Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
14
Completed
17
In Progress
28
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL06.STR.DHAB.01000 |
RPL06.Structure.DHAB - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 6-11/6-23 | Steel and Decking | Active | 03/31/26 | 04/16/26 | 10.0 | 5.0 |
|
3.8 |
RPL06.EY.DHD.01630 |
RPL06.EY.DHD - Install Electrical UG (GL 25-28) | GL 25-28 | Complete | 04/01/26 | 04/03/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.EY.DHD.01650 |
RPL06.EY.DHD - Install Grounding UG (GL 25-28) | GL 25-28 | Complete | 04/01/26 | 04/08/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.EY.DHD.01670 |
RPL06.EY.DHD - Install BMS UG (GL 25-28) | GL 25-28 | Complete | 04/01/26 | 04/03/26 | 6.2 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.2120 |
RPL06.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP1) | OFE | Complete | 04/01/26 | 04/01/26 | 1.2 | 0.0 |
|
0.0 |
RPL06.MCUP.LP1.1280 |
RPL06.MCUP.Loop 1 - Set MTRs (4 per day) | OFE | Active | 04/02/26 | 04/30/26 | 6.2 | 17.5 |
|
103.8 |
RPL06.MCUP.LP1.2180 |
RPL06.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP4) | OFE | Complete | 04/02/26 | 04/02/26 | 1.2 | 0.0 |
|
0.0 |
RPL06.STR.DHAB.01015 |
RPL06.Structure.DHAB - Install Decking & Detailing turnover #2 - Grid lines 6-04/6-07 | Steel and Decking | Active | 04/02/26 | 04/13/26 | 2.5 | 1.2 |
|
-11.2 |
RPL06.LOG.1120 |
Dry Cooler 230 Ton Crane Mobilization | 100 Ton Crane | Complete | 04/03/26 | 04/03/26 | 3.8 | 0.0 |
|
0.0 |
RPL06.MCUP.LP2.1200 |
RPL06.MCUP.Loop 2 - OFE - WBS Summary | OFE | Active | 04/03/26 | 05/27/26 | 40.0 | 26.2 |
|
195.0 |
RPL06.MCUP.LP2.2100 |
RPL06.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP5) | OFE | Complete | 04/03/26 | 04/06/26 | 1.2 | 0.0 |
|
0.0 |
RPL06.MCUP.LP2.1180 |
RPL06.MCUP.Loop 2 - Cure for Pads | Foundations | Complete | 04/04/26 | 04/10/26 | 8.8 | 0.0 |
|
0.0 |
ICM.B6.1835 |
[SSDCB1] Delivery of FCA - Fan Coil Assembly (First Delivery) | Construction | Complete | 04/06/26 | 04/06/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.CFCI.5680 |
RPL06 - Submittals Prep & Submit for Review - Glass / Frames | Glass & Glazing (Alum. Entrances & Curtainwall) | Active | 04/06/26 | 04/30/26 | 10.0 | 17.5 |
|
140.0 |
RPL06.MCUP.LP1.1220 |
RPL06.MCUP.Loop 1 - Set mCup #1 & #2 - Dry Coolers (12) (4 per week) | OFE | Complete | 04/06/26 | 04/09/26 | 18.8 | 0.0 |
|
0.0 |
RPL06.STR.DHAB.01025 |
RPL06.Structure.DHAB - Install Decking & Detailing turnover #3 - Grid lines 6-07/6-09 | Steel and Decking | Active | 04/06/26 | 04/15/26 | 1.2 | 2.5 |
|
-6.2 |
RPL06.MCUP.LP1.1380 |
RPL06.MCUP.Loop 1 - Set mCUPs 06MY.MCUP.02 (1 per 5 days) | OFE | Active | 04/07/26 | 04/13/26 | 6.2 | 1.2 |
|
100.0 |
RPL06.MCUP.LP2.2120 |
RPL06.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP6) | OFE | Complete | 04/07/26 | 04/08/26 | 1.2 | 0.0 |
|
0.0 |
RPL06.CFCI.6980 |
RPL06 - (DPR) Fabricate / Deliver - Interior Wall Panels (IWP) | Interior Wall Panels | Active | 04/09/26 | 05/13/26 | 43.8 | 28.8 |
|
111.2 |
RPL06.EY.DHD.01690 |
