Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
52
Completed
48
In Progress
54
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
PRE.EP.1000 |
Identify Program Directives, Initiatives, and Expectations - Precon/Estimating | Precon- Early Precon | Complete | 05/20/24 | 07/08/24 | 47.5 | 0.0 |
|
0.0 |
PRE.EP.1020 |
Precon Kick Off (Target Value, Risk, Schedule) | Precon- Early Precon | Complete | 07/11/24 | 07/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.EP.1040 |
Initial PWO Document Creation (GC) | Precon- Early Precon | Complete | 07/29/24 | 08/16/24 | 6.2 | 0.0 |
|
0.0 |
PRE.EP.1060 |
GC PWO Exhibits Received | Precon- Early Precon | Complete | 07/29/24 | 07/29/24 | 0.0 | 0.0 |
|
0.0 |
PRE.EP.1080 |
PWO Meta Legal Review Send Draft | Precon- Early Precon | Complete | 08/16/24 | 10/18/24 | 5.0 | 0.0 |
|
0.0 |
PRE.BNS.1000 |
Baseline 1 Development | Precon - Budget & Schedule | Complete | 09/02/24 | 10/11/24 | 35.0 | 0.0 |
|
0.0 |
PRE.BNS.1020 |
Develop Baseline 1 Budget & Schedule | Precon - Budget & Schedule | Complete | 09/02/24 | 10/10/24 | 35.0 | 0.0 |
|
0.0 |
PRE.BNS.1040 |
Baseline 1 Issuance | Precon - Budget & Schedule | Complete | 10/11/24 | 10/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1060 |
Establish Baseline 1 | Precon - Budget & Schedule | Complete | 10/11/24 | 10/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.CIDD.1000 |
Issue Bid Package List with Subcontractors & Meta Approval | Precon - Critical Information / Decision Dates | Complete | 10/11/24 | 10/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.CIDD.1020 |
Initial Procurement Plan Approved | Precon - Critical Information / Decision Dates | Complete | 10/11/24 | 10/11/24 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1080 |
Meta Review & Comment - Baseline 1 | Precon - Budget & Schedule | Complete | 10/14/24 | 11/01/24 | 18.8 | 0.0 |
|
0.0 |
DES.PRS.1000 |
Development of PRS | PRS | Complete | 10/16/24 | 05/26/25 | 46.2 | 0.0 |
|
0.0 |
PRE.EP.1100 |
Revised PWO Document Submission (GC) | Precon- Early Precon | Complete | 10/21/24 | 11/04/24 | 6.2 | 0.0 |
|
0.0 |
ICM.G.0001.2 |
RPL06 Commencement Date | IMS P0 Milestones | Complete | 11/01/24 | 11/01/24 | 0.0 | 0.0 |
|
0.0 |
PRE.EP.1120 |
PWO Meta Legal Review | Precon- Early Precon | Complete | 11/05/24 | 12/03/24 | 18.8 | 0.0 |
|
0.0 |
PRE.EP.1140 |
PWO Signed | Precon- Early Precon | Complete | 12/04/24 | 12/04/24 | 0.0 | 0.0 |
|
0.0 |
DES.EP.1120 |
Site BIM Coordination Package [Civil & Struct. Foundation] | Early Packages | Complete | 01/03/25 | 03/31/25 | 75.0 | 0.0 |
|
0.0 |
PRE.BNS.1100 |
Finalize GC/GRs for BL 2 (DPR to Meta) | Precon - Budget & Schedule | Complete | 01/13/25 | 07/28/25 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1120 |
