Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL06.INT.DHA.01210 |
RPL06.Interior.DHA - Control Fault Domain 1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 08/10/26 | 08/14/26 | 6.2 | 6.2 |
|
55.0 |
RPL06.INT.DHA.01230 |
RPL06.Interior.DHA - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 2 | Not Started | 08/10/26 | 09/22/26 | 38.8 | 38.8 |
|
18.8 |
RPL06.INT.DHA.03540 |
RPL06.Interior.DHA - OFE - Control Fault Domain 2 (LV Side Aisle) | Control Fault Domain 2 | Not Started | 08/10/26 | 08/13/26 | 5.0 | 5.0 |
|
2.5 |
RPL06.INT.DHB.01630 |
RPL06.Interior.DHB - Control Fault Domain 4 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 08/10/26 | 08/13/26 | 5.0 | 5.0 |
|
88.8 |
RPL06.INT.DHB.01660 |
RPL06.Interior.DHB - Tie-ins - Control Fault Domain 4 - WBS Summary | Control Fault Domain 4 | Not Started | 08/10/26 | 11/20/26 | 91.2 | 91.2 |
|
52.5 |
RPL06.INT.SSB.14160 |
RPL06.Interior.SSB LO #01 to #05 - Install Controls / EPMS / BMS OH and In-wall | OH & Framing | Not Started | 08/10/26 | 08/11/26 | 2.5 | 2.5 |
|
72.5 |
RPL06.INT.SSBC.3660 |
RPL06.Interior.SSBC LO #06 - Mechanical L2 Checklist Completion | Interior Leave Out Wall #06 SSB/SSBC North for MDF2 | Not Started | 08/10/26 | 08/21/26 | 12.5 | 12.5 |
|
127.5 |
RPL06.INT.SSBC.4640 |
RPL06.Interior.SSBC LO #07 - Electrical L2 Checklist Completion | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 08/10/26 | 08/21/26 | 12.5 | 12.5 |
|
121.2 |
RPL06.SKN.W.LO.01390 |
RPL06.SKIN.LO#16 - Stemwall Water Proofing | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 08/10/26 | 08/14/26 | 6.2 | 6.2 |
|
68.8 |
ICM.B6.1212 |
[SSDCB1] Start Flush & Fill of Chilled Water System | Commissioning | Not Started | 08/11/26 | 08/11/26 | 0.0 | 0.0 |
|
71.2 |
RPL.06.D.63720.XG |
RMUs/MV Skids Set (Ready for Longhorn Pulls) - DHB | Give Milestones (XREFs) | Not Started | 08/11/26 | 08/11/26 | 0.0 | 0.0 |
|
403.8 |
RPL.06.D.63960.XG |
Ready for MV Cable Pull DH B (MVs - Qty 10)* | Give Milestones (XREFs) | Not Started | 08/11/26 | 08/11/26 | 0.0 | 0.0 |
|
403.8 |
RPL.06.D.64210.XR |
FW Water Available for mCUP Flush/Fill - Utility connections | Receive Milestones (XREFs) | Not Started | 08/11/26 | 08/11/26 | 0.0 | 0.0 |
|
65.0 |
RPL.06.D.64410.XR |
Discharge Available for Fill/Flush Cx - Utility connections | Receive Milestones (XREFs) | Not Started | 08/11/26 | 08/11/26 | 0.0 | 0.0 |
|
65.0 |
RPL06.CX.MCUP.01150 |
RPL06.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup Yard & FWM - Loop 1 (mCUPs 1-4) (Phase 1) | Fill and Flush | Not Started | 08/11/26 | 08/17/26 | 6.2 | 6.2 |
|
65.0 |
RPL06.INT.ENDC.07080 |
RPL06.Interior.End-Corridor - Final Finishes & Fixtures - Water Proofing/ Tape Paint | Restrooms | Not Started | 08/11/26 | 08/17/26 | 6.2 | 6.2 |
|
190.0 |
RPL06.INT.ENDC.6100 |
