Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
7
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL06.INT.DHB.02140 |
RPL06.Interior.DHB - Priority - Install Unistruts & Hangers (All Trades) | OverHead | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
5.0 |
RPL06.INT.DHB.02340 |
RPL06.Interior.DHB - Priority - Install IMP Exterior Inwall Rough-In (These walls available early) | OverHead | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
5.0 |
RPL06.INT.SSB.06540 |
RPL06.Interior.SSB - Priority - Install Drywall at Exterior Walls | Priority Walls and OverHead | Not Started | 06/02/26 | 06/22/26 | 18.8 | 18.8 |
|
63.8 |
RPL06.INT.SSBC.01090 |
RPL06.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 1 of 2) - 6GSMDF2 (ROJ05.14.26) | OFE/MOFE & CFCI | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
101.2 |
RPL06.INT.SSBC.06720 |
RPL06.Interior.SSBC - Priority GL6.04 - (P0) Tape Finish Paint (Both Sides) | Priority Wall Grid Line 6-04 | Not Started | 06/02/26 | 06/08/26 | 6.2 | 6.2 |
|
82.5 |
RPL06.INT.CTRC.1180 |
RPL06.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) (IFP Accleration) | Early Priority OH MEPF | Not Started | 06/03/26 | 06/11/26 | 8.8 | 8.8 |
|
186.2 |
RPL06.INT.CTRC.7740 |
RPL06.Interior.Center-Corridor - Priority - Install IMP Exterior Inwall Rough-In - Day | Priority Walls & Overhead | Not Started | 06/03/26 | 06/04/26 | 2.5 | 2.5 |
|
46.2 |
RPL06.INT.CTRC.8940 |
RPL06.Interior.Center-Corridor - Priority - Install IMP Exterior Inwall Rough-In - Swing | Priority Walls & Overhead | Not Started | 06/03/26 | 06/04/26 | 2.5 | 2.5 |
|
46.2 |
RPL06.INT.DHA.03380 |
RPL06.Interior.DHA - Temp Conditions - Drop Curtains (from Corridor to EJ) | Temp Conditions | Not Started | 06/03/26 | 06/11/26 | 8.8 | 8.8 |
|
-7.5 |
RPL06.SKN.DHAB.01050 |
RPL06.SKIN.DHAB - Install Lighting | Glazing, Doors and Ext Devices | Not Started | 06/03/26 | 06/08/26 | 5.0 | 5.0 |
|
246.2 |
RPL06.EY.DHC.01730 |
RPL06.EY.DHC - Flow Fill (GL 23-28) | GL 23-28 | Not Started | 06/04/26 | 06/05/26 | 2.5 | 2.5 |
|
155.0 |
RPL06.EY.ENDC.01340 |
RPL06.EY.End - Install Grounding UG | Underground | Not Started | 06/04/26 | 06/10/26 | 6.2 | 6.2 |
|
242.5 |
RPL06.EY.SSB.02060 |
RPL06.EY.SSB - Install Remaining Permanent Duct with insulation to AHU Units | Temp Conditions | Not Started | 06/04/26 | 06/15/26 | 10.0 | 10.0 |
|
83.8 |
RPL06.INT.SSB.01050 |
RPL06.Interior.SSB - Priority - (P1) Frame Walls | Priority Wall - P1 | Not Started | 06/04/26 | 06/10/26 | 6.2 | 6.2 |
|
140.0 |
RPL06.INT.SSB.06875 |
RPL06.Interior.SSB - Priority - (P1) including ERAD (6.1) & ENS Storage (10.7) | Priority Wall - P1 | Not Started | 06/04/26 | 06/29/26 | 22.5 | 22.5 |
