Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
81
Completed
19
In Progress
84
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL06.MR.1260 |
RPL06.MR - Mobilization Complete | Make Ready | Complete | 02/09/26 | 02/09/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01190 |
RPL06.SubStructure.DHCD - Scan, Install Flowfill - Grid lines 6-19/6-27 (2nd Layer Backfill) | Underground | Complete | 02/11/26 | 03/03/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01030 |
RPL06.SubStructure.SSB - Foundation For Storm Shelter Rebar CMU | Foundations | Complete | 02/11/26 | 02/12/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01100 |
RPL06.SubStructure.SSB - Install Grounding Wire - Grid lines 6-01/6-10 | Foundations | Complete | 02/11/26 | 02/12/26 | 3.8 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01240 |
RPL06.SubStructure.SSB - Install UG Utilities - Electrical,Pathway Verification & Backfill - Part 1 - Swing | Underground | Complete | 02/11/26 | 02/18/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.6500 |
Submittals Review & Approval - Roof Drain (Scupper & Downspots) | (CFCI) Div. 33 - Utilities Storm / Sanitary Manholes and Inlets - Area 2 | Complete | 02/13/26 | 02/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01120 |
RPL06.SubStructure.SSB - Scan, Install Flowfill - Grid lines 6-01/6-10 (1st Layer Backfill) | Underground | Complete | 02/13/26 | 02/19/26 | 3.8 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.1300 |
RPL06.MCUP.Loop 1 - Install UG Generator Conduit Feed | Electrical UG | Complete | 02/16/26 | 02/23/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01100 |
RPL06.SubStructure.DHAB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS scope) | Underground | Complete | 02/16/26 | 02/27/26 | 3.8 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01150 |
RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 - Day | Underground | Complete | 02/16/26 | 02/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01170 |
RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 2 - Day | Underground | Complete | 02/16/26 | 02/27/26 | 3.8 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01250 |
RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing/Testing/Backfill - Part 2 - Swing | Underground | Complete | 02/16/26 | 02/27/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01270 |
RPL06.SubStructure.DHAB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 2 - Swing | Underground | Complete | 02/16/26 | 02/27/26 | 3.8 | 0.0 |
|
0.0 |
RPL06.VDC.1440 |
T2-4 (mCUP Yard / Ext.) - Review & Approve BIM Shop | TIER 2 - 4 - mCUP Yard / Exterior | Complete | 02/16/26 | 02/27/26 | 31.2 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01070 |
RPL06.SubStructure.SSB - Install Stem Walls - Grid lines 6-01/6-10 | Foundations | Complete | 02/17/26 | 02/25/26 | 7.5 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01110 |
RPL06.SubStructure.SSB - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill | Underground | Complete | 02/18/26 | 02/23/26 | 3.8 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01180 |
RPL06.SubStructure.SSB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 2 - Day | Underground | Complete | 02/18/26 | 02/23/26 | 3.8 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01200 |
RPL06.SubStructure.SSB - Scan, Install Flowfill - Grid lines 6-01/6-10 (2nd Layer Backfill) | Underground | Complete | 02/18/26 | 02/23/26 | 3.8 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01280 |
