Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL07 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:16 PM
· 5237 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
88
Completed
12
In Progress
88
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL07.CFCI.3730 |
RPL07 - Submittals Prep & Submit for Review - Gypsum System | (CFCI) Div. 09 - Gypsum System & Ceilings | Complete | 03/02/26 | 03/13/26 | 18.8 | 0.0 |
|
0.0 |
RPL07.CFCI.4550 |
RPL07 - Submittals Review & Approval - Doors, Frames and Hardware | Doors, Frames & Hardware (HM and Wood) | Complete | 03/02/26 | 03/05/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.4840 |
RPL07 - Submittals Review & Approval - Joint Sealants | Joint Sealants | Complete | 03/02/26 | 03/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.CFCI.4850 |
RPL07 - Submittals Review & Approval - Interior Expansion Joints (Spec 07 95 13.13) XX | Building Expansion Joints (Spec 07 95 13.13) | Complete | 03/02/26 | 03/06/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CFCI.5660 |
RPL07 - Fabricate / Deliver - SOG/SOMD/Pads Struc. Conc. (Rebar) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 03/02/26 | 03/30/26 | 18.8 | 0.0 |
|
0.0 |
RPL07.MR.1281 |
RPL07.MR - Make Ready Work (for unavailability of roads around West Half of Pad) | Make Ready | Complete | 03/02/26 | 03/06/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.SUB.1000 |
RPL07.SubStructure.BLDG - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | SubStructure | Active | 03/02/26 | 04/16/26 | 41.2 | 5.0 |
|
48.8 |
RPL07.SUB.DHAB.01000 |
RPL07.SubStructure.DHAB - Install Drilled Piers - Grid lines 7-10/7-17 (West of GL 17) | Foundations | Complete | 03/02/26 | 03/06/26 | 3.8 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01020 |
RPL07.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | DH B & DH A | Active | 03/02/26 | 04/16/26 | 41.2 | 5.0 |
|
48.8 |
RPL07.VDC.1320 |
T2-4 (mCUP Yard / Ext.) - Prepare & Submit BIM Shops | TIER 2 - 4 - mCUP Yard / Exterior | Complete | 03/02/26 | 03/30/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.VDC.1420 |
T2-4 (DH A & B) - BIM Model & Coordination | TIER 2 - 4 - DH A & B | Complete | 03/02/26 | 03/27/26 | 27.5 | 0.0 |
|
0.0 |
RPL07.VDC.1460 |
T2-4 (EF) - BIM Model & Coordination | TIER 2 - 4 - EF | Complete | 03/02/26 | 03/27/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.VDC.1480 |
T2-4 (DH C & D) - BIM Model & Coordination | TIER 2 - 4 - DH C & D | Complete | 03/02/26 | 03/27/26 | 12.5 | 0.0 |
|
0.0 |
ICM.B7.1060 |
[SSDCB2] Start Foundations | Construction | Complete | 03/03/26 | 03/03/26 | 0.0 | 0.0 |
|
0.0 |
PRE.FA.1060 |
BMS Controls - Final Agreement | Trade Partner Final Agreement | Complete | 03/03/26 | 03/03/26 | 0.0 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01000 |
RPL07.SubStructure.SSB - Install Drilled Piers - Grid lines 7-01/7-10 | Foundations | Complete | 03/03/26 | 03/05/26 | 5.0 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01010 |
RPL07.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Complete | 03/03/26 | 04/10/26 | 32.5 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01020 |
RPL07.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | SSB | Complete | 03/03/26 | 04/10/26 | 35.0 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01140 |
RPL07.SubStructure.SSB - Piers Protection Concrete Capping (LOE) | Foundations | Complete | 03/04/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01265 |
RPL07.SubStructure.SSB - Piers Protection Concrete Capping (Pre WI#01) | Foundations | Complete | 03/04/26 | 03/10/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01040 |
