Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
3
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.SKN.DHCD.01030 RPL06.SKIN.DHCD - Install Awning over Doors Glazing, Doors and Ext Devices Not Started 07/14/26 07/20/26 6.2 6.2
0%
295.0
RPL06.CFCI.5270 Campus - Fabricate / Deliver - Asphalt / Paving (CFCI) Div. 32 - Asphalt/ Conc. Paving Not Started 07/15/26 08/04/26 18.8 18.8
0%
178.8
RPL06.CON.WP2.06000 RPL06.Conn - Interior GSIDFs - WBS Summary GS.IDF (Interior) Not Started 07/15/26 02/22/27 188.8 188.8
0%
240.0
RPL06.CON.WP2.06200 RPL06.Conn - GSIDF/DH B2 - WBS Summary Int. IDF OFE/MOFE - GSIDF6B2 Not Started 07/15/26 07/30/26 15.0 15.0
0%
382.5
RPL06.CON.WP2.06220 RPL06.Conn - GSIDF/DH B2 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 07/15/26 07/15/26 1.2 1.2
0%
226.2
RPL06.CON.WP2.06400 RPL06.Conn - GSIDF/DH A2 - WBS Summary Int. IDF OFE/MOFE - GSIDF6A2 Not Started 07/15/26 07/30/26 15.0 15.0
0%
382.5
RPL06.CON.WP2.06420 RPL06.Conn - GSIDF/DH A2 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 07/15/26 07/15/26 1.2 1.2
0%
238.8
RPL06.EY.DHB.01220 RPL06.EY.DHB - Install MV, RMUs & Electrical Panels (Qty 12) OFE Not Started 07/15/26 08/11/26 25.0 25.0
0%
18.8
RPL06.EY.DHB.01230 RPL06.EY.DHB - OFE - MV - WBS Summary OFE Not Started 07/15/26 09/14/26 53.8 53.8
0%
147.5
RPL06.INT.CTRC.01160 RPL06.Interior.Center-Corridor (N) - Install Fitout (Spoke Parts, Tech, SCR etc.) - WBS Summary Fit out (North) Not Started 07/15/26 02/10/27 180.0 180.0
0%
62.5
RPL06.INT.CTRC.01460 RPL06.Interior.Center-Corridor (N) - Install Lighting Fit out (North) Not Started 07/15/26 07/23/26 8.8 8.8
0%
171.2
RPL06.INT.DHB.01200 RPL06.Interior.DHB - MES Skids Tie-ins (LOE) DHB - MES Skids Not Started 07/15/26 08/27/26 40.0 40.0
0%
70.0
RPL06.INT.DHB.01201 RPL06.Interior.DHB - MES Skids - Set & Anchor Interconnects DHB - MES Skids Not Started 07/15/26 08/11/26 25.0 25.0
0%
70.0
RPL06.INT.ENDC.1080 RPL06.Interior.End-Cor - Priority - Tape Finish Paint Priority Soffit both sides (Top Out) & Draft Blanket Priority Walls & Overhead Not Started 07/15/26 07/23/26 8.8 8.8
0%
131.2
RPL06.INT.ENDC.1100 RPL06.Interior.End-Cor - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) Priority Walls & Overhead Not Started 07/15/26 07/21/26 6.2 6.2
0%
136.2
RPL06.INT.SSBC.3360 RPL06.Interior.SSBC LO #06 - Hang Drywall Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 07/15/26 07/16/26 2.5 2.5
0%
120.0
RPL06.CON.WP2.06240 RPL06.Conn - GSIDF/DH B2 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 07/16/26 07/23/26 7.5 7.5
0%
386.2
RPL06.CON.WP2.06260 RPL06.Conn - GSIDF/DH B2 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 07/16/26 07/28/26 11.2 11.2
0%
226.2
RPL06.CON.WP2.06440 RPL06.Conn - GSIDF/DH A2 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 07/16/26 07/23/26 7.5 7.5
0%
386.2
RPL06.CON.WP2.06460 RPL06.Conn - GSIDF/DH A2 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 07/16/26 07/28/26 11.2 11.2
0%
238.8
RPL06.INT.CTRC.01110 RPL06.Interior.Center-Corridor - Priority - Early Tape Finish Paint for Ancillary Skid (Room #3.6) Priority Wall Grid Line 6-16 / 6-17 Not Started 07/16/26 07/22/26 6.2 6.2
