Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL06.INT.SSB.14720 |
RPL06.Interior.SSB LO #01 to #05 - Fire Safing / Wall Finishes | Finishes | Not Started | 09/30/26 | 10/06/26 | 6.2 | 6.2 |
|
103.8 |
RPL06.INT.SSB.14740 |
RPL06.Interior.SSB LO #01 to #05 - Install Split Systems | Finishes | Not Started | 09/30/26 | 10/02/26 | 3.8 | 3.8 |
|
92.5 |
RPL06.WP3B.014920 |
RPL06.Conn EF2<>DHB.12 Splice (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.12 | Not Started | 09/30/26 | 10/07/26 | 7.5 | 7.5 |
|
152.5 |
RPL06.WP3B.016360 |
RPL06.Conn EF2<>DHB.12 Install (Z-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.12 | Not Started | 09/30/26 | 09/30/26 | 1.2 | 1.2 |
|
152.5 |
RPL06.EY.DHC.01250 |
RPL06.EY.DHC - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Not Started | 10/01/26 | 10/14/26 | 12.5 | 12.5 |
|
103.8 |
RPL06.EY.DHC.01260 |
RPL06.EY.DHC - Tie-ins - WBS Summary | Tie-ins | Not Started | 10/01/26 | 03/23/27 | 146.2 | 146.2 |
|
113.8 |
RPL06.INT.DHB.02620 |
RPL06.Interior.DHB - OFE - Control Fault Domain 4 (Mech Side Aisle) | Control Fault Domain 4 | Not Started | 10/01/26 | 10/15/26 | 13.8 | 13.8 |
|
22.5 |
RPL06.INT.DHC.01550 |
RPL06.Interior.DHC - Control Fault Domain 4 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 10/01/26 | 10/06/26 | 5.0 | 5.0 |
|
138.8 |
RPL06.INT.DHC.01580 |
RPL06.Interior.DHC - Tie-ins - Control Fault Domain 4 - WBS Summary | Control Fault Domain 4 | Not Started | 10/01/26 | 03/03/27 | 128.8 | 128.8 |
|
57.5 |
RPL06.INT.SBC.03600 |
RPL06.Interior.SSB-Corridor - BoW - Electrical Trim Out (Both side) | Balance of Walls & Overhead | Not Started | 10/01/26 | 10/09/26 | 8.8 | 8.8 |
|
63.8 |
RPL06.INT.SBC.03620 |
RPL06.Interior.SSB-Corridor - BoW - Duct Drops / Trim out | Balance of Walls & Overhead | Not Started | 10/01/26 | 10/07/26 | 6.2 | 6.2 |
|
63.8 |
RPL06.INT.SBC.03700 |
RPL06.Interior.SSB-Corridor - BoW - Install Balance of Refrigerant Line | Balance of Walls & Overhead | Not Started | 10/01/26 | 10/07/26 | 6.2 | 6.2 |
|
103.8 |
RPL06.INT.SBC.03720 |
RPL06.Interior.SSB-Corridor - BoW - Security Trim Out (Both side) | Balance of Walls & Overhead | Not Started | 10/01/26 | 10/09/26 | 8.8 | 8.8 |
|
63.8 |
RPL06.INT.SBC.03840 |
RPL06.Interior.SSB-Corridor - BoW - Install Lights | Balance of Walls & Overhead | Not Started | 10/01/26 | 10/14/26 | 12.5 | 12.5 |
|
73.8 |
RPL06.INT.SSB.01550 |
RPL06.Interior.SSB - BoW - Install TVs and Conf Sound | Balance of Walls and OverHead | Not Started | 10/01/26 | 10/07/26 | 6.2 | 6.2 |
|
163.8 |
RPL06.INT.SSB.01560 |
RPL06.Interior.SSB - BoW - Install & QC Asset Tags | Balance of Walls and OverHead | Not Started | 10/01/26 | 10/02/26 | 2.5 | 2.5 |
