Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
1
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL06.CON.WP4.01400 |
RPL06.Conn WP4 FENW DHB CFD3 Infrastructure | Infrastructure | Not Started | 10/27/26 | 11/24/26 | 25.0 | 25.0 |
|
126.2 |
RPL06.CX.DHA.01380 |
RPL06.CX.DHA - L3/L4 - Control Fault Domain 03 - FW Flush and Fill | Control Fault Domain 3 | Not Started | 10/27/26 | 11/04/26 | 8.8 | 8.8 |
|
65.0 |
RPL06.CX.DHB.01340 |
RPL06.CX.DHB - L3/L4 - Control Fault Domain 02 - TW Flush and Fill | Control Fault Domain 2 | Not Started | 10/27/26 | 11/05/26 | 10.0 | 10.0 |
|
43.8 |
RPL06.INT.DHA.01620 |
RPL06.Interior.DHA - Control Fault Domain 3 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/27/26 | 11/17/26 | 18.8 | 18.8 |
|
48.8 |
RPL06.INT.DHB.01560 |
RPL06.Conn DHB - CFD3 - Set Passive Racks for WP#3b (16) | Infrastructure | Not Started | 10/27/26 | 10/29/26 | 3.8 | 3.8 |
|
63.8 |
RPL06.INT.DHB.02840 |
RPL06.Conn DHB - CFD3 - Set Passive Racks for PON (16) | Infrastructure | Not Started | 10/27/26 | 10/29/26 | 3.8 | 3.8 |
|
123.8 |
RPL06.INT.SBC.03960 |
RPL06.Interior.SSB-Corridor - BoW - Final Paint and Tube Steel Paint (IFP Add) | Balance of Walls & Overhead | Not Started | 10/27/26 | 11/04/26 | 8.8 | 8.8 |
|
63.8 |
RPL06.INT.SSBC.01290 |
RPL06.Interior.SSB-Corridor - Install Cable Tray | Fit out | Not Started | 10/27/26 | 11/02/26 | 6.2 | 6.2 |
|
67.5 |
GCD.RPL06.3727 |
[RPL06] TC-C Ready : All General Services [RPL06-MDFs] | TC-C Ready: General Services | Not Started | 10/28/26 | 10/28/26 | 0.0 | 0.0 |
|
303.8 |
GCD.RPL06.4105 |
[RPL06] TC-C Ready : Production Cabling Start [DHA Rows 09-16] | TC-C Ready: Production Cabling - DHA | Not Started | 10/28/26 | 10/28/26 | 0.0 | 0.0 |
|
336.2 |
GCD.RPL06.4925 |
L3/L4 Finish EY - DHD | EY | Not Started | 10/28/26 | 10/28/26 | 0.0 | 0.0 |
|
228.8 |
RPL06.CON.WP3B.01980 |
RPL06.Conn EF1<>DHA.03 - WBS Summary | EF1<>DHA.03 | Not Started | 10/28/26 | 11/12/26 | 13.8 | 13.8 |
|
72.5 |
RPL06.CX.DHA.01280 |
RPL06.CX.DHA - L3/L4 - Control Fault Domain 01 - TW Flush and Fill | Control Fault Domain 1 | Not Started | 10/28/26 | 11/06/26 | 10.0 | 10.0 |
|
50.0 |
RPL06.INT.CTRC.06880 |
RPL06.Interior.Center-Corridor - Final Finishes & Fixtures - Water Proofing/ Tape Paint | Restrooms | Not Started | 10/28/26 | 11/03/26 | 6.2 | 6.2 |
|
37.5 |
RPL06.INT.CTRC.1240 |
RPL06.Interior.Center-Corridor - BoW - Install Mechanical Piping/ Refrigerant On-wall | Balance of Walls & Overhead | Not Started | 10/28/26 | 11/03/26 | 6.2 | 6.2 |
|
73.8 |
RPL06.INT.CTRC.1600 |
RPL06.Interior.Center-Corridor - BoW - Electrical Trim Out | Balance of Walls & Overhead | Not Started | 10/28/26 | 11/05/26 | 8.8 | 8.8 |