Site Logistics Create and Approval for BL 2 | BL2 | Complete | 01/13/25 | 09/19/25 | 5.0 | 0.0 |
|
0.0 |
PRE.BNS.1140 |
Develop Project Review Set - Baseline 2 Estimate & Schedule | BL2 | Complete | 01/13/25 | 08/28/25 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.6510 |
Fabricate / Deliver - Roof Drain (Scupper & Downspots) | (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 | Active | 02/21/25 | 05/15/26 | 25.0 | 31.2 |
|
278.8 |
DES.EP.1040 |
Design Kick Off ( with Product Development Design Package) | Early Packages | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.PRED |
PRED | Obsolete | Complete | 03/03/25 | 03/03/25 | 0.0 | 0.0 |
|
0.0 |
DES.PRS.1020 |
Project Review Set (PRS) | PRS | Complete | 05/27/25 | 05/27/25 | 0.0 | 0.0 |
|
0.0 |
DES.PRS.1040 |
PRS Issuance | PRS | Complete | 05/27/25 | 05/27/25 | 0.0 | 0.0 |
|
0.0 |
DES.PRS.1060 |
PRS Review Cycle | PRS | Complete | 05/27/25 | 07/18/25 | 30.0 | 0.0 |
|
0.0 |
DES.PRS.1080 |
PRS Page Turn | PRS | Complete | 05/27/25 | 06/11/25 | 8.8 | 0.0 |
|
0.0 |
PRE.BNS.1160 |
Preliminary Baseline 2 Development (Progress update only DD-6.22.25) | BL2 | Complete | 05/27/25 | 08/04/25 | 30.0 | 0.0 |
|
0.0 |
PRE.BNS.1170 |
Baseline 2 Development | BL2 | Complete | 05/27/25 | 08/04/25 | 30.0 | 0.0 |
|
0.0 |
RPL.PD.D.PX110.XR |
PRS Set - RPL-0 - Complete | PRS | Complete | 05/27/25 | 05/27/25 | 0.0 | 0.0 |
|
0.0 |
DES.PRS.1100 |
IFP Design Lock | PRS | Complete | 07/18/25 | 07/18/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.OFCI.2020 |
OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHB) - 12 | (OFCI) - RPL06 - PLC Panels | Complete | 07/25/25 | 10/31/25 | 1.2 | 0.0 |
|
0.0 |
RPL06.OFCI.2030 |
OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHA) - 12 | (OFCI) - RPL06 - PLC Panels | Complete | 07/25/25 | 10/31/25 | 1.2 | 0.0 |
|
0.0 |
RPL06.OFCI.2240 |
OFE Delivery ROJ: 3MW Generator (DHD/DHC) - 2 (VC08.19.26) | (OFCI) - RPL06 - Generators | Active | 07/25/25 | 08/19/26 | 331.2 | 113.8 |
|
148.8 |
RPL06.OFCI.2260 |
OFE Delivery ROJ: 3MW Generator (DHA/DHB) - 1 (VC08.05.26) | (OFCI) - RPL06 - Generators | Active | 07/25/25 | 08/05/26 | 322.5 | 101.2 |
|
57.5 |
RPL06.OFCI.2300 |
OFE Delivery ROJ: GSB (DHD/DHC) - 2 (ROJ08.12.26) | (OFCI) - RPL06 - Generator Switchboard GSB | Complete | 07/25/25 | 01/16/26 | 326.2 | 0.0 |
|
0.0 |
RPL06.OFCI.2320 |
OFE Delivery ROJ: GSB (DHA/DHB) - 1 (ROJ06.23.26) | (OFCI) - RPL06 - Generator Switchboard GSB | Complete | 07/25/25 | 01/16/26 | 322.5 | 0.0 |
|
0.0 |
RPL06.OFCI.2830 |
OFE Delivery ROJ: UPS - Core UPS (DHB) - 12 | (OFCI) - RPL06 - UPS | Active | 07/25/25 | 06/08/26 | 323.8 | 50.0 |
|
90.0 |
RPL06.OFCI.3070 |
OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHD) - 12 | (OFCI) - RPL06 - PLC Panels | Complete | 07/25/25 | 10/31/25 | 1.2 | 0.0 |
