Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
0
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.INT.SBC.03920 RPL06.Interior.SSB-Corridor - BoW - Install Asset Tags & QC Balance of Walls & Overhead Not Started 10/15/26 10/23/26 8.8 8.8
0%
73.8
RPL06.INT.SSB.02200 RPL06.Interior.SSB - Final Finishes & Fixtures - Mechanical L2 Checklist Completion Final Finishes & Fixtures (Includes TFW, Restrooms, etc.) Not Started 10/15/26 10/28/26 12.5 12.5
0%
235.0
RPL06.WP3B.013520 RPL06.Conn EF2<>DHB.14 Install (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.14 Not Started 10/15/26 10/15/26 1.2 1.2
0%
137.5
RPL06.WP4.012420 RPL06.Conn DHB.13.09<>09 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 10/15/26 10/15/26 1.2 1.2
0%
157.5
RPL06.WP4.012440 RPL06.Conn DHB.14.13<>13 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Across-Row Not Started 10/15/26 10/15/26 1.2 1.2
0%
157.5
RPL06.WP4.012540 RPL06.Conn DHB.13.11<>11 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 10/15/26 10/19/26 3.8 3.8
0%
142.5
RPL06.WP4.012560 RPL06.Conn DHB.14.15<>15 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Across-Row Not Started 10/15/26 10/19/26 3.8 3.8
0%
142.5
RPL06.EY.DHA.01610 RPL06.EY.DHC - Install Electrical Tie-ins Build back Exterior Leave Out #17 (South) Not Started 10/16/26 10/22/26 6.2 6.2
0%
125.0
RPL06.INT.CTRC.1900 RPL06.Interior.Center-Corridor - BoW - F/R/P Pads Balance of Walls & Overhead Not Started 10/16/26 10/22/26 6.2 6.2
0%
50.0
RPL06.INT.DHA.01480 RPL06.Interior.DHA - Control Fault Domain 2 - L2 Checklist Completion Remaining Tie-ins post Mech Side Aisle install Not Started 10/16/26 11/05/26 18.8 18.8
0%
45.0
RPL06.INT.DHB.01670 RPL06.Interior.DHB - Control Fault Domain 4 - Pull BMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 10/16/26 11/05/26 18.8 18.8
0%
41.2
RPL06.INT.DHB.01680 RPL06.Interior.DHB - Control Fault Domain 4 - Pull EPMS from panel to devices Remaining Tie-ins post Mech Side Aisle install Not Started 10/16/26 11/05/26 18.8 18.8
0%
41.2
RPL06.INT.DHB.01690 RPL06.Interior.DHB - Control Fault Domain 4 - Set UPS and Panel (2) Remaining Tie-ins post Mech Side Aisle install Not Started 10/16/26 11/05/26 18.8 18.8
0%
35.0
RPL06.WP3B.014960 RPL06.Conn EF2<>DHB.14 Splice (A-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.14 Not Started 10/16/26 10/23/26 7.5 7.5
0%
137.5
RPL06.WP3B.016400 RPL06.Conn EF2<>DHB.14 Install (Z-End) Pigtails (384F) P2&3 (LV) EF2<>DHB.14 Not Started 10/16/26 10/16/26 1.2 1.2
0%
137.5
RPL06.WP4.012380 RPL06.Conn DHA.01.03<>03 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Across-Row Not Started 10/16/26 10/16/26 1.2 1.2
0%
170.0
RPL06.WP4.012400 RPL06.Conn DHA.02.07<>07 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 10/16/26 10/16/26 1.2 1.2
0%
170.0
RPL06.WP4.012580 RPL06.Conn DHA.01.02<>01 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Jumpers Not Started 10/16/26 10/21/26 5.0 5.0
