Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
93
Completed
7
In Progress
93
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.MR.1000 RPL06.MR - Logistics Area 09 and Roads Ready Make Ready Complete 01/12/26 01/12/26 0.0 0.0
100%
0.0
RPL06.SUB.DHAB.01000 RPL06.SubStructure.DHAB - Install Drilled Piers - Grid lines 6-10/6-19 Foundations Complete 01/12/26 01/14/26 6.2 0.0
100%
0.0
RPL06.SUB.DHAB.01010 RPL06.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary Foundations Complete 01/12/26 03/02/26 38.8 0.0
100%
0.0
RPL06.SUB.DHAB.01020 RPL06.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary DH B & DH A (Grid 6-10/6-19) Complete 01/12/26 03/05/26 46.2 0.0
100%
0.0
RPL06.SUB.DHAB.01130 RPL06.SubStructure.DHAB - Piers Protection Concrete Capping Foundations Complete 01/12/26 01/14/26 6.2 0.0
100%
0.0
RPL06.SUB.DHCD.01030 RPL06.SubStructure.DHCD - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-19/6-28 Foundations Complete 01/12/26 01/19/26 10.0 0.0
100%
0.0
RPL06.SUB.DHCD.01040 RPL06.SubStructure.DHCD - Install Stem walls - Grid lines 6-19/6-28 Foundations Complete 01/12/26 03/04/26 7.5 0.0
100%
0.0
RPL06.SUB.DHCD.01060 RPL06.SubStructure.DHCD - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 Underground Complete 01/12/26 01/21/26 10.0 0.0
100%
0.0
RPL06.SUB.DHCD.01070 RPL06.SubStructure.DHCD - Install UG Utilities - WBS Summary Underground Complete 01/12/26 03/25/26 53.8 0.0
100%
0.0
RPL06.SUB.DHCD.01130 RPL06.SubStructure.DHCD - Piers Protection Concrete Capping Foundations Complete 01/12/26 01/16/26 6.2 0.0
100%
0.0
RPL.06.D.61010.XR Pad Ready - RPL06 (West Pad- Grid 6-01/6-19) (Area - SSB and Partial DH A & DH B) Receive Milestones (XREFs) Complete 01/13/26 01/13/26 0.0 0.0
100%
0.0
RPL.06.D.61110.XR Pad Ready - RPL06 - mCup (3rd Pad) Receive Milestones (XREFs) Complete 01/13/26 01/13/26 0.0 0.0
100%
0.0
RPL06.SUB.DHCD.01090 RPL06.SubStructure.DHCD - Install UG Utilities - Electrical/Testing, Pathway Verification & Backfill - Part 1 (LOE) GL27 Underground Complete 01/13/26 02/02/26 7.5 0.0
100%
0.0
RPL06.SUB.DHCD.01250 RPL06.SubStructure.DHCD - Install UG Utilities - Electrical/Testing, Pathway Verification & Backfill- Part 1 (Pre WI.01) Underground Complete 01/13/26 01/20/26 7.5 0.0
100%
0.0
ICM.B6.1860 [SSDCB1] Delivery of Dry Cooling Towers (First Delivery) Construction Complete 01/14/26 01/14/26 0.0 0.0
100%
0.0
RPL06.CFCI.3300 RPL06 - Submittals Prep & Submit for Review - Exterior Louvers (w Ext Metal Panel Trade) (CrownCorr) Fixed Louvers Complete 01/14/26 01/14/26 25.0 0.0
100%
0.0
RPL06.CFCI.3580 RPL06 - Submittals Review & Approval - Plumbing (OH / In Wall) (CFCI) Div. 22 - Plumbing Complete 01/14/26 01/20/26 25.0 0.0
100%
0.0
RPL06.SUB.DHAB.01070 RPL06.SubStructure.DHAB - Install UG Utilities - WBS Summary Underground Complete 01/14/26 03/05/26 46.2 0.0
100%
0.0
RPL06.SUB.DHAB.01090 RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Day (LOE) Underground Complete 01/14/26 02/20/26 10.0 0.0
100%
0.0
RPL06.SUB.DHAB.01092 RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Day (Pre WI.01) Underground Complete 01/14/26 01/20/26 10.0 0.0
100%
0.0
RPL06.SUB.DHAB.01210 RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Swing (LOE) Underground Complete 01/14/26 02/12/26 10.0 0.0
100%
0.0
RPL06.SUB.DHAB.01430 RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Swing (Pre WI.01) Underground Complete 01/14/26 01/20/26 10.0 0.0
100%
0.0
RPL06.SUB.SSB.01000 RPL06.SubStructure.SSB - Install Drilled Piers - Grid lines 6-01/6-10 Foundations Complete 01/14/26 01/19/26 5.0 0.0
100%
0.0
RPL06.SUB.SSB.01010 RPL06.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary Foundations Complete 01/14/26 02/27/26 27.5 0.0
100%
0.0
