Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
7
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.INT.DHB.02140 RPL06.Interior.DHB - Priority - Install Unistruts & Hangers (All Trades) OverHead Not Started 06/02/26 06/08/26 6.2 6.2
0%
5.0
RPL06.INT.DHB.02340 RPL06.Interior.DHB - Priority - Install IMP Exterior Inwall Rough-In (These walls available early) OverHead Not Started 06/02/26 06/08/26 6.2 6.2
0%
5.0
RPL06.INT.SSB.06540 RPL06.Interior.SSB - Priority - Install Drywall at Exterior Walls Priority Walls and OverHead Not Started 06/02/26 06/22/26 18.8 18.8
0%
63.8
RPL06.INT.SSBC.01090 RPL06.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 1 of 2) - 6GSMDF2 (ROJ05.14.26) OFE/MOFE & CFCI Not Started 06/02/26 06/08/26 6.2 6.2
0%
101.2
RPL06.INT.SSBC.06720 RPL06.Interior.SSBC - Priority GL6.04 - (P0) Tape Finish Paint (Both Sides) Priority Wall Grid Line 6-04 Not Started 06/02/26 06/08/26 6.2 6.2
0%
82.5
RPL06.INT.CTRC.1180 RPL06.Interior.Center-Corridor - Priority - Install Duct (Highside OH space) (IFP Accleration) Early Priority OH MEPF Not Started 06/03/26 06/11/26 8.8 8.8
0%
186.2
RPL06.INT.CTRC.7740 RPL06.Interior.Center-Corridor - Priority - Install IMP Exterior Inwall Rough-In - Day Priority Walls & Overhead Not Started 06/03/26 06/04/26 2.5 2.5
0%
46.2
RPL06.INT.CTRC.8940 RPL06.Interior.Center-Corridor - Priority - Install IMP Exterior Inwall Rough-In - Swing Priority Walls & Overhead Not Started 06/03/26 06/04/26 2.5 2.5
0%
46.2
RPL06.INT.DHA.03380 RPL06.Interior.DHA - Temp Conditions - Drop Curtains (from Corridor to EJ) Temp Conditions Not Started 06/03/26 06/11/26 8.8 8.8
0%
-7.5
RPL06.SKN.DHAB.01050 RPL06.SKIN.DHAB - Install Lighting Glazing, Doors and Ext Devices Not Started 06/03/26 06/08/26 5.0 5.0
0%
246.2
RPL06.EY.DHC.01730 RPL06.EY.DHC - Flow Fill (GL 23-28) GL 23-28 Not Started 06/04/26 06/05/26 2.5 2.5
0%
155.0
RPL06.EY.ENDC.01340 RPL06.EY.End - Install Grounding UG Underground Not Started 06/04/26 06/10/26 6.2 6.2
0%
242.5
RPL06.EY.SSB.02060 RPL06.EY.SSB - Install Remaining Permanent Duct with insulation to AHU Units Temp Conditions Not Started 06/04/26 06/15/26 10.0 10.0
0%
83.8
RPL06.INT.SSB.01050 RPL06.Interior.SSB - Priority - (P1) Frame Walls Priority Wall - P1 Not Started 06/04/26 06/10/26 6.2 6.2
0%
140.0
RPL06.INT.SSB.06875 RPL06.Interior.SSB - Priority - (P1) including ERAD (6.1) & ENS Storage (10.7) Priority Wall - P1 Not Started 06/04/26 06/29/26 22.5 22.5
0%
176.2
RPL06.INT.SSB.06880 RPL06.Interior.SSB - Priority - (P1) Frame Remaining Walls Priority Wall - P1 Not Started 06/04/26 06/08/26 3.8 3.8
0%
182.5
RPL06.EY.SSB.01210 RPL06.EY.SSB - Install LD Electrical In walls Loading Dock Not Started 06/05/26 06/10/26 5.0 5.0
0%
197.5
RPL06.EY.SSB.01220 RPL06.EY.SSB - Install LD French Drain (Not Designed) Loading Dock Not Started 06/05/26 06/10/26 5.0 5.0
0%
207.5
