Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
1
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.INT.CTRC.9060 RPL06.Interior.Center-Corr - Priority GL6.16/6.17 - (P2) Install MEP In-Wall/Backing Priority Wall Grid Line 6-16 / 6-17 Not Started 06/29/26 07/02/26 5.0 5.0
0%
56.2
RPL06.INT.ENDC.1040 RPL06.Interior.End-Corridor - Priority - Install Fire Sprinkler (Highside OH space) (IFP Accleration) Early Priority OH MEPF Not Started 06/29/26 07/01/26 3.8 3.8
0%
192.5
RPL06.INT.SSBC.3180 RPL06.Interior.SSBC LO #06 - Install Door Frames Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 06/29/26 06/30/26 2.5 2.5
0%
120.0
RPL06.INT.SSBC.4140 RPL06.Interior.SSBC LO #07 - Install Security Lowside OH and In-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 06/29/26 06/30/26 2.5 2.5
0%
117.5
RPL06.INT.SSBC.4160 RPL06.Interior.SSBC LO #07 - Install Controls / EPMS / BMS OH and In-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 06/29/26 06/30/26 2.5 2.5
0%
113.8
RPL06.EY.DHA.01530 RPL06.EY.DHA - Set GS.IDF Hut (1x GS.IDF) 6X04 (ROJ04.29.26) OFE Not Started 06/30/26 07/07/26 6.2 6.2
0%
238.8
RPL06.EY.SSB.01240 RPL06.EY.SSB - Install BMS/EPMS Tie-ins Tie-ins Not Started 06/30/26 07/21/26 18.8 18.8
0%
52.5
RPL06.INT.DHA.02160 RPL06.Interior.DHA - Priority - Install Mechanical Piping OverHead Not Started 06/30/26 07/21/26 18.8 18.8
0%
37.5
RPL06.INT.ENDC.1000 RPL06.Interior.End-Cor - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall Priority Walls & Overhead Not Started 06/30/26 07/07/26 6.2 6.2
0%
131.2
RPL06.INT.SBC.03240 RPL06.Interior.SSB-Corridor - BoW - Frame Balance of Wall Balance of Walls & Overhead Not Started 06/30/26 07/07/26 6.2 6.2
0%
63.8
RPL06.INT.SBC.03260 RPL06.Interior.SSB-Corridor - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary Balance of Walls & Overhead Not Started 06/30/26 12/17/26 147.5 147.5
0%
63.8
RPL06.INT.SSB.01150 RPL06.Interior.SSB - BoW - BoW - Frame Balance of Wall Balance of Walls and OverHead Not Started 06/30/26 07/07/26 6.2 6.2
0%
123.8
RPL06.INT.SSB.01160 RPL06.Interior.SSB - BoW - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Kichten, etc) - WBS Summary Balance of Walls and OverHead Not Started 06/30/26 12/08/26 138.8 138.8
0%
120.0
RPL06.INT.SSBC.03320 RPL06.Interior.SSBC - Priority - Install Fire Safing/ Seal Penetrations through Soffit (Highside OH space) Priority Walls & Overhead Not Started 06/30/26 07/02/26 3.8 3.8
0%
63.8
RPL06.INT.SSBC.03340 RPL06.Interior.SSBC - Priority - Fixed Draft/Smoke Curtain Patching Priority Walls & Overhead Not Started 06/30/26 07/02/26 3.8 3.8
0%
63.8
RPL06.STR.DHCD.01230 RPL06.Structure.DHCD - Install SOG Sealer and Cure F/R/P Not Started 06/30/26 07/01/26 2.5 2.5
0%
111.2
DCC.B6.3235 [SSDCB1] CorpNet/Security/FacNet Ready [DHA] Connectivity Not Started 07/01/26 07/01/26 0.0 0.0
0%
373.8
RPL06.EY.ENDC.1510 RPL06.EY.DHD.T1 - Temp Conditioning Startup and Available Tent 1 Not Started 07/01/26 07/02/26 2.5 2.5
0%
2.5
RPL06.INT.CTRC.9040 RPL06.Interior.Center-Corr - Priority GL6.16/6.17 - (P2) Install IMP Wall Priority Wall Grid Line 6-16 / 6-17 Not Started 07/01/26 07/07/26 5.0 5.0
