 18.8 | 0.0 |
|
0.0 |
PRE.FA.1140 |
Roofing - Final Agreement | Trade Partner Final Agreement | Complete | 02/05/26 | 02/05/26 | 0.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3420 |
RPL07 - Review for Approval - Structural Steel | (CFCI) Div. 05 - Structural Steel | Complete | 02/05/26 | 02/13/26 | 17.5 | 0.0 |
|
0.0 |
PRE.FA.1020 |
Electrical - Final Agreement | Trade Partner Final Agreement | Complete | 02/09/26 | 02/09/26 | 0.0 | 0.0 |
|
0.0 |
PRE.TPA.1020 |
Concrete - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 02/09/26 | 02/26/26 | 10.0 | 0.0 |
|
0.0 |
PRE.TPA.1200 |
Waterproofing / Caulking / Expansion Joints - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 02/09/26 | 03/23/26 | 10.0 | 0.0 |
|
0.0 |
RPL07.CFCI.4520 |
RPL07 - SSB - Deliver - Anchor Bolts | (CFCI) Div. 05 - Anchor Bolt Delivery | Complete | 02/09/26 | 03/02/26 | 11.2 | 0.0 |
|
0.0 |
PRE.TPA.1040 |
BMS Controls - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 02/10/26 | 03/03/26 | 10.0 | 0.0 |
|
0.0 |
ICM.B7.1805 |
[SSDCB2] Delivery of Substation MSG Alpha (First Delivery) NOT DPR SCOPE | Construction | Complete | 02/12/26 | 02/12/26 | 0.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3300 |
RPL07 - Submittals Prep & Submit for Review - Exterior Louvers (w Ext Metal Panel Trade) (CrownCorr) | Fixed Louvers | Complete | 02/13/26 | 03/13/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3960 |
RPL07 - Fabricate / Deliver - Structural Steel (Joists) (OD=60 Day) | (CFCI) Div. 05 - Structural Steel (Joists) | Active | 02/13/26 | 04/15/26 | 0.0 | 3.8 |
|
37.5 |
RPL07.CFCI.3560 |
RPL07 - Fabricate / Deliver - Structural Steel | (CFCI) Div. 05 - Structural Steel | Active | 02/16/26 | 04/15/26 | 48.8 | 3.8 |
|
37.5 |
RPL07.CFCI.5670 |
RPL07 - Submittals Review & Approval - SOG/SOMD/Pads Struc. Conc. (Rebar) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 02/16/26 | 02/27/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.VDC.1300 |
T0 (mCUP Yard/Ext.) - Procure UG Materials | TIER 0 - mCUP Yard / Exterior | Complete | 02/16/26 | 03/06/26 | 18.8 | 0.0 |
|
0.0 |
RPL07.VDC.1340 |
T1 (SSB to Center EF) - Review & Approve BIM Shop | TIER 1 - SSB to Center of EF | Complete | 02/16/26 | 03/27/26 | 18.8 | 0.0 |
|
0.0 |
RPL07.VDC.1400 |
T1 (Center EF to End Corridor) - Review & Approve BIM Shop | TIER 1 - Center of EF to End Corridor | Complete | 02/16/26 | 03/26/26 | 31.2 | 0.0 |
|
0.0 |
RPL07.CFCI.4490 |
RPL07 - Fabricate / Deliver - Below Grade Waterproofing (SPW - Div 07) | Waterproofing | Complete | 02/19/26 | 03/04/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CFCI.4750 |
RPL07 - Fabricate / Deliver - Cold Formed Metal Framing | (CFCI) Div. 05 - Cold Formed Metal Framing | Active | 02/19/26 | 05/01/26 | 18.8 | 18.8 |
|
132.5 |
RPL07.CFCI.3010 |
RPL07 - Fab & Deliver - Steel Mill Order (20Wks from IFC Release) | (CFCI) Div. 05 - Structural Steel | Complete | 02/23/26 | 02/27/26 | 30.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3370 |
RPL07 - Submittals Prep & Submit for Review - Plumbing (OH / In Wall) | (CFCI) Div. 22 - Plumbing | Complete | 02/23/26 | 03/23/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3380 |
RPL07 - Submittals Prep & Submit for Review - HVAC Materials and Equipment | (CFCI) Div. 23 - HVAC Materials and Equip. | Complete | 02/23/26 | 03/30/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3390 |
RPL07 - Submittals Prep & Submit for Review - HVAC Insulation | (CFCI) Div. 23 - HVAC Insulation | Complete | 02/23/26 | 03/31/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3430 |
RPL07 - Submittals Prep & Submit for Review - Power Equipment and Material | (CFCI) Div. 26 - Power Equip. & Material | Complete | 02/23/26 | 03/23/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3690 |
RPL07 - Submittals Prep & Submit for Review - Finished Carpentry (FRP) | FRP [Hallways] | Complete | 02/23/26 | 03/20/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3710 |
RPL07 - Submittals Prep & Submit for Review - Roofing | Roofing | Complete | 02/23/26 | 03/23/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.3720 |
RPL07 - Submittals Prep & Submit for Review - Doors, Frames and Hardware | Doors, Frames & Hardware (HM and Wood) | Complete | 02/23/26 | 02/27/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.4580 |
RPL07 - Submittals Prep & Submit for Review - Joint Sealants | Joint Sealants | Complete | 02/23/26 | 02/27/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.4590 |
RPL07 - Submittals Prep & Submit for Review - Interior Expansion Joints (Spec 07 95 13.13) XX | Building Expansion Joints (Spec 07 95 13.13) | Complete | 02/23/26 | 02/27/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.5480 |
RPL07 - Fabricate / Deliver - Foundation Struc. Conc. (Rebar) | (CFCI) Div. 03 - (Foundation) Struc. Concrete | Complete | 02/23/26 | 03/04/26 | 18.8 | 0.0 |
|
0.0 |
RPL07.MR.1240 |
RPL07.MR - Install Wayfinding/ Information Boards/ Signage | Make Ready | Complete | 02/23/26 | 02/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.CFCI.6150 |
RPL07 - Submittals Review & Approval - CMU - Storm Shelter | (CFCI) Div. 04 - Concrete Masonry Units | Complete | 02/24/26 | 03/06/26 | 12.5 | 0.0 |
|
0.0 |
PRE.FA.1040 |
Concrete - Final Agreement | Trade Partner Final Agreement | Complete | 02/26/26 | 02/26/26 | 0.0 | 0.0 |
|
0.0 |
RPL07.CFCI.4030 |
RPL07 - Submittals Review & Approval - Power Equipment and Material | (CFCI) Div. 26 - Power Equip. & Material | Complete | 02/26/26 | 04/06/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CFCI.4540 |
RPL07 - Submittals Review & Approval - FSC Rough Carpentry (In Wall Backing / Blocking) | Rough Carpentry - FSC Wood | Complete | 02/26/26 | 03/13/26 | 21.2 | 0.0 |
|
0.0 |
RPL.07.D.71010.XR |
Pad Ready - RPL07 (DPR Date: xxx) West Half of building and mCUP (7-1 to 7-17) | Receive Milestones (XREFs) | Complete | 03/02/26 | 03/02/26 | 0.0 | 0.0 |
|
0.0 |