Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
7
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.EY.DHD.01810 RPL06.EY.DHD - Remaining Connections to SD GL 25-28 Not Started 04/20/26 04/20/26 1.2 1.2
0%
195.0
RPL06.SKN.N.01010 RPL06.SKIN.North - Install IMP Insulated Metal Panels System - WBS Summary DBC Move 2 Not Started 04/20/26 05/13/26 22.5 22.5
0%
393.8
RPL06.SKN.S.01000 RPL06.SKIN.South - Install IMP - Flashing,Panels & Caulking - Gridlines 6-01/6-09 (33 P with temp closures for openings) DBC Move 2 Not Started 04/20/26 04/22/26 3.8 3.8
0%
3.8
RPL06.STR.DHAB.01035 RPL06.Structure.DHAB - Install Decking & Detailing turnover #5 - Grid lines 6-14/6-18 Steel and Decking Not Started 04/20/26 04/22/26 3.8 3.8
0%
2.5
RPL06.STR.DHAB.01060 RPL06.Structure.DHAB - Adjust AB to adjust MEP Verts and Grounding wire Prep Not Started 04/20/26 04/24/26 6.2 6.2
0%
27.5
RPL06.STR.DHAB.01070 RPL06.Structure.DHAB - Install Remaining UG and Subgrade Prep - WBS Summary Prep Not Started 04/20/26 04/29/26 10.0 10.0
0%
27.5
RPL06.EY.DHD.01790 RPL06.EY.DHD - Flow Fill (GL 25-28) - Post East side SD realignment and connections GL 25-28 Not Started 04/21/26 04/22/26 2.5 2.5
0%
195.0
RPL06.MCUP.LP1.1620 RPL06.MCUP.Loop 1 - Set mCUPs 06MY.MCUP.04 (1 per 5 days) OFE Not Started 04/21/26 04/27/26 6.2 6.2
0%
100.0
RPL06.SKN.SSB.01070 RPL06.SKIN.SSB - Install Security Glazing, Doors and Ext Devices Not Started 04/21/26 04/22/26 2.5 2.5
0%
288.8
RPL06.EY.SSB.01110 RPL06.EY.SSB - Install LD Electrical UG Loading Dock Not Started 04/22/26 04/27/26 5.0 5.0
0%
-11.2
RPL06.EY.SSB.01140 RPL06.EY.SSB - Install Loading Dock, UG Utilities, OFE - WBS Summary Loading Dock Not Started 04/22/26 06/22/26 53.8 53.8
0%
197.5
RPL06.EY.SSB.02080 RPL06.EY.SSB - Flow Fill (South End) Underground Not Started 04/22/26 04/23/26 2.5 2.5
0%
83.8
RPL06.MCUP.LP1.1880 RPL06.MCUP.Loop 1 - Tie-in Mechanical #3 Tie-Ins Mechanical Not Started 04/22/26 05/08/26 16.2 16.2
0%
113.8
RPL06.SKN.SSB.01060 RPL06.SKIN.SSB - Install Awning over Doors Glazing, Doors and Ext Devices Not Started 04/22/26 04/28/26 6.2 6.2
0%
295.0
RPL06.SKN.SSB.01075 RPL06.SKIN.SSB - QC Blocking Glazing, Doors and Ext Devices Not Started 04/22/26 04/23/26 2.5 2.5
0%
285.0
RPL06.SKN.SSB.01100 RPL06.SKIN.SSB - Install Roof System - Install Temp Flashing at EJ Roofing Not Started 04/22/26 04/23/26 2.5 2.5
0%
28.8
RPL06.SKN.SSB.01110 RPL06.SKIN.SSB - Install Roof System - DenseDeck & Flame Down (6-1 to 6-9) Roofing Not Started 04/22/26 04/30/26 8.8 8.8
0%
-7.5
RPL06.EY.DHA.01110 RPL06.EY.DHA - Install SD, DW, FW UG Underground Not Started 04/23/26 05/06/26 12.5 12.5
0%
47.5
RPL06.EY.DHD.01830 RPL06.EY.DHD - Flow Fill Cure (GL 25-28) - Post East side SD realignment and connections GL 25-28 Not Started 04/23/26 04/25/26 3.8 3.8
0%
285.0
