Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
81
Completed
19
In Progress
84
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.MR.1260 RPL06.MR - Mobilization Complete Make Ready Complete 02/09/26 02/09/26 0.0 0.0
100%
0.0
RPL06.SUB.DHCD.01190 RPL06.SubStructure.DHCD - Scan, Install Flowfill - Grid lines 6-19/6-27 (2nd Layer Backfill) Underground Complete 02/11/26 03/03/26 5.0 0.0
100%
0.0
RPL06.SUB.SSB.01030 RPL06.SubStructure.SSB - Foundation For Storm Shelter Rebar CMU Foundations Complete 02/11/26 02/12/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01100 RPL06.SubStructure.SSB - Install Grounding Wire - Grid lines 6-01/6-10 Foundations Complete 02/11/26 02/12/26 3.8 0.0
100%
0.0
RPL06.SUB.SSB.01240 RPL06.SubStructure.SSB - Install UG Utilities - Electrical,Pathway Verification & Backfill - Part 1 - Swing Underground Complete 02/11/26 02/18/26 0.0 0.0
100%
0.0
RPL06.CFCI.6500 Submittals Review & Approval - Roof Drain (Scupper & Downspots) (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 Complete 02/13/26 02/20/26 6.2 0.0
100%
0.0
RPL06.SUB.SSB.01120 RPL06.SubStructure.SSB - Scan, Install Flowfill - Grid lines 6-01/6-10 (1st Layer Backfill) Underground Complete 02/13/26 02/19/26 3.8 0.0
100%
0.0
RPL06.MCUP.LP1.1300 RPL06.MCUP.Loop 1 - Install UG Generator Conduit Feed Electrical UG Complete 02/16/26 02/23/26 5.0 0.0
100%
0.0
RPL06.SUB.DHAB.01100 RPL06.SubStructure.DHAB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS scope) Underground Complete 02/16/26 02/27/26 3.8 0.0
100%
0.0
RPL06.SUB.DHAB.01150 RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 - Day Underground Complete 02/16/26 02/27/26 6.2 0.0
100%
0.0
RPL06.SUB.DHAB.01170 RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 2 - Day Underground Complete 02/16/26 02/27/26 3.8 0.0
100%
0.0
RPL06.SUB.DHAB.01250 RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 - Swing Underground Complete 02/16/26 02/27/26 6.2 0.0
100%
0.0
RPL06.SUB.DHAB.01270 RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 2 - Swing Underground Complete 02/16/26 02/27/26 3.8 0.0
100%
0.0
RPL06.VDC.1440 T2-4 (mCUP Yard / Ext.) - Review & Approve BIM Shop TIER 2 - 4 - mCUP Yard / Exterior Complete 02/16/26 02/27/26 31.2 0.0
100%
0.0
RPL06.SUB.SSB.01070 RPL06.SubStructure.SSB - Install Stem Walls - Grid lines 6-01/6-10 Foundations Complete 02/17/26 02/25/26 7.5 0.0
100%
0.0
RPL06.SUB.SSB.01110 RPL06.SubStructure.SSB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill Underground Complete 02/18/26 02/23/26 3.8 0.0
100%
0.0
RPL06.SUB.SSB.01180 RPL06.SubStructure.SSB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 2 - Day Underground Complete 02/18/26 02/23/26 3.8 0.0
100%
0.0
RPL06.SUB.SSB.01200 RPL06.SubStructure.SSB - Scan, Install Flowfill - Grid lines 6-01/6-10 (2nd Layer Backfill) Underground Complete 02/18/26 02/23/26 3.8 0.0
100%
0.0