RPL06.EY.DHD - Flow Fill (GL 25-28) - Electrical and majority Plumbing | GL 25-28 | Complete | 04/09/26 | 04/10/26 | 2.5 | 0.0 |
|
0.0 |
RPL06.STR.DHAB.01030 |
RPL06.Structure.DHAB - Install Decking & Detailing turnover #4 - Grid lines 6-10/6-14 | Steel and Decking | Active | 04/09/26 | 04/17/26 | 5.0 | 5.0 |
|
-2.5 |
GCD.RPL06.1380 |
IMP Start - RPL06 | Construction Milestones | Complete | 04/10/26 | 04/10/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.MR.1301 |
RPL06.MR - Leah Ln @Burn Rd East - Demo & Rebuild | Make Ready | Complete | 04/10/26 | 04/10/26 | 0.0 | 0.0 |
|
0.0 |
RPL06.OFCI.7540 |
OFCI Delivery: BE ESL Bag Rack Deliver/Install (DHB) | Data Hall B | Active | 04/10/26 | 05/03/27 | 18.8 | 331.2 |
|
-86.2 |
RPL06.OFCI.7560 |
OFCI Delivery: BE ESL Bag Rack Deliver/Install (DHA) | Data Hall A | Active | 04/10/26 | 05/03/27 | 18.8 | 331.2 |
|
-77.5 |
RPL06.SKN.W.01005 |
RPL06.SKIN.West - Install IMP - Flashing,Panels & Caulking - Gridlines 6F/6A (37 P with temp closures for openings) | DBC Move 1 | Active | 04/10/26 | 04/14/26 | 5.0 | 2.5 |
|
-11.2 |
RPL06.SKN.W.01010 |
RPL06.SKIN.West - Install IMP Insulated Metal Panels System - WBS Summary | DBC Move 1 | Active | 04/10/26 | 04/17/26 | 12.5 | 6.2 |
|
3.8 |
RPL06.STR.SSB.01100 |
RPL06.Structure.SSB - Adjust AB to adjust MEP Verticals and Grounding wire | Prep | Active | 04/10/26 | 04/16/26 | 6.2 | 3.8 |
|
-6.2 |
RPL06.STR.SSB.01110 |
RPL06.Structure.SSB - Install Remaining UG and Subgrade Prep - WBS Summary | Prep | Active | 04/10/26 | 04/30/26 | 18.8 | 17.5 |
|
-1.2 |
RPL06.STR.SSB.01135 |
RPL06.Structure.SSB - Extend Underground Conduits Stub ups to FFE | Prep | Active | 04/10/26 | 04/30/26 | 18.8 | 17.5 |
|
-1.2 |
RPL06.EY.DHD.01710 |
RPL06.EY.DHD - Flow Fill Cure Early (GL 25-28) | GL 25-28 | Active | 04/11/26 | 04/13/26 | 3.8 | 1.2 |
|
300.0 |
GCD.RPL06.1182 |
Start mCUP Unit Set-In-Place - RPL06 | Construction Milestones | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
341.2 |
ICM.B6.1805 |
[SSDCB1] Delivery of Substation MSG Alpha (First Delivery) NOT DPR SCOPE | Construction | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
510.0 |
PRE.MIR.1200 |
Glass & Metal Panel SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Not Started | 04/13/26 | 04/24/26 | 12.5 | 12.5 |
|
220.0 |
PRE.TPBD.1240 |
Balance of Trades - Submit for Meta Review | Trade Partner Bid Development | Not Started | 04/13/26 | 04/24/26 | 12.5 | 12.5 |
|
120.0 |
PRE.TPBD.1260 |
Kitchen Equipment - Submit for Meta Review | Trade Partner Bid Development | Not Started | 04/13/26 | 05/08/26 | 25.0 | 25.0 |
|
331.2 |
RPL.06.D.63340. XR |
Laydown Area 13 - RPL06 Ready | Receive Milestones (XREFs) | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
510.0 |
RPL.06.D.64310.XR |
Water Available for Pressure Testing | Receive Milestones (XREFs) | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
170.0 |
RPL.GF.D.N6180.XG |
GS IDF Huts Innerduct Complete for RPL 6 | Give Milestones (XREFs) | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
510.0 |
