Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.INT.SSB.14720 RPL06.Interior.SSB LO #01 to #05 - Fire Safing / Wall Finishes Finishes Not Started 09/30/26 10/06/26 6.2 6.2
0%
103.8
RPL06.INT.SSB.14740 RPL06.Interior.SSB LO #01 to #05 - Install Split Systems Finishes Not Started 09/30/26 10/02/26 3.8 3.8
0%
92.5
RPL06.WP3B.014920 RPL06.Conn EF2<>DHB.12 Splice (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 09/30/26 10/07/26 7.5 7.5
0%
152.5
RPL06.WP3B.016360 RPL06.Conn EF2<>DHB.12 Install (Z-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 09/30/26 09/30/26 1.2 1.2
0%
152.5
RPL06.EY.DHC.01250 RPL06.EY.DHC - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 10/01/26 10/14/26 12.5 12.5
0%
103.8
RPL06.EY.DHC.01260 RPL06.EY.DHC - Tie-ins - WBS Summary Tie-ins Not Started 10/01/26 03/23/27 146.2 146.2
0%
113.8
RPL06.INT.DHB.02620 RPL06.Interior.DHB - OFE - Control Fault Domain 4 (Mech Side Aisle) Control Fault Domain 4 Not Started 10/01/26 10/15/26 13.8 13.8
0%
22.5
RPL06.INT.DHC.01550 RPL06.Interior.DHC - Control Fault Domain 4 - Install Duct (LV Side) LV Side Tie-ins Not Started 10/01/26 10/06/26 5.0 5.0
0%
138.8
RPL06.INT.DHC.01580 RPL06.Interior.DHC - Tie-ins - Control Fault Domain 4 - WBS Summary Control Fault Domain 4 Not Started 10/01/26 03/03/27 128.8 128.8
0%
57.5
RPL06.INT.SBC.03600 RPL06.Interior.SSB-Corridor - BoW - Electrical Trim Out (Both side) Balance of Walls & Overhead Not Started 10/01/26 10/09/26 8.8 8.8
0%
63.8
RPL06.INT.SBC.03620 RPL06.Interior.SSB-Corridor - BoW - Duct Drops / Trim out Balance of Walls & Overhead Not Started 10/01/26 10/07/26 6.2 6.2
0%
63.8
RPL06.INT.SBC.03700 RPL06.Interior.SSB-Corridor - BoW - Install Balance of Refrigerant Line Balance of Walls & Overhead Not Started 10/01/26 10/07/26 6.2 6.2
0%
103.8
RPL06.INT.SBC.03720 RPL06.Interior.SSB-Corridor - BoW - Security Trim Out (Both side) Balance of Walls & Overhead Not Started 10/01/26 10/09/26 8.8 8.8
0%
63.8
RPL06.INT.SBC.03840 RPL06.Interior.SSB-Corridor - BoW - Install Lights Balance of Walls & Overhead Not Started 10/01/26 10/14/26 12.5 12.5
0%
73.8
RPL06.INT.SSB.01550 RPL06.Interior.SSB - BoW - Install TVs and Conf Sound Balance of Walls and OverHead Not Started 10/01/26 10/07/26 6.2 6.2
0%
163.8
RPL06.INT.SSB.01560 RPL06.Interior.SSB - BoW - Install & QC Asset Tags Balance of Walls and OverHead Not Started 10/01/26 10/02/26 2.5 2.5
0%
120.0
DCC.B6.3025 [SSDCB1] Production Gear Delivered [DHA] Front End (SSW &FSW) Connectivity Not Started 10/02/26 10/02/26 0.0 0.0
0%
160.0
RPL06.CON.WP3B.01040 RPL06.Conn WP#3B - ISP DHA - WBS Summary DHA Not Started 10/02/26 01/28/27 98.8 98.8
0%
73.8
RPL06.CON.WP4.03000 RPL06.Conn - DH A Network - WBS Summary DH A Not Started 10/02/26 03/23/27 145.0 145.0
0%
40.0
RPL06.CON.WP4.03020 RPL06.Conn WP4 FENW DHA CFD1 Infrastructure Infrastructure Not Started 10/02/26 10/29/26 25.0 25.0