RPL06.EY.SSB.02020 RPL06.EY.SSB - Install Temp Conditioning Units - CFCI Temp Conditions Not Started 06/05/26 06/11/26 6.2 6.2
0%
-11.2
RPL06.INT.CTRC.1000 RPL06.Interior.Center-Corridor - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall - Day Priority Walls & Overhead Not Started 06/05/26 06/08/26 2.5 2.5
0%
43.8
RPL06.INT.CTRC.1040 RPL06.Interior.Center-Corridor - Priority - Install Fire Sprinkler (Highside OH space) (IFP Accleration) Early Priority OH MEPF Not Started 06/05/26 06/09/26 3.8 3.8
0%
135.0
RPL06.INT.CTRC.1060 RPL06.Interior.Center-Corridor - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 06/05/26 06/09/26 3.8 3.8
0%
135.0
RPL06.INT.CTRC.8900 RPL06.Interior.Center-Corridor - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall - Swing Priority Walls & Overhead Not Started 06/05/26 06/08/26 2.5 2.5
0%
43.8
RPL06.INT.DHA.03440 RPL06.Interior.DHA - Priority - Install Backing at Exterior Wall OverHead Not Started 06/05/26 06/08/26 2.5 2.5
0%
12.5
RPL06.INT.DHB.01090 RPL06.Interior.DHB - Temp Conditions - Install Early Temp Conditions Temp Conditions Not Started 06/05/26 06/08/26 2.5 2.5
0%
-3.8
RPL06.INT.DHB.02380 RPL06.Interior.DHB - Priority - Install Backing at Exterior Wall OverHead Not Started 06/05/26 06/08/26 2.5 2.5
0%
5.0
RPL06.MCUP.LP2.1980 RPL06.MCUP.Loop 2 - Tie-in BMS #6 Tie-Ins BMS Not Started 06/05/26 06/16/26 10.0 10.0
0%
188.8
RPL06.MCUP.LP2.2040 RPL06.MCUP.Loop 2 - Tie-in - MV Loop 2 L2 Checklist Completion Tie-ins Not Started 06/05/26 06/11/26 6.2 6.2
0%
193.8
RPL06.MCUP.LP2.2160 RPL06.MCUP.Loop 2 - Cure for Generator Pads Foundations Not Started 06/05/26 06/11/26 8.8 8.8
0%
306.2
RPL06.STR.DHCD.01110 RPL06.Structure.DHCD - SOG F/R/P - WBS Summary F/R/P Not Started 06/05/26 07/01/26 23.8 23.8
0%
76.2
RPL06.STR.DHCD.01120 RPL06.Structure.DHCD - SOG F/R/P #6 - Grid lines 6-18/6-21 (Pour-9) F/R/P Not Started 06/05/26 06/08/26 2.5 2.5
0%
7.5
RPL06.EY.DHC.01750 RPL06.EY.DHC - Flow Fill Cure (GL 23-28) GL 23-28 Not Started 06/06/26 06/08/26 3.8 3.8
0%
226.2
RPL06.STR.DHAB.01240 RPL06.Structure.DHAB - Moisture requirements for floor Sealer F/R/P Not Started 06/06/26 06/12/26 8.8 8.8
0%
12.5
RPL06.EY.DHB.01740 RPL06.EY.DHB - Flow Fill (GL 10-17) GL 10-17 Not Started 06/08/26 06/09/26 2.5 2.5
0%
45.0
GCD.RPL06.1020 Weather tight SSB and DHA&B Construction Milestones Not Started 06/09/26 06/09/26 0.0 0.0
0%
290.0
GCD.RPL06.1280 Interior fit-out Start RPL06 - DHA&B Construction Milestones Not Started 06/09/26 06/09/26 0.0 0.0
0%
291.2
GCD.RPL06.2001 Cx Power Available (Temp) CX Milestones Not Started 06/09/26 06/09/26 0.0 0.0
0%
95.0
GCD.RPL06.2051 MCUP Ready for Energization - (MCUPs Loop 1) mCup Not Started 06/09/26 06/09/26 0.0 0.0
0%
120.0
RPL06.CFCI.4730 RPL06 - Submittals Review & Approval - Finished Carpentry (Millwork/Countertops) Finished Carpentry (Millwork/Tops) Not Started 06/09/26 07/07/26 25.0 25.0
0%
237.5
