Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
14
Completed
17
In Progress
28
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.STR.DHAB.01000 RPL06.Structure.DHAB - Install Erect Steel Columns and Beams, Erect Joist Grid Lines 6-11/6-23 Steel and Decking Active 03/31/26 04/16/26 10.0 5.0
0%
3.8
RPL06.EY.DHD.01630 RPL06.EY.DHD - Install Electrical UG (GL 25-28) GL 25-28 Complete 04/01/26 04/03/26 6.2 0.0
100%
0.0
RPL06.EY.DHD.01650 RPL06.EY.DHD - Install Grounding UG (GL 25-28) GL 25-28 Complete 04/01/26 04/08/26 6.2 0.0
100%
0.0
RPL06.EY.DHD.01670 RPL06.EY.DHD - Install BMS UG (GL 25-28) GL 25-28 Complete 04/01/26 04/03/26 6.2 0.0
100%
0.0
RPL06.MCUP.LP1.2120 RPL06.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP1) OFE Complete 04/01/26 04/01/26 1.2 0.0
100%
0.0
RPL06.MCUP.LP1.1280 RPL06.MCUP.Loop 1 - Set MTRs (4 per day) OFE Active 04/02/26 04/30/26 6.2 17.5
0%
103.8
RPL06.MCUP.LP1.2180 RPL06.MCUP.Loop 1 - Set Facility Water Pipe Rack (mCUP4) OFE Complete 04/02/26 04/02/26 1.2 0.0
100%
0.0
RPL06.STR.DHAB.01015 RPL06.Structure.DHAB - Install Decking & Detailing turnover #2 - Grid lines 6-04/6-07 Steel and Decking Active 04/02/26 04/13/26 2.5 1.2
100%
-11.2
RPL06.LOG.1120 Dry Cooler 230 Ton Crane Mobilization 100 Ton Crane Complete 04/03/26 04/03/26 3.8 0.0
100%
0.0
RPL06.MCUP.LP2.1200 RPL06.MCUP.Loop 2 - OFE - WBS Summary OFE Active 04/03/26 05/27/26 40.0 26.2
0%
195.0
RPL06.MCUP.LP2.2100 RPL06.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP5) OFE Complete 04/03/26 04/06/26 1.2 0.0
100%
0.0
RPL06.MCUP.LP2.1180 RPL06.MCUP.Loop 2 - Cure for Pads Foundations Complete 04/04/26 04/10/26 8.8 0.0
100%
0.0
ICM.B6.1835 [SSDCB1] Delivery of FCA - Fan Coil Assembly (First Delivery) Construction Complete 04/06/26 04/06/26 0.0 0.0
100%
0.0
RPL06.CFCI.5680 RPL06 - Submittals Prep & Submit for Review - Glass / Frames Glass & Glazing (Alum. Entrances & Curtainwall) Active 04/06/26 04/30/26 10.0 17.5
0%
140.0
RPL06.MCUP.LP1.1220 RPL06.MCUP.Loop 1 - Set mCup #1 & #2 - Dry Coolers (12) (4 per week) OFE Complete 04/06/26 04/09/26 18.8 0.0
100%
0.0
RPL06.STR.DHAB.01025 RPL06.Structure.DHAB - Install Decking & Detailing turnover #3 - Grid lines 6-07/6-09 Steel and Decking Active 04/06/26 04/15/26 1.2 2.5
100%
-6.2
RPL06.MCUP.LP1.1380 RPL06.MCUP.Loop 1 - Set mCUPs 06MY.MCUP.02 (1 per 5 days) OFE Active 04/07/26 04/13/26 6.2 1.2
100%
100.0
RPL06.MCUP.LP2.2120 RPL06.MCUP.Loop 2 - Set Facility Water Pipe Rack (mCUP6) OFE Complete 04/07/26 04/08/26 1.2 0.0
100%
0.0
RPL06.CFCI.6980 RPL06 - (DPR) Fabricate / Deliver - Interior Wall Panels (IWP) Interior Wall Panels Active 04/09/26 05/13/26 43.8 28.8
0%
111.2