0%
160.0
RPL06.Conn.FIM.00020 RPL06.Conn FIM - DHB - Prod EFs Prod EFs Not Started 10/02/26 10/15/26 12.5 12.5
0%
160.0
RPL06.INT.CC.9540 RPL06.Interior.CC Ext. LO #17 - QC - Backings/Walls Exterior Leave Out Wall #17 (CC - South) Not Started 10/02/26 10/02/26 1.2 1.2
0%
65.0
RPL06.INT.DHA.01200 RPL06.Conn DHA - CFD1 - Set Passive Racks for WP#3b (16) Infrastructure Not Started 10/02/26 10/06/26 3.8 3.8
0%
78.8
RPL06.INT.DHA.01360 RPL06.Interior.DHA - Control Fault Domain 2 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 10/02/26 10/22/26 18.8 18.8
0%
45.0
RPL06.INT.DHA.03880 RPL06.Conn DHA - CFD1 - Set Passive Racks for PON (16) Infrastructure Not Started 10/02/26 10/06/26 3.8 3.8
0%
157.5
RPL06.WP4.010840 RPL06.Conn DHB.11.03<>03 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 10/02/26 10/02/26 1.2 1.2
0%
170.0
RPL06.WP4.010900 RPL06.Conn DHB.11.02<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 10/02/26 10/07/26 5.0 5.0
0%
157.5
GCD.RPL06.2605 L3/L4 Start - DHB Rows 01-08 DH Not Started 10/05/26 10/05/26 0.0 0.0
0%
155.0
GCD.RPL06.3945 L3/L4 Start mCUP [5-6] - RPL06 mCup Not Started 10/05/26 10/05/26 0.0 0.0
0%
285.0
RPL06.CX.DHB.01050 RPL06.CX.DHB - L3/L4 - Elec. Domain 01/02 DHB ELECTRICAL Not Started 10/05/26 10/13/26 8.8 8.8
0%
28.8
RPL06.CX.MCUP.01080 RPL06.CX.mCup Loop 2 - L3/L4 - mCUP mCUP 5-6 Not Started 10/05/26 11/10/26 33.8 33.8
0%
238.8
RPL06.EY.DHB.01430 RPL06.EY.DHB - Install Irrigation Hardscape and Landscape Not Started 10/05/26 10/16/26 12.5 12.5
0%
332.5
RPL06.EY.DHB.01440 RPL06.EY.DHB - Install Exterior Signage Hardscape and Landscape Not Started 10/05/26 10/16/26 12.5 12.5
0%
176.2
RPL06.EY.DHC.01280 RPL06.EY.DHC - Install BMS/EPMS Tie-ins Tie-ins Not Started 10/05/26 10/16/26 12.5 12.5
0%
103.8
RPL06.EY.DHD.01300 RPL06.EY.DHD - Install Sleeves MEPL Hardscape and Landscape Not Started 10/05/26 10/09/26 6.2 6.2
0%
241.2
RPL06.EY.DHD.01310 RPL06.EY.DHD - MV Loop - L2 Checklist Completion Tie-ins Not Started 10/05/26 10/16/26 12.5 12.5
0%
93.8
RPL06.EY.DHD.01320 RPL06.EY.DHD - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 10/05/26 03/30/27 148.8 148.8
0%
208.8
RPL06.INT.CC.9020 RPL06.Interior.CC Ext. LO #17 - Hang Drywall Exterior Leave Out Wall #17 (CC - South) Not Started 10/05/26 10/07/26 3.8 3.8
0%
65.0
RPL06.INT.DHC.01650 RPL06.Interior.DHC - Control Fault Domain 4 - Install LV Side Aisle HAC Busway LV Side Tie-ins Not Started 10/05/26 10/08/26 5.0 5.0
0%
162.5
RPL06.INT.ENDC.01360 RPL06.Interior.End-Corridor - Install Lighting Fit out Not Started 10/05/26 10/13/26 8.8 8.8
0%
177.5
RPL06.INT.ENDC.06980 RPL06.Interior.End-Corridor - Final Finishes & Fixtures - Final Punch Walk Restrooms Not Started 10/05/26 10/06/26 2.5 2.5
0%
190.0
RPL06.INT.SBC.03740 RPL06.Interior.SSB-Corridor - BoW - Plumbing Trim Out Balance of Walls & Overhead Not Started 10/05/26 10/09/26 6.2 6.2