RPL06.SKN.S.01030 RPL06.SKIN.South - Install IMP - Flashing,Panels & Caulking - Gridlines 6-10/6-14 (with temp closures for openings) DBC Move 2 Not Started 04/23/26 04/24/26 2.5 2.5
0%
3.8
RPL06.STR.DHCD.01015 RPL06.Structure.DHCD - Install Decking & Detailing turnover #6 - Grid lines 6-18/6-21 Steel and Decking Not Started 04/23/26 04/27/26 3.8 3.8
0%
2.5
GCD.RPL06.1500 Start Slab-On-Grade Concrete - RPL06 Construction Milestones Not Started 04/24/26 04/24/26 0.0 0.0
0%
330.0
RPL06.EY.ENDC.01020 RPL06.EY.End - Install Foundations, UG Utilities, OFE - WBS Summary EY.EC Not Started 04/24/26 05/17/27 332.5 332.5
0%
166.2
RPL06.EY.ENDC.01300 RPL06.EY.DHD.T1 - Install Shallow Tent UG Tent 1 Not Started 04/24/26 04/28/26 3.8 3.8
0%
3.8
RPL06.EY.SSB.02100 RPL06.EY.SSB - Flow Fill Cure (South End) Underground Not Started 04/24/26 04/26/26 3.8 3.8
0%
125.0
RPL06.LOG.1860 Steel Crane #1 Demobilzation Steel Crane 1 Not Started 04/24/26 04/24/26 0.0 0.0
0%
43.8
RPL06.LOG.1880 Steel Crane #2 Demobilization Steel Crane 2 Not Started 04/24/26 04/24/26 0.0 0.0
0%
43.8
RPL06.STR.SSB.01140 RPL06.Structure.SSB - SOG F/R/P #1 - Grid lines 6-01/6-04 and Storm Shelter Deck (Pours-1&2) F/R/P Not Started 04/24/26 04/30/26 6.2 6.2
0%
-7.5
RPL06.STR.SSB.01150 RPL06.Structure.SSB - SOG F/R/P - WBS Summary F/R/P Not Started 04/24/26 05/14/26 18.8 18.8
0%
115.0
PRE.MIR.1260 Balance of Trades SA - Meta Review / Authorization Meta Internal Review of Trade Partner Bids Not Started 04/27/26 05/08/26 12.5 12.5
0%
120.0
PRE.TPA.1240 Glass / Metal Panel / Glazing - Award and Issue Subcontract DPR issue Trade Parter Agreements Not Started 04/27/26 05/01/26 6.2 6.2
0%
220.0
RPL.06.D.64120.XG Ready for MV Cable Pull mCUP - Loop#1 (Qty 4)* Give Milestones (XREFs) Not Started 04/27/26 04/27/26 0.0 0.0
0%
496.2
RPL06.LOG.1040 MCUP 500 Ton Crane Movement 2 300 Ton Crane Not Started 04/27/26 04/27/26 0.0 0.0
0%
191.2
RPL06.SKN.S.01040 RPL06.SKIN.South - Install IMP EJ - Grid lines 6-09/6-10 DBC Move 2 Not Started 04/27/26 05/01/26 6.2 6.2
0%
15.0
RPL06.STR.DHAB.01090 RPL06.Structure.DHAB - Asphalt Emulsion and Wrap Steel Columns Prep Not Started 04/27/26 04/29/26 3.8 3.8
0%
27.5
RPL06.EY.SSB.01150 RPL06.EY.SSB - Install LD Mechanical UG Loading Dock Not Started 04/28/26 05/11/26 12.5 12.5
0%
-11.2
RPL06.MCUP.LP2.1280 RPL06.MCUP.Loop 2 - Set mCUPs XXMY.MCUP.05 (1 per 5 days) OFE Not Started 04/28/26 05/04/26 6.2 6.2
0%
191.2
RPL06.SKN.S.01160 RPL06.SKIN.South - Install IMP - Flashing,Panels & Caulking - Gridlines 6-14/6-22 (with temp closures for openings) DBC Move 2 Not Started 04/28/26 04/30/26 3.8 3.8
0%
2.5
RPL06.STR.DHCD.01025 RPL06.Structure.DHCD - Install Decking & Detailing turnover #7 - Grid lines 6-21/6-25 Steel and Decking Not Started 04/28/26 04/30/26 3.8 3.8
0%
6.2