RPL06.EY.DHD.01690 RPL06.EY.DHD - Flow Fill (GL 25-28) - Electrical and majority Plumbing GL 25-28 Complete 04/09/26 04/10/26 2.5 0.0
100%
0.0
RPL06.STR.DHAB.01030 RPL06.Structure.DHAB - Install Decking & Detailing turnover #4 - Grid lines 6-10/6-14 Steel and Decking Active 04/09/26 04/17/26 5.0 5.0
0%
-2.5
GCD.RPL06.1380 IMP Start - RPL06 Construction Milestones Complete 04/10/26 04/10/26 0.0 0.0
100%
0.0
RPL06.MR.1301 RPL06.MR - Leah Ln @Burn Rd East - Demo & Rebuild Make Ready Complete 04/10/26 04/10/26 0.0 0.0
100%
0.0
RPL06.OFCI.7540 OFCI Delivery: BE ESL Bag Rack Deliver/Install (DHB) Data Hall B Active 04/10/26 05/03/27 18.8 331.2
0%
-86.2
RPL06.OFCI.7560 OFCI Delivery: BE ESL Bag Rack Deliver/Install (DHA) Data Hall A Active 04/10/26 05/03/27 18.8 331.2
0%
-77.5
RPL06.SKN.W.01005 RPL06.SKIN.West - Install IMP - Flashing,Panels & Caulking - Gridlines 6F/6A (37 P with temp closures for openings) DBC Move 1 Active 04/10/26 04/14/26 5.0 2.5
0%
-11.2
RPL06.SKN.W.01010 RPL06.SKIN.West - Install IMP Insulated Metal Panels System - WBS Summary DBC Move 1 Active 04/10/26 04/17/26 12.5 6.2
0%
3.8
RPL06.STR.SSB.01100 RPL06.Structure.SSB - Adjust AB to adjust MEP Verticals and Grounding wire Prep Active 04/10/26 04/16/26 6.2 3.8
0%
-6.2
RPL06.STR.SSB.01110 RPL06.Structure.SSB - Install Remaining UG and Subgrade Prep - WBS Summary Prep Active 04/10/26 04/30/26 18.8 17.5
0%
-1.2
RPL06.STR.SSB.01135 RPL06.Structure.SSB - Extend Underground Conduits Stub ups to FFE Prep Active 04/10/26 04/30/26 18.8 17.5
0%
-1.2
RPL06.EY.DHD.01710 RPL06.EY.DHD - Flow Fill Cure Early (GL 25-28) GL 25-28 Active 04/11/26 04/13/26 3.8 1.2
0%
300.0
GCD.RPL06.1182 Start mCUP Unit Set-In-Place - RPL06 Construction Milestones Not Started 04/13/26 04/13/26 0.0 0.0
0%
341.2
ICM.B6.1805 [SSDCB1] Delivery of Substation MSG Alpha (First Delivery) NOT DPR SCOPE Construction Not Started 04/13/26 04/13/26 0.0 0.0
0%
510.0
PRE.MIR.1200 Glass & Metal Panel SA - Meta Review / Authorization Meta Internal Review of Trade Partner Bids Not Started 04/13/26 04/24/26 12.5 12.5
0%
220.0
PRE.TPBD.1240 Balance of Trades - Submit for Meta Review Trade Partner Bid Development Not Started 04/13/26 04/24/26 12.5 12.5
0%
120.0
PRE.TPBD.1260 Kitchen Equipment - Submit for Meta Review Trade Partner Bid Development Not Started 04/13/26 05/08/26 25.0 25.0
0%
331.2
RPL.06.D.63340. XR Laydown Area 13 - RPL06 Ready Receive Milestones (XREFs) Not Started 04/13/26 04/13/26 0.0 0.0
0%
510.0
RPL.06.D.64310.XR Water Available for Pressure Testing Receive Milestones (XREFs) Not Started 04/13/26 04/13/26 0.0 0.0
0%
170.0
RPL.GF.D.N6180.XG GS IDF Huts Innerduct Complete for RPL 6 Give Milestones (XREFs) Not Started 04/13/26 04/13/26 0.0 0.0
0%
510.0