|
120.0 |
DCC.B6.3025 |
[SSDCB1] Production Gear Delivered [DHA] Front End (SSW &FSW) | Connectivity | Not Started | 10/02/26 | 10/02/26 | 0.0 | 0.0 |
|
160.0 |
RPL06.CON.WP3B.01040 |
RPL06.Conn WP#3B - ISP DHA - WBS Summary | DHA | Not Started | 10/02/26 | 01/28/27 | 98.8 | 98.8 |
|
73.8 |
RPL06.CON.WP4.03000 |
RPL06.Conn - DH A Network - WBS Summary | DH A | Not Started | 10/02/26 | 03/23/27 | 145.0 | 145.0 |
|
40.0 |
RPL06.CON.WP4.03020 |
RPL06.Conn WP4 FENW DHA CFD1 Infrastructure | Infrastructure | Not Started | 10/02/26 | 10/29/26 | 25.0 | 25.0 |
|
160.0 |
RPL06.Conn.FIM.00020 |
RPL06.Conn FIM - DHB - Prod EFs | Prod EFs | Not Started | 10/02/26 | 10/15/26 | 12.5 | 12.5 |
|
160.0 |
RPL06.INT.CC.9540 |
RPL06.Interior.CC Ext. LO #17 - QC - Backings/Walls | Exterior Leave Out Wall #17 (CC - South) | Not Started | 10/02/26 | 10/02/26 | 1.2 | 1.2 |
|
65.0 |
RPL06.INT.DHA.01200 |
RPL06.Conn DHA - CFD1 - Set Passive Racks for WP#3b (16) | Infrastructure | Not Started | 10/02/26 | 10/06/26 | 3.8 | 3.8 |
|
78.8 |
RPL06.INT.DHA.01360 |
RPL06.Interior.DHA - Control Fault Domain 2 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/02/26 | 10/22/26 | 18.8 | 18.8 |
|
45.0 |
RPL06.INT.DHA.03880 |
RPL06.Conn DHA - CFD1 - Set Passive Racks for PON (16) | Infrastructure | Not Started | 10/02/26 | 10/06/26 | 3.8 | 3.8 |
|
157.5 |
RPL06.WP4.010840 |
RPL06.Conn DHB.11.03<>03 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 10/02/26 | 10/02/26 | 1.2 | 1.2 |
|
170.0 |
RPL06.WP4.010900 |
RPL06.Conn DHB.11.02<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 10/02/26 | 10/07/26 | 5.0 | 5.0 |
|
157.5 |
GCD.RPL06.2605 |
L3/L4 Start - DHB Rows 01-08 | DH | Not Started | 10/05/26 | 10/05/26 | 0.0 | 0.0 |
|
155.0 |
GCD.RPL06.3945 |
L3/L4 Start mCUP [5-6] - RPL06 | mCup | Not Started | 10/05/26 | 10/05/26 | 0.0 | 0.0 |
|
285.0 |
RPL06.CX.DHB.01050 |
RPL06.CX.DHB - L3/L4 - Elec. Domain 01/02 | DHB ELECTRICAL | Not Started | 10/05/26 | 10/13/26 | 8.8 | 8.8 |
|
28.8 |
RPL06.CX.MCUP.01080 |
RPL06.CX.mCup Loop 2 - L3/L4 - mCUP | mCUP 5-6 | Not Started | 10/05/26 | 11/10/26 | 33.8 | 33.8 |
|
238.8 |
RPL06.EY.DHB.01430 |
RPL06.EY.DHB - Install Irrigation | Hardscape and Landscape | Not Started | 10/05/26 | 10/16/26 | 12.5 | 12.5 |
|
332.5 |
RPL06.EY.DHB.01440 |
RPL06.EY.DHB - Install Exterior Signage | Hardscape and Landscape | Not Started | 10/05/26 | 10/16/26 | 12.5 | 12.5 |
|
176.2 |
RPL06.EY.DHC.01280 |
RPL06.EY.DHC - Install BMS/EPMS Tie-ins | Tie-ins | Not Started | 10/05/26 | 10/16/26 | 12.5 | 12.5 |
|
103.8 |
RPL06.EY.DHD.01300 |
