Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
5
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL06.INT.SSB.01006 |
RPL06.Interior - Priority - Install Hangers Support (Center Corr to End Corr) (All Trades) | Early Priority OH MEPF | Not Started | 05/20/26 | 06/03/26 | 12.5 | 12.5 |
|
146.2 |
RPL06.INT.SSB.02680 |
RPL06.Interior.SSB - Priority - Install Layout, Unistruts & Hangers (All Trades) - Day | Priority Walls and OverHead | Not Started | 05/20/26 | 05/27/26 | 6.2 | 6.2 |
|
80.0 |
RPL06.INT.SSB.06780 |
RPL06.Interior.SSB - Priority - Install Layout, Unistruts & Hangers (All Trades) - Swing | Priority Walls and OverHead | Not Started | 05/20/26 | 05/27/26 | 6.2 | 6.2 |
|
80.0 |
RPL06.INT.SSBC.03260 |
RPL06.Interior.SSBC - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) (6400 sq ft) | Priority Walls & Overhead | Not Started | 05/20/26 | 05/27/26 | 6.2 | 6.2 |
|
105.0 |
RPL06.SKN.DHCD.01010 |
RPL06.SKIN.DHCD - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary | DH C & DH D | Not Started | 05/20/26 | 02/26/27 | 241.2 | 241.2 |
|
162.5 |
RPL06.SKN.DHCD.01070 |
RPL06.SKIN.DHCD - Install Roof System - Exterior Wall Sheething | Roofing | Not Started | 05/20/26 | 05/26/26 | 5.0 | 5.0 |
|
7.5 |
RPL06.SKN.DHCD.01080 |
RPL06.SKIN.DHCD - Install Roof System - WBS Summary | Roofing | Not Started | 05/20/26 | 06/25/26 | 32.5 | 32.5 |
|
371.2 |
RPL06.SKN.S.01070 |
RPL06.SKIN.South - Install IMP EJ - Grid lines 6-22/6-23 | DBC Move 3 | Not Started | 05/20/26 | 05/27/26 | 6.2 | 6.2 |
|
37.5 |
RPL06.SKN.S.01100 |
RPL06.SKIN.South - Secure All Exterior Mounted Boxes and Devices on Skin | IMP System | Not Started | 05/20/26 | 06/17/26 | 25.0 | 25.0 |
|
295.0 |
RPL06.SKN.S.01120 |
RPL06.SKIN.South - Install Stair Tower (DH C) | DBC Move 3 | Not Started | 05/20/26 | 05/21/26 | 2.5 | 2.5 |
|
386.2 |
RPL.06.D.63350.XR |
Pull and Term mCUP Skids - RPL06 | Receive Milestones (XREFs) | Not Started | 05/21/26 | 05/21/26 | 0.0 | 0.0 |
|
110.0 |
RPL.06.D.63850.XR |
100MW Cx Temp Power to MV Skids RPL06 mCUPs Available | Receive Milestones (XREFs) | Not Started | 05/21/26 | 05/21/26 | 0.0 | 0.0 |
|
110.0 |
RPL06.CON.WP2.07600 |
RPL06.Conn - Ext. GSIDF6X03 (mCUP yard) - WBS Summary | Ext. IDF Hut - GSIDF6X03 | Not Started | 05/21/26 | 06/23/26 | 28.8 | 28.8 |
|
446.2 |
RPL06.CON.WP2.08400 |
RPL06.Conn - Ext. GSIDF6X03 - Install Infrastructure (Racks, Waterfalls etc.) | Infrastructure | Not Started | 05/21/26 | 05/21/26 | 1.2 | 1.2 |
|
278.8 |
RPL06.EY.DHA.02140 |
RPL06.EY.DHA - Flow Fill | Underground | Not Started | 05/21/26 | 05/22/26 | 2.5 | 2.5 |
|
47.5 |
RPL06.INT.DHA.01040 |