RPL06.EY.ENDC.01360 RPL06.EY.DHD.T2 - Install Shallow Tent UG Tent 2 Not Started 04/29/26 05/01/26 3.8 3.8
0%
8.8
RPL06.EY.ENDC.1310 RPL06.EY.DHD.T1 - Install Tent Final Grading Tent 1 Not Started 04/29/26 04/30/26 2.5 2.5
0%
3.8
RPL06.EY.SSB.02120 RPL06.EY.SSB - Flow Fill (North End) Underground Not Started 04/29/26 04/30/26 2.5 2.5
0%
80.0
RPL06.MCUP.LP1.1240 RPL06.MCUP.Loop 1 - Set GS.IDF Hut (1x GS.IDF) 6X01 (ROJ03.25.26) OFE Not Started 04/29/26 05/05/26 6.2 6.2
0%
95.0
RPL06.MCUP.LP1.1260 RPL06.MCUP.Loop 1 - Set GS.IDF Hut (1x GS.IDF) 6X02 (ROJ03.25.26) OFE Not Started 04/29/26 05/05/26 6.2 6.2
0%
98.8
ICM.B6.1855 [SSDCB1] Delivery of MES - Multi Trade Rack (First Delivery) Construction Not Started 05/01/26 05/01/26 0.0 0.0
0%
126.2
PRE.FA.1200 Glass / Glazing - Final Agreement Trade Partner Final Agreement Not Started 05/01/26 05/01/26 0.0 0.0
0%
220.0
RPL06.CFCI.5700 RPL06 - Submittals Review & Approval - Glass / Frames Glass & Glazing (Alum. Entrances & Curtainwall) Not Started 05/01/26 05/21/26 18.8 18.8
0%
140.0
RPL06.EY.DHC.01100 RPL06.EY.DHC - Install SD, DW, FW UG (GL 17-23) GL 17-23 Not Started 05/01/26 05/07/26 6.2 6.2
0%
178.8
RPL06.EY.ENDC.1330 RPL06.EY.DHD.T1 - Install F/R/P Tent 1 SOG Tent 1 Not Started 05/01/26 05/07/26 6.2 6.2
0%
3.8
RPL06.EY.SSB.02140 RPL06.EY.SSB - Flow Fill Cure (North End) Underground Not Started 05/01/26 05/03/26 3.8 3.8
0%
116.2
RPL06.LOG.1160 Dry Cooler 230 Ton Crane Movement 02 100 Ton Crane Not Started 05/01/26 05/01/26 0.0 0.0
0%
190.0
RPL06.MCUP.LP1.1640 RPL06.MCUP.Loop 1 - Set Electrical Skids #3 OFE Not Started 05/01/26 05/04/26 2.5 2.5
0%
106.2
RPL06.MCUP.LP1.1680 RPL06.MCUP.Loop 1 - Set Electrical Skids #4 OFE Not Started 05/01/26 05/04/26 2.5 2.5
0%
106.2
RPL06.SKN.N.01030 RPL06.SKIN.North - Install IMP - Flashing,Panels & Caulking - Gridlines 6-10/6-14 (with temp closures for openings) DBC Move 3 Not Started 05/01/26 05/04/26 2.5 2.5
0%
2.5
RPL06.SKN.S.01010 RPL06.SKIN.South - Install IMP Insulated Metal Panels System - WBS Summary DBC Move 3 Not Started 05/01/26 05/27/26 22.5 22.5
0%
382.5
RPL06.SKN.S.01140 RPL06.SKIN.South - Install Stair Tower (DH A) DBC Move 3 Not Started 05/01/26 05/04/26 2.5 2.5
0%
127.5
RPL06.SKN.SSB.01130 RPL06.SKIN.SSB - Install Roof System - Final Roof Roofing Not Started 05/01/26 05/21/26 18.8 18.8
0%
22.5
RPL06.STR.DHAB.01110 RPL06.Structure.DHAB - SOG F/R/P - Grid Lines 6-11/6-23 - WBS Summary F/R/P Not Started 05/01/26 06/14/26 37.5 37.5
0%
10.0
RPL06.STR.DHAB.01160 RPL06.Structure.DHAB - SOG F/R/P #2 - Grid lines 6-04/6-07 (Pour-3) F/R/P Not Started 05/01/26 05/04/26 2.5 2.5
0%
13.8
RPL06.STR.DHCD.01035 RPL06.Structure.DHCD - Install Decking & Detailing turnover #8 - Grid lines 6-25/6-28 Steel and Decking Not Started 05/01/26 05/06/26 5.0 5.0
0%
6.2
RPL06.STR.DHCD.01060 RPL06.Structure.DHCD - Adjust AB to adjust MEP Verts and Grounding wire Prep Not Started 05/01/26 05/07/26 6.2 6.2
