Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
6
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL06.MCUP.LP1.1420 |
RPL06.MCUP.Loop 1 - Tie-in Electrical - WBS Summary | Tie-Ins Electrical | Not Started | 05/06/26 | 05/22/26 | 16.2 | 16.2 |
|
95.0 |
RPL06.MCUP.LP1.1480 |
RPL06.MCUP.Loop 1 - Tie-in Electrical #1 (Includes FWM) | Tie-Ins Electrical | Not Started | 05/06/26 | 05/22/26 | 16.2 | 16.2 |
|
95.0 |
RPL06.MCUP.LP1.1700 |
RPL06.MCUP.Loop 1 - Tie-in Electrical #2 | Tie-Ins Electrical | Not Started | 05/06/26 | 05/22/26 | 16.2 | 16.2 |
|
95.0 |
RPL06.MCUP.LP1.1860 |
RPL06.MCUP.Loop 1 - Tie-in Electrical #3 | Tie-Ins Electrical | Not Started | 05/06/26 | 05/19/26 | 12.5 | 12.5 |
|
98.8 |
RPL06.MCUP.LP1.1960 |
RPL06.MCUP.Loop 1 - Tie-in Electrical #4 | Tie-Ins Electrical | Not Started | 05/06/26 | 05/19/26 | 12.5 | 12.5 |
|
98.8 |
RPL06.STR.SSB.01250 |
RPL06.Structure.SSB - Moisture requirements for floor Sealer | F/R/P | Not Started | 05/06/26 | 05/12/26 | 8.8 | 8.8 |
|
166.2 |
RPL06.CON.WP2.07260 |
RPL06.Conn - Ext. GSIDF6X01 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 05/07/26 | 05/12/26 | 5.0 | 5.0 |
|
292.5 |
RPL06.CON.WP2.07460 |
RPL06.Conn - Ext. GSIDF6X02 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 05/07/26 | 05/14/26 | 7.5 | 7.5 |
|
290.0 |
RPL06.EY.DHA.01060 |
RPL06.EY.DHA - Install Electrical UG | Underground | Not Started | 05/07/26 | 05/20/26 | 12.5 | 12.5 |
|
47.5 |
RPL06.EY.DHA.01120 |
RPL06.EY.DHA - Install BMS UG | Underground | Not Started | 05/07/26 | 05/20/26 | 12.5 | 12.5 |
|
47.5 |
RPL06.EY.DHA.01560 |
RPL06.EY.DHA - Install Grounding UG | Underground | Not Started | 05/07/26 | 05/20/26 | 12.5 | 12.5 |
|
47.5 |
RPL06.INT.SSB.01010 |
RPL06.Interior.SSB - Priority - Install Duct (Highside OH space) (IFP Accleration) | Early Priority OH MEPF | Not Started | 05/07/26 | 05/20/26 | 12.5 | 12.5 |
|
2.5 |
RPL06.EY.DHB.01580 |
RPL06.EY.DHB - Install SD, DW, FW UG (GL 10-17) | GL 10-17 | Not Started | 05/08/26 | 05/21/26 | 12.5 | 12.5 |
|
45.0 |
RPL06.EY.DHC.01050 |
RPL06.EY.DHC - Install Electrical UG (GL 17-23) | GL 17-23 | Not Started | 05/08/26 | 05/14/26 | 6.2 | 6.2 |
|
178.8 |
RPL06.EY.DHC.01120 |
RPL06.EY.DHC - Install BMS UG (GL 17-23) | GL 17-23 | Not Started | 05/08/26 | 05/14/26 | 6.2 | 6.2 |
|
178.8 |
RPL06.EY.DHC.01530 |
RPL06.EY.DHC - Install Grounding UG (GL 17-23) | GL 17-23 | Not Started | 05/08/26 | 05/14/26 | 6.2 | 6.2 |
|
178.8 |
RPL06.EY.ENDC.1350 |
RPL06.EY.DHD.T1 - Install Tent 1 Saw Cut and Cure | Tent 1 | Not Started | 05/08/26 | 05/14/26 | 8.8 | 8.8 |
|
6.2 |