RPL06.CON.WP2.02000 RPL06.Conn - GS EF2 (North) - WBS Summary GS.EF2 (North) Not Started 06/09/26 10/12/26 110.0 110.0
0%
283.8
RPL06.CON.WP2.02200 RPL06.Conn - GS EF2 (North) Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Not Started 06/09/26 06/11/26 3.8 3.8
0%
375.0
RPL06.CON.WP2.03000 RPL06.Conn - GS EF1 (South) - WBS Summary GS.EF1 (South) Not Started 06/09/26 10/13/26 111.2 111.2
0%
286.2
RPL06.CON.WP2.04000 RPL06.Conn - GSMDF2 (North) - WBS Summary GS.MDF2 (North) (Includes IDF) Not Started 06/09/26 10/23/26 121.2 121.2
0%
272.5
RPL06.CON.WP2.07820 RPL06.Conn - GS EF1 (South) Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Not Started 06/09/26 06/11/26 3.8 3.8
0%
377.5
RPL06.CON.WP2.07880 RPL06.Conn - GSMDF2 (North) Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Not Started 06/09/26 06/09/26 1.2 1.2
0%
256.2
RPL06.CX.MCUP.01010 RPL06.CX.mCup Loop 1 - L3/L4 - MV Skids mCUP 1-4 Not Started 06/09/26 06/16/26 7.5 7.5
0%
95.0
RPL06.EY.DHB.01130 RPL06.EY.DHB - Cure (High Early Mix) Foundations Not Started 06/09/26 06/15/26 8.8 8.8
0%
62.5
RPL06.EY.DHC.01020 RPL06.EY.DHC - Install Foundations - WBS Summary Foundations Not Started 06/09/26 03/03/27 228.8 228.8
0%
113.8
RPL06.EY.DHC.01610 RPL06.EY.DHC - Install F/R/P Equipment Pads - 5-10 (Grid 6-23/6-28) (12'' Larger For Tolerance) Foundations Not Started 06/09/26 06/17/26 8.8 8.8
0%
155.0
RPL06.INT.CTRC.1920 RPL06.Interior.Center-Corridor - Priority - Install Drywall at Exterior Walls Priority Walls & Overhead Not Started 06/09/26 06/15/26 6.2 6.2
0%
43.8
RPL06.INT.DHA.02380 RPL06.Interior.DHA - Priority - Install Drywall at Exterior Walls OverHead Not Started 06/09/26 06/17/26 8.8 8.8
0%
12.5
RPL06.INT.DHB.02100 RPL06.Interior.DHB - Priority - Install Mechanical Piping OverHead Not Started 06/09/26 06/29/26 18.8 18.8
0%
7.5
RPL06.INT.DHB.02320 RPL06.Interior.DHB - Priority - Install Drywall at Exterior Walls OverHead Not Started 06/09/26 06/17/26 8.8 8.8
0%
5.0
RPL06.INT.DHB.02360 RPL06.Interior.DHB - Temp Conditions - CC West Duct Work Complete for Temp Condition (LVs) Temp Conditions Not Started 06/09/26 06/10/26 2.5 2.5
0%
-3.8
RPL06.INT.SSB.06900 RPL06.Interior.SSB - Priority - (P1) Install Remaining MEP In-Wall/Backing Priority Wall - P1 Not Started 06/09/26 06/10/26 2.5 2.5
0%
182.5
RPL06.INT.SSBC.01140 RPL06.Interior.SSB-Corridor - OFE - Early Equipment (1x GS.MDF piece 2 of 2) - 6GSMDF1 (ROJ05.14.26) OFE/MOFE & CFCI Not Started 06/09/26 06/15/26 6.2 6.2
0%
101.2
RPL06.INT.SSBC.3000 RPL06.Interior.SSBC LO #06 - Close Interior LO #06 SSB/SSBC (For MDF2) WBS Summary Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 06/09/26 08/21/26 66.2 66.2
0%
127.5
RPL06.INT.SSBC.3020 RPL06.Interior.SSBC LO #06 - Install Framing at LO Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 06/09/26 06/15/26 6.2 6.2
0%
120.0
RPL06.SKN.DHAB.01060 RPL06.SKIN.DHAB - Install Security Glazing, Doors and Ext Devices Not Started 06/09/26 06/10/26 2.5 2.5
0%
246.2