RPL06.SubStructure.SSB - Install UG Utilities - Electrical, Pathway Verification & Backfill - Part 2 - Swing | Underground | Complete | 02/18/26 | 02/23/26 | 3.8 | 0.0 |
|
0.0 |
RPL06.CFCI.4190 |
RPL06 - Fabricate / Deliver - Fire Suppression | (CFCI) Div. 21 - Fire Suppression | Active | 02/19/26 | 04/24/26 | 25.0 | 12.5 |
|
3.8 |
RPL06.STR.1000 |
RPL06.Structure.BLDG - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | Structure | Active | 02/20/26 | 07/01/26 | 107.5 | 71.2 |
|
76.2 |
RPL06.STR.SSB.01000 |
RPL06.Structure.SSB - Install Storm Shelter Rebar, CMU | Storm Shelter | Complete | 02/20/26 | 03/02/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.STR.SSB.01010 |
RPL06.Structure.SSB - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | SSB | Active | 02/20/26 | 05/14/26 | 66.2 | 30.0 |
|
115.0 |
RPL06.STR.SSB.01020 |
RPL06.Structure.SSB - Install Storm Shelter Steel and Decking (Coordinate with Steel Erection for New Date) - Rework | Storm Shelter | Active | 02/20/26 | 04/13/26 | 37.5 | 1.2 |
|
2.5 |
RPL06.SUB.DHAB.01110 |
RPL06.SubStructure.DHAB - Scan, Install Flowfill - Grid lines 6-10/6-19 (1st Layer Backfill) | Underground | Complete | 02/20/26 | 02/24/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01100 |
RPL06.SubStructure.DHCD - Install UG Utilities - BMS/EPMS/Testing and Pathway Verification and Backfill (new GS Scope) | Underground | Complete | 02/20/26 | 02/27/26 | 10.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01170 |
RPL06.SubStructure.DHCD - Install UG Utilities - Electrical/Testing and Pathway Verification and Backfill - Part 2 | Underground | Complete | 02/20/26 | 02/27/26 | 7.5 | 0.0 |
|
0.0 |
RPL06.CFCI.4040 |
RPL06 - Submittals Review & Approval - Lighting | (CFCI) Div. 26 - Lighting | Complete | 02/23/26 | 02/26/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.CFCI.4300 |
RPL06 - Fabricate / Deliver - Roofing | Roofing | Complete | 02/23/26 | 04/09/26 | 1.2 | 0.0 |
|
0.0 |
RPL06.CFCI.4990 |
RPL06 - Submittals Review & Approval - Vesda System | (CFCI) Div. 28 - VESDA System | Complete | 02/23/26 | 03/04/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.CFCI.6760 |
RPL06 - Submittals Review & Approval - Cable Tray | (CFCI) Div. 26 - Power Equip. & Material | Complete | 02/23/26 | 02/26/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.MCUP.LP2.1000 |
RPL06.MCUP.Loop 2 - Install Foundations, UG Utilities, OFE - WBS Summary | mCup Loop 2 | Active | 02/23/26 | 08/12/26 | 137.5 | 93.8 |
|
402.5 |
RPL06.MCUP.LP2.1060 |
RPL06.MCUP.Loop 2 - Install UG Utilities - WBS Summary | Underground | Complete | 02/23/26 | 03/06/26 | 18.8 | 0.0 |
|
0.0 |
RPL06.MCUP.LP2.1260 |
RPL06.MCUP.Loop 2 - Install UG Generator Conduit Feed | Electrical UG | Complete | 02/23/26 | 03/05/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01040 |
RPL06.SubStructure.DHAB - Install Stem Walls - Grid lines 6-10/6-19 | Foundations | Complete | 02/23/26 | 02/27/26 | 7.5 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01080 |
RPL06.SubStructure.DHAB - Install Grounding Wire - Grid lines 6-10/6-19 | Foundations | Complete | 02/23/26 | 02/27/26 | 2.5 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01080 |
RPL06.SubStructure.DHCD - Install Grounding Wire - Grid lines 6-19/6-28 | Foundations | Complete | 02/23/26 | 02/25/26 | 2.5 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01190 |