0%
141.2
RPL06.INT.SSBC.4220 RPL06.Interior.SSBC LO #07 - Fire Safing OH and In-wall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 07/16/26 07/16/26 1.2 1.2
0%
113.8
RPL06.MCUP.LP2.1860 RPL06.MCUP.Loop 2 - Install Mcup Paving Hardscape and Landscape Not Started 07/16/26 07/29/26 12.5 12.5
0%
402.5
RPL06.CON.WP2.08500 RPL06.Conn - Ext. GSIDF6X04 - Install & Test Network (FIM) Network Not Started 07/17/26 07/20/26 2.5 2.5
0%
423.8
RPL06.INT.CTRC.8980 RPL06.Interior.Center-Corr - Priority - Hang Drywall Rock all Production Entry Fiber Rooms (Room #2.7) Priority Wall Grid Line 6-16 / 6-17 Not Started 07/17/26 07/22/26 5.0 5.0
0%
43.8
RPL06.INT.DHB.01182 RPL06.Interior.DHB - LV Skids and TopHat - Maintenance and Reserve Busways DHB - LV Skids and TopHat Not Started 07/17/26 08/04/26 16.2 16.2
0%
75.0
RPL06.INT.SSBC.3400 RPL06.Interior.SSBC LO #06 - Tape Finish Paint Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 07/17/26 07/23/26 6.2 6.2
0%
120.0
RPL06.INT.SSBC.4260 RPL06.Interior.SSBC LO #07 - Install Backing Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 07/17/26 07/17/26 1.2 1.2
0%
113.8
GCD.RPL06.5605 [RPL06] FacNet Live RPL06 - All Exterior IDF huts TC-C Ready: FacNet Live Not Started 07/20/26 07/20/26 0.0 0.0
0%
423.8
GCD.RPL06.5745 [RPL06] TC-C Ready : All General Services [RPL06-Exterior IDFs] TC-C Ready: General Services Not Started 07/20/26 07/20/26 0.0 0.0
0%
423.8
RPL06.INT.DHB.01210 RPL06.Interior.DHB - OFE - Control Fault Domain 1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 1 Not Started 07/20/26 08/17/26 26.2 26.2
0%
30.0
RPL06.INT.DHB.02400 RPL06.Interior.DHB - OFE - Control Fault Domain 1 (LV Side Aisle) Control Fault Domain 1 Not Started 07/20/26 07/24/26 6.2 6.2
0%
-10.0
RPL06.INT.DHC.01050 RPL06.Interior.DHC - Priority - Install FA / Linear heat detection OverHead Not Started 07/20/26 07/24/26 6.2 6.2
0%
337.5
RPL06.INT.SBC.03280 RPL06.Interior.SSB-Corridor - BoW - Install Electrical Lowside OH and In-wall (Coord Lights location) Balance of Walls & Overhead Not Started 07/20/26 07/31/26 12.5 12.5
0%
63.8
RPL06.INT.SSB.02920 RPL06.Interior.SSB - Loading Dock and Storage - Install Headers and Top Out and Fire/Caulking Loading Dock and Storage Not Started 07/20/26 07/31/26 12.5 12.5
0%
150.0
RPL06.INT.SSBC.4280 RPL06.Interior.SSBC LO #07 - QC - Backings/Walls Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 07/20/26 07/21/26 2.5 2.5
0%
113.8
RPL06.EY.DHD.01750 RPL06.EY.DHD - Cure (High Early Mix) (Grid 6-23/6-28) Foundations Not Started 07/21/26 07/27/26 8.8 8.8
0%
191.2
RPL06.INT.DHB.02420 RPL06.Interior.DHB - OFE - Control Fault Domain 1 (HAC) Control Fault Domain 1 Not Started 07/21/26 08/14/26 23.8 23.8
0%
2.5
RPL06.INT.ENDC.06820 RPL06.Interior.End-Corridor - Final Finishes & Fixtures - MEP Rough-In Restrooms Not Started 07/21/26 07/27/26 6.2 6.2
0%
190.0
RPL06.SKN.DHCD.01040 RPL06.SKIN.DHCD - Install Louvers Glazing, Doors and Ext Devices Not Started 07/21/26 07/27/26 6.2 6.2
0%
295.0
