Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
93
Completed
7
In Progress
93
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL06.MR.1000 |
RPL06.MR - Logistics Area 09 and Roads Ready | Make Ready | Complete | 01/12/26 | 01/12/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01000 |
RPL06.SubStructure.DHAB - Install Drilled Piers - Grid lines 6-10/6-19 | Foundations | Complete | 01/12/26 | 01/14/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01010 |
RPL06.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Complete | 01/12/26 | 03/02/26 | 38.8 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01020 |
RPL06.SubStructure.DHAB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | DH B & DH A (Grid 6-10/6-19) | Complete | 01/12/26 | 03/05/26 | 46.2 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01130 |
RPL06.SubStructure.DHAB - Piers Protection Concrete Capping | Foundations | Complete | 01/12/26 | 01/14/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01030 |
RPL06.SubStructure.DHCD - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-19/6-28 | Foundations | Complete | 01/12/26 | 01/19/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01040 |
RPL06.SubStructure.DHCD - Install Stem walls - Grid lines 6-19/6-28 | Foundations | Complete | 01/12/26 | 03/04/26 | 7.5 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01060 |
RPL06.SubStructure.DHCD - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 | Underground | Complete | 01/12/26 | 01/21/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01070 |
RPL06.SubStructure.DHCD - Install UG Utilities - WBS Summary | Underground | Complete | 01/12/26 | 03/25/26 | 53.8 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01130 |
RPL06.SubStructure.DHCD - Piers Protection Concrete Capping | Foundations | Complete | 01/12/26 | 01/16/26 | 6.2 | 0.0 |
|
0.0 |
RPL.06.D.61010.XR |
Pad Ready - RPL06 (West Pad- Grid 6-01/6-19) (Area - SSB and Partial DH A & DH B) | Receive Milestones (XREFs) | Complete | 01/13/26 | 01/13/26 | 0.0 | 0.0 |
|
0.0 |
RPL.06.D.61110.XR |
Pad Ready - RPL06 - mCup (3rd Pad) | Receive Milestones (XREFs) | Complete | 01/13/26 | 01/13/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01090 |
RPL06.SubStructure.DHCD - Install UG Utilities - Electrical/Testing, Pathway Verification & Backfill - Part 1 (LOE) GL27 | Underground | Complete | 01/13/26 | 02/02/26 | 7.5 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01250 |
RPL06.SubStructure.DHCD - Install UG Utilities - Electrical/Testing, Pathway Verification & Backfill- Part 1 (Pre WI.01) | Underground | Complete | 01/13/26 | 01/20/26 | 7.5 | 0.0 |
|
0.0 |
ICM.B6.1860 |
[SSDCB1] Delivery of Dry Cooling Towers (First Delivery) | Construction | Complete | 01/14/26 | 01/14/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3300 |
RPL06 - Submittals Prep & Submit for Review - Exterior Louvers (w Ext Metal Panel Trade) (CrownCorr) | Fixed Louvers | Complete | 01/14/26 | 01/14/26 | 25.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3580 |
RPL06 - Submittals Review & Approval - Plumbing (OH / In Wall) | (CFCI) Div. 22 - Plumbing | Complete | 01/14/26 | 01/20/26 | 25.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01070 |
RPL06.SubStructure.DHAB - Install UG Utilities - WBS Summary | Underground | Complete | 01/14/26 | 03/05/26 | 46.2 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01090 |
RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Day (LOE) | Underground | Complete | 01/14/26 | 02/20/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01092 |
RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Day (Pre WI.01) | Underground | Complete | 01/14/26 | 01/20/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01210 |
RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Swing (LOE) | Underground | Complete | 01/14/26 | 02/12/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01430 |
RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Swing (Pre WI.01) | Underground | Complete | 01/14/26 | 01/20/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01000 |
RPL06.SubStructure.SSB - Install Drilled Piers - Grid lines 6-01/6-10 | Foundations | Complete | 01/14/26 | 01/19/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01010 |
RPL06.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls - WBS Summary | Foundations | Complete | 01/14/26 | 02/27/26 | 27.5 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01020 |