RPL06.CFCI.3890 RPL06 - Fabricate / Deliver - Plumbing (OH Piping) (Prefab) (CFCI) Div. 22 - Plumbing Not Started 04/13/26 05/29/26 42.5 42.5
0%
83.8
RPL06.CFCI.3900 RPL06 - Fabricate / Deliver - HVAC Materials and Equipment (CFCI) Div. 23 - HVAC Materials and Equip. Not Started 04/13/26 04/17/26 6.2 6.2
0%
18.8
RPL06.CFCI.3910 RPL06 - Fabricate / Deliver - HVAC Insulation (CFCI) Div. 23 - HVAC Insulation Not Started 04/13/26 05/08/26 25.0 25.0
0%
32.5
RPL06.CFCI.4780 RPL06 - Fabricate / Deliver - Gypsum System and Ceilings (CFCI) Div. 09 - Gypsum System & Ceilings Not Started 04/13/26 07/02/26 72.5 72.5
0%
193.8
RPL06.CFCI.4920 RPL06 - Fabricate / Deliver - Security System (CFCI) Div. 28 - Security Syst. Not Started 04/13/26 06/08/26 50.0 50.0
0%
245.0
RPL06.CFCI.5090 RPL06 - Fabricate / Deliver - Fire Alarm (CFCI) Div. 26 - Fire Alarm Not Started 04/13/26 06/08/26 50.0 50.0
0%
263.8
RPL06.CFCI.6780 RPL06 - Fabricate / Deliver - Cable Tray (CFCI) Div. 26 - Power Equip. & Material Not Started 04/13/26 07/01/26 71.2 71.2
0%
3.8
RPL06.CFCI.6800 RPL06 - Submittals Prep & Submit for Review - Stick Built IDF ( A1, B1, C1, D1) (CFCI) Div. XX - Technology IDF (Stick Built) Not Started 04/13/26 05/08/26 25.0 25.0
0%
71.2
RPL06.CON.01000 RPL06.Conn BLDG - Install GS and Production Cabling - WBS Summary Connectivity Not Started 04/13/26 09/14/27 447.5 447.5
0%
62.5
RPL06.CON.WP2.01000 RPL06.Conn - General Service - WBS Summary WP#02 GS Not Started 04/13/26 03/05/27 281.2 281.2
0%
228.8
RPL06.CON.WP2.08580 RPL06.Conn - Construction Cx Server Ready - At GSMDF WP#02 GS Not Started 04/13/26 04/13/26 0.0 0.0
0%
307.5
RPL06.CON.WP2.08600 RPL06.Conn - Construction Cx Server Ready - At mCup WP#02 GS Not Started 04/13/26 04/13/26 0.0 0.0
0%
510.0
RPL06.CON.WP2.08620 RPL06.Conn - Construction Cx Server Ready - At DH B (LV) WP#02 GS Not Started 04/13/26 04/13/26 0.0 0.0
0%
510.0
RPL06.CON.WP2.08640 RPL06.Conn - Construction Cx Server Ready - At DH B EY (MV) WP#02 GS Not Started 04/13/26 04/13/26 0.0 0.0
0%
510.0
RPL06.EY.DHA.01230 RPL06.EY.DHA - OFE - MV - WBS Summary OFE Not Started 04/13/26 10/08/26 157.5 157.5
0%
156.2
RPL06.EY.DHA.01540 RPL06.EY.DHA - Install AHUs (Qty 1) OFE Not Started 04/13/26 04/22/26 10.0 10.0
0%
285.0
RPL06.EY.DHD.01770 RPL06.EY.DHD - Realign and backfill SD by Mortenson GL 25-28 Not Started 04/13/26 04/17/26 6.2 6.2
0%
-5.0
RPL06.LOG.1020 MCUP 500 Ton Crane Movement 1 300 Ton Crane Not Started 04/13/26 04/13/26 0.0 0.0
0%
100.0
RPL06.LOG.1140 Dry Cooler 230 Ton Crane Movement 01 100 Ton Crane Not Started 04/13/26 04/13/26 0.0 0.0
0%
103.8
RPL06.LOG.1340 Steel Crane #1 Mobilization Steel Crane 1 Not Started 04/13/26 04/13/26 0.0 0.0
0%
55.0