|
0.0 |
RPL06.OFCI.3090 |
OFE Delivery ROJ: PLC Panels to Integrator - DH Manager/RIO (DHC) - 12 | (OFCI) - RPL06 - PLC Panels | Complete | 07/25/25 | 10/31/25 | 1.2 | 0.0 |
|
0.0 |
RPL06.OFCI.3110 |
OFE Delivery ROJ: UPS - Core UPS (DHA) - 12 | (OFCI) - RPL06 - UPS | Active | 07/25/25 | 06/08/26 | 26.2 | 50.0 |
|
102.5 |
RPL06.OFCI.3130 |
OFE Delivery ROJ: UPS - Core UPS (DHD) - 10 | (OFCI) - RPL06 - UPS | Active | 07/25/25 | 06/11/26 | 435.0 | 53.8 |
|
177.5 |
RPL06.OFCI.3150 |
OFE Delivery ROJ: UPS - Core UPS (DHC) - 10 | (OFCI) - RPL06 - UPS | Active | 07/25/25 | 06/11/26 | 472.5 | 53.8 |
|
193.8 |
RPL06.OFCI.3190 |
OFE Delivery ROJ: UPS - Control Power UPS (EC) - (Room #3.1) | (OFCI) - RPL06 - UPS | Complete | 07/25/25 | 12/30/25 | 26.2 | 0.0 |
|
0.0 |
RPL06.OFCI.3210 |
OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHB) - 4 | (OFCI) - RPL06 - PLC Panels | Active | 07/25/25 | 06/25/26 | 1.2 | 66.2 |
|
73.8 |
RPL06.OFCI.3230 |
OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHA) - 4 | (OFCI) - RPL06 - PLC Panels | Active | 07/25/25 | 07/14/26 | 1.2 | 81.2 |
|
71.2 |
RPL06.OFCI.3250 |
OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHD) - 4 | (OFCI) - RPL06 - PLC Panels | Active | 07/25/25 | 10/19/26 | 1.2 | 166.2 |
|
65.0 |
RPL06.OFCI.3270 |
OFE Delivery ROJ: PLC Panels to Site - Misc I/O (DHC) - 4 | (OFCI) - RPL06 - PLC Panels | Active | 07/25/25 | 11/02/26 | 1.2 | 178.8 |
|
68.8 |
RPL06.OFCI.3290 |
OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHB) - 1 | (OFCI) - RPL06 - PLC Panels | Complete | 07/25/25 | 10/31/25 | 1.2 | 0.0 |
|
0.0 |
RPL06.OFCI.3310 |
OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHA) - 1 | (OFCI) - RPL06 - PLC Panels | Complete | 07/25/25 | 10/31/25 | 1.2 | 0.0 |
|
0.0 |
RPL06.OFCI.3330 |
OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHD) - 1 | (OFCI) - RPL06 - PLC Panels | Complete | 07/25/25 | 10/31/25 | 1.2 | 0.0 |
|
0.0 |
RPL06.OFCI.3350 |
OFE Delivery ROJ: PLC Panels to Integrator - FCM I/O (DHC) - 1 | (OFCI) - RPL06 - PLC Panels | Complete | 07/25/25 | 10/31/25 | 1.2 | 0.0 |
|
0.0 |
RPL06.OFCI.6620 |
OFE Delivery ROJ: PTX-FWM (CUP) (ROJ03.12.26) | (OFCI) - RPL06 - PTX | Complete | 07/25/25 | 09/30/25 | 1.2 | 0.0 |
|
0.0 |
RPL06.OFCI.6640 |
OFE Delivery ROJ: Interior Dry Coolers - mCUP1 (CUP) - 3 pcs (ROJ03.12.26) | (OFCI) - RPL06 - Dry Coolers | Complete | 07/25/25 | 01/14/26 | 163.8 | 0.0 |
|
0.0 |
RPL06.OFCI.6660 |
OFE Delivery ROJ: Interior Dry Coolers - mCUP2 (CUP) - 3 pcs (ROJ03.12.26) | (OFCI) - RPL06 - Dry Coolers | Complete | 07/25/25 | 03/04/26 | 163.8 | 0.0 |
|
0.0 |
RPL06.OFCI.6680 |
OFE Delivery ROJ: Interior Dry Coolers - mCUP3 (CUP) - 3 pcs (ROJ04.02.26) | (OFCI) - RPL06 - Dry Coolers | Complete | 07/25/25 | 03/04/26 | 182.5 | 0.0 |