0%
157.5
RPL06.WP4.012600 RPL06.Conn DHA.02.06<>05 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 10/16/26 10/21/26 5.0 5.0
0%
157.5
GCD.RPL06.4625 L3/L4 Start - DHA Rows 01-08 DH Not Started 10/19/26 10/19/26 0.0 0.0
0%
155.0
GCD.RPL06.4965 L3/L4 Start EY - DHD EY Not Started 10/19/26 10/19/26 0.0 0.0
0%
238.8
GCD.RPL06.5845 RMU Loop Ready for Energization - DHD Loop EY Not Started 10/19/26 10/19/26 0.0 0.0
0%
93.8
RPL06.CX.DHA.01040 RPL06.CX.DHA - L3/L4 - Elec. Domain 01/02 DHA ELECTRICAL Not Started 10/19/26 10/27/26 8.8 8.8
0%
28.8
RPL06.CX.DHD.00000 RPL06.CX.DHD - L3, L4, IST - WBS Summary DHD Not Started 10/19/26 08/18/27 260.0 260.0
0%
72.5
RPL06.CX.DHD.01000 RPL06.CX.DHD - L3 - WBS Summary (Electrical) DHD ELECTRICAL Not Started 10/19/26 03/29/27 135.0 135.0
0%
103.8
RPL06.CX.DHD.01010 RPL06.CX.DHD - L3/L4 - MV Skids (8) Loop DHD ELECTRICAL Not Started 10/19/26 10/28/26 10.0 10.0
0%
93.8
RPL06.EY.DHA.01430 RPL06.EY.DHA - Install Irrigation Hardscape and Landscape Not Started 10/19/26 10/30/26 12.5 12.5
0%
320.0
RPL06.EY.DHA.01440 RPL06.EY.DHA - Install Exterior Signage Hardscape and Landscape Not Started 10/19/26 10/30/26 12.5 12.5
0%
176.2
RPL06.EY.DHB.01480 RPL06.EY.DHB - Install Landscaping Hardscape and Landscape Not Started 10/19/26 10/30/26 12.5 12.5
0%
332.5
RPL06.EY.DHC.01300 RPL06.EY.DHC - Install Sleeves MEPL Hardscape and Landscape Not Started 10/19/26 10/23/26 6.2 6.2
0%
240.0
RPL06.EY.DHC.01320 RPL06.EY.DHC - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 10/19/26 04/01/27 138.8 138.8
0%
206.2
RPL06.EY.DHD.01340 RPL06.EY.DHD - Install Lighting Hardscape and Landscape Not Started 10/19/26 10/30/26 12.5 12.5
0%
241.2
RPL06.INT.SSB.02620 RPL06.Interior.SSB - BoW - ACT - Install ACT Tiles Balance of Walls and OverHead Not Started 10/19/26 10/23/26 6.2 6.2
0%
120.0
RPL06.INT.SSB.06400 RPL06.Interior.SSB LO #16 - Electrical L2 Checklist Completion Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 10/19/26 10/30/26 12.5 12.5
0%
68.8
RPL06.INT.SSB.06420 RPL06.Interior.SSB LO #16 - Mechanical L2 Checklist Completion Leave Out Wall #16 (SSB - North of Loading Dock) Not Started 10/19/26 10/30/26 12.5 12.5
0%
68.8
RPL06.CON.WP2.08720 RPL06.Conn - GSIDF/DH B1 - WBS Summary Int. IDF Stick Built - GSIDF6B1 Not Started 10/20/26 11/05/26 16.2 16.2
0%
327.5
RPL06.CON.WP2.08740 RPL06.Conn - GSIDF/DH B1 - Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Not Started 10/20/26 10/23/26 5.0 5.0
0%
137.5
RPL06.INT.CC.9140 RPL06.Interior.CC Ext. LO #17 - Electrical Trim Out Exterior Leave Out Wall #17 (CC - South) Not Started 10/20/26 10/20/26 1.2 1.2
0%
65.0
RPL06.INT.CC.9160 RPL06.Interior.CC Ext. LO #17 - Security Trim Out Exterior Leave Out Wall #17 (CC - South) Not Started 10/20/26 10/20/26 1.2 1.2
0%
65.0
RPL06.INT.DHA.01500 RPL06.Interior.DHA - Control Fault Domain 3 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 10/20/26 11/09/26 18.8 18.8
0%