RPL06.Interior.End-Corridor - Hang Early Drywall & DFH for Ancillary Skids (Room #3.6) | Priority Wall Grid Line 6-27 | Not Started | 08/11/26 | 08/12/26 | 2.5 | 2.5 |
|
147.5 |
RPL06.EY.DHB.01250 |
RPL06.EY.DHB - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 08/12/26 | 08/25/26 | 12.5 | 12.5 |
|
18.8 |
RPL06.EY.DHB.01260 |
RPL06.EY.DHB - Tie-ins - WBS Summary | Tie-ins | Not Started | 08/12/26 | 10/05/26 | 47.5 | 47.5 |
|
147.5 |
RPL06.EY.DHB.01520 |
RPL06.EY.DHB - Install Generator including Tie-ins (#1 of Qty 2) (ROJ 08/19/26) | OFE | Not Started | 08/12/26 | 08/18/26 | 6.2 | 6.2 |
|
52.5 |
RPL06.INT.CTRC.1260 |
RPL06.Interior.Center-Corridor - BoW - Install Electrical Lowside OH and In-wall and Lights (Coordinate Lights location | Balance of Walls & Overhead | Not Started | 08/12/26 | 08/25/26 | 12.5 | 12.5 |
|
37.5 |
RPL06.INT.CTRC.1400 |
RPL06.Interior.Center-Corridor - BoW - Install Door Frames | Balance of Walls & Overhead | Not Started | 08/12/26 | 08/18/26 | 6.2 | 6.2 |
|
52.5 |
RPL06.INT.DHA.01114 |
RPL06.Interior.DHA - MES Skids - BMS Tie-Ins ( 2 per day) | DHA - MES Skids | Not Started | 08/12/26 | 09/09/26 | 25.0 | 25.0 |
|
57.5 |
RPL06.INT.DHA.01260 |
RPL06.Interior.DHA - Control Fault Domain 2 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 08/12/26 | 08/17/26 | 5.0 | 5.0 |
|
77.5 |
RPL06.INT.DHA.01300 |
RPL06.Interior.DHA - Tie-ins - Control Fault Domain 2 - WBS Summary | Control Fault Domain 2 | Not Started | 08/12/26 | 11/05/26 | 76.2 | 76.2 |
|
45.0 |
RPL06.INT.DHB.01720 |
RPL06.Interior.DHB - OFE - Control Fault Domain 5 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 5 | Not Started | 08/12/26 | 11/04/26 | 75.0 | 75.0 |
|
17.5 |
RPL06.INT.DHB.01740 |
RPL06.Interior.DHB - Control Fault Domain 4 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 08/12/26 | 08/17/26 | 5.0 | 5.0 |
|
112.5 |
RPL06.INT.DHB.02640 |
RPL06.Interior.DHB - OFE - Control Fault Domain 5 (LV Side Aisle) | Control Fault Domain 5 | Not Started | 08/12/26 | 08/17/26 | 5.0 | 5.0 |
|
57.5 |
RPL06.INT.DHD.01060 |
RPL06.Interior.DHD - OFE - LV Skids and TopHat - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 08/12/26 | 08/28/26 | 16.2 | 16.2 |
|
58.8 |
RPL06.INT.DHD.01070 |
RPL06.Interior.DHD - OFE - MES Skids - Set / Place / Anchor | OFE/MOFE & CFCI | Not Started | 08/12/26 | 08/28/26 | 16.2 | 16.2 |
|
88.8 |
RPL06.INT.DHD.02210 |
RPL06.Interior.DHD - Priority - Install Temp Doors Frame Hardware | OverHead | Not Started | 08/12/26 | 08/14/26 | 3.8 | 3.8 |
|
310.0 |
RPL06.INT.SBC.03360 |
RPL06.Interior.SSB-Corridor - BoW - Install VAV's/Duct Branches | Balance of Walls & Overhead | Not Started | 08/12/26 | 08/18/26 | 6.2 | 6.2 |
|
86.2 |
RPL06.INT.SBC.03460 |
RPL06.Interior.SSB-Corridor - BoW - Mechanical Tie-Ins | Balance of Walls & Overhead | Not Started | 08/12/26 | 08/18/26 | 6.2 | 6.2 |
