Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
6
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.MCUP.LP1.1420 RPL06.MCUP.Loop 1 - Tie-in Electrical - WBS Summary Tie-Ins Electrical Not Started 05/06/26 05/22/26 16.2 16.2
0%
95.0
RPL06.MCUP.LP1.1480 RPL06.MCUP.Loop 1 - Tie-in Electrical #1 (Includes FWM) Tie-Ins Electrical Not Started 05/06/26 05/22/26 16.2 16.2
0%
95.0
RPL06.MCUP.LP1.1700 RPL06.MCUP.Loop 1 - Tie-in Electrical #2 Tie-Ins Electrical Not Started 05/06/26 05/22/26 16.2 16.2
0%
95.0
RPL06.MCUP.LP1.1860 RPL06.MCUP.Loop 1 - Tie-in Electrical #3 Tie-Ins Electrical Not Started 05/06/26 05/19/26 12.5 12.5
0%
98.8
RPL06.MCUP.LP1.1960 RPL06.MCUP.Loop 1 - Tie-in Electrical #4 Tie-Ins Electrical Not Started 05/06/26 05/19/26 12.5 12.5
0%
98.8
RPL06.STR.SSB.01250 RPL06.Structure.SSB - Moisture requirements for floor Sealer F/R/P Not Started 05/06/26 05/12/26 8.8 8.8
0%
166.2
RPL06.CON.WP2.07260 RPL06.Conn - Ext. GSIDF6X01 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 05/07/26 05/12/26 5.0 5.0
0%
292.5
RPL06.CON.WP2.07460 RPL06.Conn - Ext. GSIDF6X02 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 05/07/26 05/14/26 7.5 7.5
0%
290.0
RPL06.EY.DHA.01060 RPL06.EY.DHA - Install Electrical UG Underground Not Started 05/07/26 05/20/26 12.5 12.5
0%
47.5
RPL06.EY.DHA.01120 RPL06.EY.DHA - Install BMS UG Underground Not Started 05/07/26 05/20/26 12.5 12.5
0%
47.5
RPL06.EY.DHA.01560 RPL06.EY.DHA - Install Grounding UG Underground Not Started 05/07/26 05/20/26 12.5 12.5
0%
47.5
RPL06.INT.SSB.01010 RPL06.Interior.SSB - Priority - Install Duct (Highside OH space) (IFP Accleration) Early Priority OH MEPF Not Started 05/07/26 05/20/26 12.5 12.5
0%
2.5
RPL06.EY.DHB.01580 RPL06.EY.DHB - Install SD, DW, FW UG (GL 10-17) GL 10-17 Not Started 05/08/26 05/21/26 12.5 12.5
0%
45.0
RPL06.EY.DHC.01050 RPL06.EY.DHC - Install Electrical UG (GL 17-23) GL 17-23 Not Started 05/08/26 05/14/26 6.2 6.2
0%
178.8
RPL06.EY.DHC.01120 RPL06.EY.DHC - Install BMS UG (GL 17-23) GL 17-23 Not Started 05/08/26 05/14/26 6.2 6.2
0%
178.8
RPL06.EY.DHC.01530 RPL06.EY.DHC - Install Grounding UG (GL 17-23) GL 17-23 Not Started 05/08/26 05/14/26 6.2 6.2
0%
178.8
RPL06.EY.ENDC.1350 RPL06.EY.DHD.T1 - Install Tent 1 Saw Cut and Cure Tent 1 Not Started 05/08/26 05/14/26 8.8 8.8
0%
6.2
RPL06.INT.SSB.01030 RPL06.Interior.SSB - Priority - Install Fire Sprinkler (Highside OH space) (IFP Accleration) Early Priority OH MEPF Not Started 05/08/26 05/14/26 6.2 6.2
0%
-7.5
RPL06.INT.SSBC.01000 RPL06.Interior.SSBC - Priority - WBS Summary Priority Walls & Overhead Not Started 05/08/26 07/02/26 48.8 48.8
0%
72.5
RPL06.INT.SSBC.03240 RPL06.Interior.SSBC - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW Draft Blanket (3200 sq ft) Priority Walls & Overhead Not Started 05/08/26 05/14/26 6.2 6.2