RPL06.SUB.SSB.01020 RPL06.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary SSB (Grid 6-01/6-10) Complete 01/14/26 03/03/26 28.8 0.0
100%
0.0
RPL06.SUB.SSB.01140 RPL06.SubStructure.SSB - Piers Protection Concrete Capping Foundations Complete 01/15/26 01/20/26 5.0 0.0
100%
0.0
PRE.TPA.1200 Waterproofing / Caulking / Expansion Joints - Award and Issue Subcontract DPR issue Trade Parter Agreements Complete 01/16/26 01/21/26 5.0 0.0
100%
0.0
RPL06.MR.1020 RPL06.MR - Trailer Complete Ready for Move-In Make Ready Complete 01/16/26 01/16/26 0.0 0.0
100%
0.0
RPL06.MR.1160 RPL06.MR - Trailer Setup & Tie-Ins Make Ready Complete 01/16/26 01/16/26 28.8 0.0
100%
0.0
RPL06.MR.1220 RPL06.MR - Parking Areas Buildout Make Ready Complete 01/16/26 01/16/26 6.2 0.0
100%
0.0
RPL06.CFCI.4490 RPL06 - Fabricate / Deliver - Below Grade Waterproofing (SPW - Div 07) Waterproofing Complete 01/19/26 01/23/26 10.0 0.0
100%
0.0
RPL06.CFCI.4690 RPL06 - Submittals Prep & Submit for Review - Security System (Prod Dat) (CFCI) Div. 28 - Security Syst. Complete 01/19/26 01/19/26 73.8 0.0
100%
0.0
RPL06.CFCI.4710 RPL06 - Submittals Prep & Submit for Review - Vesda System (CFCI) Div. 28 - VESDA System Complete 01/19/26 02/20/26 73.8 0.0
100%
0.0
RPL06.SUB.DHCD.01210 RPL06.SubStructure.DHCD - Repair and test PWR line @ Grid line 6-28 (Rework - RPL06 Issue #29) - (LOE) Foundations Complete 01/19/26 02/24/26 10.0 0.0
100%
0.0
RPL06.SUB.DHCD.01290 RPL06.SubStructure.DHCD - Repair and test PWR line @ Grid line 6-28 (Rework - RPL06 Issue #29) - (Pre WI.01) Foundations Complete 01/19/26 01/20/26 10.0 0.0
100%
0.0
RPL06.VDC.1540 T2-4 (DH A & B) - Prepare & Submit BIM Shops TIER 2 - 4 - DH A & B Active 01/19/26 04/13/26 12.5 0.0
0%
12.5
RPL06.VDC.1600 T2-4 (EF) - Prepare & Submit BIM Shops TIER 2 - 4 - EF Active 01/19/26 04/13/26 12.5 0.0
0%
56.2
RPL06.VDC.1660 T2-4 (DH C & D) - Prepare & Submit BIM Shops TIER 2 - 4 - DH C & D Active 01/19/26 04/13/26 12.5 0.0
0%
115.0
RPL06.VDC.1820 T2-4 (SSB) - Create Spool Sheet for Fab TIER 2 - 4 - SSB Active 01/19/26 04/15/26 18.8 3.8
0%
2.5
RPL06.CFCI.4700 RPL06 - Submittals Review & Approval - Security System (CFCI) Div. 28 - Security Syst. Complete 01/20/26 01/30/26 25.0 0.0
100%
0.0
RPL06.SUB.DHAB.01030 RPL06.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-10/6-19 (LOE) Foundations Complete 01/20/26 02/23/26 15.0 0.0
100%
0.0
RPL06.SUB.DHAB.01290 RPL06.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-10/6-19 (Pre WI.01) Foundations Complete 01/20/26 01/20/26 15.0 0.0
100%
0.0
RPL06.SUB.SSB.01040 RPL06.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-01/6-10 (LOE) Foundations Complete 01/20/26 02/16/26 18.8 0.0
100%
0.0
RPL06.SUB.SSB.01050 RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (LOE) Underground Complete 01/20/26 02/13/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01052 RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (Pre WI.01) Underground Complete 01/20/26 01/20/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01060 RPL06.SubStructure.SSB - Install UG Utilities - WBS Summary Underground Complete 01/20/26 03/03/26 28.8 0.0
100%
0.0
RPL06.SUB.SSB.01090 RPL06.SubStructure.SSB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 1- Day (LOE) Underground Complete 01/20/26 02/18/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01092 RPL06.SubStructure.SSB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 1- Day (Pre WI.01) Underground Complete 01/20/26 01/20/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01220 RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (LOE) Underground Complete 01/20/26 02/13/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01222 RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (Pre WI.01) Underground Complete 01/20/26 01/20/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01300 RPL06.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-01/6-10 (Pre WI.01) Foundations Complete 01/20/26 01/20/26 18.8 0.0