RPL06.SKN.DHCD.01100 RPL06.SKIN.DHCD - Install Scupper and Downspouts Glazing, Doors and Ext Devices Not Started 07/21/26 07/27/26 6.2 6.2
0%
307.5
RPL06.EY.SSB.01250 RPL06.EY.SSB - Install Sleeves MEPL Hardscape and Landscape Not Started 07/22/26 07/28/26 6.2 6.2
0%
172.5
RPL06.EY.SSB.01270 RPL06.EY.SSB - Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 07/22/26 03/24/27 210.0 210.0
0%
212.5
RPL06.INT.CTRC.1080 RPL06.Interior.Center-Corridor - Priority - Install Mechanical Piping/ Refrigerant (Highside OH space) Priority Walls & Overhead Not Started 07/22/26 07/28/26 6.2 6.2
0%
37.5
RPL06.INT.DHA.01060 RPL06.Interior.DHA - OFE - LV Skids and TopHat - Set / Place / Anchor OFE/MOFE & CFCI Not Started 07/22/26 08/11/26 18.8 18.8
0%
-10.0
RPL06.INT.DHA.01070 RPL06.Interior.DHA - OFE - MES Skids - Set / Place / Anchor OFE/MOFE & CFCI Not Started 07/22/26 08/11/26 18.8 18.8
0%
57.5
RPL06.INT.DHB.01220 RPL06.Interior.DHB - Control Fault Domain 1 - Install Duct (LV Side) LV Side Tie-ins Not Started 07/22/26 07/28/26 6.2 6.2
0%
46.2
RPL06.INT.DHB.01250 RPL06.Interior.DHB - Tie-ins - Control Fault Domain 1 - WBS Summary Control Fault Domain 1 Not Started 07/22/26 10/01/26 63.8 63.8
0%
32.5
RPL06.INT.ENDC.01170 RPL06.Interior.End-Corridor - Install Security OH and In-wall Fit out Not Started 07/22/26 07/30/26 8.8 8.8
0%
177.5
RPL06.INT.ENDC.01180 RPL06.Interior.End-Corridor - Install Plumbing OH and In-wall Fit out Not Started 07/22/26 08/03/26 11.2 11.2
0%
180.0
RPL06.INT.ENDC.1140 RPL06.Interior.End-Cor - Priority - Install Plumbing (Highside OH space) Priority Walls & Overhead Not Started 07/22/26 07/28/26 6.2 6.2
0%
136.2
RPL06.INT.ENDC.1160 RPL06.Interior.End-Cor - Priority - Install FA (Highside OH space) Priority Walls & Overhead Not Started 07/22/26 07/28/26 6.2 6.2
0%
136.2
RPL06.INT.SSB.02860 RPL06.Interior.SSB - Final Finishes & Fixtures - MEP Rough-In Final Finishes & Fixtures (Includes TFW, Restrooms, etc.) Not Started 07/22/26 07/28/26 6.2 6.2
0%
235.0
RPL06.INT.SSB.05860 RPL06.Interior.SSB - BoW - BoW - Install Mechanical Piping/ Refrigerant (Lowside OH space) Balance of Walls and OverHead Not Started 07/22/26 07/28/26 6.2 6.2
0%
123.8
RPL06.INT.SSBC.4360 RPL06.Interior.SSBC LO #07 - Hang Drywall Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 07/22/26 07/23/26 2.5 2.5
0%
113.8
RPL06.INT.CTRC.9000 RPL06.Interior.Center-Corr - Priority - Tape, Paint & Finish Production Entry Fiber Rooms (Room #2.7) Priority Wall Grid Line 6-16 / 6-17 Not Started 07/23/26 07/29/26 6.2 6.2
0%
43.8
RPL06.INT.DHB.01202 RPL06.Interior.DHB - MES Skids - Piping Tie-Ins & Inspections DHB - MES Skids Not Started 07/23/26 08/19/26 25.0 25.0
0%
70.0
RPL06.INT.SBC.03300 RPL06.Interior.SSB-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls & Overhead Not Started 07/23/26 07/31/26 8.8 8.8
0%
78.8
RPL06.INT.SBC.03340 RPL06.Interior.SSB-Corridor - BoW - Install Security Lowside OH and In-wall Balance of Walls & Overhead Not Started 07/23/26 07/31/26 8.8 8.8
0%
156.2
RPL06.INT.SSB.14000 RPL06.Interior.Center-Corridor Leave Out #01 #02 #03 #04 #5 - SSB (for Elec. Room) WBS Summary Interior Leave Out Wall #01, #02, #03, #04, #05 SSB for Electrical Room Not Started 07/23/26 12/04/26 116.2 116.2
