Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
85
Completed
15
In Progress
85
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL06.CFCI.6240 |
RPL06 - Fabricate / Deliver - AHUs (EY.SSBC, EY.DHA) | (CFCI) Div. 23 - Air Handler Units (AHUs) | Active | 11/06/25 | 04/13/26 | 61.2 | 0.0 |
|
121.2 |
RPL06.CFCI.6920 |
RPL06 - Fabricate / Deliver - AHUs (EYEC) | (CFCI) Div. 23 - Air Handler Units (AHUs) | Active | 11/06/25 | 01/28/27 | 327.5 | 250.0 |
|
67.5 |
RPL06.VDC.1280 |
T1 (Center EF to End Corridor) - Prepare & Submit BIM Shops (Steel) | TIER 1 - Center of EF to End Corridor | Complete | 11/10/25 | 11/10/25 | 12.5 | 0.0 |
|
0.0 |
RPL06.VDC.1340 |
T1 (SSB to Center EF) - Review & Approve BIM Shop (For Steel) | TIER 1 - SSB to Center of EF | Complete | 11/11/25 | 11/24/25 | 12.5 | 0.0 |
|
0.0 |
RPL06.VDC.1400 |
T1 (Center EF to End Corridor) - Review & Approve BIM Shop (Steel) | TIER 1 - Center of EF to End Corridor | Complete | 11/11/25 | 11/24/25 | 12.5 | 0.0 |
|
0.0 |
RPL06.CFCI.3040 |
RPL06 - Submittals Prep & Submit for Review - Structural Steel (Joists) | (CFCI) Div. 05 - Structural Steel (Joists) | Complete | 11/12/25 | 11/12/25 | 12.5 | 0.0 |
|
0.0 |
RPL06.CFCI.6150 |
RPL06 - Submittals Review & Approval - CMU - Storm Shelter | (CFCI) Div. 04 - Concrete Masonry Units | Complete | 11/12/25 | 11/17/25 | 12.5 | 0.0 |
|
0.0 |
PRE.FA.1040 |
Concrete - Final Agreement | Trade Partner Final Agreement | Complete | 11/13/25 | 11/13/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3930 |
RPL06 - Submittals Review & Approval - Structural Steel (Joists) | (CFCI) Div. 05 - Structural Steel (Joists) | Complete | 11/13/25 | 11/17/25 | 11.2 | 0.0 |
|
0.0 |
RPL06.EY.DHA.02100 |
RPL06.EY.DHA - Install Early SD UG Part 1 | Underground | Complete | 11/17/25 | 11/17/25 | 7.5 | 0.0 |
|
0.0 |
RPL06.EY.DHB.01030 |
RPL06.EY.DHB - Install Foundations, UG Utilities, OFE - WBS Summary | EY.DHB | Active | 11/17/25 | 10/30/26 | 275.0 | 171.2 |
|
332.5 |
RPL06.EY.DHB.01070 |
RPL06.EY.DHB - Install UG Utilities - WBS Summary | Underground | Active | 11/17/25 | 06/12/26 | 152.5 | 48.8 |
|
42.5 |
RPL06.EY.DHB.01560 |
RPL06.EY.DHB - Install Early SD UG | Underground | Complete | 11/17/25 | 11/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.EY.DHC.01030 |
RPL06.EY.DHC - Install Foundations, UG Utilities, OFE - WBS Summary | EY.DHC | Active | 11/17/25 | 04/01/27 | 287.5 | 286.2 |
|
206.2 |
RPL06.EY.DHC.01060 |
RPL06.EY.DHC - Install UG Utilities - WBS Summary | Underground | Active | 11/17/25 | 02/17/27 | 250.0 | 248.8 |
|
113.8 |
RPL06.EY.DHC.01550 |
RPL06.EY.DHC - Install Early SD UG | Underground | Complete | 11/17/25 | 11/17/25 | 12.5 | 0.0 |
|
0.0 |
PRE.FA.1240 |
Doors / Frames / Hardware - Final Agreement | Trade Partner Final Agreement | Complete | 11/18/25 | 11/18/25 | 0.0 | 0.0 |
|
0.0 |
PRE.TPA.1020 |
Concrete - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 11/18/25 | 11/18/25 | 10.0 | 0.0 |
|
0.0 |
PRE.TPA.1220 |
Ceiling - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 11/18/25 | 02/03/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.CFCI.3380 |
RPL06 - Submittals Prep & Submit for Review - HVAC Materials and Equipment | (CFCI) Div. 23 - HVAC Materials and Equip. | Complete | 11/18/25 | 11/25/25 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3560 |