0%
43.8
RPL06.INT.CTRC.9080 RPL06.Interior.Center-Corr - Priority GL6.16/6.17 - (P2) Hang Drywall (Both Sides) Priority Wall Grid Line 6-16 / 6-17 Not Started 07/01/26 07/07/26 5.0 5.0
0%
56.2
RPL06.INT.SSBC.3200 RPL06.Interior.SSBC LO #06 - Mechanical Tie-In Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 07/01/26 07/02/26 2.5 2.5
0%
120.0
RPL06.INT.SSBC.3300 RPL06.Interior.SSBC LO #06 - Electrical Tie-In Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 07/01/26 07/08/26 6.2 6.2
0%
120.0
RPL06.INT.SSBC.4240 RPL06.Interior.SSBC LO #07 - Install Electrical Lowside OH and In-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 07/01/26 07/06/26 3.8 3.8
0%
113.8
DCC.B6.3125 [SSDCB1] GS Gear Delivered [DHB] Connectivity Not Started 07/02/26 07/02/26 0.0 0.0
0%
438.8
DCC.B6.3135 [SSDCB1] GS Gear Delivered [DHA] Connectivity Not Started 07/02/26 07/02/26 0.0 0.0
0%
438.8
RPL06.INT.DHA.02320 RPL06.Interior.DHA - Priority - Install Electrical OverHead Not Started 07/02/26 07/23/26 18.8 18.8
0%
62.5
RPL06.INT.DHC.01080 RPL06.Interior.DHC - OFE - WBS Summary OFE/MOFE & CFCI Not Started 07/02/26 01/22/27 173.8 173.8
0%
1.2
RPL06.INT.DHC.02670 RPL06.Interior.DHC - CFCI - Pre Set 16"" FW Pipe OFE/MOFE & CFCI Not Started 07/02/26 07/16/26 12.5 12.5
0%
76.2
RPL06.INT.DHD.01080 RPL06.Interior.DHD - OFE - WBS Summary OFE/MOFE & CFCI Not Started 07/02/26 01/07/27 161.2 161.2
0%
12.5
RPL06.INT.DHD.02670 RPL06.Interior.DHD - CFCI - Pre Set 16"" FW Pipe OFE/MOFE & CFCI Not Started 07/02/26 07/16/26 12.5 12.5
0%
76.2
RPL06.SKN.DHCD.01000 RPL06.SKIN.DHCD - Install Temp Doors Glazing, Doors and Ext Devices Not Started 07/02/26 07/06/26 2.5 2.5
0%
295.0
RPL06.SKN.DHCD.01020 RPL06.SKIN.DHCD - Install Windows, Doors, Louvers and Ext Devices - WBS Summary Glazing, Doors and Ext Devices Not Started 07/02/26 02/26/27 203.8 203.8
0%
125.0
RPL06.EY.DHC.01130 RPL06.EY.DHC - Cure (High Early Mix) Foundations Not Started 07/03/26 07/09/26 8.8 8.8
0%
223.8
GCD.RPL06.1290 Interior fit-out Start RPL06 - DHC&D Construction Milestones Not Started 07/06/26 07/06/26 0.0 0.0
0%
365.0
RPL06.EY.ENDC.1810 RPL06.EY.DHD.T2 - Tent Temp Conditioning Startup and Available Tent 2 Not Started 07/06/26 07/07/26 2.5 2.5
0%
7.5
RPL06.INT.DHC.02230 RPL06.Interior.DHC - Priority - Install Drywall at Exterior Walls OverHead Not Started 07/06/26 07/10/26 6.2 6.2
0%
335.0
RPL06.INT.SSB.01330 RPL06.Interior.SSB - Loading Dock and Storage - Hang Drywall Loading Dock and Storage Not Started 07/06/26 07/17/26 12.5 12.5
0%
150.0
PRE.FA.1300 Non-Critical Trade Buyout - Final Agreement Trade Partner Final Agreement Not Started 07/07/26 07/07/26 0.0 0.0
0%
120.0
RPL.GF.D.N6170.XG GS.IDF Hut 4 Install Complete for RPL06 Give Milestones (XREFs) Not Started 07/07/26 07/07/26 0.0 0.0
0%
435.0
RPL06.CON.WP2.08680 RPL06.Conn - CorpNet & FacNet Ready - GS - Core WP#02 GS Not Started 07/07/26 07/07/26 0.0 0.0
0%
372.5
RPL06.INT.ENDC.01120 RPL06.Interior.End-Corridor - Frame Remaining Walls Fit out Not Started 07/07/26 07/10/26 5.0 5.0