RPL06.Interior.DHA - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 05/21/26 | 05/26/26 | 3.8 | 3.8 |
|
-7.5 |
RPL06.INT.DHB.01010 |
RPL06.Interior.DHB - Priority - Install Duct (IFP Accleration) | Early Priority OH MEPF | Not Started | 05/21/26 | 05/28/26 | 6.2 | 6.2 |
|
-3.8 |
RPL06.INT.DHB.01030 |
RPL06.Interior.DHB - Priority - Install Fire Sprinkler (IFP Accleration) | Early Priority OH MEPF | Not Started | 05/21/26 | 05/28/26 | 6.2 | 6.2 |
|
135.0 |
RPL06.INT.DHB.02160 |
RPL06.Interior.DHBADC - Priority - Install Fixed Draft/Smoke Curtain (#5) | Early Priority OH MEPF | Not Started | 05/21/26 | 06/03/26 | 11.2 | 11.2 |
|
18.8 |
RPL06.INT.SSBC.01011 |
RPL06.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) (IFP Accleration) | Early Priority OH MEPF | Not Started | 05/21/26 | 05/28/26 | 6.2 | 6.2 |
|
7.5 |
RPL06.MCUP.LP2.1560 |
RPL06.MCUP.Loop 2 - Tie-in Electrical - WBS Summary | Tie-Ins Electrical | Not Started | 05/21/26 | 06/04/26 | 12.5 | 12.5 |
|
193.8 |
RPL06.MCUP.LP2.1620 |
RPL06.MCUP.Loop 2 - Tie-in Electrical #5 | Tie-Ins Electrical | Not Started | 05/21/26 | 06/04/26 | 12.5 | 12.5 |
|
188.8 |
RPL06.MCUP.LP2.2000 |
RPL06.MCUP.Loop 2 - Tie-in Electrical #6 | Tie-Ins Electrical | Not Started | 05/21/26 | 06/04/26 | 12.5 | 12.5 |
|
193.8 |
RPL06.STR.DHAB.01180 |
RPL06.Structure.DHAB - SOG F/R/P #4 - Grid lines 6-11/6-14 (Pours-5&6) | F/R/P | Not Started | 05/21/26 | 05/26/26 | 3.8 | 3.8 |
|
5.0 |
RPL06.CFCI.5690 |
RPL06 - Fabricate / Deliver - Glass / Frames | Glass & Glazing (Alum. Entrances & Curtainwall) | Not Started | 05/22/26 | 08/03/26 | 62.5 | 62.5 |
|
140.0 |
RPL06.CON.WP2.08520 |
RPL06.Conn - Ext. GSIDF6X03 - Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 05/22/26 | 05/28/26 | 5.0 | 5.0 |
|
278.8 |
RPL06.EY.DHB.01600 |
RPL06.EY.DHB - Install Electrical UG (GL 10-17) | GL 10-17 | Not Started | 05/22/26 | 06/05/26 | 12.5 | 12.5 |
|
45.0 |
RPL06.EY.DHB.01620 |
RPL06.EY.DHB - Install Grounding UG (GL 10-17) | GL 10-17 | Not Started | 05/22/26 | 06/05/26 | 12.5 | 12.5 |
|
45.0 |
RPL06.EY.DHB.01640 |
RPL06.EY.DHB - Install BMS/EPMS UG (GL 10-17) | GL 10-17 | Not Started | 05/22/26 | 06/05/26 | 12.5 | 12.5 |
|
45.0 |
RPL06.INT.SSBC.06680 |
RPL06.Interior.SSBC - Priority GL6.04 - (P0) Install MEP In-Wall/Backing | Priority Wall Grid Line 6-04 | Not Started | 05/22/26 | 05/28/26 | 5.0 | 5.0 |
|
82.5 |
RPL06.SKN.DHAB.01120 |
RPL06.SKIN.DHAB - Install Roof System - Final Roof | Roofing | Not Started | 05/22/26 | 06/09/26 | 15.0 | 15.0 |
|
111.2 |
RPL06.SKN.SSB.01140 |
RPL06.SKIN.SSB - Install Roof System - Install EJ | Roofing | Not Started | 05/22/26 | 05/29/26 | 6.2 | 6.2 |
|
22.5 |
RPL06.EY.DHA.02160 |