RPL06.INT.SSB.01030 |
RPL06.Interior.SSB - Priority - Install Fire Sprinkler (Highside OH space) (IFP Accleration) | Early Priority OH MEPF | Not Started | 05/08/26 | 05/14/26 | 6.2 | 6.2 |
|
-7.5 |
RPL06.INT.SSBC.01000 |
RPL06.Interior.SSBC - Priority - WBS Summary | Priority Walls & Overhead | Not Started | 05/08/26 | 07/02/26 | 48.8 | 48.8 |
|
72.5 |
RPL06.INT.SSBC.03240 |
RPL06.Interior.SSBC - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW Draft Blanket (3200 sq ft) | Priority Walls & Overhead | Not Started | 05/08/26 | 05/14/26 | 6.2 | 6.2 |
|
13.8 |
RPL06.INT.SSBC.03520 |
RPL06.Interior.SSBC - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls & Overhead | Not Started | 05/08/26 | 05/12/26 | 3.8 | 3.8 |
|
82.5 |
RPL06.MCUP.LP1.1540 |
RPL06.MCUP.Loop 1 - Tie-in BMS - WBS Summary | Tie-Ins BMS | Not Started | 05/08/26 | 05/22/26 | 13.8 | 13.8 |
|
101.2 |
RPL06.MCUP.LP1.1580 |
RPL06.MCUP.Loop 1 - Tie-in EPMS - WBS Summary | Tie-Ins EPMS | Not Started | 05/08/26 | 05/22/26 | 13.8 | 13.8 |
|
95.0 |
RPL06.MCUP.LP1.1780 |
RPL06.MCUP.Loop 1 - Tie-in EPMS #3 | Tie-Ins EPMS | Not Started | 05/08/26 | 05/19/26 | 10.0 | 10.0 |
|
98.8 |
RPL06.MCUP.LP1.1800 |
RPL06.MCUP.Loop 1 - Tie-in BMS #3 | Tie-Ins BMS | Not Started | 05/08/26 | 05/19/26 | 10.0 | 10.0 |
|
105.0 |
RPL06.MCUP.LP1.1900 |
RPL06.MCUP.Loop 1 - Tie-in EPMS #4 | Tie-Ins EPMS | Not Started | 05/08/26 | 05/19/26 | 10.0 | 10.0 |
|
98.8 |
RPL06.SKN.DHAB.01000 |
RPL06.SKIN.DHAB - Install Temp Doors | Glazing, Doors and Ext Devices | Not Started | 05/08/26 | 05/11/26 | 2.5 | 2.5 |
|
10.0 |
RPL06.SKN.DHAB.01010 |
RPL06.SKIN.DHAB - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | DH A & DH B | Not Started | 05/08/26 | 06/12/26 | 31.2 | 31.2 |
|
267.5 |
RPL06.SKN.DHAB.01020 |
RPL06.SKIN.DHAB - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Not Started | 05/08/26 | 06/12/26 | 31.2 | 31.2 |
|
267.5 |
RPL06.SKN.DHAB.01070 |
RPL06.SKIN.DHAB - Install Roof System - Exterior Wall Sheething and EJ | Roofing | Not Started | 05/08/26 | 05/11/26 | 2.5 | 2.5 |
|
5.0 |
RPL06.SKN.DHAB.01080 |
RPL06.SKIN.DHAB - Install Roof System - WBS Summary | Roofing | Not Started | 05/08/26 | 06/11/26 | 30.0 | 30.0 |
|
111.2 |
RPL06.SKN.N.01050 |
RPL06.SKIN.North - Install IMP - Flashing,Panels & Caulking - Gridlines 6-23/6-28 (21 P with temp closures for openings) | DBC Move 3 | Not Started | 05/08/26 | 05/11/26 | 2.5 | 2.5 |
|
2.5 |
RPL06.SKN.N.01120 |
RPL06.SKIN.North - Install Stair Tower (DH B) | DBC Move 2 | Not Started | 05/08/26 | 05/11/26 | 2.5 | 2.5 |
|
121.2 |
RPL06.STR.DHCD.01090 |