RPL06.STR.DHCD.01130 RPL06.Structure.DHCD - SOG F/R/P #7 - Grid lines 6-21/6-25 (Pour-10) F/R/P Not Started 06/09/26 06/10/26 2.5 2.5
0%
12.5
RPL06.CON.WP2.09240 RPL06.Conn - GSMDF2 (North) - Install Copper, WAPs, Security Camera & Access Control ISP (MDF RPL06 <> MDF RPL06) Not Started 06/10/26 06/23/26 12.5 12.5
0%
256.2
RPL06.EY.DHB.01760 RPL06.EY.DHB - Flow Fill Cure (GL 10-17) GL 10-17 Not Started 06/10/26 06/12/26 3.8 3.8
0%
63.8
RPL06.INT.DHA.03400 RPL06.Interior.DHA - Temp Conditions - Install Early Temp Conditions Temp Conditions Not Started 06/10/26 06/11/26 2.5 2.5
0%
-7.5
RPL06.INT.DHD.01040 RPL06.Interior.DHD - Priority - Install Temp Lighting Early Priority OH MEPF Not Started 06/10/26 06/12/26 3.8 3.8
0%
135.0
RPL06.MCUP.LP1.2040 RPL06.MCUP.Loop 1 - Install Mcup Paving Hardscape and Landscape Not Started 06/10/26 06/23/26 12.5 12.5
0%
433.8
RPL06.SKN.DHAB.01130 RPL06.SKIN.DHAB - Install Roof System - Install EJ Roofing Not Started 06/10/26 06/11/26 2.5 2.5
0%
111.2
RPL06.SKN.DHCD.01110 RPL06.SKIN.DHCD - Install Roof System - Final Roof Roofing Not Started 06/10/26 06/25/26 15.0 15.0
0%
371.2
RPL.GF.D.N6100.XG GSEF #1 Infrastructure Ready RPL06 Give Milestones (XREFs) Not Started 06/11/26 06/11/26 0.0 0.0
0%
456.2
RPL.GF.D.N6110.XG GSEF #2 Infrastructure Ready RPL06 Give Milestones (XREFs) Not Started 06/11/26 06/11/26 0.0 0.0
0%
456.2
RPL06.EY.ENDC.01040 RPL06.EY.End - Install BMS UG Underground Not Started 06/11/26 06/17/26 6.2 6.2
0%
242.5
RPL06.EY.SSB.01230 RPL06.EY.SSB - Install LD F/R/P Loading Dock Walls Loading Dock Not Started 06/11/26 06/22/26 10.0 10.0
0%
197.5
RPL06.INT.CTRC.1100 RPL06.Interior.Center-Corridor - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) Priority Walls & Overhead Not Started 06/11/26 06/19/26 8.8 8.8
0%
43.8
RPL06.INT.DHB.01050 RPL06.Interior.DHB - Priority - Install FA / Linear heat detection OverHead Not Started 06/11/26 06/17/26 6.2 6.2
0%
5.0
RPL06.INT.DHB.02300 RPL06.Interior.DHB - Priority - Install Electrical OverHead Not Started 06/11/26 07/01/26 18.8 18.8
0%
5.0
RPL06.INT.SSB.06820 RPL06.Interior.SSB - Priority - (P1) Install MEP In-Wall/Backing Priority Wall - P1 Not Started 06/11/26 06/16/26 5.0 5.0
0%
176.2
RPL06.INT.SSB.06920 RPL06.Interior.SSB - Priority - (P1) Remaining Wall Hang Drywall (Both Sides) Priority Wall - P1 Not Started 06/11/26 06/15/26 3.8 3.8
0%
182.5
RPL06.SKN.DHAB.01140 RPL06.SKIN.DHAB - Install Perm Doors Glazing, Doors and Ext Devices Not Started 06/11/26 06/12/26 2.5 2.5
0%
246.2
RPL06.STR.DHCD.01140 RPL06.Structure.DHCD - SOG F/R/P #8 - Grid lines 6-25/6-28 (Pours-11&12) F/R/P Not Started 06/11/26 06/15/26 3.8 3.8
0%
77.5
RPL06.CON.WP2.07240 RPL06.Conn - Ext. GSIDF6X01 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 06/12/26 06/19/26 7.5 7.5
0%
446.2
RPL06.CON.WP2.07440 RPL06.Conn - Ext. GSIDF6X02 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 06/12/26 06/19/26 7.5 7.5