73.8
RPL06.INT.DHA.01530 RPL06.Interior.DHA - Control Fault Domain 3 - Install copper from GS.IDF to BMS and EPMS panels (UG from Center IDF) Remaining Tie-ins post Mech Side Aisle install Not Started 10/20/26 11/09/26 18.8 18.8
0%
48.8
RPL06.INT.ENDC.1560 RPL06.Interior.End-Corridor - BoW - Hang Drywall Balance of Walls & Overhead Not Started 10/20/26 10/28/26 8.8 8.8
0%
131.2
RPL06.WP3B.016860 RPL06.Conn EF1<>DHA.01 Test Pigtails (384F) P1&4 (LV) EF1<>DHA.01 Not Started 10/20/26 10/21/26 2.5 2.5
0%
78.8
RPL06.WP4.012860 RPL06.Conn DHB.13.11<>11 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 10/20/26 10/20/26 1.2 1.2
0%
155.0
RPL06.WP4.012880 RPL06.Conn DHB.14.15<>15 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Across-Row Not Started 10/20/26 10/20/26 1.2 1.2
0%
155.0
RPL06.WP4.012940 RPL06.Conn DHB.13.10<>09 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 10/20/26 10/23/26 5.0 5.0
0%
142.5
RPL06.WP4.012960 RPL06.Conn DHB.14.14<>13 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Jumpers Not Started 10/20/26 10/23/26 5.0 5.0
0%
142.5
GCD.RPL06.2606 L3/L4 Start - DHB Rows 09-16 DH Not Started 10/21/26 10/21/26 0.0 0.0
0%
140.0
RPL06.CON.WP2.07940 RPL06.Conn - GSMDF2 (North) Test Network (FIM) Network Not Started 10/21/26 10/23/26 3.8 3.8
0%
272.5
RPL06.CX.DHA.01060 RPL06.CX.DHA - L3/L4 - UPS Start-up DHA ELECTRICAL Not Started 10/21/26 11/03/26 12.5 12.5
0%
76.2
RPL06.CX.DHB.01080 RPL06.CX.DHB - L3/L4 - Elec. Domain 03/04 DHB ELECTRICAL Not Started 10/21/26 10/26/26 5.0 5.0
0%
43.8
RPL06.CX.MCUP.01370 RPL06.CX.mCup Loop 2 - L3/L4 - mCUP - Flush and Fill - DHD & DHC (Phase 4) Fill and Flush Not Started 10/21/26 10/27/26 6.2 6.2
0%
98.8
RPL06.INT.CTRC.06860 RPL06.Interior.Center-Corridor - Final Finishes & Fixtures - Install Cement Board/ Drywall Restrooms Not Started 10/21/26 10/27/26 6.2 6.2
0%
37.5
RPL06.INT.SBC.03660 RPL06.Interior.SSB-Corridor - BoW - Install Horizontal Steel Supports for Cable Tray (IFP Add) Balance of Walls & Overhead Not Started 10/21/26 10/26/26 5.0 5.0
0%
63.8
RPL06.WP4.012740 RPL06.Conn DHA.01.02 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 10/21/26 11/03/26 12.5 12.5
0%
128.8
RPL06.WP4.012760 RPL06.Conn DHA.02.06 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 10/21/26 11/03/26 12.5 12.5
0%
128.8
RPL06.WP4.012820 RPL06.Conn DHB.11.03 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 10/21/26 11/03/26 12.5 12.5
0%
128.8
RPL06.WP4.012840 RPL06.Conn DHB.12.07 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 10/21/26 11/03/26 12.5 12.5
0%
128.8
RPL06.INT.CC.9180 RPL06.Interior.CC Ext. LO #17 - Plumbing Trim Out Exterior Leave Out Wall #17 (CC - South) Not Started 10/22/26 10/22/26 1.2 1.2
0%
65.0
RPL06.INT.CC.9200 RPL06.Interior.CC Ext. LO #17 - Fire Life Safety Trim Out Exterior Leave Out Wall #17 (CC - South) Not Started 10/22/26 10/22/26 1.2 1.2
0%
65.0