|
0.0 |
RPL06.OFCI.6720 |
OFE Delivery ROJ: Interior Dry Coolers - mCUP4 (CUP) - 3 pcs (ROJ04.02.26) | (OFCI) - RPL06 - Dry Coolers | Active | 07/25/25 | 04/13/26 | 182.5 | 0.0 |
|
103.8 |
RPL06.OFCI.6760 |
OFE Delivery ROJ: Interior Dry Coolers - mCUP5 (CUP) - 3 pcs (ROJ04.24.26) | (OFCI) - RPL06 - Dry Coolers | Active | 07/25/25 | 04/24/26 | 201.2 | 12.5 |
|
196.2 |
RPL06.OFCI.6780 |
OFE Delivery ROJ: Interior Dry Coolers - mCUP6 (CUP) - 3 pcs (ROJ04.24.26) | (OFCI) - RPL06 - Dry Coolers | Active | 07/25/25 | 04/24/26 | 201.2 | 12.5 |
|
196.2 |
RPL06.OFCI.6785 |
OFE Delivery ROJ: Exterior Dry Coolers - mCUP1 (CUP) - 3 pcs (ROJ03.12.26) | (OFCI) - RPL06 - Dry Coolers | Complete | 07/25/25 | 01/14/26 | 163.8 | 0.0 |
|
0.0 |
RPL06.OFCI.6790 |
OFE Delivery ROJ: Exterior Dry Coolers - mCUP2 (CUP) - 3 pcs (ROJ03.12.26) | (OFCI) - RPL06 - Dry Coolers | Complete | 07/25/25 | 03/04/26 | 163.8 | 0.0 |
|
0.0 |
RPL06.OFCI.6795 |
OFE Delivery ROJ: Exterior Dry Coolers - mCUP3 (CUP) - 3 pcs (ROJ04.02.26) | (OFCI) - RPL06 - Dry Coolers | Complete | 07/25/25 | 03/04/26 | 182.5 | 0.0 |
|
0.0 |
RPL06.OFCI.6805 |
OFE Delivery ROJ: Exterior Dry Coolers - mCUP4 (CUP) - 3 pcs (ROJ04.02.26) | (OFCI) - RPL06 - Dry Coolers | Active | 07/25/25 | 04/13/26 | 182.5 | 0.0 |
|
103.8 |
RPL06.OFCI.6815 |
OFE Delivery ROJ: Exterior Dry Coolers - mCUP5 (CUP) - 3 pcs (ROJ04.24.26) | (OFCI) - RPL06 - Dry Coolers | Active | 07/25/25 | 04/24/26 | 201.2 | 12.5 |
|
196.2 |
RPL06.OFCI.6820 |
OFE Delivery ROJ: Exterior Dry Coolers - mCUP6 (CUP) - 3 pcs (ROJ04.24.26) | (OFCI) - RPL06 - Dry Coolers | Active | 07/25/25 | 04/24/26 | 201.2 | 12.5 |
|
196.2 |
RPL06.OFE.1050 |
OFE Delivery ROJ: MV Skid (DHB) - 12 (ROJ05.26.26) (RVCD 07.13.26) | (MOFE) - RPL06 - RMU Electrical Yard / MV Skids - Outside | Active | 07/25/25 | 07/13/26 | 1.2 | 80.0 |
|
20.0 |
RPL06.OFE.1060 |
OFE Delivery ROJ: MV Skid (DHA) - 12 (ROJ06.09.26) (RVCD 07.20.26) | (MOFE) - RPL06 - RMU Electrical Yard / MV Skids - Outside | Active | 07/25/25 | 07/20/26 | 296.2 | 86.2 |
|
32.5 |
RPL06.OFE.1080 |
OFE Delivery ROJ: MV Skid (DHD) - 10 (ROJ07.15.26) (RVCD 07.24.26) | (MOFE) - RPL06 - RMU Electrical Yard / MV Skids - Outside | Active | 07/25/25 | 07/24/26 | 305.0 | 91.2 |
|
115.0 |
RPL06.OFE.1100 |
OFE Delivery ROJ: MV Skid (DHC) - 10 (ROJ07.29.26) (RVCD 08.10.26) | (MOFE) - RPL06 - RMU Electrical Yard / MV Skids - Outside | Active | 07/25/25 | 08/10/26 | 335.0 | 105.0 |
|
123.8 |
RPL06.OFE.1110 |
OFE Delivery ROJ: GS.MDF (DHB) - 1 (ROJ05.14.26) (RVCD 05.29.26) | (MOFE) - RPL06 - GS.MDF Module (Facnet) | Active | 07/25/25 | 05/29/26 | 1.2 | 42.5 |
|
102.5 |
RPL06.OFE.1140 |
OFE Delivery ROJ: GS.IDF Hut - Exterior (mCUP) - 2 qty (GSIDF6X01,02,03) (ROJ03.25.26) (RVCD 04.29.26) | (MOFE) - RPL06 - GS.IDF (Exterior and Interior) | Active | 07/25/25 | 04/28/26 | 163.8 | 15.0 |
