Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
2
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL06.EY.ENDC.1390 |
RPL06.EY.DHD.T1 - Install Tent Electrical Panels | Tent 1 | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
6.2 |
RPL06.EY.ENDC.1410 |
RPL06.EY.DHD.T1 - Install Tent Heating and Cooling Equipment | Tent 1 | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
2.5 |
RPL06.EY.ENDC.1430 |
RPL06.EY.DHD.T1 - Install Tent Overhead Doors | Tent 1 | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
10.0 |
RPL06.EY.ENDC.1450 |
RPL06.EY.DHD.T1 - Install Tent Fit-out | Tent 1 | Not Started | 06/16/26 | 06/29/26 | 12.5 | 12.5 |
|
3.8 |
RPL06.INT.SSB.01140 |
RPL06.Interior.SSB - Loading Dock and Storage - Frame Walls | Loading Dock and Storage | Not Started | 06/16/26 | 06/25/26 | 10.0 | 10.0 |
|
150.0 |
RPL06.INT.SSB.01170 |
RPL06.Interior.SSB - Loading Dock and Storage - WBS Summary | Loading Dock and Storage | Not Started | 06/16/26 | 11/13/26 | 132.5 | 132.5 |
|
138.8 |
RPL06.INT.SSB.01660 |
RPL06.Interior.SSB - Priority - Install Plumbing (Highside OH space) | Priority Walls and OverHead | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
70.0 |
RPL06.INT.SSB.01680 |
RPL06.Interior.SSB - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) | Priority Walls and OverHead | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
63.8 |
RPL06.INT.SSB.03200 |
RPL06.Interior.SSB - Priority - Install Fire Alarm hangers & members (Highside OH space) | Priority Walls and OverHead | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
251.2 |
RPL06.INT.SSB.06940 |
RPL06.Interior.SSB - Priority - (P1) Remaining Wall Tape Finish Paint (Both Sides) | Priority Wall - P1 | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
182.5 |
RPL06.INT.SSBC.3080 |
RPL06.Interior.SSBC LO #06 - Install Mechanical Piping Lowside OH and in-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 06/16/26 | 06/17/26 | 2.5 | 2.5 |
|
120.0 |
RPL06.INT.SSBC.4000 |
RPL06.Interior.SSBC LO #07 - Close Interior LO #07 SSB/SSBC (For MDF1) WBS Summary | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 06/16/26 | 08/28/26 | 66.2 | 66.2 |
|
121.2 |
RPL06.INT.SSBC.4020 |
RPL06.Interior.SSBC LO #07 - Install Framing at LO | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
113.8 |
RPL06.STR.DHCD.01150 |
RPL06.Structure.DHCD - Zone SOG Cure | F/R/P | Not Started | 06/16/26 | 06/22/26 | 8.8 | 8.8 |
|
111.2 |
RPL06.WP4.010000 |
RPL06.Conn GSMDF1 Pull Fanout (5F) [PON (Active, In-Row)] | GSMDF1 | Not Started | 06/16/26 | 06/16/26 | 1.2 | 1.2 |
|
251.2 |
RPL06.CON.WP2.07900 |
RPL06.Conn -MDF1<>MDF2 Install Cabling (Pull, Splice & Terminate) | ISP (MDF RPL06 <> MDF RPL06) | Not Started | 06/17/26 | 06/22/26 | 5.0 | 5.0 |
