Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
5
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.INT.SSB.01006 RPL06.Interior - Priority - Install Hangers Support (Center Corr to End Corr) (All Trades) Early Priority OH MEPF Not Started 05/20/26 06/03/26 12.5 12.5
0%
146.2
RPL06.INT.SSB.02680 RPL06.Interior.SSB - Priority - Install Layout, Unistruts & Hangers (All Trades) - Day Priority Walls and OverHead Not Started 05/20/26 05/27/26 6.2 6.2
0%
80.0
RPL06.INT.SSB.06780 RPL06.Interior.SSB - Priority - Install Layout, Unistruts & Hangers (All Trades) - Swing Priority Walls and OverHead Not Started 05/20/26 05/27/26 6.2 6.2
0%
80.0
RPL06.INT.SSBC.03260 RPL06.Interior.SSBC - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) (6400 sq ft) Priority Walls & Overhead Not Started 05/20/26 05/27/26 6.2 6.2
0%
105.0
RPL06.SKN.DHCD.01010 RPL06.SKIN.DHCD - IMP, Roof, Windows, Doors, Ext Devices - WBS Summary DH C & DH D Not Started 05/20/26 02/26/27 241.2 241.2
0%
162.5
RPL06.SKN.DHCD.01070 RPL06.SKIN.DHCD - Install Roof System - Exterior Wall Sheething Roofing Not Started 05/20/26 05/26/26 5.0 5.0
0%
7.5
RPL06.SKN.DHCD.01080 RPL06.SKIN.DHCD - Install Roof System - WBS Summary Roofing Not Started 05/20/26 06/25/26 32.5 32.5
0%
371.2
RPL06.SKN.S.01070 RPL06.SKIN.South - Install IMP EJ - Grid lines 6-22/6-23 DBC Move 3 Not Started 05/20/26 05/27/26 6.2 6.2
0%
37.5
RPL06.SKN.S.01100 RPL06.SKIN.South - Secure All Exterior Mounted Boxes and Devices on Skin IMP System Not Started 05/20/26 06/17/26 25.0 25.0
0%
295.0
RPL06.SKN.S.01120 RPL06.SKIN.South - Install Stair Tower (DH C) DBC Move 3 Not Started 05/20/26 05/21/26 2.5 2.5
0%
386.2
RPL.06.D.63350.XR Pull and Term mCUP Skids - RPL06 Receive Milestones (XREFs) Not Started 05/21/26 05/21/26 0.0 0.0
0%
110.0
RPL.06.D.63850.XR 100MW Cx Temp Power to MV Skids RPL06 mCUPs Available Receive Milestones (XREFs) Not Started 05/21/26 05/21/26 0.0 0.0
0%
110.0
RPL06.CON.WP2.07600 RPL06.Conn - Ext. GSIDF6X03 (mCUP yard) - WBS Summary Ext. IDF Hut - GSIDF6X03 Not Started 05/21/26 06/23/26 28.8 28.8
0%
446.2
RPL06.CON.WP2.08400 RPL06.Conn - Ext. GSIDF6X03 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 05/21/26 05/21/26 1.2 1.2
0%
278.8
RPL06.EY.DHA.02140 RPL06.EY.DHA - Flow Fill Underground Not Started 05/21/26 05/22/26 2.5 2.5
0%
47.5
RPL06.INT.DHA.01040 RPL06.Interior.DHA - Priority - Install Temp Lighting Early Priority OH MEPF Not Started 05/21/26 05/26/26 3.8 3.8
0%
-7.5
RPL06.INT.DHB.01010 RPL06.Interior.DHB - Priority - Install Duct (IFP Accleration) Early Priority OH MEPF Not Started 05/21/26 05/28/26 6.2 6.2
0%
-3.8
RPL06.INT.DHB.01030 RPL06.Interior.DHB - Priority - Install Fire Sprinkler (IFP Accleration) Early Priority OH MEPF Not Started 05/21/26 05/28/26 6.2 6.2
0%
135.0