RPL06.EY.DHA - Flow Fill Cure | Underground | Not Started | 05/23/26 | 05/25/26 | 3.8 | 3.8 |
|
71.2 |
GCD.RPL06.1456 |
Start RPL06 EY RMU Equipment Pad Placement - RPL06 | Construction Milestones | Not Started | 05/26/26 | 05/26/26 | 0.0 | 0.0 |
|
303.8 |
PRE.TPA.1280 |
Kitchen Equipment - Award and Issue Subcontract | DPR issue Trade Parter Agreements | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
331.2 |
RPL06.CFCI.4450 |
RPL06 - Submittals Prep & Submit for Review - Finished Carpentry (Millwork/Countertops) | Finished Carpentry (Millwork/Tops) | Not Started | 05/26/26 | 07/07/26 | 37.5 | 37.5 |
|
237.5 |
RPL06.CFCI.4610 |
RPL06 - Submittals Prep & Submit for Review - Interior Painting (Spec 09 91 23) XX | (CFCI) Div. 09 - Painting | Not Started | 05/26/26 | 07/07/26 | 37.5 | 37.5 |
|
138.8 |
RPL06.CFCI.6840 |
RPL06 - Fabricate / Deliver - Stick Built IDF (A1) | (CFCI) Div. XX - Technology IDF (Stick Built) | Not Started | 05/26/26 | 09/01/26 | 87.5 | 87.5 |
|
83.8 |
RPL06.CFCI.6860 |
RPL06 - Fabricate / Deliver - Stick Built IDF (B1) | (CFCI) Div. XX - Technology IDF (Stick Built) | Not Started | 05/26/26 | 08/18/26 | 75.0 | 75.0 |
|
76.2 |
RPL06.CFCI.6880 |
RPL06 - Fabricate / Deliver - Stick Built IDF (C1) | (CFCI) Div. XX - Technology IDF (Stick Built) | Not Started | 05/26/26 | 12/10/26 | 172.5 | 172.5 |
|
75.0 |
RPL06.CFCI.6900 |
RPL06 - Fabricate / Deliver - Stick Built IDF (D1) | (CFCI) Div. XX - Technology IDF (Stick Built) | Not Started | 05/26/26 | 11/24/26 | 160.0 | 160.0 |
|
71.2 |
RPL06.EY.DHA.01010 |
RPL06.EY.DHA - Install F/R/P Equipment Pads - 1-12 (Grid 6-01/6-16) (12'' Larger For Tolerance) | Foundations | Not Started | 05/26/26 | 06/22/26 | 25.0 | 25.0 |
|
50.0 |
RPL06.EY.DHA.01020 |
RPL06.EY.DHA - Install Foundations - WBS Summary | Foundations | Not Started | 05/26/26 | 06/29/26 | 31.2 | 31.2 |
|
50.0 |
RPL06.EY.DHB.01010 |
RPL06.EY.DHB - Install F/R/P Equipment Pads - 1-6(Grid 6-01/6-09) (12'' Larger For Tolerance) | Foundations | Not Started | 05/26/26 | 06/08/26 | 12.5 | 12.5 |
|
43.8 |
RPL06.EY.DHB.01020 |
RPL06.EY.DHB - Install Foundations - WBS Summary | Foundations | Not Started | 05/26/26 | 07/03/26 | 35.0 | 35.0 |
|
43.8 |
RPL06.EY.SSB.01100 |
RPL06.EY.SSB - OFE - WBS Summary | OFE | Not Started | 05/26/26 | 06/03/26 | 8.8 | 8.8 |
|
83.8 |
RPL06.EY.SSB.01120 |
RPL06.EY.SSB - Install AHU (QTY 3) | OFE | Not Started | 05/26/26 | 06/03/26 | 8.8 | 8.8 |
|
83.8 |
RPL06.EY.SSB.01380 |
RPL06.EY.SSB - Install Floor Mounted AC units (4) - CFCI | OFE | Not Started | 05/26/26 | 06/03/26 | 8.8 | 8.8 |
|
81.2 |
RPL06.INT.SSB.06580 |