|
365.0 |
RPL06.CON.WP2.07980 |
RPL06.Conn - MDF1<>MDF2 Install Cabling (Pull, Splice & Terminate) | ISP (MDF RPL06 <> MDF RPL06) | Not Started | 06/17/26 | 06/22/26 | 5.0 | 5.0 |
|
376.2 |
RPL06.CON.WP2.09260 |
RPL06.Conn - GSMDF1 (South) - Install Copper, WAPs, Security Camera & Access Control | ISP (MDF RPL06 <> MDF RPL06) | Not Started | 06/17/26 | 06/30/26 | 12.5 | 12.5 |
|
262.5 |
RPL06.CON.WP2.09320 |
RPL06.Conn - GS EF2 (North)<>GSMDF1 (South) Install Cabling (Pull, Splice & Terminate) | Cabling | Not Started | 06/17/26 | 06/19/26 | 3.8 | 3.8 |
|
377.5 |
RPL06.CX.MCUP.01040 |
RPL06.CX.mCup Loop 1 - L3/L4 - mCUP - FWM | mCUP 1-4 | Not Started | 06/17/26 | 06/30/26 | 12.5 | 12.5 |
|
100.0 |
RPL06.INT.SSB.06840 |
RPL06.Interior.SSB - Priority - (P1) Hang Drywall (Both Sides) | Priority Wall - P1 | Not Started | 06/17/26 | 06/22/26 | 5.0 | 5.0 |
|
176.2 |
RPL06.MCUP.LP2.2080 |
RPL06.MCUP.Loop 2 - Tie-in - Mechanical L2 Checklist Completion | Tie-ins | Not Started | 06/17/26 | 06/23/26 | 6.2 | 6.2 |
|
188.8 |
RPL06.WP4.010020 |
RPL06.Conn GSMDF2 Pull Fanout (5F) [PON (Active, In-Row)] | GSMDF2 | Not Started | 06/17/26 | 06/17/26 | 1.2 | 1.2 |
|
251.2 |
RPL06.WP4.010040 |
RPL06.Conn GSMDF1 Install Fanout (5F) [PON (Active, In-Row)] | GSMDF1 | Not Started | 06/17/26 | 07/01/26 | 13.8 | 13.8 |
|
252.5 |
RPL06.CON.WP2.09360 |
RPL06.Conn - GS EF1 (South) Test Network (FIM) | Network | Not Started | 06/18/26 | 06/23/26 | 5.0 | 5.0 |
|
383.8 |
RPL06.EY.DHC.01630 |
RPL06.EY.DHC - Cure (High Early Mix) | Foundations | Not Started | 06/18/26 | 06/24/26 | 8.8 | 8.8 |
|
266.2 |
RPL06.EY.ENDC.1690 |
RPL06.EY.DHD.T2 - Install Tent Electrical Panels | Tent 2 | Not Started | 06/18/26 | 06/24/26 | 6.2 | 6.2 |
|
11.2 |
RPL06.EY.ENDC.1710 |
RPL06.EY.DHD.T2 - Install Tent Heating and Cooling Equipment | Tent 2 | Not Started | 06/18/26 | 06/24/26 | 6.2 | 6.2 |
|
7.5 |
RPL06.EY.ENDC.1730 |
RPL06.EY.DHD.T2 - Install Tent Overhead Doors | Tent 2 | Not Started | 06/18/26 | 06/24/26 | 6.2 | 6.2 |
|
15.0 |
RPL06.EY.ENDC.1750 |
RPL06.EY.DHD.T2 - Install Tent Fit-out | Tent 2 | Not Started | 06/18/26 | 07/01/26 | 12.5 | 12.5 |
|
8.8 |
RPL06.INT.DHA.01050 |
RPL06.Interior.DHA - Priority - Install FA / Linear heat detection | OverHead | Not Started | 06/18/26 | 06/24/26 | 6.2 | 6.2 |
|
12.5 |
RPL06.INT.DHA.02140 |
RPL06.Interior.DHA - Priority - Install Plumbing | OverHead | Not Started | 06/18/26 | 06/24/26 | 6.2 | 6.2 |
|
12.5 |
RPL06.INT.DHB.01120 |
RPL06.Interior.DHB - Priority - Install Security | OverHead | Not Started | 06/18/26 | 06/24/26 | 6.2 | 6.2 |
|
5.0 |
RPL06.INT.DHC.01010 |
RPL06.Interior.DHC - Priority - Install Duct (IFP Accleration) | Early Priority OH MEPF | Not Started | 06/18/26 | 06/23/26 | 5.0 | 5.0 |
