Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
1
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL06.INT.CTRC.9060 |
RPL06.Interior.Center-Corr - Priority GL6.16/6.17 - (P2) Install MEP In-Wall/Backing | Priority Wall Grid Line 6-16 / 6-17 | Not Started | 06/29/26 | 07/02/26 | 5.0 | 5.0 |
|
56.2 |
RPL06.INT.ENDC.1040 |
RPL06.Interior.End-Corridor - Priority - Install Fire Sprinkler (Highside OH space) (IFP Accleration) | Early Priority OH MEPF | Not Started | 06/29/26 | 07/01/26 | 3.8 | 3.8 |
|
192.5 |
RPL06.INT.SSBC.3180 |
RPL06.Interior.SSBC LO #06 - Install Door Frames | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 06/29/26 | 06/30/26 | 2.5 | 2.5 |
|
120.0 |
RPL06.INT.SSBC.4140 |
RPL06.Interior.SSBC LO #07 - Install Security Lowside OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 06/29/26 | 06/30/26 | 2.5 | 2.5 |
|
117.5 |
RPL06.INT.SSBC.4160 |
RPL06.Interior.SSBC LO #07 - Install Controls / EPMS / BMS OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 06/29/26 | 06/30/26 | 2.5 | 2.5 |
|
113.8 |
RPL06.EY.DHA.01530 |
RPL06.EY.DHA - Set GS.IDF Hut (1x GS.IDF) 6X04 (ROJ04.29.26) | OFE | Not Started | 06/30/26 | 07/07/26 | 6.2 | 6.2 |
|
238.8 |
RPL06.EY.SSB.01240 |
RPL06.EY.SSB - Install BMS/EPMS Tie-ins | Tie-ins | Not Started | 06/30/26 | 07/21/26 | 18.8 | 18.8 |
|
52.5 |
RPL06.INT.DHA.02160 |
RPL06.Interior.DHA - Priority - Install Mechanical Piping | OverHead | Not Started | 06/30/26 | 07/21/26 | 18.8 | 18.8 |
|
37.5 |
RPL06.INT.ENDC.1000 |
RPL06.Interior.End-Cor - Priority - Install Unistruts & Hangers (All Trades) Both side of Corridor Wall | Priority Walls & Overhead | Not Started | 06/30/26 | 07/07/26 | 6.2 | 6.2 |
|
131.2 |
RPL06.INT.SBC.03240 |
RPL06.Interior.SSB-Corridor - BoW - Frame Balance of Wall | Balance of Walls & Overhead | Not Started | 06/30/26 | 07/07/26 | 6.2 | 6.2 |
|
63.8 |
RPL06.INT.SBC.03260 |
RPL06.Interior.SSB-Corridor - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Bathroom, etc) - WBS Summary | Balance of Walls & Overhead | Not Started | 06/30/26 | 12/17/26 | 147.5 | 147.5 |
|
63.8 |
RPL06.INT.SSB.01150 |
RPL06.Interior.SSB - BoW - BoW - Frame Balance of Wall | Balance of Walls and OverHead | Not Started | 06/30/26 | 07/07/26 | 6.2 | 6.2 |
|
123.8 |
RPL06.INT.SSB.01160 |
RPL06.Interior.SSB - BoW - Balace Of Wall (ERAD, Maintance, Network infra, Spoke, Kichten, etc) - WBS Summary | Balance of Walls and OverHead | Not Started | 06/30/26 | 12/08/26 | 138.8 | 138.8 |
|
120.0 |
RPL06.INT.SSBC.03320 |
RPL06.Interior.SSBC - Priority - Install Fire Safing/ Seal Penetrations through Soffit (Highside OH space) | Priority Walls & Overhead | Not Started | 06/30/26 | 07/02/26 | 3.8 | 3.8 |
|
63.8 |
RPL06.INT.SSBC.03340 |
RPL06.Interior.SSBC - Priority - Fixed Draft/Smoke Curtain Patching | Priority Walls & Overhead | Not Started | 06/30/26 | 07/02/26 | 3.8 | 3.8 |