RPL06.Interior.SSB - Priority - QC - Backings/Walls | Priority Walls and OverHead | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
63.8 |
RPL06.LOG.1300 |
Dry Cooler 230 Ton Crane Demobilization | 100 Ton Crane | Not Started | 05/26/26 | 05/28/26 | 3.8 | 3.8 |
|
402.5 |
RPL06.MCUP.LP1.2060 |
RPL06.MCUP.Loop 1 - Tie-in - Electrical L2 Checklist Completion | Tie-ins | Not Started | 05/26/26 | 06/08/26 | 12.5 | 12.5 |
|
95.0 |
RPL06.MCUP.LP2.1240 |
RPL06.MCUP.Loop 2 - Set MTRs (4 per day) | OFE | Not Started | 05/26/26 | 05/27/26 | 2.5 | 2.5 |
|
190.0 |
RPL06.MCUP.LP2.1660 |
RPL06.MCUP.Loop 2 - Tie-in BMS - WBS Summary | Tie-Ins BMS | Not Started | 05/26/26 | 06/16/26 | 20.0 | 20.0 |
|
188.8 |
RPL06.MCUP.LP2.1680 |
RPL06.MCUP.Loop 2 - Tie-in EPMS - WBS Summary | Tie-Ins EPMS | Not Started | 05/26/26 | 06/04/26 | 10.0 | 10.0 |
|
193.8 |
RPL06.MCUP.LP2.1700 |
RPL06.MCUP.Loop 2 - Tie-in EPMS #5 (Includes GS.IDF6X03) | Tie-Ins EPMS | Not Started | 05/26/26 | 06/04/26 | 10.0 | 10.0 |
|
193.8 |
RPL06.MCUP.LP2.1720 |
RPL06.MCUP.Loop 2 - Tie-in BMS #5 (Includes GS.IDF6X03) | Tie-Ins BMS | Not Started | 05/26/26 | 06/04/26 | 10.0 | 10.0 |
|
188.8 |
RPL06.MCUP.LP2.1940 |
RPL06.MCUP.Loop 2 - Tie-in EPMS #6 | Tie-Ins EPMS | Not Started | 05/26/26 | 06/04/26 | 10.0 | 10.0 |
|
193.8 |
RPL06.MCUP.LP2.2020 |
RPL06.MCUP.Loop 1 - Tie-in Mechanical #6 | Tie-Ins Mechanical | Not Started | 05/26/26 | 06/11/26 | 16.2 | 16.2 |
|
192.5 |
ICM.B6.1750 |
[SSDCB1] Room Ready for GS.MDF Module Placement | Construction | Not Started | 05/27/26 | 05/27/26 | 0.0 | 0.0 |
|
301.2 |
PRE.FA.1280 |
Architectural/Security Fencing - Final Agreement | Trade Partner Final Agreement | Not Started | 05/27/26 | 05/27/26 | 0.0 | 0.0 |
|
451.2 |
RPL06.EY.DHD.01570 |
RPL06.EY.DHD - Flow Fill (GL 17-23) | GL 17-25 | Not Started | 05/27/26 | 05/28/26 | 2.5 | 2.5 |
|
147.5 |
RPL06.INT.DHA.01010 |
RPL06.Interior.DHA - Priority - Install Duct (IFP Accleration) | Early Priority OH MEPF | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
-7.5 |
RPL06.INT.SSBC.06660 |
RPL06.Interior.SSBC - Priority GL6.04 - (P0) Install IMP Wall | Priority Wall Grid Line 6-04 | Not Started | 05/27/26 | 06/01/26 | 5.0 | 5.0 |
|
101.2 |
RPL06.INT.SSBC.06700 |
RPL06.Interior.SSBC - Priority GL6.04 - (P0) Hang Drywall (Both Sides) | Priority Wall Grid Line 6-04 | Not Started | 05/27/26 | 06/01/26 | 5.0 | 5.0 |
|
82.5 |
RPL06.MCUP.LP1.2000 |
RPL06.MCUP.Loop 1 - Install Lighting | Hardscape and Landscape | Not Started | 05/27/26 | 06/09/26 | 12.5 | 12.5 |
|
433.8 |
RPL06.SKN.DHAB.01040 |
RPL06.SKIN.DHAB - Install Louvers | Glazing, Doors and Ext Devices | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