RPL06.EY.DHD - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 10/05/26 | 10/09/26 | 6.2 | 6.2 |
|
241.2 |
RPL06.EY.DHD.01310 |
RPL06.EY.DHD - MV Loop - L2 Checklist Completion | Tie-ins | Not Started | 10/05/26 | 10/16/26 | 12.5 | 12.5 |
|
93.8 |
RPL06.EY.DHD.01320 |
RPL06.EY.DHD - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 10/05/26 | 03/30/27 | 148.8 | 148.8 |
|
208.8 |
RPL06.INT.CC.9020 |
RPL06.Interior.CC Ext. LO #17 - Hang Drywall | Exterior Leave Out Wall #17 (CC - South) | Not Started | 10/05/26 | 10/07/26 | 3.8 | 3.8 |
|
65.0 |
RPL06.INT.DHC.01650 |
RPL06.Interior.DHC - Control Fault Domain 4 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 10/05/26 | 10/08/26 | 5.0 | 5.0 |
|
162.5 |
RPL06.INT.ENDC.01360 |
RPL06.Interior.End-Corridor - Install Lighting | Fit out | Not Started | 10/05/26 | 10/13/26 | 8.8 | 8.8 |
|
177.5 |
RPL06.INT.ENDC.06980 |
RPL06.Interior.End-Corridor - Final Finishes & Fixtures - Final Punch Walk | Restrooms | Not Started | 10/05/26 | 10/06/26 | 2.5 | 2.5 |
|
190.0 |
RPL06.INT.SBC.03740 |
RPL06.Interior.SSB-Corridor - BoW - Plumbing Trim Out | Balance of Walls & Overhead | Not Started | 10/05/26 | 10/09/26 | 6.2 | 6.2 |
|
63.8 |
RPL06.INT.SBC.03760 |
RPL06.Interior.SSB-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out | Balance of Walls & Overhead | Not Started | 10/05/26 | 10/13/26 | 8.8 | 8.8 |
|
63.8 |
RPL06.INT.SSB.03140 |
RPL06.Interior.SSB - BoW - Install Door (verify with trades if ready to install door) | Balance of Walls and OverHead | Not Started | 10/05/26 | 10/09/26 | 6.2 | 6.2 |
|
120.0 |
RPL06.INT.SSB.14200 |
RPL06.Interior.SSB LO #01 to #05 - Mechanical Tie-In | Finishes | Not Started | 10/05/26 | 10/05/26 | 1.2 | 1.2 |
|
92.5 |
RPL06.INT.SSB.14300 |
RPL06.Interior.SSB LO #01 to #05 - Electrical Tie-In | Finishes | Not Started | 10/05/26 | 10/09/26 | 6.2 | 6.2 |
|
92.5 |
RPL06.INT.SSB.14760 |
RPL06.Interior.SSB LO #01 to #05 - Install Remaining Refrigerant Line | Finishes | Not Started | 10/05/26 | 10/09/26 | 6.2 | 6.2 |
|
98.8 |
RPL06.WP4.011120 |
RPL06.Conn DHB.12.06<>05 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 10/05/26 | 10/05/26 | 1.2 | 1.2 |
|
165.0 |
RPL06.WP4.011220 |
RPL06.Conn DHB.12.07<>07 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 10/05/26 | 10/07/26 | 3.8 | 3.8 |
|
157.5 |
RPL06.CON.WP4.01200 |
RPL06.Conn WP4 FENW DHB CFD2 Infrastructure | Infrastructure | Not Started | 10/06/26 | 11/02/26 | 25.0 | 25.0 |
|
145.0 |
RPL06.CX.DHA.01090 |
RPL06.CX.DHA - L4 - WBS Summary (Mechanical) | DHA MECHANICAL | Not Started | 10/06/26 | 03/22/27 | 141.2 | 141.2 |
|
25.0 |
RPL06.CX.DHA.01260 |