|
63.8 |
RPL06.STR.DHCD.01230 |
RPL06.Structure.DHCD - Install SOG Sealer and Cure | F/R/P | Not Started | 06/30/26 | 07/01/26 | 2.5 | 2.5 |
|
111.2 |
DCC.B6.3235 |
[SSDCB1] CorpNet/Security/FacNet Ready [DHA] | Connectivity | Not Started | 07/01/26 | 07/01/26 | 0.0 | 0.0 |
|
373.8 |
RPL06.EY.ENDC.1510 |
RPL06.EY.DHD.T1 - Temp Conditioning Startup and Available | Tent 1 | Not Started | 07/01/26 | 07/02/26 | 2.5 | 2.5 |
|
2.5 |
RPL06.INT.CTRC.9040 |
RPL06.Interior.Center-Corr - Priority GL6.16/6.17 - (P2) Install IMP Wall | Priority Wall Grid Line 6-16 / 6-17 | Not Started | 07/01/26 | 07/07/26 | 5.0 | 5.0 |
|
43.8 |
RPL06.INT.CTRC.9080 |
RPL06.Interior.Center-Corr - Priority GL6.16/6.17 - (P2) Hang Drywall (Both Sides) | Priority Wall Grid Line 6-16 / 6-17 | Not Started | 07/01/26 | 07/07/26 | 5.0 | 5.0 |
|
56.2 |
RPL06.INT.SSBC.3200 |
RPL06.Interior.SSBC LO #06 - Mechanical Tie-In | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 07/01/26 | 07/02/26 | 2.5 | 2.5 |
|
120.0 |
RPL06.INT.SSBC.3300 |
RPL06.Interior.SSBC LO #06 - Electrical Tie-In | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 07/01/26 | 07/08/26 | 6.2 | 6.2 |
|
120.0 |
RPL06.INT.SSBC.4240 |
RPL06.Interior.SSBC LO #07 - Install Electrical Lowside OH and In-wall | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 07/01/26 | 07/06/26 | 3.8 | 3.8 |
|
113.8 |
DCC.B6.3125 |
[SSDCB1] GS Gear Delivered [DHB] | Connectivity | Not Started | 07/02/26 | 07/02/26 | 0.0 | 0.0 |
|
438.8 |
DCC.B6.3135 |
[SSDCB1] GS Gear Delivered [DHA] | Connectivity | Not Started | 07/02/26 | 07/02/26 | 0.0 | 0.0 |
|
438.8 |
RPL06.INT.DHA.02320 |
RPL06.Interior.DHA - Priority - Install Electrical | OverHead | Not Started | 07/02/26 | 07/23/26 | 18.8 | 18.8 |
|
62.5 |
RPL06.INT.DHC.01080 |
RPL06.Interior.DHC - OFE - WBS Summary | OFE/MOFE & CFCI | Not Started | 07/02/26 | 01/22/27 | 173.8 | 173.8 |
|
1.2 |
RPL06.INT.DHC.02670 |
RPL06.Interior.DHC - CFCI - Pre Set 16"" FW Pipe | OFE/MOFE & CFCI | Not Started | 07/02/26 | 07/16/26 | 12.5 | 12.5 |
|
76.2 |
RPL06.INT.DHD.01080 |
RPL06.Interior.DHD - OFE - WBS Summary | OFE/MOFE & CFCI | Not Started | 07/02/26 | 01/07/27 | 161.2 | 161.2 |
|
12.5 |
RPL06.INT.DHD.02670 |
RPL06.Interior.DHD - CFCI - Pre Set 16"" FW Pipe | OFE/MOFE & CFCI | Not Started | 07/02/26 | 07/16/26 | 12.5 | 12.5 |
|
76.2 |
RPL06.SKN.DHCD.01000 |
RPL06.SKIN.DHCD - Install Temp Doors | Glazing, Doors and Ext Devices | Not Started | 07/02/26 | 07/06/26 | 2.5 | 2.5 |
|
295.0 |
RPL06.SKN.DHCD.01020 |
RPL06.SKIN.DHCD - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Not Started | 07/02/26 | 02/26/27 | 203.8 | 203.8 |
|
125.0 |
RPL06.EY.DHC.01130 |
RPL06.EY.DHC - Cure (High Early Mix) | Foundations | Not Started | 07/03/26 | 07/09/26 | 8.8 | 8.8 |
|
223.8 |
GCD.RPL06.1290 |
