Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.INT.DHA.01210 RPL06.Interior.DHA - Control Fault Domain 1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 08/10/26 08/14/26 6.2 6.2
0%
55.0
RPL06.INT.DHA.01230 RPL06.Interior.DHA - OFE - Control Fault Domain 2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 2 Not Started 08/10/26 09/22/26 38.8 38.8
0%
18.8
RPL06.INT.DHA.03540 RPL06.Interior.DHA - OFE - Control Fault Domain 2 (LV Side Aisle) Control Fault Domain 2 Not Started 08/10/26 08/13/26 5.0 5.0
0%
2.5
RPL06.INT.DHB.01630 RPL06.Interior.DHB - Control Fault Domain 4 - Install Duct (LV Side) LV Side Tie-ins Not Started 08/10/26 08/13/26 5.0 5.0
0%
88.8
RPL06.INT.DHB.01660 RPL06.Interior.DHB - Tie-ins - Control Fault Domain 4 - WBS Summary Control Fault Domain 4 Not Started 08/10/26 11/20/26 91.2 91.2
0%
52.5
RPL06.INT.SSB.14160 RPL06.Interior.SSB LO #01 to #05 - Install Controls / EPMS / BMS OH and In-wall OH & Framing Not Started 08/10/26 08/11/26 2.5 2.5
0%
72.5
RPL06.INT.SSBC.3660 RPL06.Interior.SSBC LO #06 - Mechanical L2 Checklist Completion Interior Leave Out Wall #06 SSB/SSBC North for MDF2 Not Started 08/10/26 08/21/26 12.5 12.5
0%
127.5
RPL06.INT.SSBC.4640 RPL06.Interior.SSBC LO #07 - Electrical L2 Checklist Completion Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 08/10/26 08/21/26 12.5 12.5
0%
121.2
RPL06.SKN.W.LO.01390 RPL06.SKIN.LO#16 - Stemwall Water Proofing Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) Not Started 08/10/26 08/14/26 6.2 6.2
0%
68.8
ICM.B6.1212 [SSDCB1] Start Flush & Fill of Chilled Water System Commissioning Not Started 08/11/26 08/11/26 0.0 0.0
0%
71.2
RPL.06.D.63720.XG RMUs/MV Skids Set (Ready for Longhorn Pulls) - DHB Give Milestones (XREFs) Not Started 08/11/26 08/11/26 0.0 0.0
0%
403.8
RPL.06.D.63960.XG Ready for MV Cable Pull DH B (MVs - Qty 10)* Give Milestones (XREFs) Not Started 08/11/26 08/11/26 0.0 0.0
0%
403.8
RPL.06.D.64210.XR FW Water Available for mCUP Flush/Fill - Utility connections Receive Milestones (XREFs) Not Started 08/11/26 08/11/26 0.0 0.0
0%
65.0
RPL.06.D.64410.XR Discharge Available for Fill/Flush Cx - Utility connections Receive Milestones (XREFs) Not Started 08/11/26 08/11/26 0.0 0.0
0%
65.0
RPL06.CX.MCUP.01150 RPL06.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup Yard & FWM - Loop 1 (mCUPs 1-4) (Phase 1) Fill and Flush Not Started 08/11/26 08/17/26 6.2 6.2
0%
65.0
RPL06.INT.ENDC.07080 RPL06.Interior.End-Corridor - Final Finishes & Fixtures - Water Proofing/ Tape Paint Restrooms Not Started 08/11/26 08/17/26 6.2 6.2
0%
190.0
RPL06.INT.ENDC.6100 RPL06.Interior.End-Corridor - Hang Early Drywall & DFH for Ancillary Skids (Room #3.6) Priority Wall Grid Line 6-27 Not Started 08/11/26 08/12/26 2.5 2.5
0%
147.5
RPL06.EY.DHB.01250 RPL06.EY.DHB - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 08/12/26 08/25/26 12.5 12.5
0%
18.8
RPL06.EY.DHB.01260 RPL06.EY.DHB - Tie-ins - WBS Summary Tie-ins Not Started 08/12/26 10/05/26 47.5 47.5
0%
147.5
RPL06.EY.DHB.01520 RPL06.EY.DHB - Install Generator including Tie-ins (#1 of Qty 2) (ROJ 08/19/26) OFE Not Started 08/12/26 08/18/26 6.2 6.2
