Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:16 PM · 5237 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
88
Completed
12
In Progress
88
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL07.CFCI.3730 RPL07 - Submittals Prep & Submit for Review - Gypsum System (CFCI) Div. 09 - Gypsum System & Ceilings Complete 03/02/26 03/13/26 18.8 0.0
100%
0.0
RPL07.CFCI.4550 RPL07 - Submittals Review & Approval - Doors, Frames and Hardware Doors, Frames & Hardware (HM and Wood) Complete 03/02/26 03/05/26 25.0 0.0
100%
0.0
RPL07.CFCI.4840 RPL07 - Submittals Review & Approval - Joint Sealants Joint Sealants Complete 03/02/26 03/06/26 25.0 0.0
100%
0.0
RPL07.CFCI.4850 RPL07 - Submittals Review & Approval - Interior Expansion Joints (Spec 07 95 13.13) XX Building Expansion Joints (Spec 07 95 13.13) Complete 03/02/26 03/06/26 12.5 0.0
100%
0.0
RPL07.CFCI.5660 RPL07 - Fabricate / Deliver - SOG/SOMD/Pads Struc. Conc. (Rebar) (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete Complete 03/02/26 03/30/26 18.8 0.0
100%
0.0
RPL07.MR.1281 RPL07.MR - Make Ready Work (for unavailability of roads around West Half of Pad) Make Ready Complete 03/02/26 03/06/26 6.2 0.0
100%
0.0
RPL07.SUB.1000 RPL07.SubStructure.BLDG - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary SubStructure Active 03/02/26 04/16/26 41.2 5.0
0%
48.8
RPL07.SUB.DHAB.01000 RPL07.SubStructure.DHAB - Install Drilled Piers - Grid lines 7-10/7-17 (West of GL 17) Foundations Complete 03/02/26 03/06/26 3.8 0.0
100%
0.0
RPL07.SUB.DHAB.01020 RPL07.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary DH B & DH A Active 03/02/26 04/16/26 41.2 5.0
0%
48.8
RPL07.VDC.1320 T2-4 (mCUP Yard / Ext.) - Prepare & Submit BIM Shops TIER 2 - 4 - mCUP Yard / Exterior Complete 03/02/26 03/30/26 12.5 0.0
100%
0.0
RPL07.VDC.1420 T2-4 (DH A & B) - BIM Model & Coordination TIER 2 - 4 - DH A & B Complete 03/02/26 03/27/26 27.5 0.0
100%
0.0
RPL07.VDC.1460 T2-4 (EF) - BIM Model & Coordination TIER 2 - 4 - EF Complete 03/02/26 03/27/26 12.5 0.0
100%
0.0
RPL07.VDC.1480 T2-4 (DH C & D) - BIM Model & Coordination TIER 2 - 4 - DH C & D Complete 03/02/26 03/27/26 12.5 0.0
100%
0.0
ICM.B7.1060 [SSDCB2] Start Foundations Construction Complete 03/03/26 03/03/26 0.0 0.0
100%
0.0
PRE.FA.1060 BMS Controls - Final Agreement Trade Partner Final Agreement Complete 03/03/26 03/03/26 0.0 0.0
100%
0.0
RPL07.SUB.SSB.01000 RPL07.SubStructure.SSB - Install Drilled Piers - Grid lines 7-01/7-10 Foundations Complete 03/03/26 03/05/26 5.0 0.0
100%
0.0
RPL07.SUB.SSB.01010 RPL07.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary Foundations Complete 03/03/26 04/10/26 32.5 0.0
100%
0.0
RPL07.SUB.SSB.01020 RPL07.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary SSB Complete 03/03/26 04/10/26 35.0 0.0
100%
0.0
RPL07.SUB.SSB.01140 RPL07.SubStructure.SSB - Piers Protection Concrete Capping (LOE) Foundations Complete 03/04/26 03/16/26 5.0 0.0
100%
0.0
RPL07.SUB.SSB.01265 RPL07.SubStructure.SSB - Piers Protection Concrete Capping (Pre WI#01) Foundations Complete 03/04/26 03/10/26 6.2 0.0
100%
0.0
RPL07.SUB.SSB.01040 RPL07.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 7-01/7-10 (LOE) Foundations Complete 03/05/26 03/20/26 18.8 0.0