RPL06 - Fabricate / Deliver - Structural Steel | (CFCI) Div. 05 - Structural Steel | Complete | 11/18/25 | 03/02/26 | 57.5 | 0.0 |
|
0.0 |
RPL06.CFCI.3720 |
RPL06 - Submittals Prep & Submit for Review - Doors, Frames and Hardware | Doors, Frames & Hardware (HM and Wood) | Complete | 11/18/25 | 12/01/25 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3960 |
RPL06 - Fabricate / Deliver Structural Steel (Joists) (OD=60 Day) | (CFCI) Div. 05 - Structural Steel (Joists) | Complete | 11/18/25 | 03/02/26 | 66.2 | 0.0 |
|
0.0 |
PRE.FA.1120 |
Fire Suppression - Final Agreement | Trade Partner Final Agreement | Complete | 11/19/25 | 11/19/25 | 0.0 | 0.0 |
|
0.0 |
PRE.TPA.1160 |
Roofing - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 11/20/25 | 12/05/25 | 10.0 | 0.0 |
|
0.0 |
PRE.TPA.1040 |
BMS Controls - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 11/24/25 | 02/04/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3360 |
RPL06 - Submittals Prep & Submit for Review - Fire Suppression | (CFCI) Div. 21 - Fire Suppression | Complete | 11/24/25 | 02/04/26 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3710 |
RPL06 - Submittals Prep & Submit for Review - Roofing | Roofing | Complete | 11/24/25 | 02/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.4520 |
RPL06 - SSB - Deliver - Anchor Bolts | (CFCI) Div. 05 - Anchor Bolt Delivery | Complete | 11/24/25 | 12/02/25 | 5.0 | 0.0 |
|
0.0 |
RPL06.CFCI.5670 |
RPL06 - Submittals Review & Approval - SOG/SOMD/Pads Struc. Conc. (Rebar) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 11/24/25 | 12/10/25 | 12.5 | 0.0 |
|
0.0 |
RPL06.CFCI.6540 |
RPL06 - (DBC) Submittals Prep & Submit for Review - Exterior Insulated Metal Panels (IMP) | Exterior Metal Panels | Complete | 11/24/25 | 11/24/25 | 25.0 | 0.0 |
|
0.0 |
RPL06.VDC.1960 |
T1 (Bldg 06) - Prepare & Submit BIM Shops (For DBC) | TIER 1 - SSB to Center of EF | Complete | 11/24/25 | 11/24/25 | 12.5 | 0.0 |
|
0.0 |
PRE.FA.1100 |
Mechanical / Plumbing - Final Agreement | Trade Partner Final Agreement | Complete | 11/25/25 | 11/25/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.6560 |
RPL06 - Submittals Prep & Submit for Review - Exterior Insulated Metal Panels (IMP) | Exterior Metal Panels | Complete | 11/25/25 | 12/01/25 | 12.5 | 0.0 |
|
0.0 |
RPL06.VDC.1920 |
T1 (Bldg 06) - Review & Approve BIM Shop (For DBC) | TIER 1 - SSB to Center of EF | Complete | 11/25/25 | 12/01/25 | 12.5 | 0.0 |
|
0.0 |
PRE.BNS.1520 |
fGMP Rev 1 Issuance | FGMP | Complete | 11/26/25 | 11/26/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3590 |
RPL06 - Submittals Review & Approval - HVAC Materials and Equipment | (CFCI) Div. 23 - HVAC Materials and Equip. | Complete | 11/26/25 | 12/10/25 | 12.5 | 0.0 |
|
0.0 |
PRE.BNS.1540 |
fGMP Rev 2 Development (Dec '25 EOM) | FGMP | Complete | 12/01/25 | 12/17/25 | 41.2 | 0.0 |
|
0.0 |
RPL06.CFCI.3830 |
RPL06 - Submittals Prep & Submit for Review - Building Controls | (CFCI) Div. 23 - Building Controls | Complete | 12/01/25 | 12/18/25 | 12.5 | 0.0 |
|
0.0 |
RPL06.CFCI.4030 |
RPL06 - Submittals Review & Approval - Power Equipment and Material | (CFCI) Div. 26 - Power Equip. & Material | Complete | 12/01/25 | 12/16/25 | 15.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3650 |
RPL06 - Submittals Prep & Submit for Review - Cold Formed Metal Framing | (CFCI) Div. 05 - Cold Formed Metal Framing | Complete | 12/02/25 | 12/04/25 | 18.8 | 0.0 |
|
0.0 |