RPL06.SubStructure.DHAB - Scan, Install Flowfill - Grid lines 6-10/6-19 (2nd Layer Backfill) | Underground | Complete | 02/24/26 | 02/27/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.SUB.SSB.01080 |
RPL06.SubStructure.SSB - Strip Form Work And Apply Water Proofing System | Foundations | Complete | 02/24/26 | 02/27/26 | 3.8 | 0.0 |
|
0.0 |
RPL.06.D.70060.XR |
External Tie from RPL10 - Roofing DenseDeck & Flame Down Crew Flow (RPL10.SKN.NS43.01090) | Internal Milestones (XREFs) | Complete | 02/25/26 | 02/25/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01230 |
RPL06.SubStructure.DHCD - Install Remaining Pier caps, foundation, Gradebeams & Stem walls @ Grid line 6-28 | Foundations | Complete | 02/25/26 | 03/04/26 | 7.5 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01430 |
RPL06.SubStructure.DHCD - Install UG Utilities - Electrical/Testing, Pathway Verification & Backfill-Part 1 -Rem @ GL 28 | Underground | Complete | 02/25/26 | 02/27/26 | 3.8 | 0.0 |
|
0.0 |
RPL06.STR.SSB.01120 |
RPL06.Structure.SSB - Install AB Rough Grade & Crane Road Prep | Underground | Complete | 02/26/26 | 03/03/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01050 |
RPL06.SubStructure.DHAB - Strip Form Work And Apply Water Proofing System | Foundations | Complete | 02/26/26 | 03/02/26 | 2.5 | 0.0 |
|
0.0 |
RPL06.SUB.DHAB.01450 |
RPL06.SubStructure.DHAB - Install UG Utilities - Plumbing PWR line | Underground | Complete | 02/26/26 | 03/04/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.CFCI.4320 |
RPL06 - Fabricate / Deliver - Lighting | (CFCI) Div. 26 - Lighting | Active | 02/27/26 | 07/15/26 | 187.5 | 82.5 |
|
175.0 |
RPL06.MCUP.LP1.2220 |
RPL06.MCUP.Loop 1 - Mechanical Pipe Hydro Testing | Mechanical UG | Complete | 02/27/26 | 02/27/26 | 1.2 | 0.0 |
|
0.0 |
RPL06.MCUP.LP2.1120 |
RPL06.MCUP.Loop 2 - Install Grounding Wire, Grounding Rod, Exothermic Weld & Backfill | Grounding UG | Complete | 02/27/26 | 03/04/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.STR.DHAB.01080 |
RPL06.Structure.DHAB - Install AB Rough Grade & Crane Road Prep | Underground | Complete | 02/27/26 | 03/05/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.CFCI.4760 |
RPL06 - Fabricate / Deliver - FSC Rough Carpentry (In Wall Backing / Blocking) | Rough Carpentry - FSC Wood | Active | 03/02/26 | 06/01/26 | 12.5 | 43.8 |
|
142.5 |
RPL06.CFCI.6040 |
Submittals Prep & Submit for Review - Technical Water (Assume HDPE Pipe) | (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) | Complete | 03/02/26 | 03/02/26 | 18.8 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.1020 |
RPL06.MCUP.Loop 1 - Install Foundations - WBS Summary | Foundations | Complete | 03/02/26 | 04/06/26 | 31.2 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.2200 |
RPL06.MCUP.Loop 1 - Flow Fill & Backfill (Loop 1 & 2) | Foundations | Complete | 03/02/26 | 03/19/26 | 22.5 | 0.0 |
|
0.0 |
RPL06.MCUP.LP2.1080 |
RPL06.MCUP.Loop 2 - Install Mechanical UG | Mechanical UG | Complete | 03/02/26 | 03/06/26 | 8.8 | 0.0 |
|
0.0 |
RPL06.MCUP.LP2.1100 |
RPL06.MCUP.Loop 2 - Install Electrical UG | Electrical UG | Complete | 03/02/26 | 03/05/26 | 18.8 | 0.0 |
|
0.0 |
RPL06.MCUP.LP2.1140 |
RPL06.MCUP.Loop 2 - Install Controls/EPMS/BMS UG | Controls/EPMS/BMS UG | Complete | 03/02/26 | 03/06/26 | 18.8 | 0.0 |
|
0.0 |
RPL.06.D.70040.XR |
External Tie from RPL10 - Exterior IMP Crew Flow (RPL10.SKN.W.01000) | Internal Milestones (XREFs) | Complete | 03/03/26 | 03/03/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.5340 |