RPL06.CFCI.3890 |
RPL06 - Fabricate / Deliver - Plumbing (OH Piping) (Prefab) | (CFCI) Div. 22 - Plumbing | Not Started | 04/13/26 | 05/29/26 | 42.5 | 42.5 |
|
83.8 |
RPL06.CFCI.3900 |
RPL06 - Fabricate / Deliver - HVAC Materials and Equipment | (CFCI) Div. 23 - HVAC Materials and Equip. | Not Started | 04/13/26 | 04/17/26 | 6.2 | 6.2 |
|
18.8 |
RPL06.CFCI.3910 |
RPL06 - Fabricate / Deliver - HVAC Insulation | (CFCI) Div. 23 - HVAC Insulation | Not Started | 04/13/26 | 05/08/26 | 25.0 | 25.0 |
|
32.5 |
RPL06.CFCI.4780 |
RPL06 - Fabricate / Deliver - Gypsum System and Ceilings | (CFCI) Div. 09 - Gypsum System & Ceilings | Not Started | 04/13/26 | 07/02/26 | 72.5 | 72.5 |
|
193.8 |
RPL06.CFCI.4920 |
RPL06 - Fabricate / Deliver - Security System | (CFCI) Div. 28 - Security Syst. | Not Started | 04/13/26 | 06/08/26 | 50.0 | 50.0 |
|
245.0 |
RPL06.CFCI.5090 |
RPL06 - Fabricate / Deliver - Fire Alarm | (CFCI) Div. 26 - Fire Alarm | Not Started | 04/13/26 | 06/08/26 | 50.0 | 50.0 |
|
263.8 |
RPL06.CFCI.6780 |
RPL06 - Fabricate / Deliver - Cable Tray | (CFCI) Div. 26 - Power Equip. & Material | Not Started | 04/13/26 | 07/01/26 | 71.2 | 71.2 |
|
3.8 |
RPL06.CFCI.6800 |
RPL06 - Submittals Prep & Submit for Review - Stick Built IDF ( A1, B1, C1, D1) | (CFCI) Div. XX - Technology IDF (Stick Built) | Not Started | 04/13/26 | 05/08/26 | 25.0 | 25.0 |
|
71.2 |
RPL06.CON.01000 |
RPL06.Conn BLDG - Install GS and Production Cabling - WBS Summary | Connectivity | Not Started | 04/13/26 | 09/14/27 | 447.5 | 447.5 |
|
62.5 |
RPL06.CON.WP2.01000 |
RPL06.Conn - General Service - WBS Summary | WP#02 GS | Not Started | 04/13/26 | 03/05/27 | 281.2 | 281.2 |
|
228.8 |
RPL06.CON.WP2.08580 |
RPL06.Conn - Construction Cx Server Ready - At GSMDF | WP#02 GS | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
307.5 |
RPL06.CON.WP2.08600 |
RPL06.Conn - Construction Cx Server Ready - At mCup | WP#02 GS | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
510.0 |
RPL06.CON.WP2.08620 |
RPL06.Conn - Construction Cx Server Ready - At DH B (LV) | WP#02 GS | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
510.0 |
RPL06.CON.WP2.08640 |
RPL06.Conn - Construction Cx Server Ready - At DH B EY (MV) | WP#02 GS | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
510.0 |
RPL06.EY.DHA.01230 |
RPL06.EY.DHA - OFE - MV - WBS Summary | OFE | Not Started | 04/13/26 | 10/08/26 | 157.5 | 157.5 |
|
156.2 |
RPL06.EY.DHA.01540 |
RPL06.EY.DHA - Install AHUs (Qty 1) | OFE | Not Started | 04/13/26 | 04/22/26 | 10.0 | 10.0 |
|
285.0 |
RPL06.EY.DHD.01770 |
RPL06.EY.DHD - Realign and backfill SD by Mortenson | GL 25-28 | Not Started | 04/13/26 | 04/17/26 | 6.2 | 6.2 |
|
-5.0 |
RPL06.LOG.1020 |
MCUP 500 Ton Crane Movement 1 | 300 Ton Crane | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
100.0 |
RPL06.LOG.1140 |
Dry Cooler 230 Ton Crane Movement 01 | 100 Ton Crane | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
103.8 |
RPL06.LOG.1340 |
Steel Crane #1 Mobilization | Steel Crane 1 | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
55.0 |
RPL06.LOG.1360 |