100%
0.0
RPL07.SUB.SSB.01070 RPL07.SubStructure.SSB - Install Stem Walls - Grid lines 7-01/7-10 (LOE) Foundations Complete 03/05/26 03/21/26 7.5 0.0
100%
0.0
RPL07.SUB.SSB.01275 RPL07.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 7-01/7-10 (Pre WI#01) Foundations Complete 03/05/26 03/10/26 5.0 0.0
100%
0.0
RPL07.SUB.SSB.01285 RPL07.SubStructure.SSB - Install Stem Walls - Grid lines 7-01/7-10 (Pre WI#01) Foundations Complete 03/05/26 03/10/26 5.0 0.0
100%
0.0
RPL07.VDC.1380 T0 (Bldg07) - Procure UG Materials TIER 0 - Building 07 Complete 03/05/26 03/16/26 15.0 0.0
100%
0.0
RPL07.MR.1260 RPL07.MR - Mobilization Complete Make Ready Complete 03/06/26 03/06/26 0.0 0.0
100%
0.0
RPL07.SUB.DHAB.01060 RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 1 (West of GL 17) (LOE) Underground Complete 03/06/26 03/17/26 7.5 0.0
100%
0.0
RPL07.SUB.DHAB.01365 RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 1 (West of GL 17) (Pre WI#01) Underground Complete 03/06/26 03/10/26 3.8 0.0
100%
0.0
RPL07.SUB.SSB.01030 RPL07.SubStructure.SSB - Foundation For Storm Shelter Rebar CMU (LOE) Foundations Complete 03/06/26 03/16/26 6.2 0.0
100%
0.0
RPL07.SUB.SSB.01050 RPL07.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 (LOE) Underground Complete 03/06/26 03/16/26 11.2 0.0
100%
0.0
RPL07.SUB.SSB.01060 RPL07.SubStructure.SSB - Install UG Utilities - WBS Summary Underground Complete 03/06/26 03/27/26 30.0 0.0
100%
0.0
RPL07.SUB.SSB.01220 RPL07.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Acclimation to Swing Shift (LOE) Underground Complete 03/06/26 03/18/26 10.0 0.0
100%
0.0
RPL07.SUB.SSB.01295 RPL07.SubStructure.SSB - Foundation For Storm Shelter Rebar CMU (Pre WI#01) Foundations Complete 03/06/26 03/10/26 3.8 0.0
100%
0.0
RPL07.SUB.SSB.01305 RPL07.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 (Pre WI#01) Underground Complete 03/06/26 03/10/26 3.8 0.0
100%
0.0
RPL07.SUB.SSB.01315 RPL07.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Acclimation to Swing Shift (Pre WI#01) Underground Complete 03/06/26 03/10/26 3.8 0.0
100%
0.0
PRE.TPA.1220 Ceiling - Award and Issue Subcontract DPR issue Trade Parter Agreements Active 03/09/26 04/14/26 6.2 2.5
0%
82.5
RPL.07.D.71015.XR Pad Ready - RPL07 (DPR Date: xxx) East Half of Building (7-17 to 7-28) Receive Milestones (XREFs) Complete 03/09/26 03/09/26 0.0 0.0
100%
0.0
RPL07.MR.1301 RPL07.MR - Make Ready Work (for unavailability of roads around East Half of Pad) (LOE) Make Ready Complete 03/09/26 03/17/26 8.8 0.0
100%
0.0
RPL07.MR.1306 RPL07.MR - Make Ready Work (for unavailability of roads around East Half of Pad) (Pre WI#01) Make Ready Complete 03/09/26 03/10/26 2.5 0.0
100%
0.0
RPL07.SUB.DHAB.01090 RPL07.SubStructure.DHAB - Install UG UT - Elec/Testing, Pathway Verification & Backfill - Part 1 (West of GL 17)(LOE) Underground Complete 03/09/26 03/23/26 11.2 0.0
100%
0.0
RPL07.SUB.DHAB.01130 RPL07.SubStructure.DHAB - Piers Protection Concrete Capping - Grid lines 7-10/7-17 (West of GL 17) Foundations Complete 03/09/26 03/10/26 3.8 0.0
100%
0.0