0%
13.8
RPL06.INT.SSBC.03520 RPL06.Interior.SSBC - Priority - Install IMP Exterior Inwall Rough-In Priority Walls & Overhead Not Started 05/08/26 05/12/26 3.8 3.8
0%
82.5
RPL06.MCUP.LP1.1540 RPL06.MCUP.Loop 1 - Tie-in BMS - WBS Summary Tie-Ins BMS Not Started 05/08/26 05/22/26 13.8 13.8
0%
101.2
RPL06.MCUP.LP1.1580 RPL06.MCUP.Loop 1 - Tie-in EPMS - WBS Summary Tie-Ins EPMS Not Started 05/08/26 05/22/26 13.8 13.8
0%
95.0
RPL06.MCUP.LP1.1780 RPL06.MCUP.Loop 1 - Tie-in EPMS #3 Tie-Ins EPMS Not Started 05/08/26 05/19/26 10.0 10.0
0%
98.8
RPL06.MCUP.LP1.1800 RPL06.MCUP.Loop 1 - Tie-in BMS #3 Tie-Ins BMS Not Started 05/08/26 05/19/26 10.0 10.0
0%
105.0
RPL06.MCUP.LP1.1900 RPL06.MCUP.Loop 1 - Tie-in EPMS #4 Tie-Ins EPMS Not Started 05/08/26 05/19/26 10.0 10.0
0%
98.8
RPL06.SKN.DHAB.01000 RPL06.SKIN.DHAB - Install Temp Doors Glazing, Doors and Ext Devices Not Started 05/08/26 05/11/26 2.5 2.5
0%
10.0
RPL06.SKN.DHAB.01010 RPL06.SKIN.DHAB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary DH A & DH B Not Started 05/08/26 06/12/26 31.2 31.2
0%
267.5
RPL06.SKN.DHAB.01020 RPL06.SKIN.DHAB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Not Started 05/08/26 06/12/26 31.2 31.2
0%
267.5
RPL06.SKN.DHAB.01070 RPL06.SKIN.DHAB - Install Roof System - Exterior Wall Sheething and EJ Roofing Not Started 05/08/26 05/11/26 2.5 2.5
0%
5.0
RPL06.SKN.DHAB.01080 RPL06.SKIN.DHAB - Install Roof System - WBS Summary Roofing Not Started 05/08/26 06/11/26 30.0 30.0
0%
111.2
RPL06.SKN.N.01050 RPL06.SKIN.North - Install IMP - Flashing,Panels & Caulking - Gridlines 6-23/6-28 (21 P with temp closures for openings) DBC Move 3 Not Started 05/08/26 05/11/26 2.5 2.5
0%
2.5
RPL06.SKN.N.01120 RPL06.SKIN.North - Install Stair Tower (DH B) DBC Move 2 Not Started 05/08/26 05/11/26 2.5 2.5
0%
121.2
RPL06.STR.DHCD.01090 RPL06.Structure.DHCD - Asphalt Emulsion and Wrap Steel Columns Prep Not Started 05/08/26 05/12/26 3.8 3.8
0%
27.5
PRE.MIR.1280 Kitchen Equipment SA - Meta Review / Authorization Meta Internal Review of Trade Partner Bids Not Started 05/11/26 05/22/26 12.5 12.5
0%
331.2
PRE.TPA.1300 Architectural/Security Fencing - Award and Issue Subcontract DPR issue Trade Parter Agreements Not Started 05/11/26 05/27/26 15.0 15.0
0%
451.2
PRE.TPA.1320 Non-Critical Trade Buyout - Award and Issue Subcontract DPR issue Trade Parter Agreements Not Started 05/11/26 07/07/26 50.0 50.0
0%
120.0
RPL.06.D.64160.XG Ready for MV Cable Pull mCUP - Loop#2 (Qty 2)* Give Milestones (XREFs) Not Started 05/11/26 05/11/26 0.0 0.0
0%
483.8
RPL06.CFCI.6820 RPL06 - Submittals Review & Approval - Stick Built IDF ( A1, B1, C1, D1) (CFCI) Div. XX - Technology IDF (Stick Built) Not Started 05/11/26 05/22/26 12.5 12.5
0%
71.2