0%
166.2
RPL06.INT.ENDC.01130 RPL06.Interior.End-Corridor - Install Fitout (Restroom, Janitor, Fire Riser, Humidifier) - WBS Summary Fit out Not Started 07/07/26 04/07/27 235.0 235.0
0%
130.0
RPL06.INT.ENDC.06940 RPL06.Interior.End-Corridor - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings Restrooms Not Started 07/07/26 07/20/26 12.5 12.5
0%
190.0
RPL06.INT.SSBC.4180 RPL06.Interior.SSBC LO #07 - Install Door Frames Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 07/07/26 07/08/26 2.5 2.5
0%
113.8
RPL06.SKN.DHCD.01140 RPL06.SKIN.DHCD - Install Blocking of Canopy & Backing of Exterior Wall Glazing, Doors and Ext Devices Not Started 07/07/26 07/13/26 6.2 6.2
0%
295.0
DCC.B6.3225 [SSDCB1] CorpNet/Security/FacNet Ready [DHB] Connectivity Not Started 07/08/26 07/08/26 0.0 0.0
0%
365.0
GCD.RPL06.1655 Start MES Installation - RPL06 Construction Milestones Not Started 07/08/26 07/08/26 0.0 0.0
0%
76.2
GCD.RPL06.1700 Start LV Electrical Skid Set-In-Place - RPL06 Construction Milestones Not Started 07/08/26 07/08/26 0.0 0.0
0%
266.2
ICM.B6.1840 [SSDCB1] Delivery of DES - Data Hall Electrical Room Skid (First Delivery) Construction Not Started 07/08/26 07/08/26 0.0 0.0
0%
68.8
RPL.GF.D.N6180.XR Fiber Pulls, Test & Term within GS EF 1 Complete Receive Milestones (XREFs) Not Started 07/08/26 07/08/26 0.0 0.0
0%
356.2
RPL.GF.D.N6190.XR Fiber Pulls, Test & Term within GS EF 2 Complete Receive Milestones (XREFs) Not Started 07/08/26 07/08/26 0.0 0.0
0%
353.8
RPL06.CFCI.4620 RPL06 - Submittals Prep & Submit for Review -Epoxy Flooring (Spec 09 67 23) XX (CFCI) Div. 09 - Epoxy Flooring Not Started 07/08/26 07/08/26 0.0 0.0
0%
138.8
RPL06.CFCI.4810 RPL06 - Submittals Prep & Submit for Review - Specialities (CFCI) Div. 10 - Specialities Not Started 07/08/26 07/08/26 0.0 0.0
0%
120.0
RPL06.CFCI.4820 Campus - Submittals Prep & Submit for Review - Asphalt / Paving (CFCI) Div. 32 - Asphalt/ Conc. Paving Not Started 07/08/26 07/14/26 6.2 6.2
0%
178.8
RPL06.CFCI.4830 RPL06 - Submittals Prep & Submit for Review - Carpet (CFCI) Div. 09 - Carpet Not Started 07/08/26 07/29/26 20.0 20.0
0%
138.8
RPL06.CFCI.4870 RPL06 - Submittals Review & Approval - Interior Painting (Spec 09 91 23) XX (CFCI) Div. 09 - Painting Not Started 07/08/26 08/04/26 25.0 25.0
0%
146.2
RPL06.CFCI.4880 RPL06 - Submittals Review & Approval -Epoxy Flooring (Spec 09 67 23) XX (CFCI) Div. 09 - Epoxy Flooring Not Started 07/08/26 08/04/26 25.0 25.0
0%
190.0
RPL06.CFCI.4960 RPL06 - Fabricate / Deliver - Finished Carpentry (Millwork/Countertops) Finished Carpentry (Millwork/Tops) Not Started 07/08/26 08/14/26 35.0 35.0
0%
237.5
RPL06.CFCI.5070 RPL06 - Submittals Review & Approval - Specialities (CFCI) Div. 10 - Specialities Not Started 07/08/26 08/04/26 25.0 25.0
0%
120.0
RPL06.CFCI.5280 Campus - Submittals Review & Approval - Landscaping / Irrigation (CFCI) Div. 32 - Landscape/ Irrigation Not Started 07/08/26 08/04/26 25.0 25.0
0%
297.5
RPL06.CON.WP2.07800 RPL06.Conn - Ext. GSIDF6X04 (South Elec Yard) - WBS Summary Ext. IDF Hut - GSIDF6X04 Not Started 07/08/26 07/28/26 18.8 18.8