|
176.2 |
RPL06.INT.SSB.06880 |
RPL06.Interior.SSB - Priority - (P1) Frame Remaining Walls | Priority Wall - P1 | Not Started | 06/04/26 | 06/08/26 | 3.8 | 3.8 |
|
182.5 |
RPL06.EY.SSB.01210 |
RPL06.EY.SSB - Install LD Electrical In walls | Loading Dock | Not Started | 06/05/26 | 06/10/26 | 5.0 | 5.0 |
|
197.5 |
RPL06.EY.SSB.01220 |
RPL06.EY.SSB - Install LD French Drain (Not Designed) | Loading Dock | Not Started | 06/05/26 | 06/10/26 | 5.0 | 5.0 |
|
207.5 |
RPL06.EY.SSB.02020 |
RPL06.EY.SSB - Install Temp Conditioning Units - CFCI | Temp Conditions | Not Started | 06/05/26 | 06/11/26 | 6.2 | 6.2 |
|
-11.2 |
RPL06.INT.CTRC.1000 |
RPL06.Interior.Center-Corridor - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall - Day | Priority Walls & Overhead | Not Started | 06/05/26 | 06/08/26 | 2.5 | 2.5 |
|
43.8 |
RPL06.INT.CTRC.1040 |
RPL06.Interior.Center-Corridor - Priority - Install Fire Sprinkler (Highside OH space) (IFP Accleration) | Early Priority OH MEPF | Not Started | 06/05/26 | 06/09/26 | 3.8 | 3.8 |
|
135.0 |
RPL06.INT.CTRC.1060 |
RPL06.Interior.Center-Corridor - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 06/05/26 | 06/09/26 | 3.8 | 3.8 |
|
135.0 |
RPL06.INT.CTRC.8900 |
RPL06.Interior.Center-Corridor - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall - Swing | Priority Walls & Overhead | Not Started | 06/05/26 | 06/08/26 | 2.5 | 2.5 |
|
43.8 |
RPL06.INT.DHA.03440 |
RPL06.Interior.DHA - Priority - Install Backing at Exterior Wall | OverHead | Not Started | 06/05/26 | 06/08/26 | 2.5 | 2.5 |
|
12.5 |
RPL06.INT.DHB.01090 |
RPL06.Interior.DHB - Temp Conditions - Install Early Temp Conditions | Temp Conditions | Not Started | 06/05/26 | 06/08/26 | 2.5 | 2.5 |
|
-3.8 |
RPL06.INT.DHB.02380 |
RPL06.Interior.DHB - Priority - Install Backing at Exterior Wall | OverHead | Not Started | 06/05/26 | 06/08/26 | 2.5 | 2.5 |
|
5.0 |
RPL06.MCUP.LP2.1980 |
RPL06.MCUP.Loop 2 - Tie-in BMS #6 | Tie-Ins BMS | Not Started | 06/05/26 | 06/16/26 | 10.0 | 10.0 |
|
188.8 |
RPL06.MCUP.LP2.2040 |
RPL06.MCUP.Loop 2 - Tie-in - MV Loop 2 L2 Checklist Completion | Tie-ins | Not Started | 06/05/26 | 06/11/26 | 6.2 | 6.2 |
|
193.8 |
RPL06.MCUP.LP2.2160 |
RPL06.MCUP.Loop 2 - Cure for Generator Pads | Foundations | Not Started | 06/05/26 | 06/11/26 | 8.8 | 8.8 |
|
306.2 |
RPL06.STR.DHCD.01110 |
RPL06.Structure.DHCD - SOG F/R/P - WBS Summary | F/R/P | Not Started | 06/05/26 | 07/01/26 | 23.8 | 23.8 |
|
76.2 |
RPL06.STR.DHCD.01120 |
RPL06.Structure.DHCD - SOG F/R/P #6 - Grid lines 6-18/6-21 (Pour-9) | F/R/P | Not Started | 06/05/26 | 06/08/26 | 2.5 | 2.5 |
|
7.5 |
RPL06.EY.DHC.01750 |
RPL06.EY.DHC - Flow Fill Cure (GL 23-28) | GL 23-28 | Not Started | 06/06/26 | 06/08/26 | 3.8 | 3.8 |