RPL06.INT.DHB.02680 RPL06.Interior.DHB - OFE - Control Fault Domain 5 (Mech Side Aisle) Control Fault Domain 5 Not Started 10/22/26 11/04/26 12.5 12.5
0%
17.5
RPL06.WP3B.016880 RPL06.Conn EF1<>DHA.02 Test Pigtails (384F) P1&4 (LV) EF1<>DHA.02 Not Started 10/22/26 10/23/26 2.5 2.5
0%
152.5
RPL06.WP3B.017820 RPL06.Conn EF2<>DHB.13 Test Pigtails (384F) P2&3 (LV) EF2<>DHB.13 Not Started 10/22/26 10/23/26 2.5 2.5
0%
140.0
RPL06.WP4.013040 RPL06.Conn DHA.01.02<>01 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Jumpers Not Started 10/22/26 10/22/26 1.2 1.2
0%
161.2
RPL06.WP4.013060 RPL06.Conn DHA.02.06<>05 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 10/22/26 10/22/26 1.2 1.2
0%
161.2
RPL06.WP4.013100 RPL06.Conn DHA.01.04<>03 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Jumpers Not Started 10/22/26 10/27/26 5.0 5.0
0%
157.5
RPL06.WP4.013120 RPL06.Conn DHA.02.08<>07 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 10/22/26 10/27/26 5.0 5.0
0%
157.5
RPL06.CON.WP4.03200 RPL06.Conn WP4 FENW DHA CFD2 Infrastructure Infrastructure Not Started 10/23/26 11/20/26 25.0 25.0
0%
141.2
RPL06.EY.DHA.01570 RPL06.EY.DHC - Install BMS Tie-ins Build back Exterior Leave Out #17 (South) Not Started 10/23/26 11/05/26 12.5 12.5
0%
125.0
RPL06.INT.CC.9240 RPL06.Interior.CC Ext. LO #17 - Install Asset Tags Exterior Leave Out Wall #17 (CC - South) Not Started 10/23/26 10/23/26 1.2 1.2
0%
65.0
RPL06.INT.CTRC.1580 RPL06.Interior.Center-Corridor - BoW - Tape Finish Paint Balance of Walls & Overhead Not Started 10/23/26 10/27/26 3.8 3.8
0%
50.0
RPL06.INT.DHA.01340 RPL06.Conn DHA - CFD2 - Set Passive Racks for WP#3b (16) Infrastructure Not Started 10/23/26 10/27/26 3.8 3.8
0%
72.5
RPL06.INT.DHA.01550 RPL06.Interior.DHA - Control Fault Domain 4 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Not Started 10/23/26 11/13/26 18.8 18.8
0%
48.8
RPL06.INT.DHA.01560 RPL06.Interior.DHA - Control Fault Domain 4 - Install FW Remaining Tie-ins post Mech Side Aisle install Not Started 10/23/26 11/13/26 18.8 18.8
0%
42.5
RPL06.INT.DHA.02240 RPL06.Interior.DHA - Control Fault Domain 4 - Install TW Remaining Tie-ins post Mech Side Aisle install Not Started 10/23/26 11/13/26 18.8 18.8
0%
42.5
RPL06.INT.DHA.03840 RPL06.Interior.DHA - Control Fault Domain 4 - Install Duct (MES Side) Remaining Tie-ins post Mech Side Aisle install Not Started 10/23/26 11/13/26 18.8 18.8
0%
42.5
RPL06.INT.DHA.03900 RPL06.Conn DHA - CFD2 - Set Passive Racks for PON (16) Infrastructure Not Started 10/23/26 10/27/26 3.8 3.8
0%
138.8
RPL06.INT.DHB.01730 RPL06.Interior.DHB - Control Fault Domain 4 - Install Mechanical Side Aisle Cable Tray Remaining Tie-ins post Mech Side Aisle install Not Started 10/23/26 11/13/26 18.8 18.8
0%
52.5
RPL06.INT.DHB.01760 RPL06.Interior.DHB - Control Fault Domain 4 - Install copper from GS.IDF to BMS and EPMS panels (UG from Center IDF) Remaining Tie-ins post Mech Side Aisle install Not Started 10/23/26 11/13/26 18.8 18.8
0%
35.0