RPL06.CFCI.4550 |
RPL06 - Submittals Review & Approval - Doors, Frames and Hardware | Doors, Frames & Hardware (HM and Wood) | Complete | 12/02/25 | 12/19/25 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.4980 |
RPL06 - Submittals Review & Approval - (FRP) | FRP [Hallways] | Complete | 12/02/25 | 12/15/25 | 21.2 | 0.0 |
|
0.0 |
RPL06.CFCI.6580 |
RPL06 - (DBC) Fabricate / Deliver - Exterior Insulated Metal Panels (IMP) | Exterior Metal Panels | Complete | 12/02/25 | 02/18/26 | 16.2 | 0.0 |
|
0.0 |
RPL06.VDC.1680 |
T1 (Bldg 06) - Procure IMP Walls (For DBC) | TIER 1 - SSB to Center of EF | Complete | 12/02/25 | 02/13/26 | 35.0 | 0.0 |
|
0.0 |
RPL06.VDC.1940 |
T1 (Bldg 06) - GC QC BIM Model (For DBC) | TIER 1 - SSB to Center of EF | Complete | 12/02/25 | 01/16/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.CFCI.4580 |
RPL06 - Submittals Prep & Submit for Review - Joint Sealants | Joint Sealants | Complete | 12/04/25 | 01/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.4530 |
RPL06 - Submittals Review & Approval - Cold Formed Metal Framing | (CFCI) Div. 05 - Cold Formed Metal Framing | Complete | 12/05/25 | 12/08/25 | 12.5 | 0.0 |
|
0.0 |
RPL06.VDC.1240 |
T1 (Bldg 06) - BIM Coordination OH MEP/Prepare & Submit BIM Shops (For Steel - 11/10/25) | TIER 1 - SSB to Center of EF | Complete | 12/08/25 | 01/14/26 | 72.5 | 0.0 |
|
0.0 |
RPL06.VDC.1320 |
T2-4 (mCUP Yard / Ext.) - Prepare & Submit BIM Shops | TIER 2 - 4 - mCUP Yard / Exterior | Complete | 12/08/25 | 02/13/26 | 12.5 | 0.0 |
|
0.0 |
RPL.06.D.70080.XR |
External Tie from RPL-10 - EY MV Concrete Foundations Crew Flow (RPL10.EY.NS3.01015) | Internal Milestones (XREFs) | Complete | 12/09/25 | 12/09/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3700 |
RPL06 - Submittals Prep & Submit for Review - Below Grade Waterproofing (SPW - Div 07) | Waterproofing | Complete | 12/09/25 | 01/08/26 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.4750 |
RPL06 - Fabricate / Deliver - Cold Formed Metal Framing | (CFCI) Div. 05 - Cold Formed Metal Framing | Complete | 12/09/25 | 03/02/26 | 18.8 | 0.0 |
|
0.0 |
RPL06.CFCI.1030 |
RPL06 - Submittals Prep & Submit for Review - Struc. Conc. (SOG/SOMD Ready Mix) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 12/10/25 | 12/10/25 | 6.2 | 0.0 |
|
0.0 |
RPL06.CFCI.1040 |
RPL06 - Submittals Review & Approval - Struc. Conc. (SOG/SOMD/Pads Ready Mix) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 12/11/25 | 01/06/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.CFCI.3190 |
RPL06 - Coordinate Scope and Submittal Req's - Vesda System | (CFCI) Div. 28 - VESDA System | Complete | 12/11/25 | 01/16/26 | 12.5 | 0.0 |
|
0.0 |
PRE.MIR.1160 |
Waterproofing / Caulking / Expansion Joints SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 12/12/25 | 01/07/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.CFCI.3680 |
RPL06 - Submittals Prep & Submit for Review - FSC -Rough Carpentry (In Wall Backing / Blocking) | Rough Carpentry - FSC Wood | Complete | 12/12/25 | 12/12/25 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.4540 |
RPL06 - Submittals Review & Approval - FSC Rough Carpentry (In Wall Backing / Blocking) | Rough Carpentry - FSC Wood | Complete | 12/15/25 | 12/16/25 | 21.2 | 0.0 |
|
0.0 |
RPL06.CFCI.4590 |