RPL06.CX.DHA - L3/L4 - Control Fault Domain 01 - FW Flush and Fill | Control Fault Domain 1 | Not Started | 10/06/26 | 10/14/26 | 8.8 | 8.8 |
|
61.2 |
RPL06.CX.DHB.01090 |
RPL06.CX.DHB - L4 - WBS Summary (Mechanical) | DHB MECHANICAL | Not Started | 10/06/26 | 03/08/27 | 128.8 | 128.8 |
|
25.0 |
RPL06.CX.DHB.01260 |
RPL06.CX.DHB - L3/L4 - Control Fault Domain 01 - FW Flush and Fill | Control Fault Domain 1 | Not Started | 10/06/26 | 10/14/26 | 8.8 | 8.8 |
|
43.8 |
RPL06.CX.MCUP.01100 |
RPL06.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - mCup Yard - Loop 2 (mCUPs 5-6) (Phase 3) | Fill and Flush | Not Started | 10/06/26 | 10/12/26 | 6.2 | 6.2 |
|
98.8 |
RPL06.INT.DHA.01410 |
RPL06.Interior.DHA - Control Fault Domain 3 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/06/26 | 10/26/26 | 18.8 | 18.8 |
|
55.0 |
RPL06.INT.DHA.01420 |
RPL06.Interior.DHA - Control Fault Domain 3 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/06/26 | 10/26/26 | 18.8 | 18.8 |
|
48.8 |
RPL06.INT.DHA.02220 |
RPL06.Interior.DHA - Control Fault Domain 3 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/06/26 | 10/26/26 | 18.8 | 18.8 |
|
48.8 |
RPL06.INT.DHA.03820 |
RPL06.Interior.DHA - Control Fault Domain 3 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/06/26 | 10/26/26 | 18.8 | 18.8 |
|
48.8 |
RPL06.INT.DHB.01420 |
RPL06.Conn DHB - CFD2 - Set Passive Racks for WP#3b (16) | Infrastructure | Not Started | 10/06/26 | 10/08/26 | 3.8 | 3.8 |
|
77.5 |
RPL06.INT.DHB.01590 |
RPL06.Interior.DHB - Control Fault Domain 3 - Install Mechanical Side Aisle Cable Tray | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/06/26 | 10/26/26 | 18.8 | 18.8 |
|
63.8 |
RPL06.INT.DHB.01620 |
RPL06.Interior.DHB - Control Fault Domain 3 - Install copper from GS.IDF to BMS and EPMS panels (UG from Center IDF) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/06/26 | 10/26/26 | 18.8 | 18.8 |
|
41.2 |
RPL06.INT.DHB.02820 |
RPL06.Conn DHB - CFD2 - Set Passive Racks for PON (16) | Infrastructure | Not Started | 10/06/26 | 10/08/26 | 3.8 | 3.8 |
|
142.5 |
RPL06.INT.DHC.01670 |
RPL06.Interior.DHC - Control Fault Domain 4 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 10/06/26 | 10/09/26 | 5.0 | 5.0 |
|
177.5 |
RPL06.INT.ENDC.1520 |
RPL06.Interior.End-Corridor - BoW - Install Backing at Exterior Wall | Balance of Walls & Overhead | Not Started | 10/06/26 | 10/12/26 | 6.2 | 6.2 |
|
131.2 |
RPL06.INT.SSB.02380 |
RPL06.Interior.SSB - Final Finishes & Fixtures - Final Punch Walk | Final Finishes & Fixtures (Includes TFW, Restrooms, etc.) | Not Started | 10/06/26 | 10/07/26 | 2.5 | 2.5 |
|
235.0 |
RPL06.WP3B.014900 |