RPL07.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 7-01/7-10 (LOE) | Foundations | Complete | 03/05/26 | 03/20/26 | 18.8 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01070 |
RPL07.SubStructure.SSB - Install Stem Walls - Grid lines 7-01/7-10 (LOE) | Foundations | Complete | 03/05/26 | 03/21/26 | 7.5 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01275 |
RPL07.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 7-01/7-10 (Pre WI#01) | Foundations | Complete | 03/05/26 | 03/10/26 | 5.0 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01285 |
RPL07.SubStructure.SSB - Install Stem Walls - Grid lines 7-01/7-10 (Pre WI#01) | Foundations | Complete | 03/05/26 | 03/10/26 | 5.0 | 0.0 |
|
0.0 |
RPL07.VDC.1380 |
T0 (Bldg07) - Procure UG Materials | TIER 0 - Building 07 | Complete | 03/05/26 | 03/16/26 | 15.0 | 0.0 |
|
0.0 |
RPL07.MR.1260 |
RPL07.MR - Mobilization Complete | Make Ready | Complete | 03/06/26 | 03/06/26 | 0.0 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01060 |
RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 1 (West of GL 17) (LOE) | Underground | Complete | 03/06/26 | 03/17/26 | 7.5 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01365 |
RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 1 (West of GL 17) (Pre WI#01) | Underground | Complete | 03/06/26 | 03/10/26 | 3.8 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01030 |
RPL07.SubStructure.SSB - Foundation For Storm Shelter Rebar CMU (LOE) | Foundations | Complete | 03/06/26 | 03/16/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01050 |
RPL07.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 (LOE) | Underground | Complete | 03/06/26 | 03/16/26 | 11.2 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01060 |
RPL07.SubStructure.SSB - Install UG Utilities - WBS Summary | Underground | Complete | 03/06/26 | 03/27/26 | 30.0 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01220 |
RPL07.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Acclimation to Swing Shift (LOE) | Underground | Complete | 03/06/26 | 03/18/26 | 10.0 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01295 |
RPL07.SubStructure.SSB - Foundation For Storm Shelter Rebar CMU (Pre WI#01) | Foundations | Complete | 03/06/26 | 03/10/26 | 3.8 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01305 |
RPL07.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 (Pre WI#01) | Underground | Complete | 03/06/26 | 03/10/26 | 3.8 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01315 |
RPL07.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Acclimation to Swing Shift (Pre WI#01) | Underground | Complete | 03/06/26 | 03/10/26 | 3.8 | 0.0 |
|
0.0 |
PRE.TPA.1220 |
Ceiling - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Active | 03/09/26 | 04/14/26 | 6.2 | 2.5 |
|
82.5 |
RPL.07.D.71015.XR |
Pad Ready - RPL07 (DPR Date: xxx) East Half of Building (7-17 to 7-28) | Receive Milestones (XREFs) | Complete | 03/09/26 | 03/09/26 | 0.0 | 0.0 |
|
0.0 |
RPL07.MR.1301 |
RPL07.MR - Make Ready Work (for unavailability of roads around East Half of Pad) (LOE) | Make Ready | Complete | 03/09/26 | 03/17/26 | 8.8 | 0.0 |
|
0.0 |
RPL07.MR.1306 |
RPL07.MR - Make Ready Work (for unavailability of roads around East Half of Pad) (Pre WI#01) | Make Ready | Complete | 03/09/26 | 03/10/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01090 |
RPL07.SubStructure.DHAB - Install UG UT - Elec/Testing, Pathway Verification & Backfill - Part 1 (West of GL 17)(LOE) | Underground | Complete | 03/09/26 | 03/23/26 | 11.2 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01130 |
RPL07.SubStructure.DHAB - Piers Protection Concrete Capping - Grid lines 7-10/7-17 (West of GL 17) | Foundations | Complete | 03/09/26 | 03/10/26 | 3.8 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01330 |