|
95.0 |
RPL06.OFE.1150 |
OFE Delivery ROJ: GS.IDF Hut - Exterior (mCUP & South Yard*) - 2qty (GSIDF6X04) (ROJ04.29.26) (RVCD - 5.14.26) | (MOFE) - RPL06 - GS.IDF (Exterior and Interior) | Active | 07/25/25 | 05/13/26 | 248.8 | 28.8 |
|
188.8 |
RPL06.OFE.1200 |
OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF6B2) - 1 qty (ROJ06.24.26) (RVCD 07.01.26) | (MOFE) - RPL06 - GS.IDF (Exterior and Interior) | Active | 07/25/25 | 07/01/26 | 255.0 | 71.2 |
|
115.0 |
RPL06.OFE.1220 |
OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF6A2) - 1 qty (ROJ06.24.26) (RVCD 07.01.26) | (MOFE) - RPL06 - GS.IDF (Exterior and Interior) | Active | 07/25/25 | 07/01/26 | 318.8 | 71.2 |
|
115.0 |
RPL06.OFE.1228 |
OFE Delivery ROJ: FWM (CUP) - 1 (ROJ07.15.26) | (MOFE) - RPL06 - Facility Water | Complete | 07/25/25 | 09/30/25 | 165.0 | 0.0 |
|
0.0 |
RPL06.OFE.1230 |
OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF6D2) - 1 qty (ROJ07.23.26) (RVCD 08.19.26) | (MOFE) - RPL06 - GS.IDF (Exterior and Interior) | Active | 07/25/25 | 08/19/26 | 1.2 | 113.8 |
|
146.2 |
RPL06.OFE.1240 |
OFE Delivery ROJ: GS.MDF (DHA) - 1 (ROJ05.14.26) (RVCD 05.29.26) | (MOFE) - RPL06 - GS.MDF Module (Facnet) | Active | 07/25/25 | 05/29/26 | 7.5 | 42.5 |
|
108.8 |
RPL06.OFE.1250 |
OFE Delivery ROJ: GS.IDF Room - Interior (GSIDF6C2) - 1 qty (ROJ07.23.26) (RVCD 08.19.26) | (MOFE) - RPL06 - GS.IDF (Exterior and Interior) | Active | 07/25/25 | 08/19/26 | 1.2 | 113.8 |
|
140.0 |
RPL06.OFE.1400 |
OFE Delivery ROJ: MES Skids CDU/MTR (DHB) - 10 (Deliver 2 per day) (ROJ05.19.26) | (MOFE) - RPL06 - MES CDU/MTR | Active | 07/25/25 | 05/01/26 | 1.2 | 18.8 |
|
126.2 |
RPL06.OFE.1420 |
OFE Delivery ROJ: MES Skids CDU/MTR (DHA) - 10 (Deliver 2 per day) (ROJ06.03.26) | (MOFE) - RPL06 - MES CDU/MTR | Active | 07/25/25 | 06/02/26 | 290.0 | 45.0 |
|
100.0 |
RPL06.OFE.1440 |
OFE Delivery ROJ: MES Skids CDU/MTR (DHD) - 8 (Deliver 2 per day) (ROJ07.09.26) | (MOFE) - RPL06 - MES CDU/MTR | Active | 07/25/25 | 07/08/26 | 298.8 | 76.2 |
|
118.8 |
RPL06.OFE.1460 |
OFE Delivery ROJ: MES Skids CDU/MTR (DHC) - 8 (Deliver 2 per day) (ROJ07.23.26) | (MOFE) - RPL06 - MES CDU/MTR | Active | 07/25/25 | 07/22/26 | 328.8 | 88.8 |
|
95.0 |
RPL06.OFE.2050 |
OFE Delivery ROJ: mCUP - mCUP1 - 1 (6 Pieces) (ROJ03.13.26) | (MOFE) - RPL06 - mCUP | Complete | 07/25/25 | 03/31/26 | 191.2 | 0.0 |
|
0.0 |
RPL06.OFE.3480 |
OFE Delivery ROJ: mCUP - mCUP5 - 1 (6 Pieces) (ROJ04.10.26) | (MOFE) - RPL06 - mCUP | Active | 07/25/25 | 04/13/26 | 225.0 | 0.0 |
|
205.0 |
RPL06.OFE.3490 |
OFE Delivery ROJ: mCUP - mCUP2 - 1 (6 Pieces) (ROJ03.20.26) | (MOFE) - RPL06 - mCUP | Complete | 07/25/25 | 04/07/26 | 197.5 | 0.0 |
|
0.0 |
RPL06.OFE.3510 |