|
51.2 |
RPL06.INT.CTRC.1620 |
RPL06.Interior.Center-Corridor - BoW - Security Trim Out | Balance of Walls & Overhead | Not Started | 10/28/26 | 11/05/26 | 8.8 | 8.8 |
|
51.2 |
RPL06.INT.CTRC.1640 |
RPL06.Interior.Center-Corridor - BoW - Duct Drops / Trim out | Balance of Walls & Overhead | Not Started | 10/28/26 | 11/03/26 | 6.2 | 6.2 |
|
51.2 |
RPL06.INT.CTRC.1740 |
RPL06.Interior.Center-Corridor - BoW - Install Remaining Lights | Balance of Walls & Overhead | Not Started | 10/28/26 | 11/10/26 | 12.5 | 12.5 |
|
50.0 |
RPL06.INT.ENDC.01410 |
RPL06.Interior.End-Corridor - Mechanical L2 Checklist Completion | Fit out | Not Started | 10/28/26 | 11/10/26 | 12.5 | 12.5 |
|
177.5 |
RPL06.WP3B.011140 |
RPL06.Conn EF1<>DHA.03 Pull Pigtails (384F) P1&4 (LV) | EF1<>DHA.03 | Not Started | 10/28/26 | 10/29/26 | 2.5 | 2.5 |
|
72.5 |
RPL06.WP4.013160 |
RPL06.Conn DHA.03 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 10/28/26 | 10/28/26 | 1.2 | 1.2 |
|
83.8 |
RPL06.WP4.013180 |
RPL06.Conn DHA.04 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 10/28/26 | 10/28/26 | 1.2 | 1.2 |
|
147.5 |
RPL06.WP4.013280 |
RPL06.Conn DHA.03.09 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 10/28/26 | 11/10/26 | 12.5 | 12.5 |
|
110.0 |
RPL06.WP4.013300 |
RPL06.Conn DHA.04.13 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 10/28/26 | 11/10/26 | 12.5 | 12.5 |
|
110.0 |
RPL06.WP4.013560 |
RPL06.Conn DHA.03 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 10/28/26 | 10/28/26 | 1.2 | 1.2 |
|
138.8 |
RPL06.WP4.013580 |
RPL06.Conn DHA.04 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 10/28/26 | 10/28/26 | 1.2 | 1.2 |
|
138.8 |
RPL06.WP4.013600 |
RPL06.Conn DHA.01.04<>03 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Jumpers | Not Started | 10/28/26 | 10/28/26 | 1.2 | 1.2 |
|
157.5 |
RPL06.WP4.013620 |
RPL06.Conn DHA.02.08<>07 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 10/28/26 | 10/28/26 | 1.2 | 1.2 |
|
157.5 |
GCD.RPL06.4945 |
L3 Finish - DHD | DH | Not Started | 10/29/26 | 10/29/26 | 0.0 | 0.0 |
|
228.8 |
GCD.RPL06.5325 |
L3/L4 Start EY - DHC | EY | Not Started | 10/29/26 | 10/29/26 | 0.0 | 0.0 |
|
241.2 |
ICM.B6.2510.D |
[SSDCB1] L3/4 Start - DHD | Commissioning | Not Started | 10/29/26 | 10/29/26 | 0.0 | 0.0 |
|
228.8 |
RPL06.CX.DHC.01000 |
RPL06.CX.DHC - L3, L4, IST - WBS Summary | DHC | Not Started | 10/29/26 | 09/01/27 | 262.5 | 262.5 |
|
60.0 |
RPL06.CX.DHC.01010 |
RPL06.CX.DHC - L3 - WBS Summary (Electrical) | DHC ELECTRICAL | Not Started | 10/29/26 | 03/31/27 | 127.5 | 127.5 |
|
113.8 |
RPL06.CX.DHC.01020 |
RPL06.CX.DHC - L3/L4 - MV Skids (8) Loop | DHC ELECTRICAL | Not Started | 10/29/26 | 11/09/26 | 10.0 | 10.0 |