|
181.2 |
RPL06.INT.ENDC.1060 |
RPL06.Interior.End-Corridor - Priority - Install Temp Lighting (Show In Model) | Early Priority OH MEPF | Not Started | 06/18/26 | 06/22/26 | 3.8 | 3.8 |
|
135.0 |
RPL06.INT.SSBC.3100 |
RPL06.Interior.SSBC LO #06 - Install Fire Life Safety Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 06/18/26 | 06/19/26 | 2.5 | 2.5 |
|
123.8 |
RPL06.INT.SSBC.3120 |
RPL06.Interior.SSBC LO #06 - Install Plumbing Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 06/18/26 | 06/19/26 | 2.5 | 2.5 |
|
120.0 |
RPL06.SKN.E.01040 |
RPL06.SKIN.East - Secure All Exterior Mounted Boxes and Devices on Skin | IMP System | Not Started | 06/18/26 | 07/01/26 | 12.5 | 12.5 |
|
295.0 |
RPL06.WP4.010060 |
RPL06.Conn GSMDF2 Install Fanout (5F) [PON (Active, In-Row)] | GSMDF2 | Not Started | 06/18/26 | 07/02/26 | 13.8 | 13.8 |
|
251.2 |
RPL06.Conn.MS.01220 |
CorpNet FacNet Available (mCUP) | Connectivity Milestones | Not Started | 06/19/26 | 06/19/26 | 0.0 | 0.0 |
|
448.8 |
RPL06.EY.SSB.01175 |
RPL06.EY.SSB - Install Mechanical/refrigerantTie-ins | Tie-ins | Not Started | 06/19/26 | 07/02/26 | 12.5 | 12.5 |
|
67.5 |
RPL06.EY.SSB.01180 |
RPL06.EY.SSB - Tie-ins - WBS Summary | Tie-ins | Not Started | 06/19/26 | 08/14/26 | 50.0 | 50.0 |
|
42.5 |
RPL06.EY.SSB.01400 |
RPL06.EY.SSB - Install Duct/ insulation into the building Main (include penetration detail) | Tie-ins | Not Started | 06/19/26 | 07/10/26 | 18.8 | 18.8 |
|
42.5 |
RPL06.INT.DHA.03460 |
RPL06.Interior.DHA - Temp Conditions - Temp Conditioning Achieved & Acclimated for West of CC (SSB/DHB/DHA) | Temp Conditions | Not Started | 06/19/26 | 06/25/26 | 6.2 | 6.2 |
|
-11.2 |
RPL06.INT.DHD.01000 |
RPL06.Interior.DHD - Priority OH - WBS Summary | OverHead | Not Started | 06/19/26 | 08/21/26 | 56.2 | 56.2 |
|
310.0 |
RPL06.INT.DHD.01020 |
RPL06.Interior.DHD - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHD | Not Started | 06/19/26 | 02/18/27 | 207.5 | 207.5 |
|
158.8 |
RPL06.INT.DHD.01980 |
RPL06.Interior.DHD - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall | OverHead | Not Started | 06/19/26 | 06/25/26 | 6.2 | 6.2 |
|
80.0 |
RPL06.INT.DHD.02250 |
RPL06.Interior.DHD - Priority - Install IMP Exterior Inwall Rough-In | OverHead | Not Started | 06/19/26 | 06/25/26 | 6.2 | 6.2 |
|
80.0 |
RPL06.MCUP.LP2.1520 |
RPL06.MCUP.Loop 2 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 06/19/26 | 08/12/26 | 47.5 | 47.5 |
|
402.5 |
RPL06.MCUP.LP2.1540 |
RPL06.MCUP.Loop 2 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 06/19/26 | 06/23/26 | 3.8 | 3.8 |
|
402.5 |
RPL06.CON.WP2.07280 |
RPL06.Conn - Ext. GSIDF6X01 - Install & Test Network (FIM) | Network | Not Started | 06/22/26 | 06/23/26 | 2.5 | 2.5 |