0%
52.5
RPL06.INT.CTRC.1260 RPL06.Interior.Center-Corridor - BoW - Install Electrical Lowside OH and In-wall and Lights (Coordinate Lights location Balance of Walls & Overhead Not Started 08/12/26 08/25/26 12.5 12.5
0%
37.5
RPL06.INT.CTRC.1400 RPL06.Interior.Center-Corridor - BoW - Install Door Frames Balance of Walls & Overhead Not Started 08/12/26 08/18/26 6.2 6.2
0%
52.5
RPL06.INT.DHA.01114 RPL06.Interior.DHA - MES Skids - BMS Tie-Ins ( 2 per day) DHA - MES Skids Not Started 08/12/26 09/09/26 25.0 25.0
0%
57.5
RPL06.INT.DHA.01260 RPL06.Interior.DHA - Control Fault Domain 2 - Install Duct (LV Side) LV Side Tie-ins Not Started 08/12/26 08/17/26 5.0 5.0
0%
77.5
RPL06.INT.DHA.01300 RPL06.Interior.DHA - Tie-ins - Control Fault Domain 2 - WBS Summary Control Fault Domain 2 Not Started 08/12/26 11/05/26 76.2 76.2
0%
45.0
RPL06.INT.DHB.01720 RPL06.Interior.DHB - OFE - Control Fault Domain 5 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 5 Not Started 08/12/26 11/04/26 75.0 75.0
0%
17.5
RPL06.INT.DHB.01740 RPL06.Interior.DHB - Control Fault Domain 4 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 08/12/26 08/17/26 5.0 5.0
0%
112.5
RPL06.INT.DHB.02640 RPL06.Interior.DHB - OFE - Control Fault Domain 5 (LV Side Aisle) Control Fault Domain 5 Not Started 08/12/26 08/17/26 5.0 5.0
0%
57.5
RPL06.INT.DHD.01060 RPL06.Interior.DHD - OFE - LV Skids and TopHat - Set / Place / Anchor OFE/MOFE & CFCI Not Started 08/12/26 08/28/26 16.2 16.2
0%
58.8
RPL06.INT.DHD.01070 RPL06.Interior.DHD - OFE - MES Skids - Set / Place / Anchor OFE/MOFE & CFCI Not Started 08/12/26 08/28/26 16.2 16.2
0%
88.8
RPL06.INT.DHD.02210 RPL06.Interior.DHD - Priority - Install Temp Doors Frame Hardware OverHead Not Started 08/12/26 08/14/26 3.8 3.8
0%
310.0
RPL06.INT.SBC.03360 RPL06.Interior.SSB-Corridor - BoW - Install VAV's/Duct Branches Balance of Walls & Overhead Not Started 08/12/26 08/18/26 6.2 6.2
0%
86.2
RPL06.INT.SBC.03460 RPL06.Interior.SSB-Corridor - BoW - Mechanical Tie-Ins Balance of Walls & Overhead Not Started 08/12/26 08/18/26 6.2 6.2
0%
63.8
RPL06.INT.SSB.06700 RPL06.Interior.SSB - Final Finishes & Fixtures - Water Proofing/ Tape Paint Final Finishes & Fixtures (Includes TFW, Restrooms, etc.) Not Started 08/12/26 08/18/26 6.2 6.2
0%
235.0
RPL06.INT.SSB.14240 RPL06.Interior.SSB LO #01 to #05 - Install Electrical Lowside OH and In-wall OH & Framing Not Started 08/12/26 08/20/26 8.8 8.8
0%
72.5
RPL06.INT.SSBC.03380 RPL06.Interior.SSB-Corridor - Set Equipment Interior (CRAC Units) OFE/MOFE & CFCI Not Started 08/12/26 08/18/26 6.2 6.2
0%
141.2
RPL06.SKN.S.LO.01100 RPL06.SKIN.LO#17 - Close Exterior Leave Out #17 CC (South) WBS Summary Build back Exterior Leave Out Walls #17 (CC - South) Not Started 08/12/26 09/03/26 21.2 21.2
0%
86.2
RPL06.SKN.S.LO.03020 RPL06.SKIN.LO#17 - Pour back Stemwall Build back Exterior Leave Out Walls #17 (CC - South) Not Started 08/12/26 08/13/26 2.5 2.5
0%
86.2
RPL06.INT.DHB.01260 RPL06.Interior.DHB - Control Fault Domain 1 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 08/13/26 09/10/26 25.0 25.0