RPL07.SubStructure.DHAB - Install UG UT - Elec/Testing, Pathway Ver. & BF - Part 1 **Swing Shift** (West of GL 17)(LOE) | Underground | Complete | 03/09/26 | 03/23/26 | 11.2 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01345 |
RPL07.SubStr.DHAB - Install UG UT - Elec/Testing, Pathway Ver. & BF - Part 1 **Swing** (West of GL 17) (Pre WI#01) | Underground | Complete | 03/09/26 | 03/10/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01355 |
RPL07.SubStr.DHAB - Install UG UT - Elec/Testing, Pathway Verification & Backfill - Part 1 (West of GL 17) (Pre WI#01) | Underground | Complete | 03/09/26 | 03/10/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01090 |
RPL07.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 1 (LOE) | Underground | Complete | 03/09/26 | 03/19/26 | 11.2 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01240 |
RPL07.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Backfill - Acclimation to Swing Shift (LOE) | Underground | Complete | 03/09/26 | 03/19/26 | 11.2 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01325 |
RPL07.SubStructure.SSB - Install UG Utilities - Electrical/Testing & Pathway Verification & Backfill - Pt1 (Pre WI#01) | Underground | Complete | 03/09/26 | 03/10/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01335 |
RPL07.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Backfill - Acclimation to Swing Shift (Pre WI#01) | Underground | Complete | 03/09/26 | 03/10/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.PI.1000 |
Weather Event #1 - 03.11.2026 - 03.12.2026 | Project Impacts | Complete | 03/11/26 | 03/12/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01005 |
RPL07.SubStructure.DHAB - Install Drilled Piers - Grid lines 7-17/7-23 (East of GL 17) (LOE) | Foundations | Complete | 03/11/26 | 03/14/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01010 |
RPL07.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Active | 03/11/26 | 04/16/26 | 32.5 | 2.5 |
|
48.8 |
RPL07.SUB.DHAB.01335 |
RPL07.SubStructure.DHAB - Install Drilled Piers - Grid lines 7-17/7-23 (East of GL 17) (Pre WI#01) | Foundations | Complete | 03/11/26 | 03/11/26 | 1.2 | 0.0 |
|
0.0 |
RPL07.SUB.DHCD.01000 |
RPL07.SubStructure.DHCD - Install Drilled Piers - Grid lines 7-22/7-28 | Foundations | Complete | 03/11/26 | 03/14/26 | 5.0 | 0.0 |
|
0.0 |
RPL07.SUB.DHCD.01010 |
RPL07.SubStructure.DHCD - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Active | 03/11/26 | 04/15/26 | 25.0 | 3.8 |
|
41.2 |
RPL07.SUB.DHCD.01020 |
RPL07.SubStructure.DHCD - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | DH D & DH C | Active | 03/11/26 | 04/15/26 | 25.0 | 3.8 |
|
41.2 |
RPL07.MR.1311 |
RPL07.MR - Make Ready Work (for unavailability of roads around East Half of Pad) (Post WI#01) | Make Ready | Complete | 03/13/26 | 03/17/26 | 3.8 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01310 |
RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 1 **Swing Shift** (West of GL 17) | Underground | Complete | 03/13/26 | 03/19/26 | 7.5 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01340 |
RPL07.SubStructure.DHAB - Install Drilled Piers - Grid lines 7-17/7-23 (East of GL 17) (Post WI#01) | Foundations | Complete | 03/13/26 | 03/14/26 | 3.8 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01350 |
RPL07.SubStr.DHAB - Install UG UT - Elec/Testing, Pathway Ver. & BF - Part 1 **Swing** (West of GL 17) (Post WI#01) | Underground | Complete | 03/13/26 | 03/24/26 | 5.0 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01360 |