10.0 |
RPL06.SKN.DHAB.01110 |
RPL06.SKIN.DHAB - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
277.5 |
RPL06.SKN.DHCD.01090 |
RPL06.SKIN.DHCD - Install Roof System - DenseDeck & Flame Down (6-23 to 6-28) | Roofing | Not Started | 05/27/26 | 06/04/26 | 8.8 | 8.8 |
|
7.5 |
RPL06.STR.DHAB.01100 |
RPL06.Structure.DHAB - SOG F/R/P #5 - Grid lines 6-14/6-18 (Pours-7&8) | F/R/P | Not Started | 05/27/26 | 05/29/26 | 3.8 | 3.8 |
|
5.0 |
RPL06.CON.WP2.09180 |
RPL06.Conn - CorpNet & FacNet Available (mCUP) | WP#02 GS | Not Started | 05/28/26 | 05/28/26 | 0.0 | 0.0 |
|
468.8 |
RPL06.Conn.MS.01080 |
RPL06.Conn Wifi Ready - mCUP Yard (Pred from RPL10 CorpNet needed?) | Connectivity Milestones | Not Started | 05/28/26 | 05/28/26 | 0.0 | 0.0 |
|
278.8 |
RPL06.EY.DHC.01670 |
RPL06.EY.DHC - Install Electrical UG (GL 23-28) | GL 23-28 | Not Started | 05/28/26 | 06/03/26 | 6.2 | 6.2 |
|
155.0 |
RPL06.EY.DHC.01690 |
RPL06.EY.DHC - Install Grounding UG (GL 23-28) | GL 23-28 | Not Started | 05/28/26 | 06/03/26 | 6.2 | 6.2 |
|
155.0 |
RPL06.EY.DHC.01710 |
RPL06.EY.DHC - Install BMS UG (GL 23-28) | GL 23-28 | Not Started | 05/28/26 | 06/03/26 | 6.2 | 6.2 |
|
155.0 |
RPL06.INT.SSBC.02400 |
RPL06.Interior.SSBC - Priority - Install Layout, Top Track, Unistruts & Hangers (All Trades) Both sides of Wall | Priority Walls & Overhead | Not Started | 05/28/26 | 06/02/26 | 5.0 | 5.0 |
|
81.2 |
ICM.B6.1865 |
[SSDCB1] Delivery of MDF GS.MDF Module (First Delivery) | Construction | Not Started | 05/29/26 | 05/29/26 | 0.0 | 0.0 |
|
102.5 |
RPL.GF.D.N6170.XR |
Natural Gas Available for Fill/Flush Cx - Utility connections | Receive Milestones (XREFs) | Not Started | 05/29/26 | 05/29/26 | 0.0 | 0.0 |
|
122.5 |
RPL06.CX.1180 |
RPL06.CX.BLDG - L3, L4, IST - WBS Summary | Commissioning | Not Started | 05/29/26 | 09/01/27 | 396.2 | 396.2 |
|
60.0 |
RPL06.CX.MCUP.01000 |
RPL06.CX.mCup Loop 1 - L3, L4, IST - WBS Summary | mCUP 1-4 | Not Started | 05/29/26 | 10/05/26 | 112.5 | 112.5 |
|
187.5 |
RPL06.CX.MCUP.01390 |
RPL06.CX.mCup Loop 1 - L3/L4 - mCUP - Start-up of Boilers | mCUP 1-4 | Not Started | 05/29/26 | 06/04/26 | 6.2 | 6.2 |
|
122.5 |
RPL06.EY.DHD.01590 |
RPL06.EY.DHD - Flow FIll Cure (GL 17-23) | GL 17-25 | Not Started | 05/29/26 | 05/31/26 | 3.8 | 3.8 |
|
211.2 |
RPL06.EY.SSB.01205 |
RPL06.EY.SSB -Cure Loading Dock Ramp | Loading Dock | Not Started | 05/29/26 | 06/04/26 | 8.8 | 8.8 |
|
-17.5 |
RPL06.INT.DHA.01030 |
RPL06.Interior.DHA - Priority - Install Fire Sprinkler (IFP Accleration) | Early Priority OH MEPF | Not Started | 05/29/26 | 06/04/26 | 6.2 | 6.2 |
|
135.0 |
RPL06.INT.DHB.01020 |
