Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:16 PM · 5237 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
93
Completed
6
In Progress
93
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
PRE.MIR.1100 Roofing SA - Meta Review / Authorization Meta Internal Review of Trade Partner Bids Complete 10/30/25 11/11/25 12.5 0.0
100%
0.0
PRE.TPBD.1060 Steel SA Package Trade Partner Bid Development Complete 10/30/25 10/30/25 12.5 0.0
100%
0.0
PRE.MIR.1040 Steel SA - Meta Review / Authorization Meta Internal Review of Trade Partner Bids Complete 10/31/25 11/14/25 12.5 0.0
100%
0.0
RPL07.CFCI.6210 RPL07 - SOG Mock-up (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete Complete 10/31/25 10/31/25 6.2 0.0
100%
0.0
RPL07.VDC.1140 T1 (Center EF to End Corridor) - BIM Model & Coordination TIER 1 - Center of EF to End Corridor Complete 11/03/25 01/23/26 17.5 0.0
100%
0.0
PRE.TPBD.1040 Turnkey Concrete (Foundations Only) - Submit for Meta Review Trade Partner Bid Development Complete 11/06/25 11/06/25 1.2 0.0
100%
0.0
PRE.MIR.1060 Turnkey Concrete SA - Meta Review / Authorization Meta Internal Review of Trade Partner Bids Complete 11/07/25 11/18/25 12.5 0.0
100%
0.0
RPL07.VDC.1100 T1 (SSB to Center EF) - BIM Model & Coordination TIER 1 - SSB to Center of EF Complete 11/17/25 01/23/26 17.5 0.0
100%
0.0
RPL07.VDC.1180 T2-4 (mCUP Yard / Ext.) - BIM Model & Coordination TIER 2 - 4 - mCUP Yard / Exterior Complete 11/17/25 01/21/26 15.0 0.0
100%
0.0
RPL.07.D.73910.XG Production Cabling Start - SS-1 Entry to SS-1 DH-A - Obsolete Obsolete Not Started 11/24/25 11/24/25 0.0 0.0
0%
644.0
RPL07.CFCI.3660 RPL07 - Submittals Prep & Submit for Review - Strut (CFCI) Div. 05 - Slotted Channel Framing (Strut) Complete 12/04/25 01/06/26 25.0 0.0
100%
0.0
PRE.TPBD.1180 Waterproofing / Caulking / Expansion Joints - Submit for Meta Review Trade Partner Bid Development Complete 12/11/25 12/12/25 37.5 0.0
100%
0.0
PRE.MIR.1160 Waterproofing / Caulking / Expansion Joints SA - Meta Review / Authorization Meta Internal Review of Trade Partner Bids Complete 12/12/25 01/07/26 12.5 0.0
100%
0.0
RPL07.VDC.1080 T0 (mCUP Yard/Ext.) - Prepare & Submit BIM Shops TIER 0 - mCUP Yard / Exterior Complete 12/15/25 03/16/26 12.5 0.0
100%
0.0
RPL07.VDC.1360 T2-4 (SSB) - BIM Model & Coordination TIER 2 - 4 - SSB Complete 12/15/25 03/27/26 22.5 0.0
100%
0.0
PRE.TPA.1120 Fire Suppression - Award and Issue Subcontract DPR issue Trade Parter Agreements Complete 12/16/25 12/16/25 10.0 0.0
100%
0.0
PRE.FA.1000 Electrical - LOI Issued to Start Coordination Trade Partner Final Agreement Complete 12/22/25 12/22/25 10.0 0.0
100%
0.0
PRE.FA.1100 Mechanical / Plumbing - Final Agreement Trade Partner Final Agreement Complete 12/22/25 12/22/25 0.0 0.0
100%
0.0
PRE.FA.1120 Fire Suppression - Final Agreement Trade Partner Final Agreement Complete 12/22/25 12/22/25 0.0 0.0
100%
0.0
RPL07.CFCI.6220 RPL07 - Submittals Prep & Submit for Review - AHUs (CFCI) Div. 23 - Air Handler Units (AHUs) Complete 12/29/25 01/08/26 25.0 0.0
