Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
2
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.EY.ENDC.1390 RPL06.EY.DHD.T1 - Install Tent Electrical Panels Tent 1 Not Started 06/16/26 06/22/26 6.2 6.2
0%
6.2
RPL06.EY.ENDC.1410 RPL06.EY.DHD.T1 - Install Tent Heating and Cooling Equipment Tent 1 Not Started 06/16/26 06/22/26 6.2 6.2
0%
2.5
RPL06.EY.ENDC.1430 RPL06.EY.DHD.T1 - Install Tent Overhead Doors Tent 1 Not Started 06/16/26 06/22/26 6.2 6.2
0%
10.0
RPL06.EY.ENDC.1450 RPL06.EY.DHD.T1 - Install Tent Fit-out Tent 1 Not Started 06/16/26 06/29/26 12.5 12.5
0%
3.8
RPL06.INT.SSB.01140 RPL06.Interior.SSB - Loading Dock and Storage - Frame Walls Loading Dock and Storage Not Started 06/16/26 06/25/26 10.0 10.0
0%
150.0
RPL06.INT.SSB.01170 RPL06.Interior.SSB - Loading Dock and Storage - WBS Summary Loading Dock and Storage Not Started 06/16/26 11/13/26 132.5 132.5
0%
138.8
RPL06.INT.SSB.01660 RPL06.Interior.SSB - Priority - Install Plumbing (Highside OH space) Priority Walls and OverHead Not Started 06/16/26 06/22/26 6.2 6.2
0%
70.0
RPL06.INT.SSB.01680 RPL06.Interior.SSB - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) Priority Walls and OverHead Not Started 06/16/26 06/22/26 6.2 6.2
0%
63.8
RPL06.INT.SSB.03200 RPL06.Interior.SSB - Priority - Install Fire Alarm hangers & members (Highside OH space) Priority Walls and OverHead Not Started 06/16/26 06/22/26 6.2 6.2
0%
251.2
RPL06.INT.SSB.06940 RPL06.Interior.SSB - Priority - (P1) Remaining Wall Tape Finish Paint (Both Sides) Priority Wall - P1 Not Started 06/16/26 06/22/26 6.2 6.2
0%
182.5
RPL06.INT.SSBC.3080 RPL06.Interior.SSBC LO #06 - Install Mechanical Piping Lowside OH and in-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 06/16/26 06/17/26 2.5 2.5
0%
120.0
RPL06.INT.SSBC.4000 RPL06.Interior.SSBC LO #07 - Close Interior LO #07 SSB/SSBC (For MDF1) WBS Summary Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 06/16/26 08/28/26 66.2 66.2
0%
121.2
RPL06.INT.SSBC.4020 RPL06.Interior.SSBC LO #07 - Install Framing at LO Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 06/16/26 06/22/26 6.2 6.2
0%
113.8
RPL06.STR.DHCD.01150 RPL06.Structure.DHCD - Zone SOG Cure F/R/P Not Started 06/16/26 06/22/26 8.8 8.8
0%
111.2
RPL06.WP4.010000 RPL06.Conn GSMDF1 Pull Fanout (5F) [PON (Active, In-Row)] GSMDF1 Not Started 06/16/26 06/16/26 1.2 1.2
0%
251.2
RPL06.CON.WP2.07900 RPL06.Conn -MDF1<>MDF2 Install Cabling (Pull, Splice & Terminate) ISP (MDF RPL06 <> MDF RPL06) Not Started 06/17/26 06/22/26 5.0 5.0
0%
365.0
RPL06.CON.WP2.07980 RPL06.Conn - MDF1<>MDF2 Install Cabling (Pull, Splice & Terminate) ISP (MDF RPL06 <> MDF RPL06) Not Started 06/17/26 06/22/26 5.0 5.0
0%
376.2
RPL06.CON.WP2.09260 RPL06.Conn - GSMDF1 (South) - Install Copper, WAPs, Security Camera & Access Control ISP (MDF RPL06 <> MDF RPL06) Not Started 06/17/26 06/30/26 12.5 12.5
0%
262.5
RPL06.CON.WP2.09320 RPL06.Conn - GS EF2 (North)<>GSMDF1 (South) Install Cabling (Pull, Splice & Terminate) Cabling Not Started 06/17/26 06/19/26 3.8 3.8