|
226.2 |
RPL06.STR.DHAB.01240 |
RPL06.Structure.DHAB - Moisture requirements for floor Sealer | F/R/P | Not Started | 06/06/26 | 06/12/26 | 8.8 | 8.8 |
|
12.5 |
RPL06.EY.DHB.01740 |
RPL06.EY.DHB - Flow Fill (GL 10-17) | GL 10-17 | Not Started | 06/08/26 | 06/09/26 | 2.5 | 2.5 |
|
45.0 |
GCD.RPL06.1020 |
Weather tight SSB and DHA&B | Construction Milestones | Not Started | 06/09/26 | 06/09/26 | 0.0 | 0.0 |
|
290.0 |
GCD.RPL06.1280 |
Interior fit-out Start RPL06 - DHA&B | Construction Milestones | Not Started | 06/09/26 | 06/09/26 | 0.0 | 0.0 |
|
291.2 |
GCD.RPL06.2001 |
Cx Power Available (Temp) | CX Milestones | Not Started | 06/09/26 | 06/09/26 | 0.0 | 0.0 |
|
95.0 |
GCD.RPL06.2051 |
MCUP Ready for Energization - (MCUPs Loop 1) | mCup | Not Started | 06/09/26 | 06/09/26 | 0.0 | 0.0 |
|
120.0 |
RPL06.CFCI.4730 |
RPL06 - Submittals Review & Approval - Finished Carpentry (Millwork/Countertops) | Finished Carpentry (Millwork/Tops) | Not Started | 06/09/26 | 07/07/26 | 25.0 | 25.0 |
|
237.5 |
RPL06.CON.WP2.02000 |
RPL06.Conn - GS EF2 (North) - WBS Summary | GS.EF2 (North) | Not Started | 06/09/26 | 10/12/26 | 110.0 | 110.0 |
|
283.8 |
RPL06.CON.WP2.02200 |
RPL06.Conn - GS EF2 (North) Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 06/09/26 | 06/11/26 | 3.8 | 3.8 |
|
375.0 |
RPL06.CON.WP2.03000 |
RPL06.Conn - GS EF1 (South) - WBS Summary | GS.EF1 (South) | Not Started | 06/09/26 | 10/13/26 | 111.2 | 111.2 |
|
286.2 |
RPL06.CON.WP2.04000 |
RPL06.Conn - GSMDF2 (North) - WBS Summary | GS.MDF2 (North) (Includes IDF) | Not Started | 06/09/26 | 10/23/26 | 121.2 | 121.2 |
|
272.5 |
RPL06.CON.WP2.07820 |
RPL06.Conn - GS EF1 (South) Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 06/09/26 | 06/11/26 | 3.8 | 3.8 |
|
377.5 |
RPL06.CON.WP2.07880 |
RPL06.Conn - GSMDF2 (North) Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 06/09/26 | 06/09/26 | 1.2 | 1.2 |
|
256.2 |
RPL06.CX.MCUP.01010 |
RPL06.CX.mCup Loop 1 - L3/L4 - MV Skids | mCUP 1-4 | Not Started | 06/09/26 | 06/16/26 | 7.5 | 7.5 |
|
95.0 |
RPL06.EY.DHB.01130 |
RPL06.EY.DHB - Cure (High Early Mix) | Foundations | Not Started | 06/09/26 | 06/15/26 | 8.8 | 8.8 |
|
62.5 |
RPL06.EY.DHC.01020 |
RPL06.EY.DHC - Install Foundations - WBS Summary | Foundations | Not Started | 06/09/26 | 03/03/27 | 228.8 | 228.8 |
|
113.8 |
RPL06.EY.DHC.01610 |
RPL06.EY.DHC - Install F/R/P Equipment Pads - 5-10 (Grid 6-23/6-28) (12'' Larger For Tolerance) | Foundations | Not Started | 06/09/26 | 06/17/26 | 8.8 | 8.8 |
|
155.0 |
RPL06.INT.CTRC.1920 |
RPL06.Interior.Center-Corridor - Priority - Install Drywall at Exterior Walls | Priority Walls & Overhead | Not Started | 06/09/26 | 06/15/26 | 6.2 | 6.2 |