0%
416.2
RPL06.CON.WP2.08460 RPL06.Conn - Ext. GSIDF6X04 - Install Infrastructure (Racks, Waterfalls etc.) ??pred?? Infrastructure Not Started 07/08/26 07/08/26 1.2 1.2
0%
238.8
RPL06.INT.CTRC.01070 RPL06.Interior.Center-Corridor - Priority - Early MEPF Inwall Rough-In for Ancillary Skid (Room #3.6) Priority Wall Grid Line 6-16 / 6-17 Not Started 07/08/26 07/10/26 3.8 3.8
0%
141.2
RPL06.INT.CTRC.01130 RPL06.Interior.Center-Corridor - OFE - DHB (1x GS.IDF) B2 (ROJ06.24.26) OFE/MOFE & CFCI Not Started 07/08/26 07/14/26 6.2 6.2
0%
111.2
RPL06.INT.CTRC.01200 RPL06.Interior.Center-Corridor - OFE - DHA (1x GS.IDF) A2 (ROJ06.24.26) OFE/MOFE & CFCI Not Started 07/08/26 07/14/26 6.2 6.2
0%
111.2
RPL06.INT.CTRC.8960 RPL06.Interior.Center-Corr - Priority - All MEP In-wall in Production Entry Fiber Rooms (Room #2.7) Priority Wall Grid Line 6-16 / 6-17 Not Started 07/08/26 07/16/26 8.8 8.8
0%
43.8
RPL06.INT.CTRC.9100 RPL06.Interior.Center-Corr - Priority GL6.16/6.17 - (P2) Tape Finish Paint (Both Sides) Priority Wall Grid Line 6-16 / 6-17 Not Started 07/08/26 07/14/26 6.2 6.2
0%
56.2
RPL06.INT.DHB.01140 RPL06.Interior.DHB - OFE - LV Skids and TopHat - Set / Place / Anchor OFE/MOFE & CFCI Not Started 07/08/26 07/28/26 18.8 18.8
0%
-10.0
RPL06.INT.DHB.01150 RPL06.Interior.DHB - OFE - MES Skids - Set / Place / Anchor OFE/MOFE & CFCI Not Started 07/08/26 07/28/26 18.8 18.8
0%
70.0
RPL06.INT.ENDC.1920 RPL06.Interior.End-Cor - Priority - Install Drywall at Exterior Walls Priority Walls & Overhead Not Started 07/08/26 07/14/26 6.2 6.2
0%
131.2
RPL06.INT.SBC.03420 RPL06.Interior.SSB-Corridor - BoW - Install Door Frames Balance of Walls & Overhead Not Started 07/08/26 07/14/26 6.2 6.2
0%
88.8
RPL06.INT.SBC.05800 RPL06.Interior.SSB-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside OH and in-wall Balance of Walls & Overhead Not Started 07/08/26 07/17/26 10.0 10.0
0%
63.8
RPL06.INT.SSB.01180 RPL06.Interior.SSB - BoW - Install Door Frames Balance of Walls and OverHead Not Started 07/08/26 07/14/26 6.2 6.2
0%
145.0
RPL06.INT.SSB.01210 RPL06.Interior.SSB - BoW - Install Electrical Lowside OH and In-wall Balance of Walls and OverHead Not Started 07/08/26 07/21/26 12.5 12.5
0%
123.8
RPL06.INT.SSB.01880 RPL06.Interior.SSB - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings Final Finishes & Fixtures (Includes TFW, Restrooms, etc.) Not Started 07/08/26 07/21/26 12.5 12.5
0%
235.0
DCC.B6.3300 [SSDCB1] Cabling Start : OSP Pathways - Primary GS Connectivity Not Started 07/09/26 07/09/26 0.0 0.0
0%
433.8
DCC.B6.3707 [SSDCB1] Cabling Start : General Services (GS) Connectivity Not Started 07/09/26 07/09/26 0.0 0.0
0%
433.8
RPL06.CON.WP2.08480 RPL06.Conn - Ext. GSIDF6X04 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 07/09/26 07/16/26 7.5 7.5
0%
423.8
RPL06.CON.WP2.08540 RPL06.Conn - Ext. GSIDF6X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH A) Cabling Not Started 07/09/26 07/10/26 2.5 2.5
0%
238.8