0%
45.0
RPL06.INT.DHB.01270 RPL06.Interior.DHB - Control Fault Domain 1 - Pull EPMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 08/13/26 09/10/26 25.0 25.0
0%
45.0
RPL06.INT.DHB.01280 RPL06.Interior.DHB - Control Fault Domain 1 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 08/13/26 09/10/26 25.0 25.0
0%
32.5
RPL06.INT.DHB.01750 RPL06.Interior.DHB - Control Fault Domain 4 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 08/13/26 08/18/26 5.0 5.0
0%
135.0
RPL06.INT.ENDC.1240 RPL06.Interior.End-Corridor - BoW - Install Mechanical Piping/ Refrigerant Lowside OH and in-wall Balance of Walls & Overhead Not Started 08/13/26 08/19/26 6.2 6.2
0%
131.2
RPL06.INT.ENDC.1400 RPL06.Interior.End-Corridor - BoW - Install Door Frames Balance of Walls & Overhead Not Started 08/13/26 08/19/26 6.2 6.2
0%
221.2
RPL06.INT.ENDC.6120 RPL06.Interior.End-Corridor - Early Tape Finish Paint for Ancillary Skids (Room #3.6) Priority Wall Grid Line 6-27 Not Started 08/13/26 08/19/26 6.2 6.2
0%
147.5
RPL06.INT.SSB.01190 RPL06.Interior.SSB - Loading Dock and Storage - Install Electrical Rough-In Loading Dock and Storage Not Started 08/13/26 08/21/26 8.8 8.8
0%
153.8
RPL06.INT.SSB.01740 RPL06.Interior.SSB - Loading Dock and Storage - Install VAV's/Duct Branches Loading Dock and Storage Not Started 08/13/26 08/26/26 12.5 12.5
0%
150.0
RPL06.INT.SSB.02940 RPL06.Interior.SSB - Loading Dock and Storage - Install Blocking/Steel support Assembly for Metal Canopy Loading Dock and Storage Not Started 08/13/26 08/19/26 6.2 6.2
0%
173.8
RPL06.EY.DHB.01280 RPL06.EY.DHB - Install BMS/EPMS Tie-ins Tie-ins Not Started 08/14/26 08/27/26 12.5 12.5
0%
18.8
RPL06.INT.CTRC.1960 RPL06.Interior.Center-Corridor - BoW - Install Horizontal Steel Supports for Cable Tray (IFP Add) Balance of Walls & Overhead Not Started 08/14/26 08/21/26 7.5 7.5
0%
43.8
RPL06.INT.DHA.01115 RPL06.Interior.DHA - MES Skids - EPMS Tie-Ins ( 2 per day) DHA - MES Skids Not Started 08/14/26 09/11/26 25.0 25.0
0%
57.5
RPL06.INT.DHA.01350 RPL06.Interior.DHA - OFE - Control Fault Domain 3 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 3 Not Started 08/14/26 10/12/26 51.2 51.2
0%
16.2
RPL06.INT.DHA.01370 RPL06.Interior.DHA - Control Fault Domain 2 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 08/14/26 08/19/26 5.0 5.0
0%
86.2
RPL06.INT.DHA.03600 RPL06.Interior.DHA - OFE - Control Fault Domain 3 (LV Side Aisle) Control Fault Domain 3 Not Started 08/14/26 08/19/26 5.0 5.0
0%
21.2
RPL06.INT.DHB.01770 RPL06.Interior.DHB - Control Fault Domain 5 - Install Duct (LV Side) LV Side Tie-ins Not Started 08/14/26 08/19/26 5.0 5.0
0%
85.0
RPL06.INT.DHB.01800 RPL06.Interior.DHB - Tie-ins - Control Fault Domain 5 - WBS Summary Control Fault Domain 5 Not Started 08/14/26 12/15/26 105.0 105.0
0%
26.2
RPL06.INT.DHC.02130 RPL06.Interior.DHC - Priority - Install Mechanical Piping OverHead Not Started 08/14/26 08/31/26 15.0 15.0
0%
305.0
RPL06.INT.DHD.01090 RPL06.Interior.DHD - LV Skids and TopHat Tie-ins (LOE) DHD - LV Skids and TopHat Not Started 08/14/26 09/14/26 26.2 26.2
0%