RPL06.INT.SSB.02960 RPL06.Interior.SSB - Loading Dock and Storage - Install Flooring Loading Dock and Storage Not Started 10/23/26 10/29/26 6.2 6.2
0%
138.8
RPL06.INT.SSB.14620 RPL06.Interior.SSB LO #01 to #05 - Install Door (Verify with Trades before installation) Finishes Not Started 10/23/26 11/02/26 8.8 8.8
0%
72.5
RPL06.OFCI.6960 OFCI Delivery: FE Fiber for CFD A.3 (ROJ ) (RVCD ) Data Hall A Not Started 10/23/26 11/13/26 18.8 18.8
0%
75.0
RPL06.WP4.013140 RPL06.Conn DHB.14.14 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 10/23/26 11/05/26 12.5 12.5
0%
113.8
RPL06.WP4.015020 RPL06.Conn DHB.13.10 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 10/23/26 11/05/26 12.5 12.5
0%
113.8
GCD.RPL06.5885 RMU Loop Ready for Energization - DHC Loop EY Not Started 10/26/26 10/26/26 0.0 0.0
0%
103.8
RPL06.CON.WP2.08020 RPL06.Conn - GSMDF1 (South) Test Network (FIM) Network Not Started 10/26/26 10/28/26 3.8 3.8
0%
272.5
RPL06.CON.WP2.08760 RPL06.Conn - GSIDF/DH B1 - Install Cabling (Pull, Splice & terminate) Cabling Not Started 10/26/26 11/02/26 7.5 7.5
0%
328.8
RPL06.CON.WP2.08800 RPL06.Conn - GSIDF/DH B1 - Install Copper, WAPs, Security Camera & Access Control Cabling Not Started 10/26/26 11/05/26 11.2 11.2
0%
137.5
RPL06.CX.DHA.01070 RPL06.CX.DHA - L3/L4 - House Power (for mechainical) DHA HOUSE POWER Not Started 10/26/26 11/06/26 12.5 12.5
0%
18.8
RPL06.CX.DHB.01100 RPL06.CX.DHB - L3/L4 - Control Fault Domain 01 Control Fault Domain 1 Not Started 10/26/26 12/02/26 31.2 31.2
0%
18.8
RPL06.CX.DHB.01380 RPL06.CX.DHB - L3/L4 - Control Fault Domain 03 - FW Flush and Fill Control Fault Domain 3 Not Started 10/26/26 11/03/26 8.8 8.8
0%
46.2
RPL06.EY.DHC.01330 RPL06.EY.DHC - Install Early EY Paving Hardscape and Landscape Not Started 10/26/26 10/30/26 6.2 6.2
0%
240.0
RPL06.EY.ENDC.1950 RPL06.EY.DHD.T1 - HAC Prefab prior to install for DH D Tent 1 Not Started 10/26/26 10/30/26 6.2 6.2
0%
12.5
RPL06.INT.SBC.03680 RPL06.Interior.SSB-Corridor - BoW - Install Door (Verify with Trades before installation) Balance of Walls & Overhead Not Started 10/26/26 11/03/26 8.8 8.8
0%
73.8
RPL06.INT.SSB.03160 RPL06.Interior.SSB - BoW - Final Paint Balance of Walls and OverHead Not Started 10/26/26 10/30/26 6.2 6.2
0%
120.0
RPL06.WP3B.017840 RPL06.Conn EF2<>DHB.14 Test Pigtails (384F) P2&3 (LV) EF2<>DHB.14 Not Started 10/26/26 10/27/26 2.5 2.5
0%
137.5
RPL06.WP4.013400 RPL06.Conn DHB.13.10<>09 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 10/26/26 10/26/26 1.2 1.2
0%
146.2
RPL06.WP4.013420 RPL06.Conn DHB.14.14<>13 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Jumpers Not Started 10/26/26 10/26/26 1.2 1.2
0%
146.2
RPL06.WP4.013520 RPL06.Conn DHB.13.12<>11 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 10/26/26 10/29/26 5.0 5.0
0%
142.5
RPL06.WP4.013540 RPL06.Conn DHB.14.16<>15 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Jumpers Not Started 10/26/26 10/29/26 5.0 5.0
0%
142.5