|
63.8 |
RPL06.INT.SSB.06700 |
RPL06.Interior.SSB - Final Finishes & Fixtures - Water Proofing/ Tape Paint | Final Finishes & Fixtures (Includes TFW, Restrooms, etc.) | Not Started | 08/12/26 | 08/18/26 | 6.2 | 6.2 |
|
235.0 |
RPL06.INT.SSB.14240 |
RPL06.Interior.SSB LO #01 to #05 - Install Electrical Lowside OH and In-wall | OH & Framing | Not Started | 08/12/26 | 08/20/26 | 8.8 | 8.8 |
|
72.5 |
RPL06.INT.SSBC.03380 |
RPL06.Interior.SSB-Corridor - Set Equipment Interior (CRAC Units) | OFE/MOFE & CFCI | Not Started | 08/12/26 | 08/18/26 | 6.2 | 6.2 |
|
141.2 |
RPL06.SKN.S.LO.01100 |
RPL06.SKIN.LO#17 - Close Exterior Leave Out #17 CC (South) WBS Summary | Build back Exterior Leave Out Walls #17 (CC - South) | Not Started | 08/12/26 | 09/03/26 | 21.2 | 21.2 |
|
86.2 |
RPL06.SKN.S.LO.03020 |
RPL06.SKIN.LO#17 - Pour back Stemwall | Build back Exterior Leave Out Walls #17 (CC - South) | Not Started | 08/12/26 | 08/13/26 | 2.5 | 2.5 |
|
86.2 |
RPL06.INT.DHB.01260 |
RPL06.Interior.DHB - Control Fault Domain 1 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/13/26 | 09/10/26 | 25.0 | 25.0 |
|
45.0 |
RPL06.INT.DHB.01270 |
RPL06.Interior.DHB - Control Fault Domain 1 - Pull EPMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/13/26 | 09/10/26 | 25.0 | 25.0 |
|
45.0 |
RPL06.INT.DHB.01280 |
RPL06.Interior.DHB - Control Fault Domain 1 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/13/26 | 09/10/26 | 25.0 | 25.0 |
|
32.5 |
RPL06.INT.DHB.01750 |
RPL06.Interior.DHB - Control Fault Domain 4 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 08/13/26 | 08/18/26 | 5.0 | 5.0 |
|
135.0 |
RPL06.INT.ENDC.1240 |
RPL06.Interior.End-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside OH and in-wall | Balance of Walls & Overhead | Not Started | 08/13/26 | 08/19/26 | 6.2 | 6.2 |
|
131.2 |
RPL06.INT.ENDC.1400 |
RPL06.Interior.End-Corridor - BoW - Install Door Frames | Balance of Walls & Overhead | Not Started | 08/13/26 | 08/19/26 | 6.2 | 6.2 |
|
221.2 |
RPL06.INT.ENDC.6120 |
RPL06.Interior.End-Corridor - Early Tape Finish Paint for Ancillary Skids (Room #3.6) | Priority Wall Grid Line 6-27 | Not Started | 08/13/26 | 08/19/26 | 6.2 | 6.2 |
|
147.5 |
RPL06.INT.SSB.01190 |
RPL06.Interior.SSB - Loading Dock and Storage - Install Electrical Rough-In | Loading Dock and Storage | Not Started | 08/13/26 | 08/21/26 | 8.8 | 8.8 |
|
153.8 |
RPL06.INT.SSB.01740 |
RPL06.Interior.SSB - Loading Dock and Storage - Install VAV's/Duct Branches | Loading Dock and Storage | Not Started | 08/13/26 | 08/26/26 | 12.5 | 12.5 |
|
150.0 |
RPL06.INT.SSB.02940 |
RPL06.Interior.SSB - Loading Dock and Storage - Install Blocking/Steel support Assembly for Metal Canopy | Loading Dock and Storage | Not Started | 08/13/26 | 08/19/26 | 6.2 | 6.2 |
|
173.8 |
RPL06.EY.DHB.01280 |