Steel Crane #2 Mobilization | Steel Crane 2 | Not Started | 04/13/26 | 04/13/26 | 0.0 | 0.0 |
|
55.0 |
RPL06.MCUP.FWM.01000 |
RPL06.MCUP.FWM - Install PTX | FWM | Not Started | 04/13/26 | 04/15/26 | 3.8 | 3.8 |
|
112.5 |
RPL06.MCUP.FWM.01030 |
RPL06.MCUP.FWM - Install MVS | FWM | Not Started | 04/13/26 | 04/15/26 | 3.8 | 3.8 |
|
112.5 |
RPL06.MCUP.LP1.1320 |
RPL06.MCUP.Loop 1 - Set mCup #3 & #4 - Dry Coolers (12) (4 per week) | OFE | Not Started | 04/13/26 | 05/01/26 | 18.8 | 18.8 |
|
103.8 |
RPL06.STR.SSB.01020D |
RPL06.Structure.SSB - Install Decking | Storm Shelter | Not Started | 04/13/26 | 04/13/26 | 1.2 | 1.2 |
|
2.5 |
RPL06.SUB.DHCD.01490 |
RPL06.SubStructure.DHCD - Apply Water Proofing System | Foundations | Not Started | 04/13/26 | 04/17/26 | 6.2 | 6.2 |
|
183.8 |
RPL06.VDC.1640 |
T2-4 (DH A & B) - Review & Approve BIM Shop | TIER 2 - 4 - DH A & B | Not Started | 04/13/26 | 05/15/26 | 31.2 | 31.2 |
|
12.5 |
RPL06.VDC.1700 |
T2-4 (EF) - Review & Approve BIM Shop | TIER 2 - 4 - EF | Not Started | 04/13/26 | 05/15/26 | 31.2 | 31.2 |
|
56.2 |
RPL06.VDC.1720 |
T2-4 (DH C & D) - Review & Approve BIM Shop | TIER 2 - 4 - DH C & D | Not Started | 04/13/26 | 05/15/26 | 31.2 | 31.2 |
|
115.0 |
RPL06.VDC.1740 |
T2-4 (mCUP Yard / Ext.) - Procurement Equipments | TIER 2 - 4 - mCUP Yard / Exterior | Not Started | 04/13/26 | 05/01/26 | 18.8 | 18.8 |
|
97.5 |
RPL06.MCUP.LP1.1400 |
RPL06.MCUP.Loop 1 - Tie-ins - WBS Summary | Tie-ins | Not Started | 04/14/26 | 06/08/26 | 48.8 | 48.8 |
|
393.8 |
RPL06.MCUP.LP1.1500 |
RPL06.MCUP.Loop 1 - Set mCUPs 06MY.MCUP.03 (1 per 5 days) | OFE | Not Started | 04/14/26 | 04/20/26 | 6.2 | 6.2 |
|
100.0 |
RPL06.MCUP.LP1.1660 |
RPL06.MCUP.Loop 1 - Tie-in SD, DW | Tie-ins | Not Started | 04/14/26 | 05/04/26 | 18.8 | 18.8 |
|
423.8 |
RPL06.EY.SSB.01020 |
RPL06.EY.SSB - Install Foundations, UG Utilities, OFE - WBS Summary | EY.SSB | Not Started | 04/15/26 | 03/24/27 | 295.0 | 295.0 |
|
212.5 |
RPL06.EY.SSB.01040 |
RPL06.EY.SSB - Install Electrical UG (South End) | Underground | Not Started | 04/15/26 | 04/21/26 | 6.2 | 6.2 |
|
-11.2 |
RPL06.EY.SSB.01060 |
RPL06.EY.SSB - Install UG Utilities - WBS Summary | Underground | Not Started | 04/15/26 | 05/03/26 | 16.2 | 16.2 |
|
81.2 |
RPL06.EY.SSB.01080 |
RPL06.EY.SSB - Install BMS UG (South End) | Underground | Not Started | 04/15/26 | 04/21/26 | 6.2 | 6.2 |
|
83.8 |
RPL06.EY.SSB.01130 |
RPL06.EY.SSB - Install SD, DW, FW UG (North End) | Underground | Not Started | 04/15/26 | 04/28/26 | 12.5 | 12.5 |
|
80.0 |
RPL06.EY.SSB.01420 |
RPL06.EY.SSB - Install Grounding UG | Underground | Not Started | 04/15/26 | 04/21/26 | 6.2 | 6.2 |
|
83.8 |
RPL06.SKN.N.01000 |
RPL06.SKIN.North - Install IMP - Flashing,Panels & Caulking - Gridlines 6-01/6-09 (33P with temp closures for openings) | DBC Move 1 | Not Started | 04/15/26 | 04/17/26 | 3.8 | 3.8 |
|
3.8 |
RPL06.SKN.SSB.01000 |
RPL06.SKIN.SSB - Install Temp Doors | Glazing, Doors and Ext Devices | Not Started | 04/15/26 | 04/16/26 | 2.5 | 2.5 |
|
298.8 |
RPL06.SKN.SSB.01020 |