RPL06.INT.DHB.02160 RPL06.Interior.DHBADC - Priority - Install Fixed Draft/Smoke Curtain (#5) Early Priority OH MEPF Not Started 05/21/26 06/03/26 11.2 11.2
0%
18.8
RPL06.INT.SSBC.01011 RPL06.Interior.SSB-Corridor - Priority - Install Duct (Highside OH space) (IFP Accleration) Early Priority OH MEPF Not Started 05/21/26 05/28/26 6.2 6.2
0%
7.5
RPL06.MCUP.LP2.1560 RPL06.MCUP.Loop 2 - Tie-in Electrical - WBS Summary Tie-Ins Electrical Not Started 05/21/26 06/04/26 12.5 12.5
0%
193.8
RPL06.MCUP.LP2.1620 RPL06.MCUP.Loop 2 - Tie-in Electrical #5 Tie-Ins Electrical Not Started 05/21/26 06/04/26 12.5 12.5
0%
188.8
RPL06.MCUP.LP2.2000 RPL06.MCUP.Loop 2 - Tie-in Electrical #6 Tie-Ins Electrical Not Started 05/21/26 06/04/26 12.5 12.5
0%
193.8
RPL06.STR.DHAB.01180 RPL06.Structure.DHAB - SOG F/R/P #4 - Grid lines 6-11/6-14 (Pours-5&6) F/R/P Not Started 05/21/26 05/26/26 3.8 3.8
0%
5.0
RPL06.CFCI.5690 RPL06 - Fabricate / Deliver - Glass / Frames Glass & Glazing (Alum. Entrances & Curtainwall) Not Started 05/22/26 08/03/26 62.5 62.5
0%
140.0
RPL06.CON.WP2.08520 RPL06.Conn - Ext. GSIDF6X03 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 05/22/26 05/28/26 5.0 5.0
0%
278.8
RPL06.EY.DHB.01600 RPL06.EY.DHB - Install Electrical UG (GL 10-17) GL 10-17 Not Started 05/22/26 06/05/26 12.5 12.5
0%
45.0
RPL06.EY.DHB.01620 RPL06.EY.DHB - Install Grounding UG (GL 10-17) GL 10-17 Not Started 05/22/26 06/05/26 12.5 12.5
0%
45.0
RPL06.EY.DHB.01640 RPL06.EY.DHB - Install BMS/EPMS UG (GL 10-17) GL 10-17 Not Started 05/22/26 06/05/26 12.5 12.5
0%
45.0
RPL06.INT.SSBC.06680 RPL06.Interior.SSBC - Priority GL6.04 - (P0) Install MEP In-Wall/Backing Priority Wall Grid Line 6-04 Not Started 05/22/26 05/28/26 5.0 5.0
0%
82.5
RPL06.SKN.DHAB.01120 RPL06.SKIN.DHAB - Install Roof System - Final Roof Roofing Not Started 05/22/26 06/09/26 15.0 15.0
0%
111.2
RPL06.SKN.SSB.01140 RPL06.SKIN.SSB - Install Roof System - Install EJ Roofing Not Started 05/22/26 05/29/26 6.2 6.2
0%
22.5
RPL06.EY.DHA.02160 RPL06.EY.DHA - Flow Fill Cure Underground Not Started 05/23/26 05/25/26 3.8 3.8
0%
71.2
GCD.RPL06.1456 Start RPL06 EY RMU Equipment Pad Placement - RPL06 Construction Milestones Not Started 05/26/26 05/26/26 0.0 0.0
0%
303.8
PRE.TPA.1280 Kitchen Equipment - Award and Issue Subcontract DPR issue Trade Parter Agreements Not Started 05/26/26 06/01/26 6.2 6.2
0%
331.2
RPL06.CFCI.4450 RPL06 - Submittals Prep & Submit for Review - Finished Carpentry (Millwork/Countertops) Finished Carpentry (Millwork/Tops) Not Started 05/26/26 07/07/26 37.5 37.5
0%
237.5
RPL06.CFCI.4610 RPL06 - Submittals Prep & Submit for Review - Interior Painting (Spec 09 91 23) XX (CFCI) Div. 09 - Painting Not Started 05/26/26 07/07/26 37.5 37.5
0%
138.8
RPL06.CFCI.6840 RPL06 - Fabricate / Deliver - Stick Built IDF (A1) (CFCI) Div. XX - Technology IDF (Stick Built) Not Started 05/26/26 09/01/26 87.5 87.5
0%
83.8