0%
27.5
RPL06.STR.DHCD.01070 RPL06.Structure.DHCD - Install Remaining UG and Subgrade Prep - WBS Summary Prep Not Started 05/01/26 05/12/26 10.0 10.0
0%
27.5
RPL06.STR.SSB.01190 RPL06.Structure.SSB - Zone SOG Cure F/R/P Not Started 05/01/26 05/05/26 6.2 6.2
0%
-10.0
RPL.06.D.63750.XG RMUs Set - mCUP Loop 1 Give Milestones (XREFs) Not Started 05/04/26 05/04/26 0.0 0.0
0%
490.0
RPL06.EY.DHB.01060 RPL06.EY.DHB - Install Electrical UG (GL 01-09) GL 01-09 Not Started 05/04/26 05/15/26 12.5 12.5
0%
45.0
RPL06.EY.DHB.01120 RPL06.EY.DHB - Install BMS/EPMS UG (GL 01-09) GL 01-09 Not Started 05/04/26 05/15/26 12.5 12.5
0%
45.0
RPL06.EY.DHB.01540 RPL06.EY.DHB - Install Grounding UG (GL 01-09) GL 01-09 Not Started 05/04/26 05/15/26 12.5 12.5
0%
45.0
RPL06.EY.ENDC.1610 RPL06.EY.DHD.T2 - Install Tent Final Grading Tent 2 Not Started 05/04/26 05/05/26 2.5 2.5
0%
8.8
RPL06.EY.SSB.01000 RPL06.EY.SSB - Install F/R/P Equipment Pads Foundations Not Started 05/04/26 05/15/26 12.5 12.5
0%
81.2
RPL06.EY.SSB.01010 RPL06.EY.SSB - Install Foundations - WBS Summary Foundations Not Started 05/04/26 05/22/26 18.8 18.8
0%
81.2
RPL06.INT.1000 RPL06.Interior.BLDG - Install Priority OH, Walls, OFE and Fitout - WBS Summary Interior Build-out Not Started 05/04/26 05/12/27 321.2 321.2
0%
98.8
RPL06.INT.SSB.01040 RPL06.Interior.SSB - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 05/04/26 05/08/26 6.2 6.2
0%
-5.0
RPL06.MCUP.LP1.1460 RPL06.MCUP.Loop 1 - Tie-in Mechanical #1 (Includes FWM) Tie-Ins Mechanical Not Started 05/04/26 05/22/26 18.8 18.8
0%
101.2
RPL06.MCUP.LP1.1980 RPL06.MCUP.Loop 1 - Tie-in Mechanical #4 Tie-Ins Mechanical Not Started 05/04/26 05/20/26 16.2 16.2
0%
103.8
RPL06.MCUP.LP2.1220 RPL06.MCUP.Loop 2 - Set mCup #5 & #6 - Dry Coolers (12) (4 per week) OFE Not Started 05/04/26 05/22/26 18.8 18.8
0%
190.0
RPL06.VDC.1780 T2-4 (DH A & B) - GC QC BIM Model TIER 2 - 4 - DH A & B Not Started 05/04/26 05/04/26 0.0 0.0
0%
12.5
RPL.GF.D.N6145.XG GS.IDF Hut 1 Install Complete for RPL06 Give Milestones (XREFs) Not Started 05/05/26 05/05/26 0.0 0.0
0%
488.8
RPL.GF.D.N6155.XG GS.IDF Hut 2 Install Complete for RPL06 Give Milestones (XREFs) Not Started 05/05/26 05/05/26 0.0 0.0
0%
488.8
RPL06.INT.SSBC.01020 RPL06.Interior.SSB-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary SSB Corridor Not Started 05/05/26 12/21/26 198.8 198.8
0%
108.8
RPL06.INT.SSBC.02410 RPL06.Interior.SSBC - Priority GL6.04 - (P0) including GS.EF(2.7). GS.MDF(2.2) & MDF Mech. (4.6) - WBS Summary Priority Wall Grid Line 6-04 Not Started 05/05/26 06/08/26 30.0 30.0
0%
95.0
RPL06.INT.SSBC.02420 RPL06.Interior.SSBC - Priority GL6.04 - (P0) Apply Intumescent Paint to Deck (Coordination of soffits to sealer) - Day Priority Wall Grid Line 6-04 Not Started 05/05/26 05/13/26 8.8 8.8