RPL06.Structure.DHCD - Asphalt Emulsion and Wrap Steel Columns | Prep | Not Started | 05/08/26 | 05/12/26 | 3.8 | 3.8 |
|
27.5 |
PRE.MIR.1280 |
Kitchen Equipment SA - Meta Review / Authorization | Meta Internal Review of Trade Partner Bids | Not Started | 05/11/26 | 05/22/26 | 12.5 | 12.5 |
|
331.2 |
PRE.TPA.1300 |
Architectural/Security Fencing - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Not Started | 05/11/26 | 05/27/26 | 15.0 | 15.0 |
|
451.2 |
PRE.TPA.1320 |
Non-Critical Trade Buyout - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Not Started | 05/11/26 | 07/07/26 | 50.0 | 50.0 |
|
120.0 |
RPL.06.D.64160.XG |
Ready for MV Cable Pull mCUP - Loop#2 (Qty 2)* | Give Milestones (XREFs) | Not Started | 05/11/26 | 05/11/26 | 0.0 | 0.0 |
|
483.8 |
RPL06.CFCI.6820 |
RPL06 - Submittals Review & Approval - Stick Built IDF ( A1, B1, C1, D1) | (CFCI) Div. XX - Technology IDF (Stick Built) | Not Started | 05/11/26 | 05/22/26 | 12.5 | 12.5 |
|
71.2 |
RPL06.MCUP.LP1.1560 |
RPL06.MCUP.Loop 1 - Tie-in BMS #1 (Includes FWM, GS.IDF6X01) | Tie-Ins BMS | Not Started | 05/11/26 | 05/22/26 | 12.5 | 12.5 |
|
101.2 |
RPL06.MCUP.LP1.1600 |
RPL06.MCUP.Loop 1 - Tie-in EPMS #1 (Includes FWM) | Tie-Ins EPMS | Not Started | 05/11/26 | 05/22/26 | 12.5 | 12.5 |
|
95.0 |
RPL06.MCUP.LP1.1720 |
RPL06.MCUP.Loop 1 - Tie-in EPMS #2 | Tie-Ins EPMS | Not Started | 05/11/26 | 05/22/26 | 12.5 | 12.5 |
|
95.0 |
RPL06.MCUP.LP1.1740 |
RPL06.MCUP.Loop 1 - Tie-in BMS #2 | Tie-Ins BMS | Not Started | 05/11/26 | 05/22/26 | 12.5 | 12.5 |
|
101.2 |
RPL06.MCUP.LP1.1940 |
RPL06.MCUP.Loop 1 - Tie-in BMS #4 (Includes GS.IDF6X02) | Tie-Ins BMS | Not Started | 05/11/26 | 05/20/26 | 10.0 | 10.0 |
|
103.8 |
RPL06.EY.DHD.01110 |
RPL06.EY.DHD - Install SD, DW, FW UG (GL 17-23) | GL 17-25 | Not Started | 05/12/26 | 05/18/26 | 6.2 | 6.2 |
|
147.5 |
RPL06.EY.SSB.01190 |
RPL06.EY.SSB - Set LD Grade and Prep | Loading Dock | Not Started | 05/12/26 | 05/15/26 | 5.0 | 5.0 |
|
-11.2 |
RPL06.INT.SSBC.06600 |
RPL06.Interior.SSBC - Priority - Install Backing at Exterior Wall | Priority Walls & Overhead | Not Started | 05/12/26 | 05/12/26 | 1.2 | 1.2 |
|
82.5 |
RPL06.LOG.1100 |
MCUP 500 Ton Crane Demobilization | 300 Ton Crane | Not Started | 05/12/26 | 05/15/26 | 5.0 | 5.0 |
|
478.8 |
RPL06.MCUP.LP1.1920 |
RPL06.MCUP.Loop 1 - Install Early Mcup Paving | Hardscape and Landscape | Not Started | 05/12/26 | 05/26/26 | 12.5 | 12.5 |
|
433.8 |
RPL06.SKN.DHAB.01090 |
RPL06.SKIN.DHAB - Install Roof System - Install Temp Flashing at EJ | Roofing | Not Started | 05/12/26 | 05/13/26 | 2.5 | 2.5 |