|
446.2 |
RPL06.CON.WP2.07480 |
RPL06.Conn - Ext. GSIDF6X02 - Install & Test Network (FIM) | Network | Not Started | 06/22/26 | 06/23/26 | 2.5 | 2.5 |
|
446.2 |
RPL06.CON.WP2.08440 |
RPL06.Conn - Ext. GSIDF6X03 - Install & Test Network (FIM) | Network | Not Started | 06/22/26 | 06/23/26 | 2.5 | 2.5 |
|
446.2 |
RPL06.CON.WP2.09340 |
RPL06.Conn - GS EF2 (North) Test Network (FIM) | Network | Not Started | 06/22/26 | 06/25/26 | 5.0 | 5.0 |
|
377.5 |
RPL06.INT.CTRC.1160 |
RPL06.Interior.Center-Corr - Priority GL6.16/6.17 - (P2) Frame Walls (Incl. Entry Fiber Rooms #3.7, Ancillary Room #3.6) | Priority Wall Grid Line 6-16 / 6-17 | Not Started | 06/22/26 | 06/30/26 | 8.8 | 8.8 |
|
43.8 |
RPL06.INT.DHC.01030 |
RPL06.Interior.DHC - Priority - Install Fire Sprinkler (IFP Accleration) | Early Priority OH MEPF | Not Started | 06/22/26 | 06/26/26 | 6.2 | 6.2 |
|
192.5 |
RPL06.INT.SSBC.3140 |
RPL06.Interior.SSBC LO #06 - Install Security Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 06/22/26 | 06/23/26 | 2.5 | 2.5 |
|
123.8 |
RPL06.INT.SSBC.3160 |
RPL06.Interior.SSBC LO #06 - Install Controls / EPMS / BMS OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 06/22/26 | 06/23/26 | 2.5 | 2.5 |
|
120.0 |
RPL06.CON.WP2.09380 |
RPL06.Conn Misc P/S/T and R/S/P @ MDF2 | ISP (MDF RPL06 <> MDF RPL06) | Not Started | 06/23/26 | 07/07/26 | 12.5 | 12.5 |
|
365.0 |
RPL06.CON.WP2.09400 |
RPL06.Conn Misc P/S/T and R/S/P @ MDF1 | ISP (MDF RPL06 <> MDF RPL06) | Not Started | 06/23/26 | 06/26/26 | 5.0 | 5.0 |
|
376.2 |
RPL06.EY.DHA.01130 |
RPL06.EY.DHA - Cure (High Early Mix) | Foundations | Not Started | 06/23/26 | 06/29/26 | 8.8 | 8.8 |
|
71.2 |
RPL06.EY.DHC.01010 |
RPL06.EY.DHC - Install F/R/P Equipment Pads - 1-5 (Grid 6-17/6-23) (12'' Larger For Tolerance) | Foundations | Not Started | 06/23/26 | 07/02/26 | 10.0 | 10.0 |
|
151.2 |
RPL06.EY.ENDC.1470 |
RPL06.EY.DHD.T1 - Install Tent Electrical Tie-ins | Tent 1 | Not Started | 06/23/26 | 06/25/26 | 3.8 | 3.8 |
|
6.2 |
RPL06.EY.ENDC.1490 |
RPL06.EY.DHD.T1 - Install Tent Mechanical Tie-ins | Tent 1 | Not Started | 06/23/26 | 06/30/26 | 7.5 | 7.5 |
|
2.5 |
RPL06.INT.ENDC.01020 |
RPL06.Interior.End-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary | End Corridor | Not Started | 06/23/26 | 05/12/27 | 277.5 | 277.5 |
|
98.8 |
RPL06.INT.ENDC.03480 |
RPL06.Interior.End-Cor - Priority - WBS Summary | Priority Walls & Overhead | Not Started | 06/23/26 | 07/30/26 | 33.8 | 33.8 |
|
140.0 |
RPL06.INT.ENDC.1020 |
RPL06.Interior.End-Cor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket | Priority Walls & Overhead | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
131.2 |
RPL06.INT.SSB.03220 |