Interior fit-out Start RPL06 - DHC&D | Construction Milestones | Not Started | 07/06/26 | 07/06/26 | 0.0 | 0.0 |
|
365.0 |
RPL06.EY.ENDC.1810 |
RPL06.EY.DHD.T2 - Tent Temp Conditioning Startup and Available | Tent 2 | Not Started | 07/06/26 | 07/07/26 | 2.5 | 2.5 |
|
7.5 |
RPL06.INT.DHC.02230 |
RPL06.Interior.DHC - Priority - Install Drywall at Exterior Walls | OverHead | Not Started | 07/06/26 | 07/10/26 | 6.2 | 6.2 |
|
335.0 |
RPL06.INT.SSB.01330 |
RPL06.Interior.SSB - Loading Dock and Storage - Hang Drywall | Loading Dock and Storage | Not Started | 07/06/26 | 07/17/26 | 12.5 | 12.5 |
|
150.0 |
PRE.FA.1300 |
Non-Critical Trade Buyout - Final Agreement | Trade Partner Final Agreement | Not Started | 07/07/26 | 07/07/26 | 0.0 | 0.0 |
|
120.0 |
RPL.GF.D.N6170.XG |
GS.IDF Hut 4 Install Complete for RPL06 | Give Milestones (XREFs) | Not Started | 07/07/26 | 07/07/26 | 0.0 | 0.0 |
|
435.0 |
RPL06.CON.WP2.08680 |
RPL06.Conn - CorpNet & FacNet Ready - GS - Core | WP#02 GS | Not Started | 07/07/26 | 07/07/26 | 0.0 | 0.0 |
|
372.5 |
RPL06.INT.ENDC.01120 |
RPL06.Interior.End-Corridor - Frame Remaining Walls | Fit out | Not Started | 07/07/26 | 07/10/26 | 5.0 | 5.0 |
|
166.2 |
RPL06.INT.ENDC.01130 |
RPL06.Interior.End-Corridor - Install Fitout (Restroom, Janitor, Fire Riser, Humidifier) - WBS Summary | Fit out | Not Started | 07/07/26 | 04/07/27 | 235.0 | 235.0 |
|
130.0 |
RPL06.INT.ENDC.06940 |
RPL06.Interior.End-Corridor - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings | Restrooms | Not Started | 07/07/26 | 07/20/26 | 12.5 | 12.5 |
|
190.0 |
RPL06.INT.SSBC.4180 |
RPL06.Interior.SSBC LO #07 - Install Door Frames | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 07/07/26 | 07/08/26 | 2.5 | 2.5 |
|
113.8 |
RPL06.SKN.DHCD.01140 |
RPL06.SKIN.DHCD - Install Blocking of Canopy & Backing of Exterior Wall | Glazing, Doors and Ext Devices | Not Started | 07/07/26 | 07/13/26 | 6.2 | 6.2 |
|
295.0 |
DCC.B6.3225 |
[SSDCB1] CorpNet/Security/FacNet Ready [DHB] | Connectivity | Not Started | 07/08/26 | 07/08/26 | 0.0 | 0.0 |
|
365.0 |
GCD.RPL06.1655 |
Start MES Installation - RPL06 | Construction Milestones | Not Started | 07/08/26 | 07/08/26 | 0.0 | 0.0 |
|
76.2 |
GCD.RPL06.1700 |
Start LV Electrical Skid Set-In-Place - RPL06 | Construction Milestones | Not Started | 07/08/26 | 07/08/26 | 0.0 | 0.0 |
|
266.2 |
ICM.B6.1840 |
[SSDCB1] Delivery of DES - Data Hall Electrical Room Skid (First Delivery) | Construction | Not Started | 07/08/26 | 07/08/26 | 0.0 | 0.0 |
|
68.8 |
RPL.GF.D.N6180.XR |
Fiber Pulls, Test & Term within GS EF 1 Complete | Receive Milestones (XREFs) | Not Started | 07/08/26 | 07/08/26 | 0.0 | 0.0 |
|
356.2 |
RPL.GF.D.N6190.XR |
Fiber Pulls, Test & Term within GS EF 2 Complete | Receive Milestones (XREFs) | Not Started | 07/08/26 | 07/08/26 | 0.0 | 0.0 |
|
353.8 |
RPL06.CFCI.4620 |