RPL06.Interior.DHB - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHB | Not Started | 05/29/26 | 12/16/26 | 173.8 | 173.8 |
|
115.0 |
RPL06.INT.DHB.01060 |
RPL06.Interior.DHB - Temp Conditions - Drop Curtains (from Corridor to EJ) | Temp Conditions | Not Started | 05/29/26 | 06/08/26 | 8.8 | 8.8 |
|
-3.8 |
RPL06.MCUP.LP2.1420 |
RPL06.MCUP.Loop 2 - Tie-in SD, DW | Tie-ins | Not Started | 05/29/26 | 06/18/26 | 18.8 | 18.8 |
|
402.5 |
RPL06.STR.DHAB.01140 |
RPL06.Structure.DHAB - Zone SOG Cure | F/R/P | Not Started | 05/30/26 | 06/05/26 | 8.8 | 8.8 |
|
7.5 |
PRE.FA.1260 |
Kitchen Equipment - Final Agreement | Trade Partner Final Agreement | Not Started | 06/01/26 | 06/01/26 | 0.0 | 0.0 |
|
331.2 |
RPL.GF.D.N6250.XR |
RPL10 FacNet Live - GS - Core (ICM.B10.3355) * | Internal Milestones (XREFs) | Not Started | 06/01/26 | 06/01/26 | 0.0 | 0.0 |
|
405.0 |
RPL06.MCUP.LP2.2140 |
RPL06.MCUP.Loop 2 - F/R/P Pads (12'' larger) Generator Pads | Foundations | Not Started | 06/01/26 | 06/04/26 | 5.0 | 5.0 |
|
208.8 |
RPL06.EY.ENDC.01000 |
RPL06.EY.End - Install Electrical UG | Underground | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
242.5 |
RPL06.INT.CTRC.01020 |
RPL06.Interior.Center-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary | Center Corridor | Not Started | 06/02/26 | 02/10/27 | 217.5 | 217.5 |
|
62.5 |
RPL06.INT.CTRC.03460 |
RPL06.Interior.Center-Corridor - Priority - Priority - WBS Summary | Priority Walls & Overhead | Not Started | 06/02/26 | 08/07/26 | 60.0 | 60.0 |
|
43.8 |
RPL06.INT.CTRC.1020 |
RPL06.Interior.Center-Corridor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket - Day | Priority Walls & Overhead | Not Started | 06/02/26 | 06/04/26 | 3.8 | 3.8 |
|
43.8 |
RPL06.INT.CTRC.8920 |
RPL06.Interior.Center-Corridor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket - Swing | Priority Walls & Overhead | Not Started | 06/02/26 | 06/04/26 | 3.8 | 3.8 |
|
46.2 |
RPL06.INT.DHA.01000 |
RPL06.Interior.DHA - Priority OH - WBS Summary | OverHead | Not Started | 06/02/26 | 08/05/26 | 57.5 | 57.5 |
|
241.2 |
RPL06.INT.DHA.01020 |
RPL06.Interior.DHA - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHA | Not Started | 06/02/26 | 12/31/26 | 183.8 | 183.8 |
|
115.0 |
RPL06.INT.DHA.01980 |
RPL06.Interior.DHA - Priority - Install Unistruts & Hangers (All Trades) | OverHead | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
12.5 |
RPL06.INT.DHA.02400 |
RPL06.Interior.DHA - Priority - IMP Exterior Inwall Rough-In | OverHead | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
12.5 |
RPL06.INT.DHB.01000 |
RPL06.Interior.DHB - Priority OH - WBS Summary | OverHead | Not Started | 06/02/26 | 07/01/26 | 27.5 | 27.5 |
|
5.0 |