RPL06 - Fabricate / Deliver - Strut | (CFCI) Div. 05 - Slotted Channel Framing (Strut) | Active | 03/03/26 | 06/01/26 | 1.2 | 43.8 |
|
142.5 |
RPL06.CFCI.6050 |
Submittals Review & Approval - Technical Water (Assume HDPE Pipe) | (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) | Complete | 03/03/26 | 03/09/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.STR.SSB.01050 |
RPL06.Structure.SSB - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Active | 03/03/26 | 04/13/26 | 22.5 | 1.2 |
|
-11.2 |
RPL06.STR.SSB.01230 |
RPL06.Structure.SSB - Steel Shake out - Grid lines 6-01/6-10 | Steel and Decking | Complete | 03/03/26 | 03/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.CFCI.6960 |
RPL06 - (DPR) Submittals Review & Approval - Interior Wall Panels (IWP) | Interior Wall Panels | Complete | 03/04/26 | 03/11/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.STR.DHCD.01080 |
RPL06.SubStructure.DHCD - Install AB Rough Grade & Crane Road Prep | Underground | Complete | 03/04/26 | 03/25/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.CFCI.5190 |
RPL06 - Fabricate / Deliver - Vesda System | (CFCI) Div. 28 - VESDA System | Active | 03/05/26 | 05/14/26 | 50.0 | 30.0 |
|
102.5 |
RPL06.SUB.DHCD.01050 |
RPL06.SubStructure.DHCD - Strip Form Work | Foundations | Complete | 03/05/26 | 03/05/26 | 1.2 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01450 |
RPL06.SubStructure.DHCD - Scan, Install Flowfill - Grid lines 6-27/6-28 (1st Layer Backfill) | Underground | Complete | 03/05/26 | 03/05/26 | 1.2 | 0.0 |
|
0.0 |
RPL06.SUB.DHCD.01470 |
RPL06.SubStructure.DHCD - Scan, Install Flowfill - Grid lines 6-27/6-28 (2st Layer Backfill) | Underground | Complete | 03/06/26 | 03/06/26 | 1.2 | 0.0 |
|
0.0 |
PRE.FA.1060 |
BMS Controls - Final Agreement | Trade Partner Final Agreement | Complete | 03/09/26 | 03/09/26 | 0.0 | 0.0 |
|
0.0 |
GCD.RPL06.1360 |
Steel Erection Start - RPL06 | Construction Milestones | Complete | 03/10/26 | 03/10/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.6060 |
Fabricate / Deliver - Technical Water (Assume HDPE Pipe) | (CFCI) Div. 33 - Utilities Technical Water (Assume HDPE) | Active | 03/10/26 | 05/05/26 | 50.0 | 21.2 |
|
282.5 |
RPL06.STR.SSB.01040 |
RPL06.Structure.SSB - Install Erect Steel Columns and Beams, Erect Joist - Grid lines 6-01/6-10 | Steel and Decking | Complete | 03/10/26 | 03/27/26 | 11.2 | 0.0 |
|
0.0 |
RPL06.10050 |
Weather Event #3 - 03/11/26 - 03/12/2026 (Rain) | Weather Impacts | Complete | 03/11/26 | 03/12/26 | 2.5 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.1100 |
RPL06.MCUP.Loop 1 - F/R/P Pads (12'' larger) | Foundations | Complete | 03/11/26 | 03/30/26 | 17.5 | 0.0 |
|
0.0 |
PRE.BNS.1420 |
GMP Approved by Meta Legal (fGMP) | FGMP | Complete | 03/17/26 | 03/17/26 | 0.0 | 0.0 |
|
0.0 |
PRE.BNS.1460 |
fGMP Review Cycle | FGMP | Complete | 03/17/26 | 03/17/26 | 6.2 | 0.0 |
|
0.0 |
PRE.BNS.1480 |
Execution of fGMP | FGMP | Complete | 03/17/26 | 03/17/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.10070 |
Weather Event #4 - 03/17/26 - 03/17/2026 (Wind) | Weather Impacts | Complete | 03/17/26 | 03/17/26 | 1.2 | 0.0 |
|
0.0 |
RPL06.STR.SSB.01020A |
RPL06.Structure.SSB - Demo, Install Anchor Bolts and Grout at Beam Location on CMU Wall | Storm Shelter | Complete | 03/17/26 | 03/18/26 | 3.8 | 0.0 |
|
0.0 |
RPL06.STR.SSB.01020B |