RPL06 - Submittals Prep & Submit for Review - Interior Expansion Joints (Spec 07 95 13.13) XX | Building Expansion Joints (Spec 07 95 13.13) | Complete | 12/15/25 | 12/19/25 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.4630 |
RPL06 - Submittals Prep & Submit for Review - Fire Alarm | (CFCI) Div. 26 - Fire Alarm | Complete | 12/15/25 | 02/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.5180 |
RPL06 - Fabricate / Deliver - (FRP) | FRP [Hallways] | Active | 12/16/25 | 09/01/26 | 37.5 | 125.0 |
|
132.5 |
PRE.BNS.1400 |
GMP Review by Legal (fGMP) | FGMP | Complete | 12/17/25 | 03/17/26 | 6.2 | 0.0 |
|
0.0 |
PRE.BNS.1560 |
fGMP Rev 2 Issuance (Dec '25 EOM) | FGMP | Complete | 12/17/25 | 12/17/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3840 |
RPL06 - Submittals Prep & Submit for Review - Lighting | (CFCI) Div. 26 - Lighting | Complete | 12/17/25 | 02/20/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.CFCI.4140 |
RPL06 - Fabricate / Deliver - Power Equipment and Material | (CFCI) Div. 26 - Power Equip. & Material | Active | 12/17/25 | 06/03/26 | 100.0 | 46.2 |
|
11.2 |
PRE.BNS.1380 |
GMP Review and Final Submission (fGMP) | FGMP | Complete | 12/18/25 | 02/19/26 | 18.8 | 0.0 |
|
0.0 |
RPL06.CFCI.4130 |
RPL06 - Submittals Review & Approval - Building Controls | (CFCI) Div. 23 - Building Controls | Complete | 12/19/25 | 12/19/25 | 12.5 | 0.0 |
|
0.0 |
RPL.06.D.61011.XR |
Pad Ready - RPL06 (East Pad - Grid 6-19/6-28) (Area - Partial DH A & DH B and DH C & DH D) | Receive Milestones (XREFs) | Complete | 12/22/25 | 12/22/25 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.4380 |
RPL06 - Fabricate / Deliver - Building Controls | (CFCI) Div. 23 - Building Controls | Complete | 12/22/25 | 12/24/25 | 27.5 | 0.0 |
|
0.0 |
RPL06.CFCI.4770 |
RPL06 - Fabricate / Deliver - Doors, Frames and Hardware | Doors, Frames & Hardware (HM and Wood) | Active | 12/22/25 | 04/17/26 | 52.5 | 6.2 |
|
210.0 |
RPL06.CFCI.4850 |
RPL06 - Submittals Review & Approval - Interior Expansion Joints (Spec 07 95 13.13) XX | Building Expansion Joints (Spec 07 95 13.13) | Complete | 12/22/25 | 01/05/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.MR.1240 |
RPL06.MR - Install Wayfinding/ Information Boards/ Signage | Make Ready | Complete | 12/23/25 | 01/05/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.MR.1281 |
RPL06.MR - Make Ready Work (for unavailability of roads around Pad) | Make Ready | Complete | 12/23/25 | 01/05/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.VDC.1220 |
T0 (mCUP Yard/Ext.) - GC QC BIM Model | TIER 0 - mCUP Yard / Exterior | Complete | 12/23/25 | 12/23/25 | 12.5 | 0.0 |
|
0.0 |
RPL06.VDC.1300 |
T0 (mCUP Yard/Ext.) - Procure UG Materials | TIER 0 - mCUP Yard / Exterior | Complete | 12/24/25 | 12/29/25 | 6.2 | 0.0 |
|
0.0 |
PRE.MIR.1220 |
Hot Aisle Containment SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Complete | 12/30/25 | 02/18/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.CFCI.3370 |
RPL06 - Submittals Prep & Submit for Review - Plumbing (OH / In Wall) | (CFCI) Div. 22 - Plumbing | Complete | 01/01/26 | 01/13/26 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3390 |
RPL06 - Submittals Prep & Submit for Review - HVAC Insulation | (CFCI) Div. 23 - HVAC Insulation | Complete | 01/01/26 | 01/20/26 | 25.0 | 0.0 |
|
0.0 |
GCD.RPL06.1010 |
Break Ground | Construction Milestones | Complete | 01/05/26 | 01/05/26 | 0.0 | 0.0 |
|
0.0 |
ICM.B6.1060 |