RPL06.CFCI.6860 RPL06 - Fabricate / Deliver - Stick Built IDF (B1) (CFCI) Div. XX - Technology IDF (Stick Built) Not Started 05/26/26 08/18/26 75.0 75.0
0%
76.2
RPL06.CFCI.6880 RPL06 - Fabricate / Deliver - Stick Built IDF (C1) (CFCI) Div. XX - Technology IDF (Stick Built) Not Started 05/26/26 12/10/26 172.5 172.5
0%
75.0
RPL06.CFCI.6900 RPL06 - Fabricate / Deliver - Stick Built IDF (D1) (CFCI) Div. XX - Technology IDF (Stick Built) Not Started 05/26/26 11/24/26 160.0 160.0
0%
71.2
RPL06.EY.DHA.01010 RPL06.EY.DHA - Install F/R/P Equipment Pads - 1-12 (Grid 6-01/6-16) (12'' Larger For Tolerance) Foundations Not Started 05/26/26 06/22/26 25.0 25.0
0%
50.0
RPL06.EY.DHA.01020 RPL06.EY.DHA - Install Foundations - WBS Summary Foundations Not Started 05/26/26 06/29/26 31.2 31.2
0%
50.0
RPL06.EY.DHB.01010 RPL06.EY.DHB - Install F/R/P Equipment Pads - 1-6(Grid 6-01/6-09) (12'' Larger For Tolerance) Foundations Not Started 05/26/26 06/08/26 12.5 12.5
0%
43.8
RPL06.EY.DHB.01020 RPL06.EY.DHB - Install Foundations - WBS Summary Foundations Not Started 05/26/26 07/03/26 35.0 35.0
0%
43.8
RPL06.EY.SSB.01100 RPL06.EY.SSB - OFE - WBS Summary OFE Not Started 05/26/26 06/03/26 8.8 8.8
0%
83.8
RPL06.EY.SSB.01120 RPL06.EY.SSB - Install AHU (QTY 3) OFE Not Started 05/26/26 06/03/26 8.8 8.8
0%
83.8
RPL06.EY.SSB.01380 RPL06.EY.SSB - Install Floor Mounted AC units (4) - CFCI OFE Not Started 05/26/26 06/03/26 8.8 8.8
0%
81.2
RPL06.INT.SSB.06580 RPL06.Interior.SSB - Priority - QC - Backings/Walls Priority Walls and OverHead Not Started 05/26/26 06/01/26 6.2 6.2
0%
63.8
RPL06.LOG.1300 Dry Cooler 230 Ton Crane Demobilization 100 Ton Crane Not Started 05/26/26 05/28/26 3.8 3.8
0%
402.5
RPL06.MCUP.LP1.2060 RPL06.MCUP.Loop 1 - Tie-in - Electrical L2 Checklist Completion Tie-ins Not Started 05/26/26 06/08/26 12.5 12.5
0%
95.0
RPL06.MCUP.LP2.1240 RPL06.MCUP.Loop 2 - Set MTRs (4 per day) OFE Not Started 05/26/26 05/27/26 2.5 2.5
0%
190.0
RPL06.MCUP.LP2.1660 RPL06.MCUP.Loop 2 - Tie-in BMS - WBS Summary Tie-Ins BMS Not Started 05/26/26 06/16/26 20.0 20.0
0%
188.8
RPL06.MCUP.LP2.1680 RPL06.MCUP.Loop 2 - Tie-in EPMS - WBS Summary Tie-Ins EPMS Not Started 05/26/26 06/04/26 10.0 10.0
0%
193.8
RPL06.MCUP.LP2.1700 RPL06.MCUP.Loop 2 - Tie-in EPMS #5 (Includes GS.IDF6X03) Tie-Ins EPMS Not Started 05/26/26 06/04/26 10.0 10.0
0%
193.8
RPL06.MCUP.LP2.1720 RPL06.MCUP.Loop 2 - Tie-in BMS #5 (Includes GS.IDF6X03) Tie-Ins BMS Not Started 05/26/26 06/04/26 10.0 10.0
0%
188.8
RPL06.MCUP.LP2.1940 RPL06.MCUP.Loop 2 - Tie-in EPMS #6 Tie-Ins EPMS Not Started 05/26/26 06/04/26 10.0 10.0
0%
193.8
RPL06.MCUP.LP2.2020 RPL06.MCUP.Loop 1 - Tie-in Mechanical #6 Tie-Ins Mechanical Not Started 05/26/26 06/11/26 16.2 16.2
0%
192.5
ICM.B6.1750 [SSDCB1] Room Ready for GS.MDF Module Placement Construction Not Started 05/27/26 05/27/26 0.0 0.0
0%
301.2
PRE.FA.1280 Architectural/Security Fencing - Final Agreement Trade Partner Final Agreement Not Started 05/27/26 05/27/26 0.0 0.0