RPL06.SUB.SSB.01280 RPL06.SubStructure.SSB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 2 - Swing Underground Complete 02/18/26 02/23/26 3.8 0.0
100%
0.0
RPL06.CFCI.4190 RPL06 - Fabricate / Deliver - Fire Suppression (CFCI) Div. 21 - Fire Suppression Active 02/19/26 04/24/26 25.0 12.5
0%
3.8
RPL06.STR.1000 RPL06.Structure.BLDG - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary Structure Active 02/20/26 07/01/26 107.5 71.2
0%
76.2
RPL06.STR.SSB.01000 RPL06.Structure.SSB - Install Storm Shelter Rebar, CMU Storm Shelter Complete 02/20/26 03/02/26 10.0 0.0
100%
0.0
RPL06.STR.SSB.01010 RPL06.Structure.SSB - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary SSB Active 02/20/26 05/14/26 66.2 30.0
0%
115.0
RPL06.STR.SSB.01020 RPL06.Structure.SSB - Install Storm Shelter Steel and Decking (Coordinate with Steel Erection for New Date) - Rework Storm Shelter Active 02/20/26 04/13/26 37.5 1.2
0%
2.5
RPL06.SUB.DHAB.01110 RPL06.SubStructure.DHAB - Scan, Install Flowfill - Grid lines 6-10/6-19 (1st Layer Backfill) Underground Complete 02/20/26 02/24/26 5.0 0.0
100%
0.0
RPL06.SUB.DHCD.01100 RPL06.SubStructure.DHCD - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS Scope) Underground Complete 02/20/26 02/27/26 10.0 0.0
100%
0.0
RPL06.SUB.DHCD.01170 RPL06.SubStructure.DHCD - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 2 Underground Complete 02/20/26 02/27/26 7.5 0.0
100%
0.0
RPL06.CFCI.4040 RPL06 - Submittals Review & Approval - Lighting (CFCI) Div. 26 - Lighting Complete 02/23/26 02/26/26 12.5 0.0
100%
0.0
RPL06.CFCI.4300 RPL06 - Fabricate / Deliver - Roofing Roofing Complete 02/23/26 04/09/26 1.2 0.0
100%
0.0
RPL06.CFCI.4990 RPL06 - Submittals Review & Approval - Vesda System (CFCI) Div. 28 - VESDA System Complete 02/23/26 03/04/26 12.5 0.0
100%
0.0
RPL06.CFCI.6760 RPL06 - Submittals Review & Approval - Cable Tray (CFCI) Div. 26 - Power Equip. & Material Complete 02/23/26 02/26/26 6.2 0.0
100%
0.0
RPL06.MCUP.LP2.1000 RPL06.MCUP.Loop 2 - Install Foundations, UG Utilities, OFE - WBS Summary mCup Loop 2 Active 02/23/26 08/12/26 137.5 93.8
0%
402.5
RPL06.MCUP.LP2.1060 RPL06.MCUP.Loop 2 - Install UG Utilities - WBS Summary Underground Complete 02/23/26 03/06/26 18.8 0.0
100%
0.0
RPL06.MCUP.LP2.1260 RPL06.MCUP.Loop 2 - Install UG Generator Conduit Feed Electrical UG Complete 02/23/26 03/05/26 5.0 0.0
100%
0.0
RPL06.SUB.DHAB.01040 RPL06.SubStructure.DHAB - Install Stem Walls - Grid lines 6-10/6-19 Foundations Complete 02/23/26 02/27/26 7.5 0.0
100%
0.0
RPL06.SUB.DHAB.01080 RPL06.SubStructure.DHAB - Install Grounding Wire - Grid lines 6-10/6-19 Foundations Complete 02/23/26 02/27/26 2.5 0.0
100%
0.0
RPL06.SUB.DHCD.01080 RPL06.SubStructure.DHCD - Install Grounding Wire - Grid lines 6-19/6-28 Foundations Complete 02/23/26 02/25/26 2.5 0.0
100%
0.0
RPL06.SUB.DHAB.01190 RPL06.SubStructure.DHAB - Scan, Install Flowfill - Grid lines 6-10/6-19 (2nd Layer Backfill) Underground Complete 02/24/26 02/27/26 5.0 0.0