100%
0.0
RPL07.VDC.1120 T0 (Bldg07) - Prepare & Submit BIM Shops TIER 0 - Building 07 Complete 12/29/25 03/16/26 12.5 0.0
100%
0.0
RPL07.CFCI.6040 Submittal Review & Approval - Technical Water (Assume HDPE Pipe) (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) Complete 12/30/25 01/22/26 18.8 0.0
100%
0.0
RPL07.CFCI.3040 RPL07 - Submittals Prep & Submit for Review - Structural Steel (Joists) (CFCI) Div. 05 - Structural Steel (Joists) Complete 01/05/26 02/04/26 25.0 0.0
100%
0.0
RPL07.CFCI.5460 RPL07 - Submittals Prep & Submit for Review - Foundation Struc. Conc. (Rebar) (CFCI) Div. 03 - (Foundation) Struc. Concrete Complete 01/05/26 01/05/26 18.8 0.0
100%
0.0
RPL07.CFCI.6540 RPL07 - (DBC) Submittals Prep & Submit for Review - IWP Exterior Metal Panels Complete 01/05/26 01/09/26 1.2 0.0
100%
0.0
PRE.TPA.1080 Steel - Trade Partner Process Mill Order DPR issue Trade Parter Agreements Complete 01/06/26 01/15/26 10.0 0.0
100%
0.0
RPL07.CFCI.3020 RPL07 - Submittals Prep & Submit for Review - Structural Steel (CFCI) Div. 05 - Structural Steel Complete 01/06/26 02/04/26 25.0 0.0
100%
0.0
RPL07.CFCI.5470 RPL07 - Submittals Review & Approval - Foundation Struc. Conc. (Rebar) (CFCI) Div. 03 - (Foundation) Struc. Concrete Complete 01/06/26 02/05/26 12.5 0.0
100%
0.0
RPL07.CFCI.5210 RPL07 - Submittals Review & Approval - Strut (CFCI) Div. 05 - Slotted Channel Framing (Strut) Complete 01/07/26 01/28/26 18.8 0.0
100%
0.0
PRE.BNS.1380 GMP Review and Final Submission (fGMP) * Obsolete Obsolete Complete 01/09/26 01/09/26 18.8 0.0
100%
0.0
PRE.BNS.1400 GMP Review by Legal (fGMP) * Obsolete Obsolete Complete 01/09/26 01/09/26 6.2 0.0
100%
0.0
PRE.BNS.1420 GMP Approved by Meta Legal (fGMP) * Obsolete Obsolete Complete 01/09/26 01/09/26 0.0 0.0
100%
0.0
PRE.BNS.1440 fGMP Issuance * Obsolete Obsolete Complete 01/09/26 01/09/26 0.0 0.0
100%
0.0
PRE.BNS.1460 fGMP Review Cycle * Obsolete Obsolete Complete 01/09/26 01/09/26 6.2 0.0
100%
0.0
RPL.GF.D.N7210.XG Circut Audit Start RPL07 DHB/A *OBSOLETE Obsolete Complete 01/09/26 01/09/26 0.0 0.0
100%
0.0
RPL.GF.D.N7220.XG Circut Audit Start RPL07 DHD/C *OBSOLETE Obsolete Complete 01/09/26 01/09/26 0.0 0.0
100%
0.0
RPL07.CFCI.3650 RPL07 - Submittals Prep & Submit for Review - Cold Formed Metal Framing (CFCI) Div. 05 - Cold Formed Metal Framing Complete 01/09/26 01/30/26 18.8 0.0
100%
0.0
RPL07.CFCI.5650 RPL07 - Submittals Prep & Submit for Review - SOG/SOMD/Pads Struc. Conc. (Rebar) (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete Complete 01/09/26 02/13/26 6.2 0.0
100%
0.0
RPL07.CFCI.6230 RPL07 - Submittals Review & Approval - AHUs (CFCI) Div. 23 - Air Handler Units (AHUs) Complete 01/09/26 01/22/26 11.2 0.0
100%
0.0
RPL07.CON.WP3B.01780 RPL07.Connectivity.WP3B Pull/Install/Test Universal Fabric EF21 (North) <> DHB.10 P1&4 (LVSA) - **OBSOLETE** Obsolete Complete 01/09/26 01/09/26 5.0 0.0
100%
0.0