RPL06.LOG.1360 Steel Crane #2 Mobilization Steel Crane 2 Not Started 04/13/26 04/13/26 0.0 0.0
0%
55.0
RPL06.MCUP.FWM.01000 RPL06.MCUP.FWM - Install PTX FWM Not Started 04/13/26 04/15/26 3.8 3.8
0%
112.5
RPL06.MCUP.FWM.01030 RPL06.MCUP.FWM - Install MVS FWM Not Started 04/13/26 04/15/26 3.8 3.8
0%
112.5
RPL06.MCUP.LP1.1320 RPL06.MCUP.Loop 1 - Set mCup #3 & #4 - Dry Coolers (12) (4 per week) OFE Not Started 04/13/26 05/01/26 18.8 18.8
0%
103.8
RPL06.STR.SSB.01020D RPL06.Structure.SSB - Install Decking Storm Shelter Not Started 04/13/26 04/13/26 1.2 1.2
0%
2.5
RPL06.SUB.DHCD.01490 RPL06.SubStructure.DHCD - Apply Water Proofing System Foundations Not Started 04/13/26 04/17/26 6.2 6.2
0%
183.8
RPL06.VDC.1640 T2-4 (DH A & B) - Review & Approve BIM Shop TIER 2 - 4 - DH A & B Not Started 04/13/26 05/15/26 31.2 31.2
0%
12.5
RPL06.VDC.1700 T2-4 (EF) - Review & Approve BIM Shop TIER 2 - 4 - EF Not Started 04/13/26 05/15/26 31.2 31.2
0%
56.2
RPL06.VDC.1720 T2-4 (DH C & D) - Review & Approve BIM Shop TIER 2 - 4 - DH C & D Not Started 04/13/26 05/15/26 31.2 31.2
0%
115.0
RPL06.VDC.1740 T2-4 (mCUP Yard / Ext.) - Procurement Equipments TIER 2 - 4 - mCUP Yard / Exterior Not Started 04/13/26 05/01/26 18.8 18.8
0%
97.5
RPL06.MCUP.LP1.1400 RPL06.MCUP.Loop 1 - Tie-ins - WBS Summary Tie-ins Not Started 04/14/26 06/08/26 48.8 48.8
0%
393.8
RPL06.MCUP.LP1.1500 RPL06.MCUP.Loop 1 - Set mCUPs 06MY.MCUP.03 (1 per 5 days) OFE Not Started 04/14/26 04/20/26 6.2 6.2
0%
100.0
RPL06.MCUP.LP1.1660 RPL06.MCUP.Loop 1 - Tie-in SD, DW Tie-ins Not Started 04/14/26 05/04/26 18.8 18.8
0%
423.8
RPL06.EY.SSB.01020 RPL06.EY.SSB - Install Foundations, UG Utilities, OFE - WBS Summary EY.SSB Not Started 04/15/26 03/24/27 295.0 295.0
0%
212.5
RPL06.EY.SSB.01040 RPL06.EY.SSB - Install Electrical UG (South End) Underground Not Started 04/15/26 04/21/26 6.2 6.2
0%
-11.2
RPL06.EY.SSB.01060 RPL06.EY.SSB - Install UG Utilities - WBS Summary Underground Not Started 04/15/26 05/03/26 16.2 16.2
0%
81.2
RPL06.EY.SSB.01080 RPL06.EY.SSB - Install BMS UG (South End) Underground Not Started 04/15/26 04/21/26 6.2 6.2
0%
83.8
RPL06.EY.SSB.01130 RPL06.EY.SSB - Install SD, DW, FW UG (North End) Underground Not Started 04/15/26 04/28/26 12.5 12.5
0%
80.0
RPL06.EY.SSB.01420 RPL06.EY.SSB - Install Grounding UG Underground Not Started 04/15/26 04/21/26 6.2 6.2
0%
83.8
RPL06.SKN.N.01000 RPL06.SKIN.North - Install IMP - Flashing,Panels & Caulking - Gridlines 6-01/6-09 (33P with temp closures for openings) DBC Move 1 Not Started 04/15/26 04/17/26 3.8 3.8
0%
3.8
RPL06.SKN.SSB.01000 RPL06.SKIN.SSB - Install Temp Doors Glazing, Doors and Ext Devices Not Started 04/15/26 04/16/26 2.5 2.5
0%
298.8
RPL06.SKN.SSB.01020 RPL06.SKIN.SSB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary SSB Not Started 04/15/26 08/25/26 116.2 116.2