OFE Delivery ROJ: mCUP - mCUP3 - 1 (6 Pieces) (ROJ03.27.26) | (MOFE) - RPL06 - mCUP | Active | 07/25/25 | 04/13/26 | 203.8 | 0.0 |
|
101.2 |
RPL06.OFE.3540 |
OFE Delivery ROJ: mCUP - mCUP4 - 1 (6 Pieces) (ROJ04.03.26) | (MOFE) - RPL06 - mCUP | Active | 07/25/25 | 04/13/26 | 210.0 | 0.0 |
|
107.5 |
RPL06.OFE.3560 |
OFE Delivery ROJ: mCUP - mCUP6 - 1 (6 Pieces) (ROJ04.17.26) | (MOFE) - RPL06 - mCUP | Active | 07/25/25 | 04/17/26 | 231.2 | 6.2 |
|
205.0 |
RPL06.OFE.5460 |
OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHB) - 21 (ROJ06.03.26) | (MOFE) - RPL06 - Floor Supported Hot Aisle Containment & Mech. Side Aisle | Active | 07/25/25 | 05/19/26 | 1.2 | 33.8 |
|
41.2 |
RPL06.OFE.5470 |
OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHA) - 21 (ROJ06.10.26) | (MOFE) - RPL06 - Floor Supported Hot Aisle Containment & Mech. Side Aisle | Active | 07/25/25 | 06/02/26 | 310.0 | 45.0 |
|
37.5 |
RPL06.OFE.5480 |
OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHD) - 17 (ROJ08.12.26) | (MOFE) - RPL06 - Floor Supported Hot Aisle Containment & Mech. Side Aisle | Active | 07/25/25 | 08/12/26 | 418.8 | 107.5 |
|
76.2 |
RPL06.OFE.5490 |
OFE Delivery ROJ: FSHAC & Mech Side Aisle (DHC) - 17 (ROJ08.26.26) | (MOFE) - RPL06 - Floor Supported Hot Aisle Containment & Mech. Side Aisle | Active | 07/25/25 | 08/26/26 | 431.2 | 120.0 |
|
65.0 |
RPL06.OFE.6800 |
OFE Delivery ROJ: LV Skid (DHB) - 12 (ROJ05.18.26) (RVCD 07.06.26) | (MOFE) - RPL06 - LV Electrical Gallery / LV Skids - Inside NS | Active | 07/25/25 | 07/06/26 | 277.5 | 73.8 |
|
-8.8 |
RPL06.OFE.6820 |
OFE Delivery ROJ: LV Skid (DHA) - 12 (ROJ06.02.26) (RVCD 07.10.26) | (MOFE) - RPL06 - LV Electrical Gallery / LV Skids - Inside NS | Active | 07/25/25 | 07/10/26 | 290.0 | 78.8 |
|
-1.2 |
RPL06.OFE.6840 |
OFE Delivery ROJ: LV Skid (DHD) - 10 (ROJ07.08.26) (RVCD 07.16.26) | (MOFE) - RPL06 - LV Electrical Gallery / LV Skids - Inside NS | Active | 07/25/25 | 07/16/26 | 298.8 | 83.8 |
|
81.2 |
RPL06.OFE.6860 |
OFE Delivery ROJ: LV Skid (DHC) - 10 (ROJ07.22.26) (RVCD 08.04.26) | (MOFE) - RPL06 - LV Electrical Gallery / LV Skids - Inside NS | Active | 07/25/25 | 08/04/26 | 328.8 | 100.0 |
|
77.5 |
RPL06.OFE.6920 |
OFE Delivery ROJ: mCUP Elec Skid - mCUP1 - 1 (ROJ03.19.26) (RVCD 04.17.26) Follows MCUP | (MOFE) - RPL06 - mCup Electrical Skids - Outside | Active | 07/25/25 | 04/16/26 | 197.5 | 5.0 |
|
116.2 |
RPL06.OFE.6940 |
OFE Delivery ROJ: mCUP Elec Skid - mCUP5 - 1 (ROJ04.16.26) (RVCD 05.15.26) Follows MCUP | (MOFE) - RPL06 - mCup Electrical Skids - Outside | Active | 07/25/25 | 05/14/26 | 231.2 | 30.0 |
|
197.5 |
RPL06.OFE.6960 |
OFE Delivery ROJ: mCUP Elec Skid - mCUP2 - 1 (ROJ03.26.26) (RVCD 04.17.26) Follows MCUP | (MOFE) - RPL06 - mCup Electrical Skids - Outside | Active | 07/25/25 | 04/16/26 | 203.8 | 5.0 |
|
116.2 |