0%
63.8
RPL06.INT.SBC.03760 RPL06.Interior.SSB-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out Balance of Walls & Overhead Not Started 10/05/26 10/13/26 8.8 8.8
0%
63.8
RPL06.INT.SSB.03140 RPL06.Interior.SSB - BoW - Install Door (verify with trades if ready to install door) Balance of Walls and OverHead Not Started 10/05/26 10/09/26 6.2 6.2
0%
120.0
RPL06.INT.SSB.14200 RPL06.Interior.SSB LO #01 to #05 - Mechanical Tie-In Finishes Not Started 10/05/26 10/05/26 1.2 1.2
0%
92.5
RPL06.INT.SSB.14300 RPL06.Interior.SSB LO #01 to #05 - Electrical Tie-In Finishes Not Started 10/05/26 10/09/26 6.2 6.2
0%
92.5
RPL06.INT.SSB.14760 RPL06.Interior.SSB LO #01 to #05 - Install Remaining Refrigerant Line Finishes Not Started 10/05/26 10/09/26 6.2 6.2
0%
98.8
RPL06.WP4.011120 RPL06.Conn DHB.12.06<>05 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 10/05/26 10/05/26 1.2 1.2
0%
165.0
RPL06.WP4.011220 RPL06.Conn DHB.12.07<>07 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 10/05/26 10/07/26 3.8 3.8
0%
157.5
RPL06.CON.WP4.01200 RPL06.Conn WP4 FENW DHB CFD2 Infrastructure Infrastructure Not Started 10/06/26 11/02/26 25.0 25.0
0%
145.0
RPL06.CX.DHA.01090 RPL06.CX.DHA - L4 - WBS Summary (Mechanical) DHA MECHANICAL Not Started 10/06/26 03/22/27 141.2 141.2
0%
25.0
RPL06.CX.DHA.01260 RPL06.CX.DHA - L3/L4 - Control Fault Domain 01 - FW Flush and Fill Control Fault Domain 1 Not Started 10/06/26 10/14/26 8.8 8.8
0%
61.2
RPL06.CX.DHB.01090 RPL06.CX.DHB - L4 - WBS Summary (Mechanical) DHB MECHANICAL Not Started 10/06/26 03/08/27 128.8 128.8
0%
25.0
RPL06.CX.DHB.01260 RPL06.CX.DHB - L3/L4 - Control Fault Domain 01 - FW Flush and Fill Control Fault Domain 1 Not Started 10/06/26 10/14/26 8.8 8.8
0%
43.8
RPL06.CX.MCUP.01100 RPL06.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - mCup Yard - Loop 2 (mCUPs 5-6) (Phase 3) Fill and Flush Not Started 10/06/26 10/12/26 6.2 6.2
0%
98.8
RPL06.INT.DHA.01410 RPL06.Interior.DHA - Control Fault Domain 3 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 10/06/26 10/26/26 18.8 18.8
0%
55.0
RPL06.INT.DHA.01420 RPL06.Interior.DHA - Control Fault Domain 3 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 10/06/26 10/26/26 18.8 18.8
0%
48.8
RPL06.INT.DHA.02220 RPL06.Interior.DHA - Control Fault Domain 3 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 10/06/26 10/26/26 18.8 18.8
0%
48.8
RPL06.INT.DHA.03820 RPL06.Interior.DHA - Control Fault Domain 3 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 10/06/26 10/26/26 18.8 18.8
0%
48.8
RPL06.INT.DHB.01420 RPL06.Conn DHB - CFD2 - Set Passive Racks for WP#3b (16) Infrastructure Not Started 10/06/26 10/08/26 3.8 3.8
0%
77.5
RPL06.INT.DHB.01590 RPL06.Interior.DHB - Control Fault Domain 3 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 10/06/26 10/26/26 18.8 18.8
0%
63.8