|
43.8 |
RPL06.INT.DHA.02380 |
RPL06.Interior.DHA - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 06/09/26 | 06/17/26 | 8.8 | 8.8 |
|
12.5 |
RPL06.INT.DHB.02100 |
RPL06.Interior.DHB - Priority - Install Mechanical Piping | OverHead | Not Started | 06/09/26 | 06/29/26 | 18.8 | 18.8 |
|
7.5 |
RPL06.INT.DHB.02320 |
RPL06.Interior.DHB - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 06/09/26 | 06/17/26 | 8.8 | 8.8 |
|
5.0 |
RPL06.INT.DHB.02360 |
RPL06.Interior.DHB - Temp Conditions - CC West Duct Work Complete for Temp Condition (LVs) | Temp Conditions | Not Started | 06/09/26 | 06/10/26 | 2.5 | 2.5 |
|
-3.8 |
RPL06.INT.SSB.06900 |
RPL06.Interior.SSB - Priority - (P1) Install Remaining MEP In-Wall/Backing | Priority Wall - P1 | Not Started | 06/09/26 | 06/10/26 | 2.5 | 2.5 |
|
182.5 |
RPL06.INT.SSBC.01140 |
RPL06.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 2 of 2) - 6GSMDF1 (ROJ05.14.26) | OFE/MOFE & CFCI | Not Started | 06/09/26 | 06/15/26 | 6.2 | 6.2 |
|
101.2 |
RPL06.INT.SSBC.3000 |
RPL06.Interior.SSBC LO #06 - Close Interior LO #06 SSB/SSBC (For MDF2) WBS Summary | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 06/09/26 | 08/21/26 | 66.2 | 66.2 |
|
127.5 |
RPL06.INT.SSBC.3020 |
RPL06.Interior.SSBC LO #06 - Install Framing at LO | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 06/09/26 | 06/15/26 | 6.2 | 6.2 |
|
120.0 |
RPL06.SKN.DHAB.01060 |
RPL06.SKIN.DHAB - Install Security | Glazing, Doors and Ext Devices | Not Started | 06/09/26 | 06/10/26 | 2.5 | 2.5 |
|
246.2 |
RPL06.STR.DHCD.01130 |
RPL06.Structure.DHCD - SOG F/R/P #7 - Grid lines 6-21/6-25 (Pour-10) | F/R/P | Not Started | 06/09/26 | 06/10/26 | 2.5 | 2.5 |
|
12.5 |
RPL06.CON.WP2.09240 |
RPL06.Conn - GSMDF2 (North) - Install Copper, WAPs, Security Camera & Access Control | ISP (MDF RPL06 <> MDF RPL06) | Not Started | 06/10/26 | 06/23/26 | 12.5 | 12.5 |
|
256.2 |
RPL06.EY.DHB.01760 |
RPL06.EY.DHB - Flow Fill Cure (GL 10-17) | GL 10-17 | Not Started | 06/10/26 | 06/12/26 | 3.8 | 3.8 |
|
63.8 |
RPL06.INT.DHA.03400 |
RPL06.Interior.DHA - Temp Conditions - Install Early Temp Conditions | Temp Conditions | Not Started | 06/10/26 | 06/11/26 | 2.5 | 2.5 |
|
-7.5 |
RPL06.INT.DHD.01040 |
RPL06.Interior.DHD - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 06/10/26 | 06/12/26 | 3.8 | 3.8 |
|
135.0 |
RPL06.MCUP.LP1.2040 |
RPL06.MCUP.Loop 1 - Install Mcup Paving | Hardscape and Landscape | Not Started | 06/10/26 | 06/23/26 | 12.5 | 12.5 |
|
433.8 |
RPL06.SKN.DHAB.01130 |
RPL06.SKIN.DHAB - Install Roof System - Install EJ | Roofing | Not Started | 06/10/26 | 06/11/26 | 2.5 | 2.5 |
|
111.2 |
RPL06.SKN.DHCD.01110 |