[SSDCB1] Start Foundations | Construction | Complete | 01/05/26 | 01/05/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.6490 |
Submittals Prep & Submit for Review - Roof Drain (Scupper & Downspots) | (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 | Complete | 01/05/26 | 02/12/26 | 25.0 | 0.0 |
|
0.0 |
RPL06.MILE.1540 |
Overall Duration - FDN to SC DHB & DHA & CCN/S - (LOE) | Overall Durations Summary | Active | 01/05/26 | 04/23/27 | 470.0 | 323.8 |
|
18.8 |
RPL06.MILE.1570 |
Overall Duration - FDN to SC DHD & DHC - (LOE) | Overall Durations Summary | Active | 01/05/26 | 07/30/27 | 517.5 | 408.8 |
|
40.0 |
RPL06.SUB.1000 |
RPL06.SubStructure.BLDG - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | SubStructure | Active | 01/05/26 | 04/17/26 | 83.8 | 6.2 |
|
183.8 |
RPL06.SUB.DHCD.01000 |
RPL06.SubStructure.DHCD - Install Drilled Piers - Grid lines 6-19/6-28 | Foundations | Complete | 01/05/26 | 01/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01010 |
RPL06.SubStructure.DHCD - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Active | 01/05/26 | 04/17/26 | 83.8 | 6.2 |
|
183.8 |
RPL06.SUB.DHCD.01020 |
RPL06.SubStructure.DHCD - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | DH D & DH C (Grid 6-19/6-28) | Active | 01/05/26 | 04/17/26 | 83.8 | 6.2 |
|
183.8 |
RPL06.VDC.1500 |
T2-4 (SSB) - Prepare & Submit BIM Shops | TIER 2 - 4 - SSB | Complete | 01/05/26 | 01/16/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.VDC.1580 |
T2-4 (SSB) - Review & Approve BIM Shop | TIER 2 - 4 - SSB | Complete | 01/05/26 | 02/09/26 | 31.2 | 0.0 |
|
0.0 |
RPL06.CFCI.5130 |
RPL06 - Fabricate / Deliver - Interior Expansion Joints (Spec 07 95 13.13) XX | Building Expansion Joints (Spec 07 95 13.13) | Active | 01/06/26 | 04/30/26 | 0.0 | 17.5 |
|
41.2 |
RPL06.CFCI.5660 |
RPL06 - Fabricate / Deliver - SOG/SOMD/Pads Struc. Conc. (Rebar) | (CFCI) Div. 03 - (SOG/SOMD) Struc. Concrete | Complete | 01/06/26 | 03/13/26 | 90.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3660 |
RPL06 - Submittals Prep & Submit for Review - Strut | (CFCI) Div. 05 - Slotted Channel Framing (Strut) | Complete | 01/07/26 | 01/08/26 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.4840 |
RPL06 - Submittals Review & Approval - Joint Sealants | Joint Sealants | Complete | 01/07/26 | 02/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.6940 |
RPL06 - (DPR) Submittals Prep & Submit for Review - Interior Wall Panels (IWP) | Interior Wall Panels | Complete | 01/07/26 | 02/18/26 | 25.0 | 0.0 |
|
0.0 |
PRE.FA.1000 |
Electrical - LOI Issued to Start Coordination | Trade Partner Final Agreement | Complete | 01/09/26 | 01/09/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.CFCI.4340 |
RPL06 - Submittals Review & Approval - Below Grade Waterproofing | Waterproofing | Complete | 01/09/26 | 01/16/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.CFCI.5210 |
RPL06 - Submittals Review & Approval - Strut | (CFCI) Div. 05 - Slotted Channel Framing (Strut) | Complete | 01/09/26 | 03/02/26 | 18.8 | 0.0 |
|
0.0 |
RPL06.CFCI.3180 |
RPL06 - Coordinate Scope and Submittal Req's - Security System (Prod Dat) | (CFCI) Div. 28 - Security Syst. | Complete | 01/12/26 | 01/16/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.6740 |
RPL06 - Submittals Prep & Submit for Review -Cable Tray | (CFCI) Div. 26 - Power Equip. & Material | Complete | 01/12/26 | 02/20/26 | 25.0 | 0.0 |
|
0.0 |