RPL07.SubStr.DHAB - Install UG UT - Elec/Testing, Pathway Verification & Backfill - Part 1 (West of GL 17) (Post WI#01) | Underground | Complete | 03/13/26 | 03/23/26 | 5.0 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01370 |
RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 1 (West of GL 17) (Post WI#01) | Underground | Complete | 03/13/26 | 03/17/26 | 3.8 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01260 |
RPL07.SubStructure.SSB - Install UG Utilities - BMS/EPMS/Testing and Backfill - Acclimation to Swing Shift | Underground | Complete | 03/13/26 | 03/19/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01270 |
RPL07.SubStructure.SSB - Piers Protection Concrete Capping (Post WI#01) | Foundations | Complete | 03/13/26 | 03/16/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01280 |
RPL07.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 7-01/7-10 (Post WI#01) | Foundations | Complete | 03/13/26 | 03/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01290 |
RPL07.SubStructure.SSB - Install Stem Walls - Grid lines 7-01/7-10 (Post WI#01) | Foundations | Complete | 03/13/26 | 03/21/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01300 |
RPL07.SubStructure.SSB - Foundation For Storm Shelter Rebar CMU (Post WI#01) | Foundations | Complete | 03/13/26 | 03/16/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01310 |
RPL07.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 (Post WI#01) | Underground | Complete | 03/13/26 | 03/16/26 | 7.5 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01320 |
RPL07.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Acclimation to Swing Shift (Post WI#01) | Underground | Complete | 03/13/26 | 03/18/26 | 5.0 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01330 |
RPL07.SubStructure.SSB - Install UG Utilities - Electrical/Testing & Pathway Verification & Backfill - Pt1 (Post WI#01) | Underground | Complete | 03/13/26 | 03/19/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01340 |
RPL07.SubStructure.SSB - Install UG Utilities - Electrical/Testing and Backfill - Acclimation to Swing Shift(Post WI#01) | Underground | Complete | 03/13/26 | 03/19/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01135 |
RPL07.SubStructure.DHAB - Piers Protection Concrete Capping - Grid lines 7-17/7-23 (East of GL 17) | Foundations | Complete | 03/14/26 | 03/16/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.CFCI.4120 |
RPL07 - Fabricate / Deliver - Exterior Louvers | Fixed Louvers | Active | 03/16/26 | 07/24/26 | 75.0 | 91.2 |
|
258.8 |
RPL07.CFCI.4560 |
RPL07 - Submittals Review & Approval - Gypsum System | (CFCI) Div. 09 - Gypsum System & Ceilings | Complete | 03/16/26 | 04/10/26 | 25.0 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01100 |
RPL07.SubStructure.DHAB - Install UG UT - BMS/EPMS/Testing, Pathway Verification & Backfill (new GS scope West of 17) | Underground | Complete | 03/16/26 | 03/24/26 | 11.2 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01150 |
RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 2 (West of GL 17) | Underground | Complete | 03/16/26 | 04/06/26 | 7.5 | 0.0 |
|
0.0 |
RPL07.SUB.DHCD.01130 |
RPL07.SubStructure.DHCD - Piers Protection Concrete Capping | Foundations | Complete | 03/16/26 | 03/19/26 | 5.0 | 0.0 |
|
0.0 |
RPL07.SUB.SSB.01110 |
RPL07.SubStructure.SSB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill | Underground | Complete | 03/16/26 | 03/20/26 | 12.5 | 0.0 |
|
0.0 |
PRE.BNS.1480 |
Execution of fGMP | FGMP | Complete | 03/17/26 | 03/17/26 | 0.0 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01030 |
RPL07.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 7-10/7-17 (West of GL 17) | Foundations | Complete | 03/17/26 | 03/26/26 | 8.8 | 0.0 |
|
0.0 |