0%
451.2
RPL06.EY.DHD.01570 RPL06.EY.DHD - Flow Fill (GL 17-23) GL 17-25 Not Started 05/27/26 05/28/26 2.5 2.5
0%
147.5
RPL06.INT.DHA.01010 RPL06.Interior.DHA - Priority - Install Duct (IFP Accleration) Early Priority OH MEPF Not Started 05/27/26 06/02/26 6.2 6.2
0%
-7.5
RPL06.INT.SSBC.06660 RPL06.Interior.SSBC - Priority GL6.04 - (P0) Install IMP Wall Priority Wall Grid Line 6-04 Not Started 05/27/26 06/01/26 5.0 5.0
0%
101.2
RPL06.INT.SSBC.06700 RPL06.Interior.SSBC - Priority GL6.04 - (P0) Hang Drywall (Both Sides) Priority Wall Grid Line 6-04 Not Started 05/27/26 06/01/26 5.0 5.0
0%
82.5
RPL06.MCUP.LP1.2000 RPL06.MCUP.Loop 1 - Install Lighting Hardscape and Landscape Not Started 05/27/26 06/09/26 12.5 12.5
0%
433.8
RPL06.SKN.DHAB.01040 RPL06.SKIN.DHAB - Install Louvers Glazing, Doors and Ext Devices Not Started 05/27/26 06/02/26 6.2 6.2
0%
10.0
RPL06.SKN.DHAB.01110 RPL06.SKIN.DHAB - Install Scupper and Downspouts Glazing, Doors and Ext Devices Not Started 05/27/26 06/02/26 6.2 6.2
0%
277.5
RPL06.SKN.DHCD.01090 RPL06.SKIN.DHCD - Install Roof System - DenseDeck & Flame Down (6-23 to 6-28) Roofing Not Started 05/27/26 06/04/26 8.8 8.8
0%
7.5
RPL06.STR.DHAB.01100 RPL06.Structure.DHAB - SOG F/R/P #5 - Grid lines 6-14/6-18 (Pours-7&8) F/R/P Not Started 05/27/26 05/29/26 3.8 3.8
0%
5.0
RPL06.CON.WP2.09180 RPL06.Conn - CorpNet & FacNet Available (mCUP) WP#02 GS Not Started 05/28/26 05/28/26 0.0 0.0
0%
468.8
RPL06.Conn.MS.01080 RPL06.Conn Wifi Ready - mCUP Yard (Pred from RPL10 CorpNet needed?) Connectivity Milestones Not Started 05/28/26 05/28/26 0.0 0.0
0%
278.8
RPL06.EY.DHC.01670 RPL06.EY.DHC - Install Electrical UG (GL 23-28) GL 23-28 Not Started 05/28/26 06/03/26 6.2 6.2
0%
155.0
RPL06.EY.DHC.01690 RPL06.EY.DHC - Install Grounding UG (GL 23-28) GL 23-28 Not Started 05/28/26 06/03/26 6.2 6.2
0%
155.0
RPL06.EY.DHC.01710 RPL06.EY.DHC - Install BMS UG (GL 23-28) GL 23-28 Not Started 05/28/26 06/03/26 6.2 6.2
0%
155.0
RPL06.INT.SSBC.02400 RPL06.Interior.SSBC - Priority - Install Layout, Top Track, Unistruts & Hangers (All Trades) Both sides of Wall Priority Walls & Overhead Not Started 05/28/26 06/02/26 5.0 5.0
0%
81.2
ICM.B6.1865 [SSDCB1] Delivery of MDF GS.MDF Module (First Delivery) Construction Not Started 05/29/26 05/29/26 0.0 0.0
0%
102.5
RPL.GF.D.N6170.XR Natural Gas Available for Fill/Flush Cx - Utility connections Receive Milestones (XREFs) Not Started 05/29/26 05/29/26 0.0 0.0
0%
122.5
RPL06.CX.1180 RPL06.CX.BLDG - L3, L4, IST - WBS Summary Commissioning Not Started 05/29/26 09/01/27 396.2 396.2
0%
60.0
RPL06.CX.MCUP.01000 RPL06.CX.mCup Loop 1 - L3, L4, IST - WBS Summary mCUP 1-4 Not Started 05/29/26 10/05/26 112.5 112.5
0%
187.5
RPL06.CX.MCUP.01390 RPL06.CX.mCup Loop 1 - L3/L4 - mCUP - Start-up of Boilers mCUP 1-4 Not Started 05/29/26 06/04/26 6.2 6.2