|
26.2 |
RPL06.SKN.DHAB.01100 |
RPL06.SKIN.DHAB - Install Roof System - DenseDeck & Flame Down (6-10 to 6-22) | Roofing | Not Started | 05/12/26 | 05/20/26 | 8.8 | 8.8 |
|
5.0 |
RPL06.SKN.DHAB.01160 |
RPL06.SKIN.DHAB - Install Blocking of Canopy & Backing of Exterior Wall | Glazing, Doors and Ext Devices | Not Started | 05/12/26 | 05/18/26 | 6.2 | 6.2 |
|
10.0 |
RPL06.SKN.E.01000 |
RPL06.SKIN.East - Install IMP - Flashing,Panels & Caulking - Gridlines 6A/6F (39 P with temp closures for openings) | DBC Move 3 | Not Started | 05/12/26 | 05/15/26 | 5.0 | 5.0 |
|
2.5 |
RPL06.SKN.N.01060 |
RPL06.SKIN.North - Install IMP EJ - Grid lines 6-22/6-23 | DBC Move 3 | Not Started | 05/12/26 | 05/18/26 | 6.2 | 6.2 |
|
45.0 |
RPL06.SKN.N.01100 |
RPL06.SKIN.North - Secure All Exterior Mounted Boxes and Devices on Skin | IMP System | Not Started | 05/12/26 | 06/09/26 | 25.0 | 25.0 |
|
302.5 |
RPL06.SKN.N.01140 |
RPL06.SKIN.North - Install Stair Tower (DH D) | DBC Move 2 | Not Started | 05/12/26 | 05/13/26 | 2.5 | 2.5 |
|
393.8 |
RPL06.EY.ENDC.1650 |
RPL06.EY.DHD.T2 - Install Tent 2 Saw Cut and Cure | Tent 2 | Not Started | 05/13/26 | 05/19/26 | 8.8 | 8.8 |
|
11.2 |
RPL06.INT.SSB.06640 |
RPL06.Interior.SSB - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls and OverHead | Not Started | 05/13/26 | 05/19/26 | 6.2 | 6.2 |
|
63.8 |
RPL06.INT.SSBC.01040 |
RPL06.Interior.SSB-Corridor - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 05/13/26 | 05/15/26 | 3.8 | 3.8 |
|
-7.5 |
RPL06.INT.SSBC.06620 |
RPL06.Interior.SSBC - Priority - QC - Backings/Walls | Priority Walls & Overhead | Not Started | 05/13/26 | 05/14/26 | 2.5 | 2.5 |
|
105.0 |
RPL06.INT.SSBC.06740 |
RPL06.Interior.SSBC - Priority - Install Drywall at Exterior Walls for SSB Electrical Room | Priority Walls & Overhead | Not Started | 05/13/26 | 05/14/26 | 2.5 | 2.5 |
|
82.5 |
RPL06.STR.SSB.01270 |
RPL06.Structure.SSB - Install SOG Sealer and Cure | F/R/P | Not Started | 05/13/26 | 05/14/26 | 2.5 | 2.5 |
|
166.2 |
RPL06.MCUP.LP2.1300 |
RPL06.MCUP.Loop 2 - Set GS.IDF Hut (1x GS.IDF) 6X03 (ROJ03.25.26) (RVCD 05.14.26) | OFE | Not Started | 05/14/26 | 05/20/26 | 6.2 | 6.2 |
|
188.8 |
RPL06.EY.DHC.01570 |
RPL06.EY.DHC - Flow Fill (GL 17-23) | GL 17-23 | Not Started | 05/15/26 | 05/18/26 | 2.5 | 2.5 |
|
178.8 |
RPL06.INT.SSB.02840 |
RPL06.Interior.SSB - Priority - Tape Finish Paint Priority Soffit (Top Out) | Priority Walls and OverHead | Not Started | 05/15/26 | 05/29/26 | 12.5 | 12.5 |
|
143.8 |
RPL06.INT.SSBC.01030 |