RPL06.INT.DHB.01620 RPL06.Interior.DHB - Control Fault Domain 3 - Install copper from GS.IDF to BMS and EPMS panels (UG from Center IDF) Remaining Tie-ins post Mech Side Aisle install Not Started 10/06/26 10/26/26 18.8 18.8
0%
41.2
RPL06.INT.DHB.02820 RPL06.Conn DHB - CFD2 - Set Passive Racks for PON (16) Infrastructure Not Started 10/06/26 10/08/26 3.8 3.8
0%
142.5
RPL06.INT.DHC.01670 RPL06.Interior.DHC - Control Fault Domain 4 - Install LV Side Aisle Cable Tray LV Side Tie-ins Not Started 10/06/26 10/09/26 5.0 5.0
0%
177.5
RPL06.INT.ENDC.1520 RPL06.Interior.End-Corridor - BoW - Install Backing at Exterior Wall Balance of Walls & Overhead Not Started 10/06/26 10/12/26 6.2 6.2
0%
131.2
RPL06.INT.SSB.02380 RPL06.Interior.SSB - Final Finishes & Fixtures - Final Punch Walk Final Finishes & Fixtures (Includes TFW, Restrooms, etc.) Not Started 10/06/26 10/07/26 2.5 2.5
0%
235.0
RPL06.WP3B.014900 RPL06.Conn EF2<>DHB.11 Splice (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.11 Not Started 10/06/26 10/06/26 1.2 1.2
0%
81.2
DCC.B6.3537 [SSDCB1] Cabling Start : Front End Production Cabling [DHA] Connectivity Not Started 10/07/26 10/07/26 0.0 0.0
0%
177.5
RPL06.CON.WP3B.01900 RPL06.Conn EF1<>DHA.01 - WBS Summary EF1<>DHA.01 Not Started 10/07/26 10/21/26 13.8 13.8
0%
78.8
RPL06.CX.DHB.01060 RPL06.CX.DHB - L3/L4 - UPS Start-up DHB ELECTRICAL Not Started 10/07/26 10/20/26 12.5 12.5
0%
68.8
RPL06.INT.CTRC.06800 RPL06.Interior.Center-Corridor - Final Finishes & Fixtures - MEP Rough-In Restrooms Not Started 10/07/26 10/13/26 6.2 6.2
0%
37.5
RPL06.INT.CTRC.1540 RPL06.Interior.Center-Corridor - BoW - QC - Backings/Walls Balance of Walls & Overhead Not Started 10/07/26 10/13/26 6.2 6.2
0%
50.0
RPL06.INT.ENDC.01370 RPL06.Interior.End-Corridor - Asset Tagging Fit out Not Started 10/07/26 10/20/26 12.5 12.5
0%
261.2
RPL06.INT.ENDC.06880 RPL06.Interior.End-Corridor - Final Finishes & Fixtures - Electrical L2 Checklist Completion Restrooms Not Started 10/07/26 10/20/26 12.5 12.5
0%
190.0
RPL06.INT.SSB.01570 RPL06.Interior.SSB - Loading Dock and Storage - Electrical L2 Checklist Completion Loading Dock and Storage Not Started 10/07/26 10/20/26 12.5 12.5
0%
146.2
RPL06.INT.SSB.14420 RPL06.Interior.SSB LO #01 to #05 - Electrical Trim Out Finishes Not Started 10/07/26 10/15/26 8.8 8.8
0%
103.8
RPL06.INT.SSB.14440 RPL06.Interior.SSB LO #01 to #05 - Security Trim Out Finishes Not Started 10/07/26 10/15/26 8.8 8.8
0%
103.8
RPL06.OFCI.6940 OFCI Delivery: FE Fiber for CFD A.2 (ROJ ) (RVCD ) Data Hall A Not Started 10/07/26 10/27/26 18.8 18.8
0%
72.5
RPL06.WP3B.011100 RPL06.Conn EF1<>DHA.01 Pull Pigtails (384F) P1&4 (LV) EF1<>DHA.01 Not Started 10/07/26 10/08/26 2.5 2.5
0%
78.8
RPL06.WP3B.017780 RPL06.Conn EF2<>DHB.11 Test Pigtails (384F) P2&3 (LV) EF2<>DHB.11 Not Started 10/07/26 10/08/26 2.5 2.5
0%
81.2