0%
72.5
RPL06.INT.SSB.14020 RPL06.Interior.SSB LO #01 to #05 - Install LO Framing OH & Framing Not Started 07/23/26 07/29/26 6.2 6.2
0%
72.5
RPL06.SKN.W.LO.01120 RPL06.SKIN.LO#16 - Close Exterior Leave Out #16 SSB (North of Loading Dock) WBS Summary Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) Not Started 07/23/26 09/04/26 40.0 40.0
0%
68.8
RPL06.SKN.W.LO.01380 RPL06.SKIN.LO#16 - Pour back Stemwall Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) Not Started 07/23/26 07/29/26 6.2 6.2
0%
68.8
RPL06.INT.DHA.01090 RPL06.Interior.DHA - LV Skids and TopHat Tie-ins (LOE) DHA - LV Skids and TopHat Not Started 07/24/26 08/24/26 27.5 27.5
0%
76.2
RPL06.INT.DHA.01091 RPL06.Interior.DHA - LV Skids and TopHat - Set & Anchor Interconnects DHA - LV Skids and TopHat Not Started 07/24/26 08/12/26 17.5 17.5
0%
76.2
RPL06.INT.DHA.01100 RPL06.Interior.DHA - Tie-ins - WBS Summary Tie-Ins Not Started 07/24/26 12/31/26 137.5 137.5
0%
115.0
RPL06.INT.DHA.02340 RPL06.Interior.DHA - Priority - Install Security OverHead Not Started 07/24/26 07/30/26 6.2 6.2
0%
241.2
RPL06.INT.DHB.01183 RPL06.Interior.DHB - LV Skids and TopHat - Top Hat Busway DHB - LV Skids and TopHat Not Started 07/24/26 08/11/26 16.2 16.2
0%
75.0
RPL06.INT.DHB.01310 RPL06.Interior.DHB - Control Fault Domain 1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 07/24/26 07/30/26 6.2 6.2
0%
55.0
RPL06.INT.DHB.02440 RPL06.Interior.DHB - OFE - Control Fault Domain 1 (Mech Side Aisle) Control Fault Domain 1 Not Started 07/24/26 08/17/26 21.2 21.2
0%
30.0
RPL06.INT.ENDC.1120 RPL06.Interior.End-Cor - Priority GL6.27 - (P3) Frame Walls (Incl. Ancillary Room #3.6) Priority Wall Grid Line 6-27 Not Started 07/24/26 07/30/26 6.2 6.2
0%
131.2
RPL06.INT.SSBC.3560 RPL06.Interior.SSBC LO #06 - Install Remaining Lights Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 07/24/26 07/28/26 3.8 3.8
0%
120.0
RPL06.INT.SSBC.3580 RPL06.Interior.SSBC LO #06 - Install Flooring Tiles/Resinous Flooring in specific rooms Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 07/24/26 07/28/26 3.8 3.8
0%
131.2
RPL06.INT.SSBC.3720 RPL06.Interior.SSBC LO #06 - Fire Safing / Wall Finishes Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 07/24/26 07/27/26 2.5 2.5
0%
127.5
RPL06.INT.SSBC.4400 RPL06.Interior.SSBC LO #07 - Tape Finish Paint Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 07/24/26 07/30/26 6.2 6.2
0%
113.8
RPL06.INT.DHB.01203 RPL06.Interior.DHB - MES Skids - CDU Tie-Ins DHB - MES Skids Not Started 07/27/26 08/21/26 25.0 25.0
0%
70.0
RPL06.INT.DHB.01320 RPL06.Interior.DHB - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 2 Not Started 07/27/26 09/08/26 38.8 38.8
0%
27.5
RPL06.INT.DHB.01330 RPL06.Interior.DHB - Control Fault Domain 1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 07/27/26 07/31/26 6.2 6.2
0%
55.0
RPL06.INT.DHB.02460 RPL06.Interior.DHB - OFE - Control Fault Domain 2 (LV Side Aisle) Control Fault Domain 2 Not Started 07/27/26 07/30/26 5.0 5.0
0%
20.0