RPL06.Interior.SSB-Corridor - Priority - Install Fire Sprinkler (Highside OH space) (IFP Accleration) | Early Priority OH MEPF | Not Started | 05/15/26 | 05/15/26 | 1.2 | 1.2 |
|
-7.5 |
RPL06.INT.SSBC.03280 |
RPL06.Interior.SSBC - Priority GL6.04 - (P0) Frame Walls (All full height Walls) (165 ln ft) | Priority Wall Grid Line 6-04 | Not Started | 05/15/26 | 05/26/26 | 8.8 | 8.8 |
|
82.5 |
RPL06.INT.SSBC.03500 |
RPL06.Interior.SSBC - Priority - Install Drywall at Exterior Walls | Priority Walls & Overhead | Not Started | 05/15/26 | 05/19/26 | 3.8 | 3.8 |
|
105.0 |
RPL06.INT.SSBC.06760 |
RPL06.Interior.SSBC - Priority - Frame, Hang Drywall, Tape Finish Paint for SSB Electrical Room | Priority Walls & Overhead | Not Started | 05/15/26 | 05/26/26 | 8.8 | 8.8 |
|
106.2 |
RPL06.MCUP.LP2.1400 |
RPL06.MCUP.Loop 2 - Tie-ins - WBS Summary | Tie-ins | Not Started | 05/15/26 | 06/23/26 | 33.8 | 33.8 |
|
398.8 |
RPL06.MCUP.LP2.1440 |
RPL06.MCUP.Loop 2 - Set Electrical Skids #5 | OFE | Not Started | 05/15/26 | 05/18/26 | 2.5 | 2.5 |
|
197.5 |
RPL06.MCUP.LP2.1500 |
RPL06.MCUP.Loop 2 - Set Electrical Skids #6 | OFE | Not Started | 05/15/26 | 05/18/26 | 2.5 | 2.5 |
|
202.5 |
RPL06.MCUP.LP2.1580 |
RPL06.MCUP.Loop 2 - Tie-in Mechanical - WBS Summary | Tie-Ins Mechanical | Not Started | 05/15/26 | 06/11/26 | 23.8 | 23.8 |
|
192.5 |
RPL06.MCUP.LP2.1600 |
RPL06.MCUP.Loop 1 - Tie-in Mechanical #5 | Tie-Ins Mechanical | Not Started | 05/15/26 | 06/03/26 | 16.2 | 16.2 |
|
190.0 |
RPL06.EY.SSB.01050 |
RPL06.EY.SSB - Install Cure (High Early Mix) | Foundations | Not Started | 05/16/26 | 05/22/26 | 8.8 | 8.8 |
|
118.8 |
RPL.06.D.63760.XG |
RMUs Set - mCUP Loop 2 | Give Milestones (XREFs) | Not Started | 05/18/26 | 05/18/26 | 0.0 | 0.0 |
|
477.5 |
RPL06.EY.DHB.01660 |
RPL06.EY.DHB - Flow Fill (GL 01-09) | GL 01-09 | Not Started | 05/18/26 | 05/19/26 | 2.5 | 2.5 |
|
45.0 |
RPL06.EY.ENDC.01010 |
RPL06.EY.End - Install UG Utilities - WBS Summary | Underground | Not Started | 05/18/26 | 06/17/26 | 27.5 | 27.5 |
|
242.5 |
RPL06.EY.ENDC.01050 |
RPL06.EY.End - Install SD, DW, FW UG | Underground | Not Started | 05/18/26 | 06/01/26 | 12.5 | 12.5 |
|
242.5 |
RPL06.EY.ENDC.02100 |
RPL06.EY.End - Install Temp Conditioning Units - CFCI | Temp Conditions | Not Started | 05/18/26 | 05/22/26 | 6.2 | 6.2 |
|
357.5 |
RPL06.EY.ENDC.1370 |
RPL06.EY.DHD.T1 - Install Tent | Tent 1 | Not Started | 05/18/26 | 06/15/26 | 25.0 | 25.0 |
|
2.5 |
RPL06.EY.SSB.01200 |
RPL06.EY.SSB - Install LD F/R/P Loading Dock Ramp | Loading Dock | Not Started | 05/18/26 | 05/28/26 | 10.0 | 10.0 |
|
-11.2 |
RPL06.INT.DHB.01040 |