RPL06.SKIN.DHCD - Install Roof System - Final Roof | Roofing | Not Started | 06/10/26 | 06/25/26 | 15.0 | 15.0 |
|
371.2 |
RPL.GF.D.N6100.XG |
GSEF #1 Infrastructure Ready RPL06 | Give Milestones (XREFs) | Not Started | 06/11/26 | 06/11/26 | 0.0 | 0.0 |
|
456.2 |
RPL.GF.D.N6110.XG |
GSEF #2 Infrastructure Ready RPL06 | Give Milestones (XREFs) | Not Started | 06/11/26 | 06/11/26 | 0.0 | 0.0 |
|
456.2 |
RPL06.EY.ENDC.01040 |
RPL06.EY.End - Install BMS UG | Underground | Not Started | 06/11/26 | 06/17/26 | 6.2 | 6.2 |
|
242.5 |
RPL06.EY.SSB.01230 |
RPL06.EY.SSB - Install LD F/R/P Loading Dock Walls | Loading Dock | Not Started | 06/11/26 | 06/22/26 | 10.0 | 10.0 |
|
197.5 |
RPL06.INT.CTRC.1100 |
RPL06.Interior.Center-Corridor - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) | Priority Walls & Overhead | Not Started | 06/11/26 | 06/19/26 | 8.8 | 8.8 |
|
43.8 |
RPL06.INT.DHB.01050 |
RPL06.Interior.DHB - Priority - Install FA / Linear heat detection | OverHead | Not Started | 06/11/26 | 06/17/26 | 6.2 | 6.2 |
|
5.0 |
RPL06.INT.DHB.02300 |
RPL06.Interior.DHB - Priority - Install Electrical | OverHead | Not Started | 06/11/26 | 07/01/26 | 18.8 | 18.8 |
|
5.0 |
RPL06.INT.SSB.06820 |
RPL06.Interior.SSB - Priority - (P1) Install MEP In-Wall/Backing | Priority Wall - P1 | Not Started | 06/11/26 | 06/16/26 | 5.0 | 5.0 |
|
176.2 |
RPL06.INT.SSB.06920 |
RPL06.Interior.SSB - Priority - (P1) Remaining Wall Hang Drywall (Both Sides) | Priority Wall - P1 | Not Started | 06/11/26 | 06/15/26 | 3.8 | 3.8 |
|
182.5 |
RPL06.SKN.DHAB.01140 |
RPL06.SKIN.DHAB - Install Perm Doors | Glazing, Doors and Ext Devices | Not Started | 06/11/26 | 06/12/26 | 2.5 | 2.5 |
|
246.2 |
RPL06.STR.DHCD.01140 |
RPL06.Structure.DHCD - SOG F/R/P #8 - Grid lines 6-25/6-28 (Pours-11&12) | F/R/P | Not Started | 06/11/26 | 06/15/26 | 3.8 | 3.8 |
|
77.5 |
RPL06.CON.WP2.07240 |
RPL06.Conn - Ext. GSIDF6X01 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 06/12/26 | 06/19/26 | 7.5 | 7.5 |
|
446.2 |
RPL06.CON.WP2.07440 |
RPL06.Conn - Ext. GSIDF6X02 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 06/12/26 | 06/19/26 | 7.5 | 7.5 |
|
446.2 |
RPL06.CON.WP2.08420 |
RPL06.Conn - Ext. GSIDF6X03 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 06/12/26 | 06/19/26 | 7.5 | 7.5 |
|
446.2 |
RPL06.CON.WP2.09300 |
RPL06.Conn - GS EF1 (South)<>GSMDF2 (North) Install Cabling (Pull, Splice & Terminate) | Cabling | Not Started | 06/12/26 | 06/17/26 | 5.0 | 5.0 |
|
381.2 |
RPL06.EY.SSB.02040 |
RPL06.EY.SSB - Install Temp Duct to Permanent Duct | Temp Conditions | Not Started | 06/12/26 | 06/18/26 | 6.2 | 6.2 |
|
-11.2 |
RPL06.INT.DHA.03420 |