RPL06.MCUP.LP1.1560 RPL06.MCUP.Loop 1 - Tie-in BMS #1 (Includes FWM, GS.IDF6X01) Tie-Ins BMS Not Started 05/11/26 05/22/26 12.5 12.5
0%
101.2
RPL06.MCUP.LP1.1600 RPL06.MCUP.Loop 1 - Tie-in EPMS #1 (Includes FWM) Tie-Ins EPMS Not Started 05/11/26 05/22/26 12.5 12.5
0%
95.0
RPL06.MCUP.LP1.1720 RPL06.MCUP.Loop 1 - Tie-in EPMS #2 Tie-Ins EPMS Not Started 05/11/26 05/22/26 12.5 12.5
0%
95.0
RPL06.MCUP.LP1.1740 RPL06.MCUP.Loop 1 - Tie-in BMS #2 Tie-Ins BMS Not Started 05/11/26 05/22/26 12.5 12.5
0%
101.2
RPL06.MCUP.LP1.1940 RPL06.MCUP.Loop 1 - Tie-in BMS #4 (Includes GS.IDF6X02) Tie-Ins BMS Not Started 05/11/26 05/20/26 10.0 10.0
0%
103.8
RPL06.EY.DHD.01110 RPL06.EY.DHD - Install SD, DW, FW UG (GL 17-23) GL 17-25 Not Started 05/12/26 05/18/26 6.2 6.2
0%
147.5
RPL06.EY.SSB.01190 RPL06.EY.SSB - Set LD Grade and Prep Loading Dock Not Started 05/12/26 05/15/26 5.0 5.0
0%
-11.2
RPL06.INT.SSBC.06600 RPL06.Interior.SSBC - Priority - Install Backing at Exterior Wall Priority Walls & Overhead Not Started 05/12/26 05/12/26 1.2 1.2
0%
82.5
RPL06.LOG.1100 MCUP 500 Ton Crane Demobilization 300 Ton Crane Not Started 05/12/26 05/15/26 5.0 5.0
0%
478.8
RPL06.MCUP.LP1.1920 RPL06.MCUP.Loop 1 - Install Early Mcup Paving Hardscape and Landscape Not Started 05/12/26 05/26/26 12.5 12.5
0%
433.8
RPL06.SKN.DHAB.01090 RPL06.SKIN.DHAB - Install Roof System - Install Temp Flashing at EJ Roofing Not Started 05/12/26 05/13/26 2.5 2.5
0%
26.2
RPL06.SKN.DHAB.01100 RPL06.SKIN.DHAB - Install Roof System - DenseDeck & Flame Down (6-10 to 6-22) Roofing Not Started 05/12/26 05/20/26 8.8 8.8
0%
5.0
RPL06.SKN.DHAB.01160 RPL06.SKIN.DHAB - Install Blocking of Canopy & Backing of Exterior Wall Glazing, Doors and Ext Devices Not Started 05/12/26 05/18/26 6.2 6.2
0%
10.0
RPL06.SKN.E.01000 RPL06.SKIN.East - Install IMP - Flashing,Panels & Caulking - Gridlines 6A/6F (39 P with temp closures for openings) DBC Move 3 Not Started 05/12/26 05/15/26 5.0 5.0
0%
2.5
RPL06.SKN.N.01060 RPL06.SKIN.North - Install IMP EJ - Grid lines 6-22/6-23 DBC Move 3 Not Started 05/12/26 05/18/26 6.2 6.2
0%
45.0
RPL06.SKN.N.01100 RPL06.SKIN.North - Secure All Exterior Mounted Boxes and Devices on Skin IMP System Not Started 05/12/26 06/09/26 25.0 25.0
0%
302.5
RPL06.SKN.N.01140 RPL06.SKIN.North - Install Stair Tower (DH D) DBC Move 2 Not Started 05/12/26 05/13/26 2.5 2.5
0%
393.8
RPL06.EY.ENDC.1650 RPL06.EY.DHD.T2 - Install Tent 2 Saw Cut and Cure Tent 2 Not Started 05/13/26 05/19/26 8.8 8.8
0%
11.2
RPL06.INT.SSB.06640 RPL06.Interior.SSB - Priority - Install IMP Exterior Inwall Rough-In Priority Walls and OverHead Not Started 05/13/26 05/19/26 6.2 6.2
0%
63.8
RPL06.INT.SSBC.01040 RPL06.Interior.SSB-Corridor - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 05/13/26 05/15/26 3.8 3.8
0%
-7.5