0%
197.5
RPL06.SKN.SSB.01030 RPL06.SKIN.SSB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Not Started 04/15/26 08/25/26 116.2 116.2
0%
197.5
RPL06.SKN.SSB.01040 RPL06.SKIN.SSB - Install Louvers Glazing, Doors and Ext Devices Not Started 04/15/26 04/21/26 6.2 6.2
0%
287.5
RPL06.SKN.SSB.01050 RPL06.SKIN.SSB - Install Lighting Glazing, Doors and Ext Devices Not Started 04/15/26 04/20/26 5.0 5.0
0%
288.8
RPL06.SKN.SSB.01080 RPL06.SKIN.SSB - Install Roof System - Exterior Wall Sheathing and EJ Roofing Not Started 04/15/26 04/21/26 6.2 6.2
0%
-7.5
RPL06.SKN.SSB.01090 RPL06.SKIN.SSB - Install Roof System - WBS Summary Roofing Not Started 04/15/26 05/29/26 40.0 40.0
0%
22.5
RPL06.SKN.SSB.01170 RPL06.SKIN.SSB - Install Blocking of Canopy & Backing of Exterior Wall Glazing, Doors and Ext Devices Not Started 04/15/26 04/21/26 6.2 6.2
0%
76.2
RPL06.SKN.W.01040 RPL06.SKIN.West - Secure All Exterior Mounted Boxes and Devices on Skin IMP System Not Started 04/15/26 04/28/26 12.5 12.5
0%
313.8
RPL06.VDC.1860 T2-4 (SSB) - Procurement Materials TIER 2 - 4 - SSB Not Started 04/16/26 05/06/26 18.8 18.8
0%
2.5
RPL06.MCUP.LP1.1360 RPL06.MCUP.Loop 1 - Set Electrical Skids #1 OFE Not Started 04/17/26 04/20/26 2.5 2.5
0%
116.2
RPL06.MCUP.LP1.1440 RPL06.MCUP.Loop 1 - Tie-in Mechanical - WBS Summary Tie-Ins Mechanical Not Started 04/17/26 05/22/26 32.5 32.5
0%
101.2
RPL06.MCUP.LP1.1520 RPL06.MCUP.Loop 1 - Set Electrical Skids #2 OFE Not Started 04/17/26 04/20/26 2.5 2.5
0%
116.2
RPL06.MCUP.LP1.1760 RPL06.MCUP.Loop 1 - Tie-in Mechanical #2 Tie-Ins Mechanical Not Started 04/17/26 05/07/26 18.8 18.8
0%
115.0
RPL06.STR.DHCD.01000 RPL06.Structure.DHCD - Install Erect Steel Columns and Beams, Erect Joist - Grid Lines 6-23/6-28 Steel and Decking Not Started 04/17/26 04/23/26 6.2 6.2
0%
3.8
RPL06.STR.DHCD.01010 RPL06.Structure.DHCD - Erect Steel/Joist/Decking - WBS Summary Steel and Decking Not Started 04/17/26 05/06/26 17.5 17.5
0%
6.2
RPL06.STR.DHCD.01020 RPL06.Structure.DHCD - Erect Steel/Joist/Decking, Remaining UG/SOG - WBS Summary DH D & DH C Not Started 04/17/26 07/01/26 66.2 66.2
0%
76.2
RPL06.STR.DHCD.01190 RPL06.Structure.DHCD - Steel Shake out - Grid Lines 6-23/6-28 Steel and Decking Not Started 04/17/26 04/23/26 6.2 6.2
0%
3.8
RPL06.STR.SSB.01130 RPL06.Structure.SSB - Asphalt Emulsion and Wrap Steel Columns Prep Not Started 04/17/26 04/22/26 5.0 5.0
0%
-6.2
RPL.06.D.64510.XR Storm Drain Available for Roof Drain Tie-ins Receive Milestones (XREFs) Not Started 04/20/26 04/20/26 0.0 0.0
0%
-5.0
RPL06.EY.DHB.01100 RPL06.EY.DHB - Install SD, DW, FW UG (GL 01-09) GL 01-09 Not Started 04/20/26 05/01/26 12.5 12.5
0%
45.0