0%
13.8
RPL06.INT.SSBC.06640 RPL06.Interior.SSBC - Priority GL6.04 - (P0) Apply Intumescent Paint to Deck (Coordination of soffits to sealer) - Swing Priority Wall Grid Line 6-04 Not Started 05/05/26 05/13/26 8.8 8.8
0%
13.8
RPL06.MCUP.LP1.1820 RPL06.MCUP.Loop 1 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 05/05/26 07/08/26 56.2 56.2
0%
433.8
RPL06.MCUP.LP1.1840 RPL06.MCUP.Loop 1 - Install Sleeves MEPL Hardscape and Landscape Not Started 05/05/26 05/11/26 6.2 6.2
0%
433.8
RPL06.MCUP.LP2.1360 RPL06.MCUP.Loop 2 - Set mCUPs XXMY.MCUP.06 (1 per 5 days) OFE Not Started 05/05/26 05/11/26 6.2 6.2
0%
191.2
RPL06.SKN.N.01040 RPL06.SKIN.North - Install IMP EJ - Grid lines 6-09/6-10 DBC Move 2 Not Started 05/05/26 05/11/26 6.2 6.2
0%
7.5
RPL06.SKN.N.01180 RPL06.SKIN.North - Install IMP - Flashing,Panels & Caulking - Gridlines 6-14/6-22 (with temp closures for openings) DBC Move 3 Not Started 05/05/26 05/07/26 3.8 3.8
0%
2.5
RPL06.STR.DHAB.01170 RPL06.Structure.DHAB - SOG F/R/P #3 - Grid lines 6-07/6-11 (Pour-4) F/R/P Not Started 05/05/26 05/06/26 2.5 2.5
0%
17.5
GCD.RPL06.1320 Steel Complete - RPL06 Construction Milestones Not Started 05/06/26 05/06/26 0.0 0.0
0%
32.5
RPL06.CON.WP2.07000 RPL06.Conn - Ext. GSIDFs - WBS Summary GS.IDF (Exterior) Not Started 05/06/26 07/28/26 72.5 72.5
0%
416.2
RPL06.CON.WP2.07200 RPL06.Conn - Ext. GSIDF6X01 (mCUP yard) - WBS Summary Ext. IDF Hut - GSIDF6X01 Not Started 05/06/26 06/23/26 42.5 42.5
0%
446.2
RPL06.CON.WP2.07220 RPL06.Conn - Ext. GSIDF6X01 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 05/06/26 05/06/26 1.2 1.2
0%
292.5
RPL06.CON.WP2.07400 RPL06.Conn - Ext. GSIDF6X02 (mCUP yard) - WBS Summary Ext. IDF Hut - GSIDF6X02 Not Started 05/06/26 06/23/26 42.5 42.5
0%
446.2
RPL06.CON.WP2.07420 RPL06.Conn - Ext. GSIDF6X02 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 05/06/26 05/06/26 1.2 1.2
0%
290.0
RPL06.EY.ENDC.1630 RPL06.EY.DHD.T2 - Install F/R/P Tent 2 SOG Tent 2 Not Started 05/06/26 05/12/26 6.2 6.2
0%
8.8
RPL06.INT.SSB.01000 RPL06.Interior.SSB - Priority - WBS Summary Priority Walls and OverHead Not Started 05/06/26 06/29/26 47.5 47.5
0%
245.0
RPL06.INT.SSB.01005 RPL06.Interior - Priority - Install Hangers Support (SSB to Center Corr) (All Trades) Early Priority OH MEPF Not Started 05/06/26 05/19/26 12.5 12.5
0%
-7.5
RPL06.INT.SSB.01020 RPL06.Interior.SSB - Install Priority OH, Walls and Fitout - WBS Summary SSB Not Started 05/06/26 12/08/26 186.2 186.2
0%
202.5
RPL06.INT.SSB.03180 RPL06.Interior.SSB - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket - Day Priority Walls and OverHead Not Started 05/06/26 05/12/26 6.2 6.2
0%
63.8
RPL06.INT.SSB.06800 RPL06.Interior.SSB - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket - Swing Priority Walls and OverHead Not Started 05/06/26 05/12/26 6.2 6.2
0%
63.8