RPL06.Interior.SSB - Priority - Install Fire Safing/ Seal all Penetrations through Soffit (Highside OH space) | Priority Walls and OverHead | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
123.8 |
RPL06.INT.SSB.06860 |
RPL06.Interior.SSB - Priority - (P1) Tape Finish Paint (Both Sides) | Priority Wall - P1 | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
176.2 |
RPL06.INT.SSBC.02180 |
RPL06.Interior.SSBC - Priority - Install Plumbing (Highside OH space) | Priority Walls & Overhead | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
70.0 |
RPL06.INT.SSBC.02200 |
RPL06.Interior.SSBC - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) | Priority Walls & Overhead | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
63.8 |
RPL06.INT.SSBC.03300 |
RPL06.Interior.SSBC - Priority - Install FA/ VESDA/ hangers & Heat Trace (Highside OH space) | Priority Walls & Overhead | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
70.0 |
RPL06.INT.SSBC.4080 |
RPL06.Interior.SSBC LO #07 - Install Mechanical Piping Lowside OH and in-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 06/23/26 | 06/24/26 | 2.5 | 2.5 |
|
113.8 |
RPL06.STR.DHCD.01210 |
RPL06.Structure.DHCD - Moisture requirements for floor Sealer | F/R/P | Not Started | 06/23/26 | 06/29/26 | 8.8 | 8.8 |
|
111.2 |
GCD.RPL06.3985 |
MCUP Ready for Energization - (MCUPs Loop 2) | mCup | Not Started | 06/24/26 | 06/24/26 | 0.0 | 0.0 |
|
327.5 |
RPL06.CX.MCUP.01020 |
RPL06.CX.mCup Loop 2 - L3, L4, IST - WBS Summary | mCUP 5-6 | Not Started | 06/24/26 | 11/25/26 | 135.0 | 135.0 |
|
238.8 |
RPL06.CX.MCUP.01030 |
RPL06.CX.mCup Loop 2 - L3/L4 - MV Skids | mCUP 5-6 | Not Started | 06/24/26 | 06/29/26 | 5.0 | 5.0 |
|
190.0 |
RPL06.INT.ENDC.1180 |
RPL06.Interior.End-Corridor - Priority - Install Duct (Highside OH space) (IFP Accleration) | Early Priority OH MEPF | Not Started | 06/24/26 | 07/02/26 | 8.8 | 8.8 |
|
181.2 |
RPL06.INT.SSBC.3240 |
RPL06.Interior.SSBC LO #06 - Install Electrical Lowside OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 06/24/26 | 06/26/26 | 3.8 | 3.8 |
|
120.0 |
RPL06.MCUP.LP1.2100 |
RPL06.MCUP.Loop 1 - Install Exterior Signage | Hardscape and Landscape | Not Started | 06/24/26 | 07/08/26 | 12.5 | 12.5 |
|
433.8 |
RPL06.MCUP.LP2.1640 |
RPL06.MCUP.Loop 2 - Install Early Mcup Paving | Hardscape and Landscape | Not Started | 06/24/26 | 07/08/26 | 12.5 | 12.5 |
|
402.5 |
RPL06.EY.ENDC.1770 |
RPL06.EY.DHD.T2 - Install Tent Electrical Tie-ins | Tent 2 | Not Started | 06/25/26 | 06/29/26 | 3.8 | 3.8 |
|
11.2 |
RPL06.EY.ENDC.1790 |
RPL06.EY.DHD.T2 - Install Tent Mechanical Tie-ins | Tent 2 | Not Started | 06/25/26 | 07/02/26 | 7.5 | 7.5 |
|
7.5 |
RPL06.INT.DHA.02360 |