0%
377.5
RPL06.CX.MCUP.01040 RPL06.CX.mCup Loop 1 - L3/L4 - mCUP - FWM mCUP 1-4 Not Started 06/17/26 06/30/26 12.5 12.5
0%
100.0
RPL06.INT.SSB.06840 RPL06.Interior.SSB - Priority - (P1) Hang Drywall (Both Sides) Priority Wall - P1 Not Started 06/17/26 06/22/26 5.0 5.0
0%
176.2
RPL06.MCUP.LP2.2080 RPL06.MCUP.Loop 2 - Tie-in - Mechanical L2 Checklist Completion Tie-ins Not Started 06/17/26 06/23/26 6.2 6.2
0%
188.8
RPL06.WP4.010020 RPL06.Conn GSMDF2 Pull Fanout (5F) [PON (Active, In-Row)] GSMDF2 Not Started 06/17/26 06/17/26 1.2 1.2
0%
251.2
RPL06.WP4.010040 RPL06.Conn GSMDF1 Install Fanout (5F) [PON (Active, In-Row)] GSMDF1 Not Started 06/17/26 07/01/26 13.8 13.8
0%
252.5
RPL06.CON.WP2.09360 RPL06.Conn - GS EF1 (South) Test Network (FIM) Network Not Started 06/18/26 06/23/26 5.0 5.0
0%
383.8
RPL06.EY.DHC.01630 RPL06.EY.DHC - Cure (High Early Mix) Foundations Not Started 06/18/26 06/24/26 8.8 8.8
0%
266.2
RPL06.EY.ENDC.1690 RPL06.EY.DHD.T2 - Install Tent Electrical Panels Tent 2 Not Started 06/18/26 06/24/26 6.2 6.2
0%
11.2
RPL06.EY.ENDC.1710 RPL06.EY.DHD.T2 - Install Tent Heating and Cooling Equipment Tent 2 Not Started 06/18/26 06/24/26 6.2 6.2
0%
7.5
RPL06.EY.ENDC.1730 RPL06.EY.DHD.T2 - Install Tent Overhead Doors Tent 2 Not Started 06/18/26 06/24/26 6.2 6.2
0%
15.0
RPL06.EY.ENDC.1750 RPL06.EY.DHD.T2 - Install Tent Fit-out Tent 2 Not Started 06/18/26 07/01/26 12.5 12.5
0%
8.8
RPL06.INT.DHA.01050 RPL06.Interior.DHA - Priority - Install FA / Linear heat detection OverHead Not Started 06/18/26 06/24/26 6.2 6.2
0%
12.5
RPL06.INT.DHA.02140 RPL06.Interior.DHA - Priority - Install Plumbing OverHead Not Started 06/18/26 06/24/26 6.2 6.2
0%
12.5
RPL06.INT.DHB.01120 RPL06.Interior.DHB - Priority - Install Security OverHead Not Started 06/18/26 06/24/26 6.2 6.2
0%
5.0
RPL06.INT.DHC.01010 RPL06.Interior.DHC - Priority - Install Duct (IFP Accleration) Early Priority OH MEPF Not Started 06/18/26 06/23/26 5.0 5.0
0%
181.2
RPL06.INT.ENDC.1060 RPL06.Interior.End-Corridor - Priority - Install Temp Lighting (Show In Model) Early Priority OH MEPF Not Started 06/18/26 06/22/26 3.8 3.8
0%
135.0
RPL06.INT.SSBC.3100 RPL06.Interior.SSBC LO #06 - Install Fire Life Safety Lowside OH and In-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 06/18/26 06/19/26 2.5 2.5
0%
123.8
RPL06.INT.SSBC.3120 RPL06.Interior.SSBC LO #06 - Install Plumbing Lowside OH and In-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 06/18/26 06/19/26 2.5 2.5
0%
120.0
RPL06.SKN.E.01040 RPL06.SKIN.East - Secure All Exterior Mounted Boxes and Devices on Skin IMP System Not Started 06/18/26 07/01/26 12.5 12.5
0%
295.0
RPL06.WP4.010060 RPL06.Conn GSMDF2 Install Fanout (5F) [PON (Active, In-Row)] GSMDF2 Not Started 06/18/26 07/02/26 13.8 13.8
0%
251.2
RPL06.Conn.MS.01220 CorpNet FacNet Available (mCUP) Connectivity Milestones Not Started 06/19/26 06/19/26 0.0 0.0
0%
448.8