RPL06.EY.DHB - Install BMS/EPMS Tie-ins | Tie-ins | Not Started | 08/14/26 | 08/27/26 | 12.5 | 12.5 |
|
18.8 |
RPL06.INT.CTRC.1960 |
RPL06.Interior.Center-Corridor - BoW - Install Horizontal Steel Supports for Cable Tray (IFP Add) | Balance of Walls & Overhead | Not Started | 08/14/26 | 08/21/26 | 7.5 | 7.5 |
|
43.8 |
RPL06.INT.DHA.01115 |
RPL06.Interior.DHA - MES Skids - EPMS Tie-Ins ( 2 per day) | DHA - MES Skids | Not Started | 08/14/26 | 09/11/26 | 25.0 | 25.0 |
|
57.5 |
RPL06.INT.DHA.01350 |
RPL06.Interior.DHA - OFE - Control Fault Domain 3 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 3 | Not Started | 08/14/26 | 10/12/26 | 51.2 | 51.2 |
|
16.2 |
RPL06.INT.DHA.01370 |
RPL06.Interior.DHA - Control Fault Domain 2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 08/14/26 | 08/19/26 | 5.0 | 5.0 |
|
86.2 |
RPL06.INT.DHA.03600 |
RPL06.Interior.DHA - OFE - Control Fault Domain 3 (LV Side Aisle) | Control Fault Domain 3 | Not Started | 08/14/26 | 08/19/26 | 5.0 | 5.0 |
|
21.2 |
RPL06.INT.DHB.01770 |
RPL06.Interior.DHB - Control Fault Domain 5 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 08/14/26 | 08/19/26 | 5.0 | 5.0 |
|
85.0 |
RPL06.INT.DHB.01800 |
RPL06.Interior.DHB - Tie-ins - Control Fault Domain 5 - WBS Summary | Control Fault Domain 5 | Not Started | 08/14/26 | 12/15/26 | 105.0 | 105.0 |
|
26.2 |
RPL06.INT.DHC.02130 |
RPL06.Interior.DHC - Priority - Install Mechanical Piping | OverHead | Not Started | 08/14/26 | 08/31/26 | 15.0 | 15.0 |
|
305.0 |
RPL06.INT.DHD.01090 |
RPL06.Interior.DHD - LV Skids and TopHat Tie-ins (LOE) | DHD - LV Skids and TopHat | Not Started | 08/14/26 | 09/14/26 | 26.2 | 26.2 |
|
141.2 |
RPL06.INT.DHD.01091 |
RPL06.Interior.DHD - LV Skids and TopHat - Set & Anchor Interconnects | DHD - LV Skids and TopHat | Not Started | 08/14/26 | 09/01/26 | 16.2 | 16.2 |
|
141.2 |
RPL06.INT.DHD.01100 |
RPL06.Interior.DHD - Tie-ins - WBS Summary | Tie-Ins | Not Started | 08/14/26 | 02/18/27 | 158.8 | 158.8 |
|
158.8 |
RPL06.INT.SSB.01290 |
RPL06.Interior.SSB - BoW - Frame Hard Lid | Balance of Walls and OverHead | Not Started | 08/14/26 | 08/20/26 | 6.2 | 6.2 |
|
123.8 |
RPL06.INT.SSBC.01410 |
RPL06.Interior.SSB-Corridor - Battery Connection | Fit out | Not Started | 08/14/26 | 08/20/26 | 6.2 | 6.2 |
|
128.8 |
RPL06.SKN.S.LO.03040 |
RPL06.SKIN.LO#17 - Cure Stemwall | Build back Exterior Leave Out Walls #17 (CC - South) | Not Started | 08/14/26 | 08/24/26 | 8.8 | 8.8 |
|
86.2 |
GCD.RPL06.1725 |
Start FSHAC set in place - RPL06 - DHA&B | Construction Milestones | Not Started | 08/17/26 | 08/17/26 | 0.0 | 0.0 |
|
231.2 |
RPL.06.D.63310.XR |
Pull and Term MV Skids - RPL06 DHA | Receive Milestones (XREFs) | Not Started | 08/17/26 | 08/17/26 | 0.0 | 0.0 |
|
55.0 |
RPL.06.D.63810.XR |
100MW Cx Temp Power to MV Skids RPL06 DHA Available | Receive Milestones (XREFs) | Not Started | 08/17/26 | 08/17/26 | 0.0 | 0.0 |