RPL07.SUB.DHAB.01330 RPL07.SubStructure.DHAB - Install UG UT - Elec/Testing, Pathway Ver. & BF - Part 1 **Swing Shift** (West of GL 17)(LOE) Underground Complete 03/09/26 03/23/26 11.2 0.0
100%
0.0
RPL07.SUB.DHAB.01345 RPL07.SubStr.DHAB - Install UG UT - Elec/Testing, Pathway Ver. & BF - Part 1 **Swing** (West of GL 17) (Pre WI#01) Underground Complete 03/09/26 03/10/26 2.5 0.0
100%
0.0
RPL07.SUB.DHAB.01355 RPL07.SubStr.DHAB - Install UG UT - Elec/Testing, Pathway Verification & Backfill - Part 1 (West of GL 17) (Pre WI#01) Underground Complete 03/09/26 03/10/26 2.5 0.0
100%
0.0
RPL07.SUB.SSB.01090 RPL07.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 1 (LOE) Underground Complete 03/09/26 03/19/26 11.2 0.0
100%
0.0
RPL07.SUB.SSB.01240 RPL07.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Backfill - Acclimation to Swing Shift (LOE) Underground Complete 03/09/26 03/19/26 11.2 0.0
100%
0.0
RPL07.SUB.SSB.01325 RPL07.SubStructure.SSB - Install UG Utilities - Electrical/Testing & Pathway Verification & Backfill - Pt1 (Pre WI#01) Underground Complete 03/09/26 03/10/26 2.5 0.0
100%
0.0
RPL07.SUB.SSB.01335 RPL07.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Backfill - Acclimation to Swing Shift (Pre WI#01) Underground Complete 03/09/26 03/10/26 2.5 0.0
100%
0.0
RPL07.PI.1000 Weather Event #1 - 03.11.2026 - 03.12.2026 Project Impacts Complete 03/11/26 03/12/26 2.5 0.0
100%
0.0
RPL07.SUB.DHAB.01005 RPL07.SubStructure.DHAB - Install Drilled Piers - Grid lines 7-17/7-23 (East of GL 17) (LOE) Foundations Complete 03/11/26 03/14/26 6.2 0.0
100%
0.0
RPL07.SUB.DHAB.01010 RPL07.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary Foundations Active 03/11/26 04/16/26 32.5 2.5
0%
48.8
RPL07.SUB.DHAB.01335 RPL07.SubStructure.DHAB - Install Drilled Piers - Grid lines 7-17/7-23 (East of GL 17) (Pre WI#01) Foundations Complete 03/11/26 03/11/26 1.2 0.0
100%
0.0
RPL07.SUB.DHCD.01000 RPL07.SubStructure.DHCD - Install Drilled Piers - Grid lines 7-22/7-28 Foundations Complete 03/11/26 03/14/26 5.0 0.0
100%
0.0
RPL07.SUB.DHCD.01010 RPL07.SubStructure.DHCD - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary Foundations Active 03/11/26 04/15/26 25.0 3.8
0%
41.2
RPL07.SUB.DHCD.01020 RPL07.SubStructure.DHCD - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary DH D & DH C Active 03/11/26 04/15/26 25.0 3.8
0%
41.2
RPL07.MR.1311 RPL07.MR - Make Ready Work (for unavailability of roads around East Half of Pad) (Post WI#01) Make Ready Complete 03/13/26 03/17/26 3.8 0.0
100%
0.0
RPL07.SUB.DHAB.01310 RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 1 **Swing Shift** (West of GL 17) Underground Complete 03/13/26 03/19/26 7.5 0.0
100%
0.0
RPL07.SUB.DHAB.01340 RPL07.SubStructure.DHAB - Install Drilled Piers - Grid lines 7-17/7-23 (East of GL 17) (Post WI#01) Foundations Complete 03/13/26 03/14/26 3.8 0.0
100%
0.0
RPL07.SUB.DHAB.01350 RPL07.SubStr.DHAB - Install UG UT - Elec/Testing, Pathway Ver. & BF - Part 1 **Swing** (West of GL 17) (Post WI#01) Underground Complete 03/13/26 03/24/26 5.0 0.0
100%
0.0
RPL07.SUB.DHAB.01360 RPL07.SubStr.DHAB - Install UG UT - Elec/Testing, Pathway Verification & Backfill - Part 1 (West of GL 17) (Post WI#01) Underground Complete 03/13/26 03/23/26 5.0 0.0