RPL06.EY.SSB.01175 RPL06.EY.SSB - Install Mechanical/refrigerantTie-ins Tie-ins Not Started 06/19/26 07/02/26 12.5 12.5
0%
67.5
RPL06.EY.SSB.01180 RPL06.EY.SSB - Tie-ins - WBS Summary Tie-ins Not Started 06/19/26 08/14/26 50.0 50.0
0%
42.5
RPL06.EY.SSB.01400 RPL06.EY.SSB - Install Duct/ insulation into the building Main (include penetration detail) Tie-ins Not Started 06/19/26 07/10/26 18.8 18.8
0%
42.5
RPL06.INT.DHA.03460 RPL06.Interior.DHA - Temp Conditions - Temp Conditioning Achieved & Acclimated for West of CC (SSB/DHB/DHA) Temp Conditions Not Started 06/19/26 06/25/26 6.2 6.2
0%
-11.2
RPL06.INT.DHD.01000 RPL06.Interior.DHD - Priority OH - WBS Summary OverHead Not Started 06/19/26 08/21/26 56.2 56.2
0%
310.0
RPL06.INT.DHD.01020 RPL06.Interior.DHD - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary DHD Not Started 06/19/26 02/18/27 207.5 207.5
0%
158.8
RPL06.INT.DHD.01980 RPL06.Interior.DHD - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall OverHead Not Started 06/19/26 06/25/26 6.2 6.2
0%
80.0
RPL06.INT.DHD.02250 RPL06.Interior.DHD - Priority - Install IMP Exterior Inwall Rough-In OverHead Not Started 06/19/26 06/25/26 6.2 6.2
0%
80.0
RPL06.MCUP.LP2.1520 RPL06.MCUP.Loop 2 - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 06/19/26 08/12/26 47.5 47.5
0%
402.5
RPL06.MCUP.LP2.1540 RPL06.MCUP.Loop 2 - Install Sleeves MEPL Hardscape and Landscape Not Started 06/19/26 06/23/26 3.8 3.8
0%
402.5
RPL06.CON.WP2.07280 RPL06.Conn - Ext. GSIDF6X01 - Install & Test Network (FIM) Network Not Started 06/22/26 06/23/26 2.5 2.5
0%
446.2
RPL06.CON.WP2.07480 RPL06.Conn - Ext. GSIDF6X02 - Install & Test Network (FIM) Network Not Started 06/22/26 06/23/26 2.5 2.5
0%
446.2
RPL06.CON.WP2.08440 RPL06.Conn - Ext. GSIDF6X03 - Install & Test Network (FIM) Network Not Started 06/22/26 06/23/26 2.5 2.5
0%
446.2
RPL06.CON.WP2.09340 RPL06.Conn - GS EF2 (North) Test Network (FIM) Network Not Started 06/22/26 06/25/26 5.0 5.0
0%
377.5
RPL06.INT.CTRC.1160 RPL06.Interior.Center-Corr - Priority GL6.16/6.17 - (P2) Frame Walls (Incl. Entry Fiber Rooms #3.7, Ancillary Room #3.6) Priority Wall Grid Line 6-16 / 6-17 Not Started 06/22/26 06/30/26 8.8 8.8
0%
43.8
RPL06.INT.DHC.01030 RPL06.Interior.DHC - Priority - Install Fire Sprinkler (IFP Accleration) Early Priority OH MEPF Not Started 06/22/26 06/26/26 6.2 6.2
0%
192.5
RPL06.INT.SSBC.3140 RPL06.Interior.SSBC LO #06 - Install Security Lowside OH and In-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 06/22/26 06/23/26 2.5 2.5
0%
123.8
RPL06.INT.SSBC.3160 RPL06.Interior.SSBC LO #06 - Install Controls / EPMS / BMS OH and In-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 06/22/26 06/23/26 2.5 2.5
0%
120.0
RPL06.CON.WP2.09380 RPL06.Conn Misc P/S/T and R/S/P @ MDF2 ISP (MDF RPL06 <> MDF RPL06) Not Started 06/23/26 07/07/26 12.5 12.5
0%
365.0
RPL06.CON.WP2.09400 RPL06.Conn Misc P/S/T and R/S/P @ MDF1 ISP (MDF RPL06 <> MDF RPL06) Not Started 06/23/26 06/26/26 5.0 5.0
0%
376.2
RPL06.EY.DHA.01130 RPL06.EY.DHA - Cure (High Early Mix) Foundations Not Started 06/23/26 06/29/26 8.8 8.8