RPL06.Conn EF2<>DHB.11 Splice (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.11 | Not Started | 10/06/26 | 10/06/26 | 1.2 | 1.2 |
|
81.2 |
DCC.B6.3537 |
[SSDCB1] Cabling Start : Front End Production Cabling [DHA] | Connectivity | Not Started | 10/07/26 | 10/07/26 | 0.0 | 0.0 |
|
177.5 |
RPL06.CON.WP3B.01900 |
RPL06.Conn EF1<>DHA.01 - WBS Summary | EF1<>DHA.01 | Not Started | 10/07/26 | 10/21/26 | 13.8 | 13.8 |
|
78.8 |
RPL06.CX.DHB.01060 |
RPL06.CX.DHB - L3/L4 - UPS Start-up | DHB ELECTRICAL | Not Started | 10/07/26 | 10/20/26 | 12.5 | 12.5 |
|
68.8 |
RPL06.INT.CTRC.06800 |
RPL06.Interior.Center-Corridor - Final Finishes & Fixtures - MEP Rough-In | Restrooms | Not Started | 10/07/26 | 10/13/26 | 6.2 | 6.2 |
|
37.5 |
RPL06.INT.CTRC.1540 |
RPL06.Interior.Center-Corridor - BoW - QC - Backings/Walls | Balance of Walls & Overhead | Not Started | 10/07/26 | 10/13/26 | 6.2 | 6.2 |
|
50.0 |
RPL06.INT.ENDC.01370 |
RPL06.Interior.End-Corridor - Asset Tagging | Fit out | Not Started | 10/07/26 | 10/20/26 | 12.5 | 12.5 |
|
261.2 |
RPL06.INT.ENDC.06880 |
RPL06.Interior.End-Corridor - Final Finishes & Fixtures - Electrical L2 Checklist Completion | Restrooms | Not Started | 10/07/26 | 10/20/26 | 12.5 | 12.5 |
|
190.0 |
RPL06.INT.SSB.01570 |
RPL06.Interior.SSB - Loading Dock and Storage - Electrical L2 Checklist Completion | Loading Dock and Storage | Not Started | 10/07/26 | 10/20/26 | 12.5 | 12.5 |
|
146.2 |
RPL06.INT.SSB.14420 |
RPL06.Interior.SSB LO #01 to #05 - Electrical Trim Out | Finishes | Not Started | 10/07/26 | 10/15/26 | 8.8 | 8.8 |
|
103.8 |
RPL06.INT.SSB.14440 |
RPL06.Interior.SSB LO #01 to #05 - Security Trim Out | Finishes | Not Started | 10/07/26 | 10/15/26 | 8.8 | 8.8 |
|
103.8 |
RPL06.OFCI.6940 |
OFCI Delivery: FE Fiber for CFD A.2 (ROJ ) (RVCD ) | Data Hall A | Not Started | 10/07/26 | 10/27/26 | 18.8 | 18.8 |
|
72.5 |
RPL06.WP3B.011100 |
RPL06.Conn EF1<>DHA.01 Pull Pigtails (384F) P1&4 (LV) | EF1<>DHA.01 | Not Started | 10/07/26 | 10/08/26 | 2.5 | 2.5 |
|
78.8 |
RPL06.WP3B.017780 |
RPL06.Conn EF2<>DHB.11 Test Pigtails (384F) P2&3 (LV) | EF2<>DHB.11 | Not Started | 10/07/26 | 10/08/26 | 2.5 | 2.5 |
|
81.2 |
RPL06.WP4.010760 |
RPL06.Conn DHA.01 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 10/07/26 | 10/07/26 | 1.2 | 1.2 |
|
90.0 |
RPL06.WP4.010780 |
RPL06.Conn DHA.02 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 10/07/26 | 10/07/26 | 1.2 | 1.2 |
|
166.2 |
RPL06.WP4.011000 |
RPL06.Conn DHA.01.01 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 10/07/26 | 10/20/26 | 12.5 | 12.5 |
|
128.8 |
RPL06.WP4.011020 |
RPL06.Conn DHA.02.05 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 10/07/26 | 10/20/26 | 12.5 | 12.5 |