100%
0.0
RPL06.SUB.SSB.01080 RPL06.SubStructure.SSB - Strip Form Work And Apply Water Proofing System Foundations Complete 02/24/26 02/27/26 3.8 0.0
100%
0.0
RPL.06.D.70060.XR External Tie from RPL10 - Roofing DenseDeck & Flame Down Crew Flow (RPL10.SKN.NS43.01090) Internal Milestones (XREFs) Complete 02/25/26 02/25/26 0.0 0.0
100%
0.0
RPL06.SUB.DHCD.01230 RPL06.SubStructure.DHCD - Install Remaining Pier caps, foundation, Gradebeams & Stem walls @ Grid line 6-28 Foundations Complete 02/25/26 03/04/26 7.5 0.0
100%
0.0
RPL06.SUB.DHCD.01430 RPL06.SubStructure.DHCD - Install UG Utilities - Electrical/Testing, Pathway Verification & Backfill-Part 1 -Rem @ GL 28 Underground Complete 02/25/26 02/27/26 3.8 0.0
100%
0.0
RPL06.STR.SSB.01120 RPL06.Structure.SSB - Install AB Rough Grade & Crane Road Prep Underground Complete 02/26/26 03/03/26 6.2 0.0
100%
0.0
RPL06.SUB.DHAB.01050 RPL06.SubStructure.DHAB - Strip Form Work And Apply Water Proofing System Foundations Complete 02/26/26 03/02/26 2.5 0.0
100%
0.0
RPL06.SUB.DHAB.01450 RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing PWR line Underground Complete 02/26/26 03/04/26 6.2 0.0
100%
0.0
RPL06.CFCI.4320 RPL06 - Fabricate / Deliver - Lighting (CFCI) Div. 26 - Lighting Active 02/27/26 07/15/26 187.5 82.5
0%
175.0
RPL06.MCUP.LP1.2220 RPL06.MCUP.Loop 1 - Mechanical Pipe Hydro Testing Mechanical UG Complete 02/27/26 02/27/26 1.2 0.0
100%
0.0
RPL06.MCUP.LP2.1120 RPL06.MCUP.Loop 2 - Install Grounding Wire, Grounding Rod, Exothermic Weld & Backfill Grounding UG Complete 02/27/26 03/04/26 6.2 0.0
100%
0.0
RPL06.STR.DHAB.01080 RPL06.Structure.DHAB - Install AB Rough Grade & Crane Road Prep Underground Complete 02/27/26 03/05/26 6.2 0.0
100%
0.0
RPL06.CFCI.4760 RPL06 - Fabricate / Deliver - FSC Rough Carpentry (In Wall Backing / Blocking) Rough Carpentry - FSC Wood Active 03/02/26 06/01/26 12.5 43.8
0%
142.5
RPL06.CFCI.6040 Submittals Prep & Submit for Review - Technical Water (Assume HDPE Pipe) (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) Complete 03/02/26 03/02/26 18.8 0.0
100%
0.0
RPL06.MCUP.LP1.1020 RPL06.MCUP.Loop 1 - Install Foundations - WBS Summary Foundations Complete 03/02/26 04/06/26 31.2 0.0
100%
0.0
RPL06.MCUP.LP1.2200 RPL06.MCUP.Loop 1 - Flow Fill & Backfill (Loop 1 & 2) Foundations Complete 03/02/26 03/19/26 22.5 0.0
100%
0.0
RPL06.MCUP.LP2.1080 RPL06.MCUP.Loop 2 - Install Mechanical UG Mechanical UG Complete 03/02/26 03/06/26 8.8 0.0
100%
0.0
RPL06.MCUP.LP2.1100 RPL06.MCUP.Loop 2 - Install Electrical UG Electrical UG Complete 03/02/26 03/05/26 18.8 0.0
100%
0.0
RPL06.MCUP.LP2.1140 RPL06.MCUP.Loop 2 - Install Controls/EPMS/BMS UG Controls/EPMS/BMS UG Complete 03/02/26 03/06/26 18.8 0.0
100%
0.0
RPL.06.D.70040.XR External Tie from RPL10 - Exterior IMP Crew Flow (RPL10.SKN.W.01000) Internal Milestones (XREFs) Complete 03/03/26 03/03/26 0.0 0.0
100%
0.0