0%
71.2
RPL06.EY.DHC.01010 RPL06.EY.DHC - Install F/R/P Equipment Pads - 1-5 (Grid 6-17/6-23) (12'' Larger For Tolerance) Foundations Not Started 06/23/26 07/02/26 10.0 10.0
0%
151.2
RPL06.EY.ENDC.1470 RPL06.EY.DHD.T1 - Install Tent Electrical Tie-ins Tent 1 Not Started 06/23/26 06/25/26 3.8 3.8
0%
6.2
RPL06.EY.ENDC.1490 RPL06.EY.DHD.T1 - Install Tent Mechanical Tie-ins Tent 1 Not Started 06/23/26 06/30/26 7.5 7.5
0%
2.5
RPL06.INT.ENDC.01020 RPL06.Interior.End-Corridor - Install Priority OH, Walls, OFE and Fitout - WBS Summary End Corridor Not Started 06/23/26 05/12/27 277.5 277.5
0%
98.8
RPL06.INT.ENDC.03480 RPL06.Interior.End-Cor - Priority - WBS Summary Priority Walls & Overhead Not Started 06/23/26 07/30/26 33.8 33.8
0%
140.0
RPL06.INT.ENDC.1020 RPL06.Interior.End-Cor - Priority - Install Priority Soffit for Wall Tie-Ins/ Rock & HoW & Draft Blanket Priority Walls & Overhead Not Started 06/23/26 06/29/26 6.2 6.2
0%
131.2
RPL06.INT.SSB.03220 RPL06.Interior.SSB - Priority - Install Fire Safing/ Seal all Penetrations through Soffit (Highside OH space) Priority Walls and OverHead Not Started 06/23/26 06/29/26 6.2 6.2
0%
123.8
RPL06.INT.SSB.06860 RPL06.Interior.SSB - Priority - (P1) Tape Finish Paint (Both Sides) Priority Wall - P1 Not Started 06/23/26 06/29/26 6.2 6.2
0%
176.2
RPL06.INT.SSBC.02180 RPL06.Interior.SSBC - Priority - Install Plumbing (Highside OH space) Priority Walls & Overhead Not Started 06/23/26 06/29/26 6.2 6.2
0%
70.0
RPL06.INT.SSBC.02200 RPL06.Interior.SSBC - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) Priority Walls & Overhead Not Started 06/23/26 06/29/26 6.2 6.2
0%
63.8
RPL06.INT.SSBC.03300 RPL06.Interior.SSBC - Priority - Install FA/ VESDA/ hangers & Heat Trace (Highside OH space) Priority Walls & Overhead Not Started 06/23/26 06/29/26 6.2 6.2
0%
70.0
RPL06.INT.SSBC.4080 RPL06.Interior.SSBC LO #07 - Install Mechanical Piping Lowside OH and in-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 06/23/26 06/24/26 2.5 2.5
0%
113.8
RPL06.STR.DHCD.01210 RPL06.Structure.DHCD - Moisture requirements for floor Sealer F/R/P Not Started 06/23/26 06/29/26 8.8 8.8
0%
111.2
GCD.RPL06.3985 MCUP Ready for Energization - (MCUPs Loop 2) mCup Not Started 06/24/26 06/24/26 0.0 0.0
0%
327.5
RPL06.CX.MCUP.01020 RPL06.CX.mCup Loop 2 - L3, L4, IST - WBS Summary mCUP 5-6 Not Started 06/24/26 11/25/26 135.0 135.0
0%
238.8
RPL06.CX.MCUP.01030 RPL06.CX.mCup Loop 2 - L3/L4 - MV Skids mCUP 5-6 Not Started 06/24/26 06/29/26 5.0 5.0
0%
190.0
RPL06.INT.ENDC.1180 RPL06.Interior.End-Corridor - Priority - Install Duct (Highside OH space) (IFP Accleration) Early Priority OH MEPF Not Started 06/24/26 07/02/26 8.8 8.8
0%
181.2
RPL06.INT.SSBC.3240 RPL06.Interior.SSBC LO #06 - Install Electrical Lowside OH and In-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 06/24/26 06/26/26 3.8 3.8
0%
120.0
RPL06.MCUP.LP1.2100 RPL06.MCUP.Loop 1 - Install Exterior Signage Hardscape and Landscape Not Started 06/24/26 07/08/26 12.5 12.5