RPL06.INT.SSBC.06620 RPL06.Interior.SSBC - Priority - QC - Backings/Walls Priority Walls & Overhead Not Started 05/13/26 05/14/26 2.5 2.5
0%
105.0
RPL06.INT.SSBC.06740 RPL06.Interior.SSBC - Priority - Install Drywall at Exterior Walls for SSB Electrical Room Priority Walls & Overhead Not Started 05/13/26 05/14/26 2.5 2.5
0%
82.5
RPL06.STR.SSB.01270 RPL06.Structure.SSB - Install SOG Sealer and Cure F/R/P Not Started 05/13/26 05/14/26 2.5 2.5
0%
166.2
RPL06.MCUP.LP2.1300 RPL06.MCUP.Loop 2 - Set GS.IDF Hut (1x GS.IDF) 6X03 (ROJ03.25.26) (RVCD 05.14.26) OFE Not Started 05/14/26 05/20/26 6.2 6.2
0%
188.8
RPL06.EY.DHC.01570 RPL06.EY.DHC - Flow Fill (GL 17-23) GL 17-23 Not Started 05/15/26 05/18/26 2.5 2.5
0%
178.8
RPL06.INT.SSB.02840 RPL06.Interior.SSB - Priority - Tape Finish Paint Priority Soffit (Top Out) Priority Walls and OverHead Not Started 05/15/26 05/29/26 12.5 12.5
0%
143.8
RPL06.INT.SSBC.01030 RPL06.Interior.SSB-Corridor - Priority - Install Fire Sprinkler (Highside OH space) (IFP Accleration) Early Priority OH MEPF Not Started 05/15/26 05/15/26 1.2 1.2
0%
-7.5
RPL06.INT.SSBC.03280 RPL06.Interior.SSBC - Priority GL6.04 - (P0) Frame Walls (All full height Walls) (165 ln ft) Priority Wall Grid Line 6-04 Not Started 05/15/26 05/26/26 8.8 8.8
0%
82.5
RPL06.INT.SSBC.03500 RPL06.Interior.SSBC - Priority - Install Drywall at Exterior Walls Priority Walls & Overhead Not Started 05/15/26 05/19/26 3.8 3.8
0%
105.0
RPL06.INT.SSBC.06760 RPL06.Interior.SSBC - Priority - Frame, Hang Drywall, Tape Finish Paint for SSB Electrical Room Priority Walls & Overhead Not Started 05/15/26 05/26/26 8.8 8.8
0%
106.2
RPL06.MCUP.LP2.1400 RPL06.MCUP.Loop 2 - Tie-ins - WBS Summary Tie-ins Not Started 05/15/26 06/23/26 33.8 33.8
0%
398.8
RPL06.MCUP.LP2.1440 RPL06.MCUP.Loop 2 - Set Electrical Skids #5 OFE Not Started 05/15/26 05/18/26 2.5 2.5
0%
197.5
RPL06.MCUP.LP2.1500 RPL06.MCUP.Loop 2 - Set Electrical Skids #6 OFE Not Started 05/15/26 05/18/26 2.5 2.5
0%
202.5
RPL06.MCUP.LP2.1580 RPL06.MCUP.Loop 2 - Tie-in Mechanical - WBS Summary Tie-Ins Mechanical Not Started 05/15/26 06/11/26 23.8 23.8
0%
192.5
RPL06.MCUP.LP2.1600 RPL06.MCUP.Loop 1 - Tie-in Mechanical #5 Tie-Ins Mechanical Not Started 05/15/26 06/03/26 16.2 16.2
0%
190.0
RPL06.EY.SSB.01050 RPL06.EY.SSB - Install Cure (High Early Mix) Foundations Not Started 05/16/26 05/22/26 8.8 8.8
0%
118.8
RPL.06.D.63760.XG RMUs Set - mCUP Loop 2 Give Milestones (XREFs) Not Started 05/18/26 05/18/26 0.0 0.0
0%
477.5
RPL06.EY.DHB.01660 RPL06.EY.DHB - Flow Fill (GL 01-09) GL 01-09 Not Started 05/18/26 05/19/26 2.5 2.5
0%
45.0
RPL06.EY.ENDC.01010 RPL06.EY.End - Install UG Utilities - WBS Summary Underground Not Started 05/18/26 06/17/26 27.5 27.5
0%
242.5
RPL06.EY.ENDC.01050 RPL06.EY.End - Install SD, DW, FW UG Underground Not Started 05/18/26 06/01/26 12.5 12.5