|
55.0 |
RPL06.INT.DHA.01380 |
RPL06.Interior.DHA - Control Fault Domain 2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 08/17/26 | 08/20/26 | 5.0 | 5.0 |
|
86.2 |
RPL06.INT.DHB.02480 |
RPL06.Interior.DHB - OFE - Control Fault Domain 2 (HAC) | Control Fault Domain 2 | Not Started | 08/17/26 | 09/04/26 | 18.8 | 18.8 |
|
2.5 |
RPL06.INT.DHD.02170 |
RPL06.Interior.DHD - Priority - Install Security | OverHead | Not Started | 08/17/26 | 08/18/26 | 2.5 | 2.5 |
|
310.0 |
RPL06.INT.SSBC.4660 |
RPL06.Interior.SSBC LO #07 - Mechanical L2 Checklist Completion | Interior Leave Out Wall #07 SSB/SSBC South for MDF1 | Not Started | 08/17/26 | 08/28/26 | 12.5 | 12.5 |
|
121.2 |
RPL06.SKN.W.LO.01395 |
RPL06.SKIN.LO#16 - Install IMP Flashing | Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) | Not Started | 08/17/26 | 08/21/26 | 6.2 | 6.2 |
|
68.8 |
GCD.RPL06.1827 |
Delivery of RMU - (First Delivery) - RPL06 - DHC&D | Construction Milestones | Not Started | 08/18/26 | 08/18/26 | 0.0 | 0.0 |
|
93.8 |
RPL06.CX.MCUP.01190 |
RPL06.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup1 and Dry Coolers | Fill and Flush | Not Started | 08/18/26 | 08/25/26 | 7.5 | 7.5 |
|
65.0 |
RPL06.CX.MCUP.01210 |
RPL06.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup2 and Dry Coolers | Fill and Flush | Not Started | 08/18/26 | 08/25/26 | 7.5 | 7.5 |
|
65.0 |
RPL06.INT.CTRC.1280 |
RPL06.Interior.Center-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall | Balance of Walls & Overhead | Not Started | 08/18/26 | 08/26/26 | 8.8 | 8.8 |
|
51.2 |
RPL06.INT.DHA.01400 |
RPL06.Interior.DHA - Control Fault Domain 3 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 08/18/26 | 08/21/26 | 5.0 | 5.0 |
|
91.2 |
RPL06.INT.DHA.01430 |
RPL06.Interior.DHA - Tie-ins - Control Fault Domain 3 (including IDF) - WBS Summary | Control Fault Domain 3 | Not Started | 08/18/26 | 11/17/26 | 80.0 | 80.0 |
|
72.5 |
RPL06.INT.DHB.01870 |
RPL06.Interior.DHB - Control Fault Domain 5 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 08/18/26 | 08/21/26 | 5.0 | 5.0 |
|
106.2 |
RPL06.INT.DHC.02150 |
RPL06.Interior.DHC - Priority - Install Electrical | OverHead | Not Started | 08/18/26 | 08/31/26 | 12.5 | 12.5 |
|
305.0 |
RPL06.INT.ENDC.06960 |
RPL06.Interior.End-Corridor - Final Finishes & Fixtures - Casework | Restrooms | Not Started | 08/18/26 | 08/26/26 | 8.8 | 8.8 |
|
190.0 |
RPL06.INT.SSBC.01400 |
RPL06.Interior.SSB-Corridor - Install Grounding | Fit out | Not Started | 08/18/26 | 08/20/26 | 3.8 | 3.8 |
|
135.0 |
RPL06.EY.DHD.01220 |
RPL06.EY.DHD - Install MV, RMUs & Electrical Panels (Qty8) | OFE | Not Started | 08/19/26 | 09/16/26 | 25.0 | 25.0 |
|
93.8 |
RPL06.EY.DHD.01230 |
RPL06.EY.DHD - OFE - MV - WBS Summary | OFE | Not Started | 08/19/26 | 03/05/27 | 168.8 | 168.8 |