|
128.8 |
RPL06.WP4.011280 |
RPL06.Conn DHB.11.02 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 10/07/26 | 10/20/26 | 12.5 | 12.5 |
|
128.8 |
RPL06.WP4.011300 |
RPL06.Conn DHB.12.06 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 10/07/26 | 10/20/26 | 12.5 | 12.5 |
|
128.8 |
RPL06.WP4.011320 |
RPL06.Conn DHA.01 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 10/07/26 | 10/07/26 | 1.2 | 1.2 |
|
157.5 |
RPL06.WP4.011340 |
RPL06.Conn DHA.02 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 10/07/26 | 10/07/26 | 1.2 | 1.2 |
|
157.5 |
RPL.GF.D.N6140.XR |
Fiber Pulls, Test & Term to Prod EF1 Complete RPL 10 to RPL06 | Receive Milestones (XREFs) | Not Started | 10/08/26 | 10/08/26 | 0.0 | 0.0 |
|
275.0 |
RPL.GF.D.N6150.XR |
Fiber Pulls, Test & Term to Prod EF2 Complete RPL 10 to RPL06 | Receive Milestones (XREFs) | Not Started | 10/08/26 | 10/08/26 | 0.0 | 0.0 |
|
272.5 |
RPL.GF.D.N6200.XR |
DAS/PS System Complete and Operational - SSB, DH B, DH A for RPL08 | Receive Milestones (XREFs) | Not Started | 10/08/26 | 10/08/26 | 0.0 | 0.0 |
|
353.8 |
RPL.GF.D.N6210.XR |
DAS/PS System Complete and Operational - DH D, DH C for RPL08 | Receive Milestones (XREFs) | Not Started | 10/08/26 | 10/08/26 | 0.0 | 0.0 |
|
353.8 |
RPL.GF.D.N6240.XR |
GS IDF Huts Innerduct Complete for RPL 6 | Receive Milestones (XREFs) | Not Started | 10/08/26 | 10/08/26 | 0.0 | 0.0 |
|
353.8 |
RPL06.CON.WP2.02400 |
RPL06.Conn - GS EF2 (North) Install OSP Cabling (Pull, Splice & Terminate) | Cabling | Not Started | 10/08/26 | 10/12/26 | 3.8 | 3.8 |
|
272.5 |
RPL06.CON.WP2.07840 |
RPL06.Conn - GS EF1 (South) Install OSP Cabling (Pull, Splice & Terminate) | Cabling | Not Started | 10/08/26 | 10/13/26 | 5.0 | 5.0 |
|
275.0 |
RPL06.INT.CC.9040 |
RPL06.Interior.CC Ext. LO #17 - Tape Finish Paint | Exterior Leave Out Wall #17 (CC - South) | Not Started | 10/08/26 | 10/14/26 | 6.2 | 6.2 |
|
65.0 |
RPL06.INT.SSB.02180 |
RPL06.Interior.SSB - Final Finishes & Fixtures - Electrical L2 Checklist Completion | Final Finishes & Fixtures (Includes TFW, Restrooms, etc.) | Not Started | 10/08/26 | 10/21/26 | 12.5 | 12.5 |
|
235.0 |
RPL06.INT.SSB.06260 |
RPL06.Interior.SSB LO #16 - Fire Safing / Wall Finishes | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 10/08/26 | 10/08/26 | 1.2 | 1.2 |
|
68.8 |
RPL06.WP3B.017800 |
RPL06.Conn EF2<>DHB.12 Test Pigtails (384F) P2&3 (LV) | EF2<>DHB.12 | Not Started | 10/08/26 | 10/09/26 | 2.5 | 2.5 |
|
152.5 |
RPL06.WP4.011040 |
RPL06.Conn DHA.01 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 10/08/26 | 10/08/26 | 1.2 | 1.2 |
|
90.0 |