RPL07.VDC.1160 |
T0 (mCUP Yard/Ext.) - Review & Approve BIM Shop | TIER 0 - mCUP Yard / Exterior | Complete | 03/17/26 | 03/30/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.VDC.1200 |
T0 (Bldg07) - Review & Approve BIM Shop | TIER 0 - Building 07 | Complete | 03/17/26 | 03/26/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01065 |
RPL07.SubStructure.DHAB - Install UG UT - Plumbing/Testing/Backfill - Part 1 (East of GL 17) | Underground | Complete | 03/18/26 | 03/19/26 | 2.5 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01070 |
RPL07.SubStructure.DHAB - Install UG UT - WBS Summary | Underground | Complete | 03/18/26 | 04/08/26 | 16.2 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01210 |
RPL07.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 7-17/7-23 (East of GL 17) | Foundations | Complete | 03/18/26 | 03/25/26 | 6.2 | 0.0 |
|
0.0 |
RPL07.SUB.DHAB.01170 |
RPL07.SubStructure.DHAB - Install UG UT - Electrical/Testing, Pathway Verification & Backfill - Part 2 (West of GL 17) | Underground | Complete | 03/19/26 | 04/02/26 | 5.0 | 0.0 |
|
0.0 |
RPL07.MCUP.LP1.1000 |
RPL07.MCUP.Loop 1 - Install Foundations, UG Utilities, OFE - WBS Summary | mCup Loop 1 | Active | 03/20/26 | 10/16/26 | 176.2 | 165.0 |
|
378.8 |
RPL07.MCUP.LP1.1040 |
RPL07.MCUP.Loop 1 - Install UG Utilities - WBS Summary | Underground | Active | 03/20/26 | 04/20/26 | 38.8 | 7.5 |
|
185.0 |
RPL07.MCUP.LP1.1080 |
RPL07.MCUP.Loop 1 - Install Electrical UG | Electrical UG | Active | 03/20/26 | 04/20/26 | 25.0 | 7.5 |
|
93.8 |
RPL07.mCUP.1060 |
RPL07.MCUP.BLDG - Install Foundations, UG Utilities, OFE 1-6 - WBS Summary | mCUP Yard | Active | 03/20/26 | 10/28/26 | 186.2 | 175.0 |
|
368.8 |
20 |
RPL07.Connectivity.WP4 FENW DHC CFD C.4 Patch & Dress for SSW to JXSW (ORv3N) **OBSOLETE** | Obsolete | Complete | 03/23/26 | 03/23/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CFCI.3190 |
RPL07 - Coordinate Scope and Submittal Req's - Vesda System | (CFCI) Div. 28 - VESDA System | Complete | 03/23/26 | 03/23/26 | 1.2 | 0.0 |
|
0.0 |
RPL07.CFCI.4710 |
RPL07 - Submittals Prep & Submit for Review - Vesda System | (CFCI) Div. 28 - VESDA System | Active | 03/23/26 | 06/12/26 | 73.8 | 55.0 |
|
111.2 |
RPL07.CFCI.4980 |
RPL07 - Submittals Review & Approval - Finished Carpentry (FRP) | FRP [Hallways] | Complete | 03/23/26 | 04/10/26 | 18.8 | 0.0 |
|
0.0 |
RPL07.CFCI.6490 |
Submittal Review & Approval - Roof Drain Pipes | (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 | Complete | 03/23/26 | 04/06/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CON.WP4.01040 |
RPL07.Connectivity.WP4 FENW DHB CFD B.1 Pull for SSW to JXSW (ORv3N) **OBSOLETE** | Obsolete | Complete | 03/23/26 | 03/23/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CON.WP4.01060 |
RPL07.Connectivity.WP4 FENW DHB CFD B.1 Pull for FSW (ORv3N) **OBSOLETE** to SSW (ORv3N) **OBSOLETE** | Obsolete | Complete | 03/23/26 | 03/23/26 | 10.0 | 0.0 |
|
0.0 |
RPL07.CON.WP4.01080 |
RPL07.Connectivity.WP4 FENW DHB CFD B.1 Pull for RSW (ORv3) to FSW (ORv3N) **OBSOLETE** | Obsolete | Complete | 03/23/26 | 03/23/26 | 10.0 | 0.0 |
|
0.0 |
RPL07.CON.WP4.010940 |
RPL07.Connectivity.WP4 FENW DHB CFD B.1 Patch & Dress for SSW to JXSW (ORv3N) **OBSOLETE** | Obsolete | Complete | 03/23/26 | 03/23/26 | 12.5 | 0.0 |
|
0.0 |
RPL07.CON.WP4.010960 |
RPL07.Connectivity.WP4 FENW DHB CFD B.1 Patch & Dress for FSW (ORv3N) **OBSOLETE** to SSW (ORv3N) **OBSOLETE** | Obsolete | Complete | 03/23/26 | 03/23/26 | 10.0 | 0.0 |
|
0.0 |
RPL07.CON.WP4.010980 |
RPL07.Connectivity.WP4 FENW DHB CFD B.1 Patch & Dress for RSW (ORv3) to FSW (ORv3N) **OBSOLETE** | Obsolete | Complete | 03/23/26 | 03/23/26 | 10.0 | 0.0 |
|
0.0 |