0%
122.5
RPL06.EY.DHD.01590 RPL06.EY.DHD - Flow FIll Cure (GL 17-23) GL 17-25 Not Started 05/29/26 05/31/26 3.8 3.8
0%
211.2
RPL06.EY.SSB.01205 RPL06.EY.SSB -Cure Loading Dock Ramp Loading Dock Not Started 05/29/26 06/04/26 8.8 8.8
0%
-17.5
RPL06.INT.DHA.01030 RPL06.Interior.DHA - Priority - Install Fire Sprinkler (IFP Accleration) Early Priority OH MEPF Not Started 05/29/26 06/04/26 6.2 6.2
0%
135.0
RPL06.INT.DHB.01020 RPL06.Interior.DHB - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary DHB Not Started 05/29/26 12/16/26 173.8 173.8
0%
115.0
RPL06.INT.DHB.01060 RPL06.Interior.DHB - Temp Conditions - Drop Curtains (from Corridor to EJ) Temp Conditions Not Started 05/29/26 06/08/26 8.8 8.8
0%
-3.8
RPL06.MCUP.LP2.1420 RPL06.MCUP.Loop 2 - Tie-in SD, DW Tie-ins Not Started 05/29/26 06/18/26 18.8 18.8
0%
402.5
RPL06.STR.DHAB.01140 RPL06.Structure.DHAB - Zone SOG Cure F/R/P Not Started 05/30/26 06/05/26 8.8 8.8
0%
7.5
PRE.FA.1260 Kitchen Equipment - Final Agreement Trade Partner Final Agreement Not Started 06/01/26 06/01/26 0.0 0.0
0%
331.2
RPL.GF.D.N6250.XR RPL10 FacNet Live - GS - Core (ICM.B10.3355) * Internal Milestones (XREFs) Not Started 06/01/26 06/01/26 0.0 0.0
0%
405.0
RPL06.MCUP.LP2.2140 RPL06.MCUP.Loop 2 - F/R/P Pads (12'' larger) Generator Pads Foundations Not Started 06/01/26 06/04/26 5.0 5.0
0%
208.8
RPL06.EY.ENDC.01000 RPL06.EY.End - Install Electrical UG Underground Not Started 06/02/26 06/08/26 6.2 6.2
0%
242.5
RPL06.INT.CTRC.01020 RPL06.Interior.Center-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary Center Corridor Not Started 06/02/26 02/10/27 217.5 217.5
0%
62.5
RPL06.INT.CTRC.03460 RPL06.Interior.Center-Corridor - Priority - Priority - WBS Summary Priority Walls & Overhead Not Started 06/02/26 08/07/26 60.0 60.0
0%
43.8
RPL06.INT.CTRC.1020 RPL06.Interior.Center-Corridor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket - Day Priority Walls & Overhead Not Started 06/02/26 06/04/26 3.8 3.8
0%
43.8
RPL06.INT.CTRC.8920 RPL06.Interior.Center-Corridor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket - Swing Priority Walls & Overhead Not Started 06/02/26 06/04/26 3.8 3.8
0%
46.2
RPL06.INT.DHA.01000 RPL06.Interior.DHA - Priority OH - WBS Summary OverHead Not Started 06/02/26 08/05/26 57.5 57.5
0%
241.2
RPL06.INT.DHA.01020 RPL06.Interior.DHA - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary DHA Not Started 06/02/26 12/31/26 183.8 183.8
0%
115.0
RPL06.INT.DHA.01980 RPL06.Interior.DHA - Priority - Install Unistruts & Hangers (All Trades) OverHead Not Started 06/02/26 06/08/26 6.2 6.2
0%
12.5
RPL06.INT.DHA.02400 RPL06.Interior.DHA - Priority - IMP Exterior Inwall Rough-In OverHead Not Started 06/02/26 06/08/26 6.2 6.2
0%
12.5
RPL06.INT.DHB.01000 RPL06.Interior.DHB - Priority OH - WBS Summary OverHead Not Started 06/02/26 07/01/26 27.5 27.5
0%
5.0