RPL06.Interior.DHA - Temp Conditions - CC West Duct Work Complete for Temp Condition (LVs) | Temp Conditions | Not Started | 06/12/26 | 06/15/26 | 2.5 | 2.5 |
|
-7.5 |
RPL06.INT.DHD.01010 |
RPL06.Interior.DHD - Priority - Install Duct (IFP Accleration) | Early Priority OH MEPF | Not Started | 06/12/26 | 06/17/26 | 5.0 | 5.0 |
|
186.2 |
RPL06.MCUP.LP2.2060 |
RPL06.MCUP.Loop 2 - Tie-in - Electrical L2 Checklist Completion | Tie-ins | Not Started | 06/12/26 | 06/18/26 | 6.2 | 6.2 |
|
193.8 |
RPL06.STR.DHAB.01260 |
RPL06.Structure.DHAB - Install SOG Sealer and Cure | F/R/P | Not Started | 06/13/26 | 06/14/26 | 2.5 | 2.5 |
|
12.5 |
RPL06.EY.DHB.01700 |
RPL06.EY.DHB - Install F/R/P Equipment Pads - 7-12(Grid 6-09/6-16) (12'' Larger For Tolerance) | Foundations | Not Started | 06/15/26 | 06/26/26 | 12.5 | 12.5 |
|
42.5 |
RPL06.INT.DHA.01080 |
RPL06.Interior.DHA - OFE - WBS Summary | OFE/MOFE & CFCI | Not Started | 06/15/26 | 11/19/26 | 138.8 | 138.8 |
|
8.8 |
RPL06.INT.DHA.03980 |
RPL06.Interior.DHA - CFCI - Pre Set 16"" FW Pipe | OFE/MOFE & CFCI | Not Started | 06/15/26 | 06/26/26 | 12.5 | 12.5 |
|
77.5 |
RPL06.INT.DHB.01100 |
RPL06.Interior.DHB - Priority - Install Temp Doors Frame Hardware | OverHead | Not Started | 06/15/26 | 06/17/26 | 3.8 | 3.8 |
|
5.0 |
RPL06.INT.DHB.01160 |
RPL06.Interior.DHB - OFE - WBS Summary | OFE/MOFE & CFCI | Not Started | 06/15/26 | 11/04/26 | 126.2 | 126.2 |
|
17.5 |
RPL06.INT.DHB.02900 |
RPL06.Interior.DHB - CFCI - Pre Set 16"" FW Pipe | OFE/MOFE & CFCI | Not Started | 06/15/26 | 06/26/26 | 12.5 | 12.5 |
|
77.5 |
RPL06.INT.DHC.01040 |
RPL06.Interior.DHC - Priority - Install Temp Lighting | Early Priority OH MEPF | Not Started | 06/15/26 | 06/17/26 | 3.8 | 3.8 |
|
135.0 |
RPL06.INT.DHD.01030 |
RPL06.Interior.DHD - Priority - Install Fire Sprinkler (IFP Accleration) | Early Priority OH MEPF | Not Started | 06/15/26 | 06/19/26 | 6.2 | 6.2 |
|
192.5 |
RPL06.CFCI.4950 |
Campus - Submittals Prep & Submit for Review - Landscaping / Irrigation | (CFCI) Div. 32 - Landscape/ Irrigation | Not Started | 06/16/26 | 07/07/26 | 18.8 | 18.8 |
|
297.5 |
RPL06.CFCI.5100 |
Campus - Submittal Review & Approval - Asphalt / Paving | (CFCI) Div. 32 - Asphalt/ Conc. Paving | Not Started | 06/16/26 | 07/14/26 | 25.0 | 25.0 |
|
178.8 |
RPL06.CON.WP2.05000 |
RPL06.Conn - GSMDF1 (South) - WBS Summary | GS.MDF1 (South) (Includes IDF) | Not Started | 06/16/26 | 10/28/26 | 118.8 | 118.8 |
|
272.5 |
RPL06.CON.WP2.07960 |
RPL06.Conn - GSMDF1 (South) Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) | Infrastructure | Not Started | 06/16/26 | 06/16/26 | 1.2 | 1.2 |
|
262.5 |
RPL06.CON.WP4.00010 |
RPL06.Conn - Network - WBS Summary | WP#4 Network | Not Started | 06/16/26 | 09/14/27 | 391.2 | 391.2 |
|
62.5 |