RPL06.SubStructure.SSB - Install Deep/Foundations/Gradebeams/Stemwalls/UG Utilities - WBS Summary | SSB (Grid 6-01/6-10) | Complete | 01/14/26 | 03/03/26 | 28.8 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01140 |
RPL06.SubStructure.SSB - Piers Protection Concrete Capping | Foundations | Complete | 01/15/26 | 01/20/26 | 5.0 | 0.0 |
|
0.0 |
PRE.TPA.1200 |
Waterproofing / Caulking / Expansion Joints - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Complete | 01/16/26 | 01/21/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.MR.1020 |
RPL06.MR - Trailer Complete Ready for Move-In | Make Ready | Complete | 01/16/26 | 01/16/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.MR.1160 |
RPL06.MR - Trailer Setup & Tie-Ins | Make Ready | Complete | 01/16/26 | 01/16/26 | 28.8 | 0.0 |
|
0.0 |
RPL06.MR.1220 |
RPL06.MR - Parking Areas Buildout | Make Ready | Complete | 01/16/26 | 01/16/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.CFCI.4490 |
RPL06 - Fabricate / Deliver - Below Grade Waterproofing (SPW - Div 07) | Waterproofing | Complete | 01/19/26 | 01/23/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.CFCI.4690 |
RPL06 - Submittals Prep & Submit for Review - Security System (Prod Dat) | (CFCI) Div. 28 - Security Syst. | Complete | 01/19/26 | 01/19/26 | 73.8 | 0.0 |
|
0.0 |
RPL06.CFCI.4710 |
RPL06 - Submittals Prep & Submit for Review - Vesda System | (CFCI) Div. 28 - VESDA System | Complete | 01/19/26 | 02/20/26 | 73.8 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01210 |
RPL06.SubStructure.DHCD - Repair and test PWR line @ Grid line 6-28 (Rework - RPL06 Issue #29) - (LOE) | Foundations | Complete | 01/19/26 | 02/24/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01290 |
RPL06.SubStructure.DHCD - Repair and test PWR line @ Grid line 6-28 (Rework - RPL06 Issue #29) - (Pre WI.01) | Foundations | Complete | 01/19/26 | 01/20/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.VDC.1540 |
T2-4 (DH A & B) - Prepare & Submit BIM Shops | TIER 2 - 4 - DH A & B | Active | 01/19/26 | 04/13/26 | 12.5 | 0.0 |
|
12.5 |
RPL06.VDC.1600 |
T2-4 (EF) - Prepare & Submit BIM Shops | TIER 2 - 4 - EF | Active | 01/19/26 | 04/13/26 | 12.5 | 0.0 |
|
56.2 |
RPL06.VDC.1660 |
T2-4 (DH C & D) - Prepare & Submit BIM Shops | TIER 2 - 4 - DH C & D | Active | 01/19/26 | 04/13/26 | 12.5 | 0.0 |
|
115.0 |
RPL06.VDC.1820 |
T2-4 (SSB) - Create Spool Sheet for Fab | TIER 2 - 4 - SSB | Active | 01/19/26 | 04/15/26 | 18.8 | 3.8 |
|
2.5 |
RPL06.CFCI.4700 |
RPL06 - Submittals Review & Approval - Security System | (CFCI) Div. 28 - Security Syst. | Complete | 01/20/26 | 01/30/26 | 25.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01030 |
RPL06.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-10/6-19 (LOE) | Foundations | Complete | 01/20/26 | 02/23/26 | 15.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01290 |
RPL06.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-10/6-19 (Pre WI.01) | Foundations | Complete | 01/20/26 | 01/20/26 | 15.0 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01040 |
RPL06.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-01/6-10 (LOE) | Foundations | Complete | 01/20/26 | 02/16/26 | 18.8 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01050 |
RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (LOE) | Underground | Complete | 01/20/26 | 02/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01052 |
RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (Pre WI.01) | Underground | Complete | 01/20/26 | 01/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01060 |
RPL06.SubStructure.SSB - Install UG Utilities - WBS Summary | Underground | Complete | 01/20/26 | 03/03/26 | 28.8 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01090 |
RPL06.SubStructure.SSB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 1- Day (LOE) | Underground | Complete | 01/20/26 | 02/18/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01092 |
RPL06.SubStructure.SSB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 1- Day (Pre WI.01) | Underground | Complete | 01/20/26 | 01/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01220 |
RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (LOE) | Underground | Complete | 01/20/26 | 02/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01222 |
RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (Pre WI.01) | Underground | Complete | 01/20/26 | 01/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01300 |
RPL06.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-01/6-10 (Pre WI.01) | Foundations | Complete | 01/20/26 | 01/20/26 | 18.8 | 0.0 |
|
0.0 |
PRE.FA.1220 |
Waterproofing / Caulking / Expansion Joints - Final Agreement | Trade Partner Final Agreement | Complete | 01/21/26 | 01/21/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.10010 |
Weather Event #1 - 01/21/26 - 01/22/2026 (Rain) | Weather Impacts | Complete | 01/21/26 | 01/22/26 | 2.5 | 0.0 |
|
0.0 |
RPL06.CFCI.3600 |
RPL06 - Submittals Review & Approval - HVAC Insulation | (CFCI) Div. 23 - HVAC Insulation | Complete | 01/21/26 | 01/28/26 | 25.0 | 0.0 |
|
0.0 |
PRE.FA.1020 |
Electrical - Final Agreement | Trade Partner Final Agreement | Complete | 01/23/26 | 01/23/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01060 |
RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (LOE) | Underground | Complete | 01/23/26 | 02/24/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01062 |
RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (Post WI.01) | Underground | Complete | 01/23/26 | 01/23/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01094 |
RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Day (Post WI.01) | Underground | Complete | 01/23/26 | 01/23/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01230 |
RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (LOE) | Underground | Complete | 01/23/26 | 02/24/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01232 |
RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (Post WI.01) | Underground | Complete | 01/23/26 | 01/23/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01310 |
RPL06.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-10/6-19 (Post WI.01) | Foundations | Complete | 01/23/26 | 01/23/26 | 15.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01270 |
RPL06.SubStructure.DHCD - Install UG Utilities - Electrical/Testing, Pathway Verification & Backfill-Part 1 (Post WI.01) | Underground | Complete | 01/23/26 | 01/23/26 | 7.5 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01310 |
RPL06.SubStructure.DHCD - Repair and test PWR line @ Grid line 6-28 (Rework - RPL06 Issue #29) - (Post WI.01) | Foundations | Complete | 01/23/26 | 01/23/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01054 |
RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (Post WI.01) | Underground | Complete | 01/23/26 | 01/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01094 |
RPL06.SubStructure.SSB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 1- Day (Post WI.01) | Underground | Complete | 01/23/26 | 01/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01224 |
RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (Post WI.01) | Underground | Complete | 01/23/26 | 01/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01320 |
RPL06.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-01/6-10 (Post WI.01) | Foundations | Complete | 01/23/26 | 01/23/26 | 18.8 | 0.0 |
|
0.0 |
RPL06.10030 |
Weather Event #2 - 01/26/26 - 01/30/2026 (Snow Storm) | Weather Impacts | Complete | 01/26/26 | 01/30/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.CFCI.3810 |
RPL06 - Submittals Review & Approval - Exterior Louvers (w Ext Metal Panel Trade) | Fixed Louvers | Complete | 01/28/26 | 01/28/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.CFCI.4120 |
RPL06 - Fabricate / Deliver - Exterior Louvers | Fixed Louvers | Active | 01/29/26 | 04/13/26 | 75.0 | 1.2 |
|
288.8 |
RPL06.SUB.DHAB.01064 |
RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (Post WI.02) | Underground | Complete | 02/02/26 | 02/24/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01096 |
RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Day (Post WI.02) | Underground | Complete | 02/02/26 | 02/20/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01234 |
RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (Post WI.02) | Underground | Complete | 02/02/26 | 02/24/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01316 |
RPL06.SubStructure.DHAB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-10/6-19 (Post WI.02) | Foundations | Complete | 02/02/26 | 02/23/26 | 15.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01410 |
RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill Part 1 - Swing (Post WI.02) | Underground | Complete | 02/02/26 | 02/12/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01390 |
RPL06.SubStructure.DHCD - Install UG Utilities - Electrical/Testing, Pathway Verification & Backfill-Part 1 (Post WI.02) | Underground | Complete | 02/02/26 | 02/02/26 | 7.5 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01056 |
RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Day (Post WI.02) | Underground | Complete | 02/02/26 | 02/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01096 |
RPL06.SubStructure.SSB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 1- Day (Post WI.02) | Underground | Complete | 02/02/26 | 02/18/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01160 |
RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 - Day | Underground | Complete | 02/02/26 | 02/13/26 | 8.8 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01226 |
RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 1 - Swing (Post WI.02) | Underground | Complete | 02/02/26 | 02/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01260 |
RPL06.SubStructure.SSB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 - Swing | Underground | Complete | 02/02/26 | 02/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01340 |
RPL06.SubStructure.SSB - Install Foundations/Anchor Bolts and Gradebeams - Grid lines 6-01/6-10 (Post WI.02) | Foundations | Complete | 02/02/26 | 02/16/26 | 18.8 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.1000 |
RPL06.MCUP.Loop 1 - Install Foundations, UG Utilities, OFE - WBS Summary | mCup Loop 1 | Active | 02/04/26 | 07/08/26 | 130.0 | 76.2 |
|
433.8 |
RPL06.MCUP.LP1.1040 |
RPL06.MCUP.Loop 1 - Install UG Utilities - WBS Summary | Underground | Complete | 02/04/26 | 03/02/26 | 26.2 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.1080 |
RPL06.MCUP.Loop 1 - Install Electrical UG | Electrical UG | Complete | 02/04/26 | 02/26/26 | 26.2 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.1140 |
RPL06.MCUP.Loop 1 - Install Controls/EPMS/BMS UG | Controls/EPMS/BMS UG | Complete | 02/04/26 | 03/02/26 | 26.2 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.1160 |
RPL06.MCUP.Loop 1 - Install Grounding Wire, Grounding Rod, Exothermic Weld & Backfill | Grounding UG | Complete | 02/04/26 | 03/02/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01370 |
RPL06.SubStructure.DHCD - Repair and test PWR line @ Grid line 6-28 (Rework - RPL06 Issue #29) - (Post WI.02) | Foundations | Complete | 02/04/26 | 02/24/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.mCUP.1060 |
RPL06.MCUP.BLDG - Install Foundations, UG Utilities, OFE 1-6 - WBS Summary | mCUP Yard | Active | 02/04/26 | 08/12/26 | 161.2 | 107.5 |
|
402.5 |
PRE.FA.1140 |
Roofing - Final Agreement | Trade Partner Final Agreement | Complete | 02/05/26 | 02/05/26 | 0.0 | 0.0 |
|
0.0 |
PRE.FA.1160 |
Drywall Metal Studs - Final Agreement | Trade Partner Final Agreement | Complete | 02/05/26 | 02/05/26 | 0.0 | 0.0 |
|
0.0 |
PRE.FA.1180 |
Ceiling - Final Agreement | Trade Partner Final Agreement | Complete | 02/05/26 | 02/05/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.3570 |
RPL06 - Submittals Review & Approval - Fire Suppression (AHJ) | (CFCI) Div. 21 - Fire Suppression | Complete | 02/05/26 | 02/18/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01110 |
RPL06.SubStructure.DHCD - Scan, Install Flowfill - Grid lines 6-19/6-27 (1st Layer Backfill) | Underground | Complete | 02/05/26 | 02/10/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.CFCI.4310 |
RPL06 - Fabricate / Deliver - CMU - Storm Shelter | (CFCI) Div. 04 - Concrete Masonry Units | Complete | 02/06/26 | 02/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.1060 |
RPL06.MCUP.Loop 1 - Install Mechanical UG | Mechanical UG | Complete | 02/06/26 | 02/27/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.MR.1261 |
RPL06.MR - Site Checklist & Control Handoff | Make Ready | Complete | 02/06/26 | 02/09/26 | 2.5 | 0.0 |
|
0.0 |
RPL06.CFCI.4010 |
RPL06 - Submittals Review & Approval - Roofing | Roofing | Complete | 02/09/26 | 02/20/26 | 11.2 | 0.0 |
|
0.0 |
RPL06.CFCI.4890 |
RPL06 - Submittals Review & Approval - Fire Alarm | (CFCI) Div. 26 - Fire Alarm | Complete | 02/09/26 | 02/20/26 | 18.8 | 0.0 |
|
0.0 |
RPL06.CFCI.5040 |
RPL06 - Fabricate / Deliver - Joint Sealants | Joint Sealants | Complete | 02/09/26 | 02/20/26 | 12.5 | 0.0 |
|
0.0 |