|
103.8 |
RPL06.INT.DHB.01890 |
RPL06.Interior.DHB - Control Fault Domain 5 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 08/19/26 | 08/24/26 | 5.0 | 5.0 |
|
106.2 |
RPL06.INT.DHD.01110 |
RPL06.Interior.DHD - MES Skids Tie-ins (LOE) | DHD - MES Skids | Not Started | 08/19/26 | 09/28/26 | 35.0 | 35.0 |
|
118.8 |
RPL06.INT.DHD.01111 |
RPL06.Interior.DHD - MES Skids - Set & Anchor Interconnects | DHD - MES Skids | Not Started | 08/19/26 | 09/10/26 | 20.0 | 20.0 |
|
118.8 |
RPL06.INT.DHD.02190 |
RPL06.Interior.DHD - Priority - Install Controls / EPMS / BMS | OverHead | Not Started | 08/19/26 | 08/21/26 | 3.8 | 3.8 |
|
310.0 |
RPL06.INT.SBC.03400 |
RPL06.Interior.SSB-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall | Balance of Walls & Overhead | Not Started | 08/19/26 | 08/25/26 | 6.2 | 6.2 |
|
86.2 |
RPL06.INT.SBC.03480 |
RPL06.Interior.SSB-Corridor - BoW - Frame Hard Lid | Balance of Walls & Overhead | Not Started | 08/19/26 | 08/25/26 | 6.2 | 6.2 |
|
63.8 |
RPL06.INT.SSB.01900 |
RPL06.Interior.SSB - Final Finishes & Fixtures - Casework | Final Finishes & Fixtures (Includes TFW, Restrooms, etc.) | Not Started | 08/19/26 | 08/27/26 | 8.8 | 8.8 |
|
235.0 |
DCC.B6.3145 |
[SSDCB1] GS Gear Delivered [DHC] | Connectivity | Not Started | 08/20/26 | 08/20/26 | 0.0 | 0.0 |
|
396.2 |
DCC.B6.3155 |
[SSDCB1] GS Gear Delivered [DHD] | Connectivity | Not Started | 08/20/26 | 08/20/26 | 0.0 | 0.0 |
|
396.2 |
RPL06.INT.DHA.01140 |
RPL06.Interior.DHA - Control Fault Domain 1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/20/26 | 09/17/26 | 25.0 | 25.0 |
|
45.0 |
RPL06.INT.DHA.01150 |
RPL06.Interior.DHA - Control Fault Domain 1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/20/26 | 09/17/26 | 25.0 | 25.0 |
|
32.5 |
RPL06.INT.DHA.01490 |
RPL06.Interior.DHA - OFE - Control Fault Domain 4 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | Control Fault Domain 4 | Not Started | 08/20/26 | 10/29/26 | 62.5 | 62.5 |
|
13.8 |
RPL06.INT.DHA.01510 |
RPL06.Interior.DHA - Control Fault Domain 3 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 08/20/26 | 08/25/26 | 5.0 | 5.0 |
|
115.0 |
RPL06.INT.DHA.02180 |
RPL06.Interior.DHA - Control Fault Domain 1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/20/26 | 09/17/26 | 25.0 | 25.0 |
|
32.5 |
RPL06.INT.DHA.03660 |
RPL06.Interior.DHA - OFE - Control Fault Domain 4 (LV Side Aisle) | Control Fault Domain 4 | Not Started | 08/20/26 | 08/25/26 | 5.0 | 5.0 |
|
33.8 |
RPL06.INT.DHA.03780 |
RPL06.Interior.DHA - Control Fault Domain 1 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/20/26 | 09/17/26 | 25.0 | 25.0 |
|
32.5 |
RPL06.INT.DHB.01300 |
RPL06.Interior.DHB - Control Fault Domain 1 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 08/20/26 | 09/17/26 | 25.0 | 25.0 |
|
32.5 |