PRE.TPA.1000 Electrical - Award and Issue Subcontract DPR issue Trade Parter Agreements Complete 01/12/26 01/12/26 10.0 0.0
100%
0.0
RPL07.CFCI.3700 RPL07 - Submittals Prep & Submit for Review - Below Grade Waterproofing (SPW - Div 07) Waterproofing Complete 01/12/26 01/30/26 25.0 0.0
100%
0.0
RPL07.CFCI.6560 RPL07 - (DBC) Submittals Review & Approval - IWP Exterior Metal Panels Complete 01/12/26 01/23/26 12.5 0.0
100%
0.0
PRE.TPA.1140 Steel Mill Order Placed DPR issue Trade Parter Agreements Complete 01/15/26 01/15/26 0.0 0.0
100%
0.0
RPL07.CFCI.6240 RPL07 - Fabricate / Deliver - AHUs (EY.SSBC, EY.DHA) (CFCI) Div. 23 - Air Handler Units (AHUs) Active 01/16/26 06/15/26 86.2 56.2
0%
125.0
RPL07.MR.1020 RPL07.MR - Trailer Complete Ready for Move-In **(Update Description & Date) Make Ready Complete 01/16/26 01/16/26 0.0 0.0
100%
0.0
RPL07.MR.1160 RPL07.MR - Trailer Setup & Tie-Ins Make Ready Complete 01/16/26 01/16/26 28.8 0.0
100%
0.0
RPL07.MR.1220 RPL07.MR - Parking Areas Buildout Make Ready Complete 01/16/26 01/16/26 6.2 0.0
100%
0.0
RPL07.CFCI.4310 RPL07 - Fabricate / Deliver - CMU - Storm Shelter (CFCI) Div. 04 - Concrete Masonry Units Complete 01/19/26 03/24/26 6.2 0.0
100%
0.0
RPL07.CFCI.6140 RPL07 - Submittals Prep & Submit for Review - CMU - Storm Shelter (CFCI) Div. 04 - Concrete Masonry Units Complete 01/19/26 02/20/26 18.8 0.0
100%
0.0
PRE.FA.1080 Steel - Final Agreement Trade Partner Final Agreement Complete 01/20/26 01/20/26 0.0 0.0
100%
0.0
PRE.TPA.1060 Steel - Award and Issue Subcontract DPR issue Trade Parter Agreements Complete 01/20/26 01/20/26 10.0 0.0
100%
0.0
RPL.07.D.70000.XR External Tie from RPL06 - Bldg Concrete Foundations Crew Flow (RPL06.SUB.DHCD.01030) Internal Milestones (XREFs) Complete 01/20/26 01/20/26 0.0 0.0
100%
0.0
RPL07.CFCI.6050 Submittals Review & Approval - Technical Water (Assume HDPE Pipe) (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) Complete 01/23/26 02/20/26 12.5 0.0
100%
0.0
RPL07.CFCI.6060 Fabricate / Deliver - Technical Water (Assume HDPE Pipe) (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) Complete 01/23/26 03/20/26 50.0 0.0
100%
0.0
RPL07.CFCI.6920 RPL07 - Fabricate / Deliver - AHUs (EY.EC) (CFCI) Div. 23 - Air Handler Units (AHUs) Active 01/23/26 05/07/27 355.0 336.2
0%
41.2
RPL07.CFCI.6580 RPL07 - (DBC) Fabricate / Deliver - IWP Exterior Metal Panels Active 01/26/26 05/12/26 43.8 27.5
0%
36.2
RPL07.VDC.1240 T1 (SSB to Center EF) - Prepare & Submit BIM Shops (ext IMP shops by 1/9/26) TIER 1 - SSB to Center of EF Complete 01/26/26 02/13/26 12.5 0.0
100%
0.0
RPL07.VDC.1280 T1 (Center EF to End Corridor) - Prepare & Submit BIM Shops TIER 1 - Center of EF to End Corridor Complete 01/26/26 02/13/26 12.5 0.0
100%
0.0
RPL07.CFCI.3680 RPL07 - Submittals Prep & Submit for Review - FSC -Rough Carpentry (In Wall Backing / Blocking) Rough Carpentry - FSC Wood Complete 01/28/26 02/25/26 25.0 0.0
100%
0.0
RPL07.CFCI.5340 RPL07 - Fabricate / Deliver - Strut (CFCI) Div. 05 - Slotted Channel Framing (Strut) Complete 01/29/26 03/06/26 25.0 0.0