RPL06.CFCI.5340 RPL06 - Fabricate / Deliver - Strut (CFCI) Div. 05 - Slotted Channel Framing (Strut) Active 03/03/26 06/01/26 1.2 43.8
0%
142.5
RPL06.CFCI.6050 Submittals Review & Approval - Technical Water (Assume HDPE Pipe) (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) Complete 03/03/26 03/09/26 12.5 0.0
100%
0.0
RPL06.STR.SSB.01050 RPL06.Structure.SSB - Erect Steel/Joist/Decking - WBS Summary Steel and Decking Active 03/03/26 04/13/26 22.5 1.2
100%
-11.2
RPL06.STR.SSB.01230 RPL06.Structure.SSB - Steel Shake out - Grid lines 6-01/6-10 Steel and Decking Complete 03/03/26 03/23/26 6.2 0.0
100%
0.0
RPL06.CFCI.6960 RPL06 - (DPR) Submittals Review & Approval - Interior Wall Panels (IWP) Interior Wall Panels Complete 03/04/26 03/11/26 12.5 0.0
100%
0.0
RPL06.STR.DHCD.01080 RPL06.SubStructure.DHCD - Install AB Rough Grade & Crane Road Prep Underground Complete 03/04/26 03/25/26 5.0 0.0
100%
0.0
RPL06.CFCI.5190 RPL06 - Fabricate / Deliver - Vesda System (CFCI) Div. 28 - VESDA System Active 03/05/26 05/14/26 50.0 30.0
0%
102.5
RPL06.SUB.DHCD.01050 RPL06.SubStructure.DHCD - Strip Form Work Foundations Complete 03/05/26 03/05/26 1.2 0.0
100%
0.0
RPL06.SUB.DHCD.01450 RPL06.SubStructure.DHCD - Scan, Install Flowfill - Grid lines 6-27/6-28 (1st Layer Backfill) Underground Complete 03/05/26 03/05/26 1.2 0.0
100%
0.0
RPL06.SUB.DHCD.01470 RPL06.SubStructure.DHCD - Scan, Install Flowfill - Grid lines 6-27/6-28 (2st Layer Backfill) Underground Complete 03/06/26 03/06/26 1.2 0.0
100%
0.0
PRE.FA.1060 BMS Controls - Final Agreement Trade Partner Final Agreement Complete 03/09/26 03/09/26 0.0 0.0
100%
0.0
GCD.RPL06.1360 Steel Erection Start - RPL06 Construction Milestones Complete 03/10/26 03/10/26 0.0 0.0
100%
0.0
RPL06.CFCI.6060 Fabricate / Deliver - Technical Water (Assume HDPE Pipe) (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) Active 03/10/26 05/05/26 50.0 21.2
0%
282.5
RPL06.STR.SSB.01040 RPL06.Structure.SSB - Install Erect Steel Columns and Beams, Erect Joist - Grid lines 6-01/6-10 Steel and Decking Complete 03/10/26 03/27/26 11.2 0.0
100%
0.0
RPL06.10050 Weather Event #3 - 03/11/26 - 03/12/2026 (Rain) Weather Impacts Complete 03/11/26 03/12/26 2.5 0.0
100%
0.0
RPL06.MCUP.LP1.1100 RPL06.MCUP.Loop 1 - F/R/P Pads (12'' larger) Foundations Complete 03/11/26 03/30/26 17.5 0.0
100%
0.0
PRE.BNS.1420 GMP Approved by Meta Legal (fGMP) FGMP Complete 03/17/26 03/17/26 0.0 0.0
100%
0.0
PRE.BNS.1460 fGMP Review Cycle FGMP Complete 03/17/26 03/17/26 6.2 0.0
100%
0.0
PRE.BNS.1480 Execution of fGMP FGMP Complete 03/17/26 03/17/26 0.0 0.0
100%
0.0
RPL06.10070 Weather Event #4 - 03/17/26 - 03/17/2026 (Wind) Weather Impacts Complete 03/17/26 03/17/26 1.2 0.0
100%
0.0
RPL06.STR.SSB.01020A RPL06.Structure.SSB - Demo, Install Anchor Bolts and Grout at Beam Location on CMU Wall Storm Shelter Complete 03/17/26 03/18/26 3.8 0.0
100%
0.0