RPL06.CON.WP2.09200 RPL06.Conn - CorpNet & FacNet Available (South EY) WP#02 GS Not Started 07/28/26 07/28/26 0.0 0.0
0%
416.2
RPL06.Conn.MS.01100 RPL06.Conn Wifi Ready - South EY (Pred from RPL10 CorpNet needed?) Connectivity Milestones Not Started 07/28/26 07/28/26 0.0 0.0
0%
238.8
RPL06.EY.ENDC.1930 RPL06.EY.DHD.T2 - HAC Prefab prior to install for DH A Tent 2 Not Started 07/28/26 08/03/26 6.2 6.2
0%
-10.0
RPL06.INT.ENDC.06860 RPL06.Interior.End-Corridor - Final Finishes & Fixtures - Hang Drywall and Fire/Caulking Restrooms Not Started 07/28/26 08/03/26 6.2 6.2
0%
202.5
RPL06.INT.ENDC.07040 RPL06.Interior.End-Corridor - Final Finishes & Fixtures - Framing RO Verification, Tile Finish & ADA Verification (Pre Restrooms Not Started 07/28/26 08/03/26 6.2 6.2
0%
190.0
RPL06.INT.ENDC.1200 RPL06.Interior.End-Cor - Priority - Install Fire Safing/ Seal Penetrations through Soffit (HighS. OH space) Priority Walls & Overhead Not Started 07/28/26 07/30/26 3.8 3.8
0%
136.2
RPL06.INT.ENDC.1420 RPL06.Interior.End-Cor - Priority - Fixed Draft/Smoke Curtain Patching Priority Walls & Overhead Not Started 07/28/26 07/30/26 3.8 3.8
0%
140.0
RPL06.INT.SSBC.3420 RPL06.Interior.SSBC LO #06 - Electrical Trim Out Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 07/28/26 07/29/26 2.5 2.5
0%
127.5
RPL06.INT.SSBC.3440 RPL06.Interior.SSBC LO #06 - Security Trim Out Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 07/28/26 07/29/26 2.5 2.5
0%
127.5
RPL06.SKN.DHCD.01050 RPL06.SKIN.DHCD - Install Lighting Glazing, Doors and Ext Devices Not Started 07/28/26 07/31/26 5.0 5.0
0%
295.0
DCC.B6.3245 [SSDCB1] CorpNet/Security/FacNet Ready [DHC] Connectivity Not Started 07/29/26 07/29/26 0.0 0.0
0%
382.5
DCC.B6.3255 [SSDCB1] CorpNet/Security/FacNet Ready [DHD] Connectivity Not Started 07/29/26 07/29/26 0.0 0.0
0%
382.5
RPL06.CON.WP2.06280 RPL06.Conn - GSIDF/DH B2 - Install & Test Network (FIM) Network Not Started 07/29/26 07/30/26 2.5 2.5
0%
382.5
RPL06.CON.WP2.06480 RPL06.Conn - GSIDF/DH A2 - Install & Test Network (FIM) Network Not Started 07/29/26 07/30/26 2.5 2.5
0%
382.5
RPL06.EY.DHA.01220 RPL06.EY.DHA - Install MV, RMUs & Electrical Panels (Qty10) OFE Not Started 07/29/26 08/25/26 25.0 25.0
0%
25.0
RPL06.EY.SSB.01290 RPL06.EY.SSB - Install Trash Enclosure (CMU) Hardscape and Landscape Not Started 07/29/26 08/25/26 25.0 25.0
0%
197.5
RPL06.INT.CTRC.1120 RPL06.Interior.Center-Corridor - Priority - Install Plumbing (Highside OH space) Priority Walls & Overhead Not Started 07/29/26 08/04/26 6.2 6.2
0%
37.5
RPL06.INT.CTRC.1140 RPL06.Interior.Center-Corridor - Priority - Install FA/ VESDA/ hangers & Heat Trace (Highside OH space) Priority Walls & Overhead Not Started 07/29/26 08/04/26 6.2 6.2
0%
37.5
RPL06.INT.DHA.01110 RPL06.Interior.DHA - MES Skids Tie-ins (LOE) DHA - MES Skids Not Started 07/29/26 09/11/26 40.0 40.0
0%
57.5
RPL06.INT.DHA.01111 RPL06.Interior.DHA - MES Skids - Set & Anchor Interconnects DHA - MES Skids Not Started 07/29/26 08/25/26 25.0 25.0
0%
57.5
RPL06.INT.DHB.01204 RPL06.Interior.DHB - MES Skids - BMS Tie-Ins DHB - MES Skids Not Started 07/29/26 08/25/26 25.0 25.0
0%
70.0