100%
0.0
RPL07.CFCI.3810 RPL07 - Submittals Review & Approval - Exterior Louvers (w Ext Metal Panel Trade) Fixed Louvers Complete 02/02/26 02/12/26 12.5 0.0
100%
0.0
RPL07.CFCI.4340 RPL07 - Submittals Review & Approval - Below Grade Waterproofing Waterproofing Complete 02/02/26 02/18/26 12.5 0.0
100%
0.0
RPL07.CFCI.4530 RPL07 - Submittals Review & Approval - Cold Formed Metal Framing (CFCI) Div. 05 - Cold Formed Metal Framing Complete 02/02/26 02/18/26 12.5 0.0
100%
0.0
PRE.TPA.1160 Roofing - Award and Issue Subcontract DPR issue Trade Parter Agreements Complete 02/03/26 02/05/26 10.0 0.0
100%
0.0
RPL07.CFCI.3930 RPL07 - Submittals Review & Approval - Structural Steel (Joists) (CFCI) Div. 05 - Structural Steel (Joists) Complete 02/04/26 02/12/26 18.8 0.0
100%
0.0
PRE.FA.1140 Roofing - Final Agreement Trade Partner Final Agreement Complete 02/05/26 02/05/26 0.0 0.0
100%
0.0
RPL07.CFCI.3420 RPL07 - Review for Approval - Structural Steel (CFCI) Div. 05 - Structural Steel Complete 02/05/26 02/13/26 17.5 0.0
100%
0.0
PRE.FA.1020 Electrical - Final Agreement Trade Partner Final Agreement Complete 02/09/26 02/09/26 0.0 0.0
100%
0.0
PRE.TPA.1020 Concrete - Award and Issue Subcontract DPR issue Trade Parter Agreements Complete 02/09/26 02/26/26 10.0 0.0
100%
0.0
PRE.TPA.1200 Waterproofing / Caulking / Expansion Joints - Award and Issue Subcontract DPR issue Trade Parter Agreements Complete 02/09/26 03/23/26 10.0 0.0
100%
0.0
RPL07.CFCI.4520 RPL07 - SSB - Deliver - Anchor Bolts (CFCI) Div. 05 - Anchor Bolt Delivery Complete 02/09/26 03/02/26 11.2 0.0
100%
0.0
PRE.TPA.1040 BMS Controls - Award and Issue Subcontract DPR issue Trade Parter Agreements Complete 02/10/26 03/03/26 10.0 0.0
100%
0.0
ICM.B7.1805 [SSDCB2] Delivery of Substation MSG Alpha (First Delivery) NOT DPR SCOPE Construction Complete 02/12/26 02/12/26 0.0 0.0
100%
0.0
RPL07.CFCI.3300 RPL07 - Submittals Prep & Submit for Review - Exterior Louvers (w Ext Metal Panel Trade) (CrownCorr) Fixed Louvers Complete 02/13/26 03/13/26 25.0 0.0
100%
0.0
RPL07.CFCI.3960 RPL07 - Fabricate / Deliver - Structural Steel (Joists) (OD=60 Day) (CFCI) Div. 05 - Structural Steel (Joists) Active 02/13/26 04/15/26 0.0 3.8
0%
37.5
RPL07.CFCI.3560 RPL07 - Fabricate / Deliver - Structural Steel (CFCI) Div. 05 - Structural Steel Active 02/16/26 04/15/26 48.8 3.8
0%
37.5
RPL07.CFCI.5670 RPL07 - Submittals Review & Approval - SOG/SOMD/Pads Struc. Conc. (Rebar) (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete Complete 02/16/26 02/27/26 12.5 0.0
100%
0.0
RPL07.VDC.1300 T0 (mCUP Yard/Ext.) - Procure UG Materials TIER 0 - mCUP Yard / Exterior Complete 02/16/26 03/06/26 18.8 0.0
100%
0.0
RPL07.VDC.1340 T1 (SSB to Center EF) - Review & Approve BIM Shop TIER 1 - SSB to Center of EF Complete 02/16/26 03/27/26 18.8 0.0
100%
0.0
RPL07.VDC.1400 T1 (Center EF to End Corridor) - Review & Approve BIM Shop TIER 1 - Center of EF to End Corridor Complete 02/16/26 03/26/26 31.2 0.0
100%
0.0