RPL06.SKIN.SSB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | SSB | Not Started | 04/15/26 | 08/25/26 | 116.2 | 116.2 |
|
197.5 |
RPL06.SKN.SSB.01030 |
RPL06.SKIN.SSB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Not Started | 04/15/26 | 08/25/26 | 116.2 | 116.2 |
|
197.5 |
RPL06.SKN.SSB.01040 |
RPL06.SKIN.SSB - Install Louvers | Glazing, Doors and Ext Devices | Not Started | 04/15/26 | 04/21/26 | 6.2 | 6.2 |
|
287.5 |
RPL06.SKN.SSB.01050 |
RPL06.SKIN.SSB - Install Lighting | Glazing, Doors and Ext Devices | Not Started | 04/15/26 | 04/20/26 | 5.0 | 5.0 |
|
288.8 |
RPL06.SKN.SSB.01080 |
RPL06.SKIN.SSB - Install Roof System - Exterior Wall Sheathing and EJ | Roofing | Not Started | 04/15/26 | 04/21/26 | 6.2 | 6.2 |
|
-7.5 |
RPL06.SKN.SSB.01090 |
RPL06.SKIN.SSB - Install Roof System - WBS Summary | Roofing | Not Started | 04/15/26 | 05/29/26 | 40.0 | 40.0 |
|
22.5 |
RPL06.SKN.SSB.01170 |
RPL06.SKIN.SSB - Install Blocking of Canopy & Backing of Exterior Wall | Glazing, Doors and Ext Devices | Not Started | 04/15/26 | 04/21/26 | 6.2 | 6.2 |
|
76.2 |
RPL06.SKN.W.01040 |
RPL06.SKIN.West - Secure All Exterior Mounted Boxes and Devices on Skin | IMP System | Not Started | 04/15/26 | 04/28/26 | 12.5 | 12.5 |
|
313.8 |
RPL06.VDC.1860 |
T2-4 (SSB) - Procurement Materials | TIER 2 - 4 - SSB | Not Started | 04/16/26 | 05/06/26 | 18.8 | 18.8 |
|
2.5 |
RPL06.MCUP.LP1.1360 |
RPL06.MCUP.Loop 1 - Set Electrical Skids #1 | OFE | Not Started | 04/17/26 | 04/20/26 | 2.5 | 2.5 |
|
116.2 |
RPL06.MCUP.LP1.1440 |
RPL06.MCUP.Loop 1 - Tie-in Mechanical - WBS Summary | Tie-Ins Mechanical | Not Started | 04/17/26 | 05/22/26 | 32.5 | 32.5 |
|
101.2 |
RPL06.MCUP.LP1.1520 |
RPL06.MCUP.Loop 1 - Set Electrical Skids #2 | OFE | Not Started | 04/17/26 | 04/20/26 | 2.5 | 2.5 |
|
116.2 |
RPL06.MCUP.LP1.1760 |
RPL06.MCUP.Loop 1 - Tie-in Mechanical #2 | Tie-Ins Mechanical | Not Started | 04/17/26 | 05/07/26 | 18.8 | 18.8 |
|
115.0 |
RPL06.STR.DHCD.01000 |
RPL06.Structure.DHCD - Install Erect Steel Columns and Beams, Erect Joist - Grid Lines 6-23/6-28 | Steel and Decking | Not Started | 04/17/26 | 04/23/26 | 6.2 | 6.2 |
|
3.8 |
RPL06.STR.DHCD.01010 |
RPL06.Structure.DHCD - Erect Steel/Joist/Decking - WBS Summary | Steel and Decking | Not Started | 04/17/26 | 05/06/26 | 17.5 | 17.5 |
|
6.2 |
RPL06.STR.DHCD.01020 |
RPL06.Structure.DHCD - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary | DH D & DH C | Not Started | 04/17/26 | 07/01/26 | 66.2 | 66.2 |
|
76.2 |
RPL06.STR.DHCD.01190 |
RPL06.Structure.DHCD - Steel Shake out - Grid Lines 6-23/6-28 | Steel and Decking | Not Started | 04/17/26 | 04/23/26 | 6.2 | 6.2 |
|
3.8 |
RPL06.STR.SSB.01130 |
RPL06.Structure.SSB - Asphalt Emulsion and Wrap Steel Columns | Prep | Not Started | 04/17/26 | 04/22/26 | 5.0 | 5.0 |
|
-6.2 |
RPL.06.D.64510.XR |
Storm Drain Available for Roof Drain Tie-ins | Receive Milestones (XREFs) | Not Started | 04/20/26 | 04/20/26 | 0.0 | 0.0 |
|
-5.0 |
RPL06.EY.DHB.01100 |
RPL06.EY.DHB - Install SD, DW, FW UG (GL 01-09) | GL 01-09 | Not Started | 04/20/26 | 05/01/26 | 12.5 | 12.5 |
|
45.0 |