0%
446.2
RPL06.CON.WP2.08420 RPL06.Conn - Ext. GSIDF6X03 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 06/12/26 06/19/26 7.5 7.5
0%
446.2
RPL06.CON.WP2.09300 RPL06.Conn - GS EF1 (South)<>GSMDF2 (North) Install Cabling (Pull, Splice & Terminate) Cabling Not Started 06/12/26 06/17/26 5.0 5.0
0%
381.2
RPL06.EY.SSB.02040 RPL06.EY.SSB - Install Temp Duct to Permanent Duct Temp Conditions Not Started 06/12/26 06/18/26 6.2 6.2
0%
-11.2
RPL06.INT.DHA.03420 RPL06.Interior.DHA - Temp Conditions - CC West Duct Work Complete for Temp Condition (LVs) Temp Conditions Not Started 06/12/26 06/15/26 2.5 2.5
0%
-7.5
RPL06.INT.DHD.01010 RPL06.Interior.DHD - Priority - Install Duct (IFP Accleration) Early Priority OH MEPF Not Started 06/12/26 06/17/26 5.0 5.0
0%
186.2
RPL06.MCUP.LP2.2060 RPL06.MCUP.Loop 2 - Tie-in - Electrical L2 Checklist Completion Tie-ins Not Started 06/12/26 06/18/26 6.2 6.2
0%
193.8
RPL06.STR.DHAB.01260 RPL06.Structure.DHAB - Install SOG Sealer and Cure F/R/P Not Started 06/13/26 06/14/26 2.5 2.5
0%
12.5
RPL06.EY.DHB.01700 RPL06.EY.DHB - Install F/R/P Equipment Pads - 7-12(Grid 6-09/6-16) (12'' Larger For Tolerance) Foundations Not Started 06/15/26 06/26/26 12.5 12.5
0%
42.5
RPL06.INT.DHA.01080 RPL06.Interior.DHA - OFE - WBS Summary OFE/MOFE & CFCI Not Started 06/15/26 11/19/26 138.8 138.8
0%
8.8
RPL06.INT.DHA.03980 RPL06.Interior.DHA - CFCI - Pre Set 16"" FW Pipe OFE/MOFE & CFCI Not Started 06/15/26 06/26/26 12.5 12.5
0%
77.5
RPL06.INT.DHB.01100 RPL06.Interior.DHB - Priority - Install Temp Doors Frame Hardware OverHead Not Started 06/15/26 06/17/26 3.8 3.8
0%
5.0
RPL06.INT.DHB.01160 RPL06.Interior.DHB - OFE - WBS Summary OFE/MOFE & CFCI Not Started 06/15/26 11/04/26 126.2 126.2
0%
17.5
RPL06.INT.DHB.02900 RPL06.Interior.DHB - CFCI - Pre Set 16"" FW Pipe OFE/MOFE & CFCI Not Started 06/15/26 06/26/26 12.5 12.5
0%
77.5
RPL06.INT.DHC.01040 RPL06.Interior.DHC - Priority - Install Temp Lighting Early Priority OH MEPF Not Started 06/15/26 06/17/26 3.8 3.8
0%
135.0
RPL06.INT.DHD.01030 RPL06.Interior.DHD - Priority - Install Fire Sprinkler (IFP Accleration) Early Priority OH MEPF Not Started 06/15/26 06/19/26 6.2 6.2
0%
192.5
RPL06.CFCI.4950 Campus - Submittals Prep & Submit for Review - Landscaping / Irrigation (CFCI) Div. 32 - Landscape/ Irrigation Not Started 06/16/26 07/07/26 18.8 18.8
0%
297.5
RPL06.CFCI.5100 Campus - Submittal Review & Approval - Asphalt / Paving (CFCI) Div. 32 - Asphalt/ Conc. Paving Not Started 06/16/26 07/14/26 25.0 25.0
0%
178.8
RPL06.CON.WP2.05000 RPL06.Conn - GSMDF1 (South) - WBS Summary GS.MDF1 (South) (Includes IDF) Not Started 06/16/26 10/28/26 118.8 118.8
0%
272.5
RPL06.CON.WP2.07960 RPL06.Conn - GSMDF1 (South) Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Not Started 06/16/26 06/16/26 1.2 1.2
0%
262.5
RPL06.CON.WP4.00010 RPL06.Conn - Network - WBS Summary WP#4 Network Not Started 06/16/26 09/14/27 391.2 391.2
0%
62.5