RPL06 - Submittals Prep & Submit for Review -Epoxy Flooring (Spec 09 67 23) XX | (CFCI) Div. 09 - Epoxy Flooring | Not Started | 07/08/26 | 07/08/26 | 0.0 | 0.0 |
|
138.8 |
RPL06.CFCI.4810 |
RPL06 - Submittals Prep & Submit for Review - Specialities | (CFCI) Div. 10 - Specialities | Not Started | 07/08/26 | 07/08/26 | 0.0 | 0.0 |
|
120.0 |
RPL06.CFCI.4820 |
Campus - Submittals Prep & Submit for Review - Asphalt / Paving | (CFCI) Div. 32 - Asphalt/ Conc. Paving | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
178.8 |
RPL06.CFCI.4830 |
RPL06 - Submittals Prep & Submit for Review - Carpet | (CFCI) Div. 09 - Carpet | Not Started | 07/08/26 | 07/29/26 | 20.0 | 20.0 |
|
138.8 |
RPL06.CFCI.4870 |
RPL06 - Submittals Review & Approval - Interior Painting (Spec 09 91 23) XX | (CFCI) Div. 09 - Painting | Not Started | 07/08/26 | 08/04/26 | 25.0 | 25.0 |
|
146.2 |
RPL06.CFCI.4880 |
RPL06 - Submittals Review & Approval -Epoxy Flooring (Spec 09 67 23) XX | (CFCI) Div. 09 - Epoxy Flooring | Not Started | 07/08/26 | 08/04/26 | 25.0 | 25.0 |
|
190.0 |
RPL06.CFCI.4960 |
RPL06 - Fabricate / Deliver - Finished Carpentry (Millwork/Countertops) | Finished Carpentry (Millwork/Tops) | Not Started | 07/08/26 | 08/14/26 | 35.0 | 35.0 |
|
237.5 |
RPL06.CFCI.5070 |
RPL06 - Submittals Review & Approval - Specialities | (CFCI) Div. 10 - Specialities | Not Started | 07/08/26 | 08/04/26 | 25.0 | 25.0 |
|
120.0 |
RPL06.CFCI.5280 |
Campus - Submittals Review & Approval - Landscaping / Irrigation | (CFCI) Div. 32 - Landscape/ Irrigation | Not Started | 07/08/26 | 08/04/26 | 25.0 | 25.0 |
|
297.5 |
RPL06.CON.WP2.07800 |
RPL06.Conn - Ext. GSIDF6X04 (South Elec Yard) - WBS Summary | Ext. IDF Hut - GSIDF6X04 | Not Started | 07/08/26 | 07/28/26 | 18.8 | 18.8 |
|
416.2 |
RPL06.CON.WP2.08460 |
RPL06.Conn - Ext. GSIDF6X04 - Install Infrastructure (Racks, Waterfalls etc.) ??pred?? | Infrastructure | Not Started | 07/08/26 | 07/08/26 | 1.2 | 1.2 |
|
238.8 |
RPL06.INT.CTRC.01070 |
RPL06.Interior.Center-Corridor - Priority - Early MEPF Inwall Rough-In for Ancillary Skid (Room #3.6) | Priority Wall Grid Line 6-16 / 6-17 | Not Started | 07/08/26 | 07/10/26 | 3.8 | 3.8 |
|
141.2 |
RPL06.INT.CTRC.01130 |
RPL06.Interior.Center-Corridor - OFE - DHB (1x GS.IDF) B2 (ROJ06.24.26) | OFE/MOFE & CFCI | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
111.2 |
RPL06.INT.CTRC.01200 |
RPL06.Interior.Center-Corridor - OFE - DHA (1x GS.IDF) A2 (ROJ06.24.26) | OFE/MOFE & CFCI | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
111.2 |
RPL06.INT.CTRC.8960 |
RPL06.Interior.Center-Corr - Priority - All MEP In-wall in Production Entry Fiber Rooms (Room #2.7) | Priority Wall Grid Line 6-16 / 6-17 | Not Started | 07/08/26 | 07/16/26 | 8.8 | 8.8 |
|
43.8 |
RPL06.INT.CTRC.9100 |