RPL06.STR.SSB.01020B RPL06.Structure.SSB - Cure Storm Shelter Complete 03/19/26 03/21/26 3.8 0.0
100%
0.0
RPL06.STR.SSB.01020C RPL06.Structure.SSB - Install Storm Shelter Steel Storm Shelter Complete 03/20/26 03/20/26 1.2 0.0
100%
0.0
RPL06.STR.DHAB.01010 RPL06.Structure.DHAB - Erect Steel/Joist/Decking - WBS Summary Steel and Decking Active 03/24/26 04/22/26 16.2 10.0
0%
2.5
RPL06.STR.DHAB.01020 RPL06.Structure.DHAB - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary DH B & DH A Active 03/24/26 06/14/26 61.2 55.0
0%
10.0
RPL06.STR.DHAB.01220 RPL06.Structure.DHAB - Steel Shake out - Grid Lines 6-11/6-23 Steel and Decking Active 03/24/26 04/16/26 6.2 5.0
0%
3.8
RPL06.VDC.1620 T2-4 (mCUP Yard / Ext.) - GC QC BIM Model TIER 2 - 4 - mCUP Yard / Exterior Complete 03/24/26 03/24/26 0.0 0.0
100%
0.0
RPL06.CFCI.7000 RPL06 - (DPR) Submittals Prep & Re-Submit for Review - Interior Wall Panels (IWP) Interior Wall Panels Complete 03/25/26 03/25/26 6.2 0.0
100%
0.0
RPL06.EY.DHD.01610 RPL06.EY.DHD - Install SD, DW, FW UG (GL 25-28) GL 25-28 Complete 03/25/26 03/31/26 6.2 0.0
100%
0.0
RPL06.STR.SSB.01060 RPL06.Structure.SSB - Install Decking & Detailing turnover #1 - Grid lines 6-01/6-04 Steel and Decking Active 03/25/26 04/13/26 3.8 1.2
100%
-11.2
RPL06.CFCI.7020 RPL06 - (DPR) Re-Submittals Review & Approval - Interior Wall Panels (IWP) Interior Wall Panels Complete 03/26/26 04/08/26 6.2 0.0
100%
0.0
RPL06.MCUP.LP1.1200 RPL06.MCUP.Loop 1 - OFE - WBS Summary OFE Active 03/26/26 05/05/26 33.8 21.2
0%
105.0
RPL06.MCUP.LP1.2160 RPL06.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP3) OFE Complete 03/26/26 03/26/26 1.2 0.0
100%
0.0
RPL06.MCUP.LP1.2140 RPL06.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP2) OFE Complete 03/27/26 03/27/26 1.2 0.0
100%
0.0
RPL06.MCUP.FWM.01010 RPL06.MCUP.FWM - Install FWM FWM Complete 03/30/26 03/30/26 3.8 0.0
100%
0.0
ICM.B6.1875 [SSDCB1] Delivery of mCUP (First Delivery) Construction Complete 03/31/26 03/31/26 0.0 0.0
100%
0.0
RPL06.LOG.1000 MCUP 500 Ton Crane Mobilization 300 Ton Crane Complete 03/31/26 03/31/26 5.0 0.0
100%
0.0
RPL06.MCUP.LP1.1180 RPL06.MCUP.Loop 1 - Cure for Pads Complete Foundations Complete 03/31/26 04/06/26 8.8 0.0
100%
0.0
RPL06.MCUP.LP1.1340 RPL06.MCUP.Loop 1 - Set mCUPs 06MY.MCUP.01 (1 per 5 days) OFE Complete 03/31/26 04/07/26 6.2 0.0
100%
0.0
RPL06.MCUP.LP2.1020 RPL06.MCUP.Loop 2 - Install Foundations - WBS Summary Foundations Active 03/31/26 06/11/26 63.8 11.2
0%
208.8
RPL06.MCUP.LP2.1160 RPL06.MCUP.Loop 2 - F/R/P Pads (12'' larger) without Generator Pads Foundations Complete 03/31/26 04/03/26 12.5 0.0
100%
0.0
RPL06.SKIN.01000 RPL06.SKIN.BLDG - Install Insulated Metal Panels (IMP), Roof, Windows, Doors, Louvers - WBS Summary Skin Active 03/31/26 02/26/27 281.2 275.0
0%
162.5
RPL06.SKN.W.01000 RPL06.SKIN - Install Metal Panel, Sealant & Starter Flashing - West North South East IMP System Active 03/31/26 04/16/26 12.5 5.0
0%
-11.2