RPL07.CFCI.4490 RPL07 - Fabricate / Deliver - Below Grade Waterproofing (SPW - Div 07) Waterproofing Complete 02/19/26 03/04/26 12.5 0.0
100%
0.0
RPL07.CFCI.4750 RPL07 - Fabricate / Deliver - Cold Formed Metal Framing (CFCI) Div. 05 - Cold Formed Metal Framing Active 02/19/26 05/01/26 18.8 18.8
0%
132.5
RPL07.CFCI.3010 RPL07 - Fab & Deliver - Steel Mill Order (20Wks from IFC Release) (CFCI) Div. 05 - Structural Steel Complete 02/23/26 02/27/26 30.0 0.0
100%
0.0
RPL07.CFCI.3370 RPL07 - Submittals Prep & Submit for Review - Plumbing (OH / In Wall) (CFCI) Div. 22 - Plumbing Complete 02/23/26 03/23/26 25.0 0.0
100%
0.0
RPL07.CFCI.3380 RPL07 - Submittals Prep & Submit for Review - HVAC Materials and Equipment (CFCI) Div. 23 - HVAC Materials and Equip. Complete 02/23/26 03/30/26 25.0 0.0
100%
0.0
RPL07.CFCI.3390 RPL07 - Submittals Prep & Submit for Review - HVAC Insulation (CFCI) Div. 23 - HVAC Insulation Complete 02/23/26 03/31/26 25.0 0.0
100%
0.0
RPL07.CFCI.3430 RPL07 - Submittals Prep & Submit for Review - Power Equipment and Material (CFCI) Div. 26 - Power Equip. & Material Complete 02/23/26 03/23/26 25.0 0.0
100%
0.0
RPL07.CFCI.3690 RPL07 - Submittals Prep & Submit for Review - Finished Carpentry (FRP) FRP [Hallways] Complete 02/23/26 03/20/26 25.0 0.0
100%
0.0
RPL07.CFCI.3710 RPL07 - Submittals Prep & Submit for Review - Roofing Roofing Complete 02/23/26 03/23/26 25.0 0.0
100%
0.0
RPL07.CFCI.3720 RPL07 - Submittals Prep & Submit for Review - Doors, Frames and Hardware Doors, Frames & Hardware (HM and Wood) Complete 02/23/26 02/27/26 25.0 0.0
100%
0.0
RPL07.CFCI.4580 RPL07 - Submittals Prep & Submit for Review - Joint Sealants Joint Sealants Complete 02/23/26 02/27/26 25.0 0.0
100%
0.0
RPL07.CFCI.4590 RPL07 - Submittals Prep & Submit for Review - Interior Expansion Joints (Spec 07 95 13.13) XX Building Expansion Joints (Spec 07 95 13.13) Complete 02/23/26 02/27/26 25.0 0.0
100%
0.0
RPL07.CFCI.5480 RPL07 - Fabricate / Deliver - Foundation Struc. Conc. (Rebar) (CFCI) Div. 03 - (Foundation) Struc. Concrete Complete 02/23/26 03/04/26 18.8 0.0
100%
0.0
RPL07.MR.1240 RPL07.MR - Install Wayfinding/ Information Boards/ Signage Make Ready Complete 02/23/26 02/27/26 6.2 0.0
100%
0.0
RPL07.CFCI.6150 RPL07 - Submittals Review & Approval - CMU - Storm Shelter (CFCI) Div. 04 - Concrete Masonry Units Complete 02/24/26 03/06/26 12.5 0.0
100%
0.0
PRE.FA.1040 Concrete - Final Agreement Trade Partner Final Agreement Complete 02/26/26 02/26/26 0.0 0.0
100%
0.0
RPL07.CFCI.4030 RPL07 - Submittals Review & Approval - Power Equipment and Material (CFCI) Div. 26 - Power Equip. & Material Complete 02/26/26 04/06/26 12.5 0.0
100%
0.0
RPL07.CFCI.4540 RPL07 - Submittals Review & Approval - FSC Rough Carpentry (In Wall Backing / Blocking) Rough Carpentry - FSC Wood Complete 02/26/26 03/13/26 21.2 0.0
100%
0.0
RPL.07.D.71010.XR Pad Ready - RPL07 (DPR Date: xxx) West Half of building and mCUP (7-1 to 7-17) Receive Milestones (XREFs) Complete 03/02/26 03/02/26 0.0 0.0
100%
0.0