RPL06.Interior.Center-Corr - Priority GL6.16/6.17 - (P2) Tape Finish Paint (Both Sides) | Priority Wall Grid Line 6-16 / 6-17 | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
56.2 |
RPL06.INT.DHB.01140 |
RPL06.Interior.DHB - OFE - LV Skids and TopHat - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 07/08/26 | 07/28/26 | 18.8 | 18.8 |
|
-10.0 |
RPL06.INT.DHB.01150 |
RPL06.Interior.DHB - OFE - MES Skids - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 07/08/26 | 07/28/26 | 18.8 | 18.8 |
|
70.0 |
RPL06.INT.ENDC.1920 |
RPL06.Interior.End-Cor - Priority - Install Drywall at Exterior Walls | Priority Walls & Overhead | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
131.2 |
RPL06.INT.SBC.03420 |
RPL06.Interior.SSB-Corridor - BoW - Install Door Frames | Balance of Walls & Overhead | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
88.8 |
RPL06.INT.SBC.05800 |
RPL06.Interior.SSB-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside OH and in-wall | Balance of Walls & Overhead | Not Started | 07/08/26 | 07/17/26 | 10.0 | 10.0 |
|
63.8 |
RPL06.INT.SSB.01180 |
RPL06.Interior.SSB - BoW - Install Door Frames | Balance of Walls and OverHead | Not Started | 07/08/26 | 07/14/26 | 6.2 | 6.2 |
|
145.0 |
RPL06.INT.SSB.01210 |
RPL06.Interior.SSB - BoW - Install Electrical Lowside OH and In-wall | Balance of Walls and OverHead | Not Started | 07/08/26 | 07/21/26 | 12.5 | 12.5 |
|
123.8 |
RPL06.INT.SSB.01880 |
RPL06.Interior.SSB - Final Finishes & Fixtures - Frame/Blocking Walls & Ceilings | Final Finishes & Fixtures (Includes TFW, Restrooms, etc.) | Not Started | 07/08/26 | 07/21/26 | 12.5 | 12.5 |
|
235.0 |
DCC.B6.3300 |
[SSDCB1] Cabling Start : OSP Pathways - Primary GS | Connectivity | Not Started | 07/09/26 | 07/09/26 | 0.0 | 0.0 |
|
433.8 |
DCC.B6.3707 |
[SSDCB1] Cabling Start : General Services (GS) | Connectivity | Not Started | 07/09/26 | 07/09/26 | 0.0 | 0.0 |
|
433.8 |
RPL06.CON.WP2.08480 |
RPL06.Conn - Ext. GSIDF6X04 - Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 07/09/26 | 07/16/26 | 7.5 | 7.5 |
|
423.8 |
RPL06.CON.WP2.08540 |
RPL06.Conn - Ext. GSIDF6X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH A) | Cabling | Not Started | 07/09/26 | 07/10/26 | 2.5 | 2.5 |
|
238.8 |
RPL06.INT.SSBC.01060 |
RPL06.Interior.SSB-Corridor - OFE - Early Equipment (1x SSB Elect) (ROJ 05.13.26) (RVCD 07.08.26) | OFE/MOFE & CFCI | Not Started | 07/09/26 | 07/22/26 | 12.5 | 12.5 |
|
68.8 |
RPL06.INT.SSBC.3220 |
RPL06.Interior.SSBC LO #06 - Fire Safing OH and In-wall | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 07/09/26 | 07/09/26 | 1.2 | 1.2 |
|
120.0 |
RPL06.INT.SSBC.4200 |
RPL06.Interior.SSBC LO #07 - Mechanical Tie-In | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 07/09/26 | 07/10/26 | 2.5 | 2.5 |
|
113.8 |
RPL06.INT.SSBC.4300 |
RPL06.Interior.SSBC LO #07 - Electrical Tie-In | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 07/09/26 | 07/15/26 | 6.2 | 6.2 |