141.2
RPL06.INT.DHD.01091 RPL06.Interior.DHD - LV Skids and TopHat - Set & Anchor Interconnects DHD - LV Skids and TopHat Not Started 08/14/26 09/01/26 16.2 16.2
0%
141.2
RPL06.INT.DHD.01100 RPL06.Interior.DHD - Tie-ins - WBS Summary Tie-Ins Not Started 08/14/26 02/18/27 158.8 158.8
0%
158.8
RPL06.INT.SSB.01290 RPL06.Interior.SSB - BoW - Frame Hard Lid Balance of Walls and OverHead Not Started 08/14/26 08/20/26 6.2 6.2
0%
123.8
RPL06.INT.SSBC.01410 RPL06.Interior.SSB-Corridor - Battery Connection Fit out Not Started 08/14/26 08/20/26 6.2 6.2
0%
128.8
RPL06.SKN.S.LO.03040 RPL06.SKIN.LO#17 - Cure Stemwall Build back Exterior Leave Out Walls #17 (CC - South) Not Started 08/14/26 08/24/26 8.8 8.8
0%
86.2
GCD.RPL06.1725 Start FSHAC set in place - RPL06 - DHA&B Construction Milestones Not Started 08/17/26 08/17/26 0.0 0.0
0%
231.2
RPL.06.D.63310.XR Pull and Term MV Skids - RPL06 DHA Receive Milestones (XREFs) Not Started 08/17/26 08/17/26 0.0 0.0
0%
55.0
RPL.06.D.63810.XR 100MW Cx Temp Power to MV Skids RPL06 DHA Available Receive Milestones (XREFs) Not Started 08/17/26 08/17/26 0.0 0.0
0%
55.0
RPL06.INT.DHA.01380 RPL06.Interior.DHA - Control Fault Domain 2 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 08/17/26 08/20/26 5.0 5.0
0%
86.2
RPL06.INT.DHB.02480 RPL06.Interior.DHB - OFE - Control Fault Domain 2 (HAC) Control Fault Domain 2 Not Started 08/17/26 09/04/26 18.8 18.8
0%
2.5
RPL06.INT.DHD.02170 RPL06.Interior.DHD - Priority - Install Security OverHead Not Started 08/17/26 08/18/26 2.5 2.5
0%
310.0
RPL06.INT.SSBC.4660 RPL06.Interior.SSBC LO #07 - Mechanical L2 Checklist Completion Interior Leave Out Wall #07 SSB/SSBC South for MDF1 Not Started 08/17/26 08/28/26 12.5 12.5
0%
121.2
RPL06.SKN.W.LO.01395 RPL06.SKIN.LO#16 - Install IMP Flashing Build back Exterior Leave Out Walls #16 (SSB - North of Loading Dock) Not Started 08/17/26 08/21/26 6.2 6.2
0%
68.8
GCD.RPL06.1827 Delivery of RMU - (First Delivery) - RPL06 - DHC&D Construction Milestones Not Started 08/18/26 08/18/26 0.0 0.0
0%
93.8
RPL06.CX.MCUP.01190 RPL06.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup1 and Dry Coolers Fill and Flush Not Started 08/18/26 08/25/26 7.5 7.5
0%
65.0
RPL06.CX.MCUP.01210 RPL06.CX.mCup Loop 1 - L3/L4 - mCUP - Flush and Fill - mCup2 and Dry Coolers Fill and Flush Not Started 08/18/26 08/25/26 7.5 7.5
0%
65.0
RPL06.INT.CTRC.1280 RPL06.Interior.Center-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls & Overhead Not Started 08/18/26 08/26/26 8.8 8.8
0%
51.2
RPL06.INT.DHA.01400 RPL06.Interior.DHA - Control Fault Domain 3 - Install Duct (LV Side) LV Side Tie-ins Not Started 08/18/26 08/21/26 5.0 5.0
0%
91.2
RPL06.INT.DHA.01430 RPL06.Interior.DHA - Tie-ins - Control Fault Domain 3 (including IDF) - WBS Summary Control Fault Domain 3 Not Started 08/18/26 11/17/26 80.0 80.0
0%
72.5
RPL06.INT.DHB.01870 RPL06.Interior.DHB - Control Fault Domain 5 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 08/18/26 08/21/26 5.0 5.0
0%
106.2
RPL06.INT.DHC.02150 RPL06.Interior.DHC - Priority - Install Electrical OverHead Not Started 08/18/26 08/31/26 12.5 12.5