0%
433.8
RPL06.MCUP.LP2.1640 RPL06.MCUP.Loop 2 - Install Early Mcup Paving Hardscape and Landscape Not Started 06/24/26 07/08/26 12.5 12.5
0%
402.5
RPL06.EY.ENDC.1770 RPL06.EY.DHD.T2 - Install Tent Electrical Tie-ins Tent 2 Not Started 06/25/26 06/29/26 3.8 3.8
0%
11.2
RPL06.EY.ENDC.1790 RPL06.EY.DHD.T2 - Install Tent Mechanical Tie-ins Tent 2 Not Started 06/25/26 07/02/26 7.5 7.5
0%
7.5
RPL06.INT.DHA.02360 RPL06.Interior.DHA - Priority - Install Temp Doors Frame Hardware OverHead Not Started 06/25/26 06/29/26 3.8 3.8
0%
262.5
RPL06.INT.DHB.01130 RPL06.Interior.DHB - Priority - Install Controls / EPMS / BMS OverHead Not Started 06/25/26 06/30/26 5.0 5.0
0%
5.0
RPL06.INT.ENDC.6060 RPL06.Interior.End-Cor - Priority - Install IMP Exterior Inwall Rough-In Priority Walls & Overhead Not Started 06/25/26 06/29/26 3.8 3.8
0%
137.5
RPL06.INT.SSBC.4100 RPL06.Interior.SSBC LO #07 - Install Fire Life Safety Lowside OH and In-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 06/25/26 06/26/26 2.5 2.5
0%
117.5
RPL06.INT.SSBC.4120 RPL06.Interior.SSBC LO #07 - Install Plumbing Lowside OH and In-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 06/25/26 06/26/26 2.5 2.5
0%
113.8
RPL06.EY.SSB.01160 RPL06.EY.SSB - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 06/26/26 07/24/26 25.0 25.0
0%
48.8
RPL06.INT.DHC.01000 RPL06.Interior.DHC - Priority OH - WBS Summary OverHead Not Started 06/26/26 09/11/26 67.5 67.5
0%
305.0
RPL06.INT.DHC.01020 RPL06.Interior.DHC - Install Priority OH, Walls, OFE and Tie-ins - WBS Summary DHC Not Started 06/26/26 03/04/27 213.8 213.8
0%
158.8
RPL06.INT.DHC.01980 RPL06.Interior.DHC - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall OverHead Not Started 06/26/26 07/02/26 6.2 6.2
0%
335.0
RPL06.INT.DHC.02250 RPL06.Interior.DHC - Priority - Install IMP Exterior Inwall Rough-In OverHead Not Started 06/26/26 07/02/26 6.2 6.2
0%
335.0
RPL06.INT.DHD.02230 RPL06.Interior.DHD - Priority - Install Drywall at Exterior Walls OverHead Not Started 06/26/26 07/02/26 6.2 6.2
0%
80.0
RPL06.INT.SSB.01510 RPL06.Interior.SSB - Loading Dock and Storage - Install Door Frames Loading Dock and Storage Not Started 06/26/26 07/02/26 6.2 6.2
0%
150.0
RPL06.INT.SSB.02900 RPL06.Interior.SSB - Loading Dock and Storage - Pre Priority OH & Walls Tasks (Unistruts,Hangers,Track) Loading Dock and Storage Not Started 06/26/26 07/02/26 6.2 6.2
0%
185.0
RPL06.WA.OFE.01000 RPL06.WA - Weather Allowance - FDN to OFE Weather Allowance Not Started 06/26/26 07/07/26 15.0 15.0
0%
-16.2
RPL06.EY.DHB.01720 RPL06.EY.DHB - Cure (High Early Mix) Foundations Not Started 06/27/26 07/03/26 8.8 8.8
0%
62.5
RPL06.EY.DHD.01010 RPL06.EY.DHD - Install F/R/P Equipment Pads - 1-5 (Grid 6-17/6-23) (12'' Larger For Tolerance) Foundations Not Started 06/29/26 07/09/26 10.0 10.0
0%
122.5
RPL06.EY.DHD.01020 RPL06.EY.DHD - Install Foundations - WBS Summary Foundations Not Started 06/29/26 03/01/27 208.8 208.8
0%
103.8