RPL06.WP4.010760 RPL06.Conn DHA.01 Pull Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 10/07/26 10/07/26 1.2 1.2
0%
90.0
RPL06.WP4.010780 RPL06.Conn DHA.02 Pull Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 10/07/26 10/07/26 1.2 1.2
0%
166.2
RPL06.WP4.011000 RPL06.Conn DHA.01.01 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 10/07/26 10/20/26 12.5 12.5
0%
128.8
RPL06.WP4.011020 RPL06.Conn DHA.02.05 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 10/07/26 10/20/26 12.5 12.5
0%
128.8
RPL06.WP4.011280 RPL06.Conn DHB.11.02 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 10/07/26 10/20/26 12.5 12.5
0%
128.8
RPL06.WP4.011300 RPL06.Conn DHB.12.06 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 10/07/26 10/20/26 12.5 12.5
0%
128.8
RPL06.WP4.011320 RPL06.Conn DHA.01 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] In-Rack Not Started 10/07/26 10/07/26 1.2 1.2
0%
157.5
RPL06.WP4.011340 RPL06.Conn DHA.02 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] In-Rack Not Started 10/07/26 10/07/26 1.2 1.2
0%
157.5
RPL.GF.D.N6140.XR Fiber Pulls, Test & Term to Prod EF1 Complete RPL 10 to RPL06 Receive Milestones (XREFs) Not Started 10/08/26 10/08/26 0.0 0.0
0%
275.0
RPL.GF.D.N6150.XR Fiber Pulls, Test & Term to Prod EF2 Complete RPL 10 to RPL06 Receive Milestones (XREFs) Not Started 10/08/26 10/08/26 0.0 0.0
0%
272.5
RPL.GF.D.N6200.XR DAS/PS System Complete and Operational - SSB, DH B, DH A for RPL08 Receive Milestones (XREFs) Not Started 10/08/26 10/08/26 0.0 0.0
0%
353.8
RPL.GF.D.N6210.XR DAS/PS System Complete and Operational - DH D, DH C for RPL08 Receive Milestones (XREFs) Not Started 10/08/26 10/08/26 0.0 0.0
0%
353.8
RPL.GF.D.N6240.XR GS IDF Huts Innerduct Complete for RPL 6 Receive Milestones (XREFs) Not Started 10/08/26 10/08/26 0.0 0.0
0%
353.8
RPL06.CON.WP2.02400 RPL06.Conn - GS EF2 (North) Install OSP Cabling (Pull, Splice & Terminate) Cabling Not Started 10/08/26 10/12/26 3.8 3.8
0%
272.5
RPL06.CON.WP2.07840 RPL06.Conn - GS EF1 (South) Install OSP Cabling (Pull, Splice & Terminate) Cabling Not Started 10/08/26 10/13/26 5.0 5.0
0%
275.0
RPL06.INT.CC.9040 RPL06.Interior.CC Ext. LO #17 - Tape Finish Paint Exterior Leave Out Wall #17 (CC - South) Not Started 10/08/26 10/14/26 6.2 6.2
0%
65.0
RPL06.INT.SSB.02180 RPL06.Interior.SSB - Final Finishes & Fixtures - Electrical L2 Checklist Completion Final Finishes & Fixtures (Includes TFW, Restrooms, etc.) Not Started 10/08/26 10/21/26 12.5 12.5
0%
235.0
RPL06.INT.SSB.06260 RPL06.Interior.SSB LO #16 - Fire Safing / Wall Finishes Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 10/08/26 10/08/26 1.2 1.2
0%
68.8
RPL06.WP3B.017800 RPL06.Conn EF2<>DHB.12 Test Pigtails (384F) P2&3 (LV) EF2<>DHB.12 Not Started 10/08/26 10/09/26 2.5 2.5
0%
152.5
RPL06.WP4.011040 RPL06.Conn DHA.01 Pull Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 10/08/26 10/08/26 1.2 1.2
0%
90.0