|
113.8 |
RPL06.MCUP.LP2.1760 |
RPL06.MCUP.Loop 2 - Install Lighting | Hardscape and Landscape | Not Started | 07/09/26 | 07/15/26 | 6.2 | 6.2 |
|
402.5 |
RPL06.EY.DHD.01120 |
RPL06.EY.DHD - Cure (High Early Mix) (Grid 6-17/6-23) | Foundations | Not Started | 07/10/26 | 07/16/26 | 8.8 | 8.8 |
|
180.0 |
RPL06.EY.DHD.01730 |
RPL06.EY.DHD - Install F/R/P Equipment Pads - 5-10 (Grid 6-23/6-28) (12'' Larger For Tolerance) | Foundations | Not Started | 07/10/26 | 07/20/26 | 8.8 | 8.8 |
|
131.2 |
RPL06.INT.SSBC.3260 |
RPL06.Interior.SSBC LO #06 - Install Backing | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 07/10/26 | 07/10/26 | 1.2 | 1.2 |
|
120.0 |
ICM.B6.1825 |
[SSDCB1] Delivery of MVS - Medium Voltage Switches (First Delivery) | Construction | Not Started | 07/13/26 | 07/13/26 | 0.0 | 0.0 |
|
20.0 |
RPL06.CON.WP2.08560 |
RPL06.Conn - Ext. GSIDF6X04 - Install Copper, WAPs, Security Camera & Access Control (EY-DH C) | Cabling | Not Started | 07/13/26 | 07/28/26 | 15.0 | 15.0 |
|
238.8 |
RPL06.EY.SSB.01170 |
RPL06.EY.SSB - Install Mechanical Main (include penetration detail) | Tie-ins | Not Started | 07/13/26 | 07/31/26 | 18.8 | 18.8 |
|
42.5 |
RPL06.INT.CTRC.01090 |
RPL06.Interior.Center-Corridor - Priority - Early Install Drywall for Ancillary Skid (Room #3.6) | Priority Wall Grid Line 6-16 / 6-17 | Not Started | 07/13/26 | 07/15/26 | 3.8 | 3.8 |
|
141.2 |
RPL06.INT.DHB.01180 |
RPL06.Interior.DHB - LV Skids and TopHat Tie-ins (LOE) | DHB - LV Skids and TopHat | Not Started | 07/13/26 | 08/11/26 | 27.5 | 27.5 |
|
75.0 |
RPL06.INT.DHB.01181 |
RPL06.Interior.DHB - LV Skids and TopHat - Set & Anchor Interconnects | DHB - LV Skids and TopHat | Not Started | 07/13/26 | 07/30/26 | 17.5 | 17.5 |
|
75.0 |
RPL06.INT.DHB.01190 |
RPL06.Interior.DHB - Tie-ins - WBS Summary | Tie-Ins | Not Started | 07/13/26 | 12/16/26 | 136.2 | 136.2 |
|
115.0 |
RPL06.INT.DHC.02110 |
RPL06.Interior.DHC - Priority - Install Plumbing | OverHead | Not Started | 07/13/26 | 07/17/26 | 6.2 | 6.2 |
|
335.0 |
RPL06.INT.ENDC.01140 |
RPL06.Interior.End-Corridor - Install Doors Frame Hardware | Fit out | Not Started | 07/13/26 | 07/17/26 | 6.2 | 6.2 |
|
180.0 |
RPL06.INT.ENDC.01150 |
RPL06.Interior.End-Corridor - Install Electrical OH and In-wall | Fit out | Not Started | 07/13/26 | 07/21/26 | 8.8 | 8.8 |
|
166.2 |
RPL06.INT.SSBC.3280 |
RPL06.Interior.SSBC LO #06 - QC - Backings/Walls | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 07/13/26 | 07/14/26 | 2.5 | 2.5 |
|
120.0 |
GCD.RPL06.1826 |
Delivery of RMU - (First Delivery) - RPL06 - DHA&B | Construction Milestones | Not Started | 07/14/26 | 07/14/26 | 0.0 | 0.0 |
|
18.8 |
RPL06.EY.ENDC.1910 |
RPL06.EY.DHD.T1 - HAC Prefab prior to install for DH B | Tent 1 | Not Started | 07/14/26 | 07/20/26 | 6.2 | 6.2 |
|
2.5 |