0%
305.0
RPL06.INT.ENDC.06960 RPL06.Interior.End-Corridor - Final Finishes & Fixtures - Casework Restrooms Not Started 08/18/26 08/26/26 8.8 8.8
0%
190.0
RPL06.INT.SSBC.01400 RPL06.Interior.SSB-Corridor - Install Grounding Fit out Not Started 08/18/26 08/20/26 3.8 3.8
0%
135.0
RPL06.EY.DHD.01220 RPL06.EY.DHD - Install MV, RMUs & Electrical Panels (Qty8) OFE Not Started 08/19/26 09/16/26 25.0 25.0
0%
93.8
RPL06.EY.DHD.01230 RPL06.EY.DHD - OFE - MV - WBS Summary OFE Not Started 08/19/26 03/05/27 168.8 168.8
0%
103.8
RPL06.INT.DHB.01890 RPL06.Interior.DHB - Control Fault Domain 5 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 08/19/26 08/24/26 5.0 5.0
0%
106.2
RPL06.INT.DHD.01110 RPL06.Interior.DHD - MES Skids Tie-ins (LOE) DHD - MES Skids Not Started 08/19/26 09/28/26 35.0 35.0
0%
118.8
RPL06.INT.DHD.01111 RPL06.Interior.DHD - MES Skids - Set & Anchor Interconnects DHD - MES Skids Not Started 08/19/26 09/10/26 20.0 20.0
0%
118.8
RPL06.INT.DHD.02190 RPL06.Interior.DHD - Priority - Install Controls / EPMS / BMS OverHead Not Started 08/19/26 08/21/26 3.8 3.8
0%
310.0
RPL06.INT.SBC.03400 RPL06.Interior.SSB-Corridor - BoW - Install Controls / EPMS / BMS OH and In-wall Balance of Walls & Overhead Not Started 08/19/26 08/25/26 6.2 6.2
0%
86.2
RPL06.INT.SBC.03480 RPL06.Interior.SSB-Corridor - BoW - Frame Hard Lid Balance of Walls & Overhead Not Started 08/19/26 08/25/26 6.2 6.2
0%
63.8
RPL06.INT.SSB.01900 RPL06.Interior.SSB - Final Finishes & Fixtures - Casework Final Finishes & Fixtures (Includes TFW, Restrooms, etc.) Not Started 08/19/26 08/27/26 8.8 8.8
0%
235.0
DCC.B6.3145 [SSDCB1] GS Gear Delivered [DHC] Connectivity Not Started 08/20/26 08/20/26 0.0 0.0
0%
396.2
DCC.B6.3155 [SSDCB1] GS Gear Delivered [DHD] Connectivity Not Started 08/20/26 08/20/26 0.0 0.0
0%
396.2
RPL06.INT.DHA.01140 RPL06.Interior.DHA - Control Fault Domain 1 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 08/20/26 09/17/26 25.0 25.0
0%
45.0
RPL06.INT.DHA.01150 RPL06.Interior.DHA - Control Fault Domain 1 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 08/20/26 09/17/26 25.0 25.0
0%
32.5
RPL06.INT.DHA.01490 RPL06.Interior.DHA - OFE - Control Fault Domain 4 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary Control Fault Domain 4 Not Started 08/20/26 10/29/26 62.5 62.5
0%
13.8
RPL06.INT.DHA.01510 RPL06.Interior.DHA - Control Fault Domain 3 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 08/20/26 08/25/26 5.0 5.0
0%
115.0
RPL06.INT.DHA.02180 RPL06.Interior.DHA - Control Fault Domain 1 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 08/20/26 09/17/26 25.0 25.0
0%
32.5
RPL06.INT.DHA.03660 RPL06.Interior.DHA - OFE - Control Fault Domain 4 (LV Side Aisle) Control Fault Domain 4 Not Started 08/20/26 08/25/26 5.0 5.0
0%
33.8
RPL06.INT.DHA.03780 RPL06.Interior.DHA - Control Fault Domain 1 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 08/20/26 09/17/26 25.0 25.0
0%
32.5
RPL06.INT.DHB.01300 RPL06.Interior.DHB - Control Fault Domain 1 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 08/20/26 09/17/26 25.0 25.0
0%
32.5