100%
0.0
RPL07.SUB.DHAB.01370 RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 1 (West of GL 17) (Post WI#01) Underground Complete 03/13/26 03/17/26 3.8 0.0
100%
0.0
RPL07.SUB.SSB.01260 RPL07.SubStructure.SSB - Install UG Utilities - BMS/EPMS/Testing and Backfill - Acclimation to Swing Shift Underground Complete 03/13/26 03/19/26 12.5 0.0
100%
0.0
RPL07.SUB.SSB.01270 RPL07.SubStructure.SSB - Piers Protection Concrete Capping (Post WI#01) Foundations Complete 03/13/26 03/16/26 2.5 0.0
100%
0.0
RPL07.SUB.SSB.01280 RPL07.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 7-01/7-10 (Post WI#01) Foundations Complete 03/13/26 03/20/26 6.2 0.0
100%
0.0
RPL07.SUB.SSB.01290 RPL07.SubStructure.SSB - Install Stem Walls - Grid lines 7-01/7-10 (Post WI#01) Foundations Complete 03/13/26 03/21/26 6.2 0.0
100%
0.0
RPL07.SUB.SSB.01300 RPL07.SubStructure.SSB - Foundation For Storm Shelter Rebar CMU (Post WI#01) Foundations Complete 03/13/26 03/16/26 2.5 0.0
100%
0.0
RPL07.SUB.SSB.01310 RPL07.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 (Post WI#01) Underground Complete 03/13/26 03/16/26 7.5 0.0
100%
0.0
RPL07.SUB.SSB.01320 RPL07.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Acclimation to Swing Shift (Post WI#01) Underground Complete 03/13/26 03/18/26 5.0 0.0
100%
0.0
RPL07.SUB.SSB.01330 RPL07.SubStructure.SSB - Install UG Utilities - Electrical/Testing & Pathway Verification & Backfill - Pt1 (Post WI#01) Underground Complete 03/13/26 03/19/26 6.2 0.0
100%
0.0
RPL07.SUB.SSB.01340 RPL07.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Backfill - Acclimation to Swing Shift(Post WI#01) Underground Complete 03/13/26 03/19/26 6.2 0.0
100%
0.0
RPL07.SUB.DHAB.01135 RPL07.SubStructure.DHAB - Piers Protection Concrete Capping - Grid lines 7-17/7-23 (East of GL 17) Foundations Complete 03/14/26 03/16/26 2.5 0.0
100%
0.0
RPL07.CFCI.4120 RPL07 - Fabricate / Deliver - Exterior Louvers Fixed Louvers Active 03/16/26 07/24/26 75.0 91.2
0%
258.8
RPL07.CFCI.4560 RPL07 - Submittals Review & Approval - Gypsum System (CFCI) Div. 09 - Gypsum System & Ceilings Complete 03/16/26 04/10/26 25.0 0.0
100%
0.0
RPL07.SUB.DHAB.01100 RPL07.SubStructure.DHAB - Install UG UT - BMS/EPMS/Testing, Pathway Verification & Backfill (new GS scope West of 17) Underground Complete 03/16/26 03/24/26 11.2 0.0
100%
0.0
RPL07.SUB.DHAB.01150 RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 2 (West of GL 17) Underground Complete 03/16/26 04/06/26 7.5 0.0
100%
0.0
RPL07.SUB.DHCD.01130 RPL07.SubStructure.DHCD - Piers Protection Concrete Capping Foundations Complete 03/16/26 03/19/26 5.0 0.0
100%
0.0
RPL07.SUB.SSB.01110 RPL07.SubStructure.SSB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill Underground Complete 03/16/26 03/20/26 12.5 0.0
100%
0.0
PRE.BNS.1480 Execution of fGMP FGMP Complete 03/17/26 03/17/26 0.0 0.0
100%
0.0
RPL07.SUB.DHAB.01030 RPL07.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 7-10/7-17 (West of GL 17) Foundations Complete 03/17/26 03/26/26 8.8 0.0
100%
0.0
RPL07.VDC.1160 T0 (mCUP Yard/Ext.) - Review & Approve BIM Shop TIER 0 - mCUP Yard / Exterior Complete 03/17/26 03/30/26 12.5 0.0