RPL06.INT.SSBC.01060 RPL06.Interior.SSB-Corridor - OFE - Early Equipment (1x SSB Elect) (ROJ 05.13.26) (RVCD 07.08.26) OFE/MOFE & CFCI Not Started 07/09/26 07/22/26 12.5 12.5
0%
68.8
RPL06.INT.SSBC.3220 RPL06.Interior.SSBC LO #06 - Fire Safing OH and In-wall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 07/09/26 07/09/26 1.2 1.2
0%
120.0
RPL06.INT.SSBC.4200 RPL06.Interior.SSBC LO #07 - Mechanical Tie-In Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 07/09/26 07/10/26 2.5 2.5
0%
113.8
RPL06.INT.SSBC.4300 RPL06.Interior.SSBC LO #07 - Electrical Tie-In Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 07/09/26 07/15/26 6.2 6.2
0%
113.8
RPL06.MCUP.LP2.1760 RPL06.MCUP.Loop 2 - Install Lighting Hardscape and Landscape Not Started 07/09/26 07/15/26 6.2 6.2
0%
402.5
RPL06.EY.DHD.01120 RPL06.EY.DHD - Cure (High Early Mix) (Grid 6-17/6-23) Foundations Not Started 07/10/26 07/16/26 8.8 8.8
0%
180.0
RPL06.EY.DHD.01730 RPL06.EY.DHD - Install F/R/P Equipment Pads - 5-10 (Grid 6-23/6-28) (12'' Larger For Tolerance) Foundations Not Started 07/10/26 07/20/26 8.8 8.8
0%
131.2
RPL06.INT.SSBC.3260 RPL06.Interior.SSBC LO #06 - Install Backing Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 07/10/26 07/10/26 1.2 1.2
0%
120.0
ICM.B6.1825 [SSDCB1] Delivery of MVS - Medium Voltage Switches (First Delivery) Construction Not Started 07/13/26 07/13/26 0.0 0.0
0%
20.0
RPL06.CON.WP2.08560 RPL06.Conn - Ext. GSIDF6X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH C) Cabling Not Started 07/13/26 07/28/26 15.0 15.0
0%
238.8
RPL06.EY.SSB.01170 RPL06.EY.SSB - Install Mechanical Main (include penetration detail) Tie-ins Not Started 07/13/26 07/31/26 18.8 18.8
0%
42.5
RPL06.INT.CTRC.01090 RPL06.Interior.Center-Corridor - Priority - Early Install Drywall for Ancillary Skid (Room #3.6) Priority Wall Grid Line 6-16 / 6-17 Not Started 07/13/26 07/15/26 3.8 3.8
0%
141.2
RPL06.INT.DHB.01180 RPL06.Interior.DHB - LV Skids and TopHat Tie-ins (LOE) DHB - LV Skids and TopHat Not Started 07/13/26 08/11/26 27.5 27.5
0%
75.0
RPL06.INT.DHB.01181 RPL06.Interior.DHB - LV Skids and TopHat - Set & Anchor Interconnects DHB - LV Skids and TopHat Not Started 07/13/26 07/30/26 17.5 17.5
0%
75.0
RPL06.INT.DHB.01190 RPL06.Interior.DHB - Tie-ins - WBS Summary Tie-Ins Not Started 07/13/26 12/16/26 136.2 136.2
0%
115.0
RPL06.INT.DHC.02110 RPL06.Interior.DHC - Priority - Install Plumbing OverHead Not Started 07/13/26 07/17/26 6.2 6.2
0%
335.0
RPL06.INT.ENDC.01140 RPL06.Interior.End-Corridor - Install Doors Frame Hardware Fit out Not Started 07/13/26 07/17/26 6.2 6.2
0%
180.0
RPL06.INT.ENDC.01150 RPL06.Interior.End-Corridor - Install Electrical OH and In-wall Fit out Not Started 07/13/26 07/21/26 8.8 8.8
0%
166.2
RPL06.INT.SSBC.3280 RPL06.Interior.SSBC LO #06 - QC - Backings/Walls Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 07/13/26 07/14/26 2.5 2.5
0%
120.0
GCD.RPL06.1826 Delivery of RMU - (First Delivery) - RPL06 - DHA&B Construction Milestones Not Started 07/14/26 07/14/26 0.0 0.0
0%
18.8
RPL06.EY.ENDC.1910 RPL06.EY.DHD.T1 - HAC Prefab prior to install for DH B Tent 1 Not Started 07/14/26 07/20/26 6.2 6.2
0%
2.5