0%
242.5
RPL06.EY.ENDC.02100 RPL06.EY.End - Install Temp Conditioning Units - CFCI Temp Conditions Not Started 05/18/26 05/22/26 6.2 6.2
0%
357.5
RPL06.EY.ENDC.1370 RPL06.EY.DHD.T1 - Install Tent Tent 1 Not Started 05/18/26 06/15/26 25.0 25.0
0%
2.5
RPL06.EY.SSB.01200 RPL06.EY.SSB - Install LD F/R/P Loading Dock Ramp Loading Dock Not Started 05/18/26 05/28/26 10.0 10.0
0%
-11.2
RPL06.INT.DHB.01040 RPL06.Interior.DHB - Priority - Install Temp Lighting Early Priority OH MEPF Not Started 05/18/26 05/20/26 3.8 3.8
0%
-7.5
RPL06.INT.SSB.06560 RPL06.Interior.SSB - Priority - Install Backing at Exterior Wall Priority Walls and OverHead Not Started 05/18/26 05/22/26 6.2 6.2
0%
63.8
RPL06.MCUP.LP1.2020 RPL06.MCUP.Loop 1 - Tie-in - MV Loop 1 L2 Checklist Completion Tie-ins Not Started 05/18/26 06/01/26 12.5 12.5
0%
95.0
RPL06.MCUP.LP1.2080 RPL06.MCUP.Loop 1 - Tie-in - Mechanical L2 Checklist Completion Tie-ins Not Started 05/18/26 06/01/26 12.5 12.5
0%
101.2
RPL06.SKN.S.01050 RPL06.SKIN.South - Install IMP - Flashing,Panels & Caulking - Gridlines 6-28/6-23 (21 P with temp closures for openings) DBC Move 3 Not Started 05/18/26 05/19/26 2.5 2.5
0%
7.5
RPL06.SKN.SSB.01120 RPL06.SKIN.SSB - Install Scupper and Downspouts Glazing, Doors and Ext Devices Not Started 05/18/26 05/22/26 6.2 6.2
0%
278.8
RPL06.VDC.1800 T2-4 (EF) - GC QC BIM Model TIER 2 - 4 - EF Not Started 05/18/26 05/18/26 0.0 0.0
0%
56.2
RPL06.VDC.1840 T2-4 (DH C & D) - GC QC BIM Model TIER 2 - 4 - DH C & D Not Started 05/18/26 05/18/26 0.0 0.0
0%
115.0
ICM.B6.1845 [SSDCB1] Delivery of FSHAC - Hot Aisle Containment (First Delivery) Construction Not Started 05/19/26 05/19/26 0.0 0.0
0%
41.2
RPL06.EY.DHC.01590 RPL06.EY.DHC - Flow Fill Cure(GL 17-23) GL 17-23 Not Started 05/19/26 05/21/26 3.8 3.8
0%
260.0
RPL06.EY.DHD.01070 RPL06.EY.DHD - Install Electrical UG (GL 17-23) GL 17-25 Not Started 05/19/26 05/26/26 6.2 6.2
0%
147.5
RPL06.EY.DHD.01130 RPL06.EY.DHD - Install Grounding UG (GL 17-23) GL 17-25 Not Started 05/19/26 05/26/26 6.2 6.2
0%
147.5
RPL06.EY.DHD.01550 RPL06.EY.DHD - Install BMS UG (GL 17-23) GL 17-25 Not Started 05/19/26 05/26/26 6.2 6.2
0%
147.5
RPL06.SKN.DHAB.01030 RPL06.SKIN.DHAB - Install Awning over Doors Glazing, Doors and Ext Devices Not Started 05/19/26 05/26/26 6.2 6.2
0%
10.0
RPL.GF.D.N6160.XG GS.IDF Hut 3 Install Complete for RPL06 Give Milestones (XREFs) Not Started 05/20/26 05/20/26 0.0 0.0
0%
475.0
RPL06.EY.DHB.01680 RPL06.EY.DHB - Flow Fill Cure (GL 01-09) GL 01-09 Not Started 05/20/26 05/22/26 3.8 3.8
0%
66.2
RPL06.EY.DHC.01650 RPL06.EY.DHC - Install SD, DW, FW UG (GL 23-28) GL 23-28 Not Started 05/20/26 05/27/26 6.2 6.2
0%
155.0
RPL06.EY.ENDC.1670 RPL06.EY.DHD.T2 - Install Tent Tent 2 Not Started 05/20/26 06/17/26 25.0 25.0
0%
7.5