RPL06.Structure.SSB - Cure | Storm Shelter | Complete | 03/19/26 | 03/21/26 | 3.8 | 0.0 |
|
0.0 |
RPL06.STR.SSB.01020C |
RPL06.Structure.SSB - Install Storm Shelter Steel | Storm Shelter | Complete | 03/20/26 | 03/20/26 | 1.2 | 0.0 |
|
0.0 |
RPL06.STR.DHAB.01010 |
RPL06.Structure.DHAB - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Active | 03/24/26 | 04/22/26 | 16.2 | 10.0 |
|
2.5 |
RPL06.STR.DHAB.01020 |
RPL06.Structure.DHAB - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | DH B & DH A | Active | 03/24/26 | 06/14/26 | 61.2 | 55.0 |
|
10.0 |
RPL06.STR.DHAB.01220 |
RPL06.Structure.DHAB - Steel Shake out - Grid Lines 6-11/6-23 | Steel and Decking | Active | 03/24/26 | 04/16/26 | 6.2 | 5.0 |
|
3.8 |
RPL06.VDC.1620 |
T2-4 (mCUP Yard / Ext.) - GC QC BIM Model | TIER 2 - 4 - mCUP Yard / Exterior | Complete | 03/24/26 | 03/24/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.7000 |
RPL06 - (DPR) Submittals Prep & Re-Submit for Review - Interior Wall Panels (IWP) | Interior Wall Panels | Complete | 03/25/26 | 03/25/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.EY.DHD.01610 |
RPL06.EY.DHD - Install SD, DW, FW UG (GL 25-28) | GL 25-28 | Complete | 03/25/26 | 03/31/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.STR.SSB.01060 |
RPL06.Structure.SSB - Install Decking & Detailing turnover #1 - Grid lines 6-01/6-04 | Steel and Decking | Active | 03/25/26 | 04/13/26 | 3.8 | 1.2 |
|
-11.2 |
RPL06.CFCI.7020 |
RPL06 - (DPR) Re-Submittals Review & Approval - Interior Wall Panels (IWP) | Interior Wall Panels | Complete | 03/26/26 | 04/08/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.1200 |
RPL06.MCUP.Loop 1 - OFE - WBS Summary | OFE | Active | 03/26/26 | 05/05/26 | 33.8 | 21.2 |
|
105.0 |
RPL06.MCUP.LP1.2160 |
RPL06.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP3) | OFE | Complete | 03/26/26 | 03/26/26 | 1.2 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.2140 |
RPL06.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP2) | OFE | Complete | 03/27/26 | 03/27/26 | 1.2 | 0.0 |
|
0.0 |
RPL06.MCUP.FWM.01010 |
RPL06.MCUP.FWM - Install FWM | FWM | Complete | 03/30/26 | 03/30/26 | 3.8 | 0.0 |
|
0.0 |
ICM.B6.1875 |
[SSDCB1] Delivery of mCUP (First Delivery) | Construction | Complete | 03/31/26 | 03/31/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.LOG.1000 |
MCUP 500 Ton Crane Mobilization | 300 Ton Crane | Complete | 03/31/26 | 03/31/26 | 5.0 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.1180 |
RPL06.MCUP.Loop 1 - Cure for Pads Complete | Foundations | Complete | 03/31/26 | 04/06/26 | 8.8 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.1340 |
RPL06.MCUP.Loop 1 - Set mCUPs 06MY.MCUP.01 (1 per 5 days) | OFE | Complete | 03/31/26 | 04/07/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.MCUP.LP2.1020 |
RPL06.MCUP.Loop 2 - Install Foundations - WBS Summary | Foundations | Active | 03/31/26 | 06/11/26 | 63.8 | 11.2 |
|
208.8 |
RPL06.MCUP.LP2.1160 |
RPL06.MCUP.Loop 2 - F/R/P Pads (12'' larger) without Generator Pads | Foundations | Complete | 03/31/26 | 04/03/26 | 12.5 | 0.0 |
|
0.0 |
RPL06.SKIN.01000 |
RPL06.SKIN.BLDG - Install Insulated Metal Panels (IMP), Roof, Windows, Doors, Louvers - WBS Summary | Skin | Active | 03/31/26 | 02/26/27 | 281.2 | 275.0 |
|
162.5 |
RPL06.SKN.W.01000 |
RPL06.SKIN - Install Metal Panel, Sealant & Starter Flashing - West North South East | IMP System | Active | 03/31/26 | 04/16/26 | 12.5 | 5.0 |
|
-11.2 |