100%
0.0
RPL07.VDC.1200 T0 (Bldg07) - Review & Approve BIM Shop TIER 0 - Building 07 Complete 03/17/26 03/26/26 6.2 0.0
100%
0.0
RPL07.SUB.DHAB.01065 RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 1 (East of GL 17) Underground Complete 03/18/26 03/19/26 2.5 0.0
100%
0.0
RPL07.SUB.DHAB.01070 RPL07.SubStructure.DHAB - Install UG UT - WBS Summary Underground Complete 03/18/26 04/08/26 16.2 0.0
100%
0.0
RPL07.SUB.DHAB.01210 RPL07.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 7-17/7-23 (East of GL 17) Foundations Complete 03/18/26 03/25/26 6.2 0.0
100%
0.0
RPL07.SUB.DHAB.01170 RPL07.SubStructure.DHAB - Install UG UT - Electrical/Testing, Pathway Verification & Backfill - Part 2 (West of GL 17) Underground Complete 03/19/26 04/02/26 5.0 0.0
100%
0.0
RPL07.MCUP.LP1.1000 RPL07.MCUP.Loop 1 - Install Foundations, UG Utilities, OFE - WBS Summary mCup Loop 1 Active 03/20/26 10/16/26 176.2 165.0
0%
378.8
RPL07.MCUP.LP1.1040 RPL07.MCUP.Loop 1 - Install UG Utilities - WBS Summary Underground Active 03/20/26 04/20/26 38.8 7.5
0%
185.0
RPL07.MCUP.LP1.1080 RPL07.MCUP.Loop 1 - Install Electrical UG Electrical UG Active 03/20/26 04/20/26 25.0 7.5
0%
93.8
RPL07.mCUP.1060 RPL07.MCUP.BLDG - Install Foundations, UG Utilities, OFE 1-6 - WBS Summary mCUP Yard Active 03/20/26 10/28/26 186.2 175.0
0%
368.8
20 RPL07.Connectivity.WP4 FENW DHC CFD C.4 Patch & Dress for SSW to JXSW (ORv3N) **OBSOLETE** Obsolete Complete 03/23/26 03/23/26 12.5 0.0
100%
0.0
RPL07.CFCI.3190 RPL07 - Coordinate Scope and Submittal Req's - Vesda System (CFCI) Div. 28 - VESDA System Complete 03/23/26 03/23/26 1.2 0.0
100%
0.0
RPL07.CFCI.4710 RPL07 - Submittals Prep & Submit for Review - Vesda System (CFCI) Div. 28 - VESDA System Active 03/23/26 06/12/26 73.8 55.0
0%
111.2
RPL07.CFCI.4980 RPL07 - Submittals Review & Approval - Finished Carpentry (FRP) FRP [Hallways] Complete 03/23/26 04/10/26 18.8 0.0
100%
0.0
RPL07.CFCI.6490 Submittal Review & Approval - Roof Drain Pipes (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 Complete 03/23/26 04/06/26 12.5 0.0
100%
0.0
RPL07.CON.WP4.01040 RPL07.Connectivity.WP4 FENW DHB CFD B.1 Pull for SSW to JXSW (ORv3N) **OBSOLETE** Obsolete Complete 03/23/26 03/23/26 12.5 0.0
100%
0.0
RPL07.CON.WP4.01060 RPL07.Connectivity.WP4 FENW DHB CFD B.1 Pull for FSW (ORv3N) **OBSOLETE** to SSW (ORv3N) **OBSOLETE** Obsolete Complete 03/23/26 03/23/26 10.0 0.0
100%
0.0
RPL07.CON.WP4.01080 RPL07.Connectivity.WP4 FENW DHB CFD B.1 Pull for RSW (ORv3) to FSW (ORv3N) **OBSOLETE** Obsolete Complete 03/23/26 03/23/26 10.0 0.0
100%
0.0
RPL07.CON.WP4.010940 RPL07.Connectivity.WP4 FENW DHB CFD B.1 Patch & Dress for SSW to JXSW (ORv3N) **OBSOLETE** Obsolete Complete 03/23/26 03/23/26 12.5 0.0
100%
0.0
RPL07.CON.WP4.010960 RPL07.Connectivity.WP4 FENW DHB CFD B.1 Patch & Dress for FSW (ORv3N) **OBSOLETE** to SSW (ORv3N) **OBSOLETE** Obsolete Complete 03/23/26 03/23/26 10.0 0.0
100%
0.0
RPL07.CON.WP4.010980 RPL07.Connectivity.WP4 FENW DHB CFD B.1 Patch & Dress for RSW (ORv3) to FSW (ORv3N) **OBSOLETE** Obsolete Complete 03/23/26 03/23/26 10.0 0.0
100%
0.0