RPL06.Interior.DHA - Priority - Install Temp Doors Frame Hardware | OverHead | Not Started | 06/25/26 | 06/29/26 | 3.8 | 3.8 |
|
262.5 |
RPL06.INT.DHB.01130 |
RPL06.Interior.DHB - Priority - Install Controls / EPMS / BMS | OverHead | Not Started | 06/25/26 | 06/30/26 | 5.0 | 5.0 |
|
5.0 |
RPL06.INT.ENDC.6060 |
RPL06.Interior.End-Cor - Priority - Install IMP Exterior Inwall Rough-In | Priority Walls & Overhead | Not Started | 06/25/26 | 06/29/26 | 3.8 | 3.8 |
|
137.5 |
RPL06.INT.SSBC.4100 |
RPL06.Interior.SSBC LO #07 - Install Fire Life Safety Lowside OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 06/25/26 | 06/26/26 | 2.5 | 2.5 |
|
117.5 |
RPL06.INT.SSBC.4120 |
RPL06.Interior.SSBC LO #07 - Install Plumbing Lowside OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 06/25/26 | 06/26/26 | 2.5 | 2.5 |
|
113.8 |
RPL06.EY.SSB.01160 |
RPL06.EY.SSB - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 06/26/26 | 07/24/26 | 25.0 | 25.0 |
|
48.8 |
RPL06.INT.DHC.01000 |
RPL06.Interior.DHC - Priority OH - WBS Summary | OverHead | Not Started | 06/26/26 | 09/11/26 | 67.5 | 67.5 |
|
305.0 |
RPL06.INT.DHC.01020 |
RPL06.Interior.DHC - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary | DHC | Not Started | 06/26/26 | 03/04/27 | 213.8 | 213.8 |
|
158.8 |
RPL06.INT.DHC.01980 |
RPL06.Interior.DHC - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall | OverHead | Not Started | 06/26/26 | 07/02/26 | 6.2 | 6.2 |
|
335.0 |
RPL06.INT.DHC.02250 |
RPL06.Interior.DHC - Priority - Install IMP Exterior Inwall Rough-In | OverHead | Not Started | 06/26/26 | 07/02/26 | 6.2 | 6.2 |
|
335.0 |
RPL06.INT.DHD.02230 |
RPL06.Interior.DHD - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 06/26/26 | 07/02/26 | 6.2 | 6.2 |
|
80.0 |
RPL06.INT.SSB.01510 |
RPL06.Interior.SSB - Loading Dock and Storage - Install Door Frames | Loading Dock and Storage | Not Started | 06/26/26 | 07/02/26 | 6.2 | 6.2 |
|
150.0 |
RPL06.INT.SSB.02900 |
RPL06.Interior.SSB - Loading Dock and Storage - Pre Priority OH & Walls Tasks (Unistruts,Hangers,Track) | Loading Dock and Storage | Not Started | 06/26/26 | 07/02/26 | 6.2 | 6.2 |
|
185.0 |
RPL06.WA.OFE.01000 |
RPL06.WA - Weather Allowance - FDN to OFE | Weather Allowance | Not Started | 06/26/26 | 07/07/26 | 15.0 | 15.0 |
|
-16.2 |
RPL06.EY.DHB.01720 |
RPL06.EY.DHB - Cure (High Early Mix) | Foundations | Not Started | 06/27/26 | 07/03/26 | 8.8 | 8.8 |
|
62.5 |
RPL06.EY.DHD.01010 |
RPL06.EY.DHD - Install F/R/P Equipment Pads - 1-5 (Grid 6-17/6-23) (12'' Larger For Tolerance) | Foundations | Not Started | 06/29/26 | 07/09/26 | 10.0 | 10.0 |
|
122.5 |
RPL06.EY.DHD.01020 |
RPL06.EY.DHD - Install Foundations - WBS Summary | Foundations | Not Started | 06/29/26 | 03/01/27 | 208.8 | 208.8 |
|
103.8 |