100%
0.0
PRE.FA.1220 Waterproofing / Caulking / Expansion Joints - Final Agreement Trade Partner Final Agreement Complete 01/21/26 01/21/26 0.0 0.0
100%
0.0
RPL06.10010 Weather Event #1 - 01/21/26 - 01/22/2026 (Rain) Weather Impacts Complete 01/21/26 01/22/26 2.5 0.0
100%
0.0
RPL06.CFCI.3600 RPL06 - Submittals Review & Approval - HVAC Insulation (CFCI) Div. 23 - HVAC Insulation Complete 01/21/26 01/28/26 25.0 0.0
100%
0.0
PRE.FA.1020 Electrical - Final Agreement Trade Partner Final Agreement Complete 01/23/26 01/23/26 0.0 0.0
100%
0.0
RPL06.SUB.DHAB.01060 RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (LOE) Underground Complete 01/23/26 02/24/26 5.0 0.0
100%
0.0
RPL06.SUB.DHAB.01062 RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (Post WI.01) Underground Complete 01/23/26 01/23/26 5.0 0.0
100%
0.0
RPL06.SUB.DHAB.01094 RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Day (Post WI.01) Underground Complete 01/23/26 01/23/26 10.0 0.0
100%
0.0
RPL06.SUB.DHAB.01230 RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (LOE) Underground Complete 01/23/26 02/24/26 5.0 0.0
100%
0.0
RPL06.SUB.DHAB.01232 RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (Post WI.01) Underground Complete 01/23/26 01/23/26 5.0 0.0
100%
0.0
RPL06.SUB.DHAB.01310 RPL06.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-10/6-19 (Post WI.01) Foundations Complete 01/23/26 01/23/26 15.0 0.0
100%
0.0
RPL06.SUB.DHCD.01270 RPL06.SubStructure.DHCD - Install UG Utilities - Electrical/Testing, Pathway Verification & Backfill-Part 1 (Post WI.01) Underground Complete 01/23/26 01/23/26 7.5 0.0
100%
0.0
RPL06.SUB.DHCD.01310 RPL06.SubStructure.DHCD - Repair and test PWR line @ Grid line 6-28 (Rework - RPL06 Issue #29) - (Post WI.01) Foundations Complete 01/23/26 01/23/26 10.0 0.0
100%
0.0
RPL06.SUB.SSB.01054 RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (Post WI.01) Underground Complete 01/23/26 01/23/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01094 RPL06.SubStructure.SSB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 1- Day (Post WI.01) Underground Complete 01/23/26 01/23/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01224 RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (Post WI.01) Underground Complete 01/23/26 01/23/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01320 RPL06.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-01/6-10 (Post WI.01) Foundations Complete 01/23/26 01/23/26 18.8 0.0
100%
0.0
RPL06.10030 Weather Event #2 - 01/26/26 - 01/30/2026 (Snow Storm) Weather Impacts Complete 01/26/26 01/30/26 6.2 0.0
100%
0.0
RPL06.CFCI.3810 RPL06 - Submittals Review & Approval - Exterior Louvers (w Ext Metal Panel Trade) Fixed Louvers Complete 01/28/26 01/28/26 12.5 0.0
100%
0.0
RPL06.CFCI.4120 RPL06 - Fabricate / Deliver - Exterior Louvers Fixed Louvers Active 01/29/26 04/13/26 75.0 1.2
0%
288.8
RPL06.SUB.DHAB.01064 RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (Post WI.02) Underground Complete 02/02/26 02/24/26 5.0 0.0
100%
0.0
RPL06.SUB.DHAB.01096 RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Day (Post WI.02) Underground Complete 02/02/26 02/20/26 10.0 0.0
100%
0.0
RPL06.SUB.DHAB.01234 RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (Post WI.02) Underground Complete 02/02/26 02/24/26 5.0 0.0
100%
0.0
RPL06.SUB.DHAB.01316 RPL06.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-10/6-19 (Post WI.02) Foundations Complete 02/02/26 02/23/26 15.0 0.0
100%
0.0