RPL06.Interior.DHB - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 05/18/26 | 05/20/26 | 3.8 | 3.8 |
|
-7.5 |
RPL06.INT.SSB.06560 |
RPL06.Interior.SSB - Priority - Install Backing at Exterior Wall | Priority Walls and OverHead | Not Started | 05/18/26 | 05/22/26 | 6.2 | 6.2 |
|
63.8 |
RPL06.MCUP.LP1.2020 |
RPL06.MCUP.Loop 1 - Tie-in - MV Loop 1 L2 Checklist Completion | Tie-ins | Not Started | 05/18/26 | 06/01/26 | 12.5 | 12.5 |
|
95.0 |
RPL06.MCUP.LP1.2080 |
RPL06.MCUP.Loop 1 - Tie-in - Mechanical L2 Checklist Completion | Tie-ins | Not Started | 05/18/26 | 06/01/26 | 12.5 | 12.5 |
|
101.2 |
RPL06.SKN.S.01050 |
RPL06.SKIN.South - Install IMP - Flashing,Panels & Caulking - Gridlines 6-28/6-23 (21 P with temp closures for openings) | DBC Move 3 | Not Started | 05/18/26 | 05/19/26 | 2.5 | 2.5 |
|
7.5 |
RPL06.SKN.SSB.01120 |
RPL06.SKIN.SSB - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 05/18/26 | 05/22/26 | 6.2 | 6.2 |
|
278.8 |
RPL06.VDC.1800 |
T2-4 (EF) - GC QC BIM Model | TIER 2 - 4 - EF | Not Started | 05/18/26 | 05/18/26 | 0.0 | 0.0 |
|
56.2 |
RPL06.VDC.1840 |
T2-4 (DH C & D) - GC QC BIM Model | TIER 2 - 4 - DH C & D | Not Started | 05/18/26 | 05/18/26 | 0.0 | 0.0 |
|
115.0 |
ICM.B6.1845 |
[SSDCB1] Delivery of FSHAC - Hot Aisle Containment (First Delivery) | Construction | Not Started | 05/19/26 | 05/19/26 | 0.0 | 0.0 |
|
41.2 |
RPL06.EY.DHC.01590 |
RPL06.EY.DHC - Flow Fill Cure(GL 17-23) | GL 17-23 | Not Started | 05/19/26 | 05/21/26 | 3.8 | 3.8 |
|
260.0 |
RPL06.EY.DHD.01070 |
RPL06.EY.DHD - Install Electrical UG (GL 17-23) | GL 17-25 | Not Started | 05/19/26 | 05/26/26 | 6.2 | 6.2 |
|
147.5 |
RPL06.EY.DHD.01130 |
RPL06.EY.DHD - Install Grounding UG (GL 17-23) | GL 17-25 | Not Started | 05/19/26 | 05/26/26 | 6.2 | 6.2 |
|
147.5 |
RPL06.EY.DHD.01550 |
RPL06.EY.DHD - Install BMS UG (GL 17-23) | GL 17-25 | Not Started | 05/19/26 | 05/26/26 | 6.2 | 6.2 |
|
147.5 |
RPL06.SKN.DHAB.01030 |
RPL06.SKIN.DHAB - Install Awning over Doors | Glazing, Doors and Ext Devices | Not Started | 05/19/26 | 05/26/26 | 6.2 | 6.2 |
|
10.0 |
RPL.GF.D.N6160.XG |
GS.IDF Hut 3 Install Complete for RPL06 | Give Milestones (XREFs) | Not Started | 05/20/26 | 05/20/26 | 0.0 | 0.0 |
|
475.0 |
RPL06.EY.DHB.01680 |
RPL06.EY.DHB - Flow Fill Cure (GL 01-09) | GL 01-09 | Not Started | 05/20/26 | 05/22/26 | 3.8 | 3.8 |
|
66.2 |
RPL06.EY.DHC.01650 |
RPL06.EY.DHC - Install SD, DW, FW UG (GL 23-28) | GL 23-28 | Not Started | 05/20/26 | 05/27/26 | 6.2 | 6.2 |
|
155.0 |
RPL06.EY.ENDC.1670 |
RPL06.EY.DHD.T2 - Install Tent | Tent 2 | Not Started | 05/20/26 | 06/17/26 | 25.0 | 25.0 |
|
7.5 |