RPL06.SUB.DHAB.01410 RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Swing (Post WI.02) Underground Complete 02/02/26 02/12/26 0.0 0.0
100%
0.0
RPL06.SUB.DHCD.01390 RPL06.SubStructure.DHCD - Install UG Utilities - Electrical/Testing, Pathway Verification & Backfill-Part 1 (Post WI.02) Underground Complete 02/02/26 02/02/26 7.5 0.0
100%
0.0
RPL06.SUB.SSB.01056 RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (Post WI.02) Underground Complete 02/02/26 02/13/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01096 RPL06.SubStructure.SSB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 1- Day (Post WI.02) Underground Complete 02/02/26 02/18/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01160 RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 - Day Underground Complete 02/02/26 02/13/26 8.8 0.0
100%
0.0
RPL06.SUB.SSB.01226 RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (Post WI.02) Underground Complete 02/02/26 02/13/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01260 RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 - Swing Underground Complete 02/02/26 02/13/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01340 RPL06.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-01/6-10 (Post WI.02) Foundations Complete 02/02/26 02/16/26 18.8 0.0
100%
0.0
RPL06.MCUP.LP1.1000 RPL06.MCUP.Loop 1 - Install Foundations, UG Utilities, OFE - WBS Summary mCup Loop 1 Active 02/04/26 07/08/26 130.0 76.2
0%
433.8
RPL06.MCUP.LP1.1040 RPL06.MCUP.Loop 1 - Install UG Utilities - WBS Summary Underground Complete 02/04/26 03/02/26 26.2 0.0
100%
0.0
RPL06.MCUP.LP1.1080 RPL06.MCUP.Loop 1 - Install Electrical UG Electrical UG Complete 02/04/26 02/26/26 26.2 0.0
100%
0.0
RPL06.MCUP.LP1.1140 RPL06.MCUP.Loop 1 - Install Controls/EPMS/BMS UG Controls/EPMS/BMS UG Complete 02/04/26 03/02/26 26.2 0.0
100%
0.0
RPL06.MCUP.LP1.1160 RPL06.MCUP.Loop 1 - Install Grounding Wire, Grounding Rod, Exothermic Weld & Backfill Grounding UG Complete 02/04/26 03/02/26 12.5 0.0
100%
0.0
RPL06.SUB.DHCD.01370 RPL06.SubStructure.DHCD - Repair and test PWR line @ Grid line 6-28 (Rework - RPL06 Issue #29) - (Post WI.02) Foundations Complete 02/04/26 02/24/26 10.0 0.0
100%
0.0
RPL06.mCUP.1060 RPL06.MCUP.BLDG - Install Foundations, UG Utilities, OFE 1-6 - WBS Summary mCUP Yard Active 02/04/26 08/12/26 161.2 107.5
0%
402.5
PRE.FA.1140 Roofing - Final Agreement Trade Partner Final Agreement Complete 02/05/26 02/05/26 0.0 0.0
100%
0.0
PRE.FA.1160 Drywall Metal Studs - Final Agreement Trade Partner Final Agreement Complete 02/05/26 02/05/26 0.0 0.0
100%
0.0
PRE.FA.1180 Ceiling - Final Agreement Trade Partner Final Agreement Complete 02/05/26 02/05/26 0.0 0.0
100%
0.0
RPL06.CFCI.3570 RPL06 - Submittals Review & Approval - Fire Suppression (AHJ) (CFCI) Div. 21 - Fire Suppression Complete 02/05/26 02/18/26 12.5 0.0
100%
0.0
RPL06.SUB.DHCD.01110 RPL06.SubStructure.DHCD - Scan, Install Flowfill - Grid lines 6-19/6-27 (1st Layer Backfill) Underground Complete 02/05/26 02/10/26 5.0 0.0
100%
0.0
RPL06.CFCI.4310 RPL06 - Fabricate / Deliver - CMU - Storm Shelter (CFCI) Div. 04 - Concrete Masonry Units Complete 02/06/26 02/17/26 6.2 0.0
100%
0.0
RPL06.MCUP.LP1.1060 RPL06.MCUP.Loop 1 - Install Mechanical UG Mechanical UG Complete 02/06/26 02/27/26 12.5 0.0
100%
0.0
RPL06.MR.1261 RPL06.MR - Site Checklist & Control Handoff Make Ready Complete 02/06/26 02/09/26 2.5 0.0
100%
0.0
RPL06.CFCI.4010 RPL06 - Submittals Review & Approval - Roofing Roofing Complete 02/09/26 02/20/26 11.2 0.0
100%
0.0
RPL06.CFCI.4890 RPL06 - Submittals Review & Approval - Fire Alarm (CFCI) Div. 26 - Fire Alarm Complete 02/09/26 02/20/26 18.8 0.0
100%
0.0
RPL06.CFCI.5040 RPL06 - Fabricate / Deliver - Joint Sealants Joint Sealants Complete 02/09/26 02/20/26 12.5 0.0
100%
0.0