|
100.0 |
RPL06.CX.DHD.01020 |
RPL06.CX.DHD - L3/L4 - House Power (for electrical) | DHD HOUSE POWER | Not Started | 10/29/26 | 11/12/26 | 12.5 | 12.5 |
|
93.8 |
RPL06.INT.CTRC.2000 |
RPL06.Interior.Center-Corridor LO #10 & #12 - Close Interior Leave Out #10 DHB/CC (For HACs in DHB) WBS Summary | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 10/29/26 | 12/15/26 | 38.8 | 38.8 |
|
46.2 |
RPL06.INT.CTRC.2520 |
RPL06.Interior.Center-Corridor LO #10 & #12 - Install IMP Wall at Leave Out (DH B) | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 10/29/26 | 11/02/26 | 3.8 | 3.8 |
|
2.5 |
RPL06.INT.DHA.03740 |
RPL06.Interior.DHA - OFE - Control Fault Domain 5 (HAC) | Control Fault Domain 5 | Not Started | 10/29/26 | 11/16/26 | 15.0 | 15.0 |
|
-10.0 |
RPL06.INT.ENDC.1580 |
RPL06.Interior.End-Corridor - BoW - Tape Finish Paint | Balance of Walls & Overhead | Not Started | 10/29/26 | 11/02/26 | 3.8 | 3.8 |
|
131.2 |
RPL06.OFCI.6880 |
OFCI Delivery: FE Fiber for CFD B.4 (ROJ ) (RVCD ) | Data Hall B | Not Started | 10/29/26 | 11/19/26 | 18.8 | 18.8 |
|
51.2 |
RPL06.PR.FE.0040 |
RPL06.PR.MDF R/S/P and Provisioning at GS.MDF 1&2 | MDFs & IDFs | Not Started | 10/29/26 | 12/07/26 | 31.2 | 31.2 |
|
272.5 |
RPL06.WP4.013320 |
RPL06.Conn DHA.03 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 10/29/26 | 10/29/26 | 1.2 | 1.2 |
|
83.8 |
RPL06.WP4.013340 |
RPL06.Conn DHA.04 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 10/29/26 | 10/29/26 | 1.2 | 1.2 |
|
147.5 |
RPL06.WP4.013920 |
RPL06.Conn DHA.03.09<>09 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 10/29/26 | 11/02/26 | 3.8 | 3.8 |
|
138.8 |
RPL06.WP4.013940 |
RPL06.Conn DHA.04.13<>13 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 10/29/26 | 11/02/26 | 3.8 | 3.8 |
|
138.8 |
RPL06.WP4.013960 |
RPL06.Conn DHA.03 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 10/29/26 | 11/02/26 | 3.8 | 3.8 |
|
157.5 |
RPL06.WP4.013980 |
RPL06.Conn DHA.04 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 10/29/26 | 11/02/26 | 3.8 | 3.8 |
|
157.5 |
GCD.RPL06.3529 |
[RPL06] TC-C Ready : Production Cabling Start [DHB Rows 17-24] | TC-C Ready: Production Cabling - DHB | Not Started | 10/30/26 | 10/30/26 | 0.0 | 0.0 |
|
333.8 |
RPL06.CON.WP3B.01280 |
RPL06.Conn EF2<>DHB.15 - WBS Summary | EF2<>DHB.15 | Not Started | 10/30/26 | 11/16/26 | 13.8 | 13.8 |
|
76.2 |
RPL06.CON.WP3B.01940 |
RPL06.Conn EF1<>DHA.04 - WBS Summary | EF1<>DHA.04 | Not Started | 10/30/26 | 11/13/26 | 12.5 | 12.5 |
|
135.0 |
RPL06.INT.CTRC.1700 |
RPL06.Interior.Center-Corridor - BoW - Plumbing Trim Out | Balance of Walls & Overhead | Not Started | 10/30/26 | 11/05/26 | 6.2 | 6.2 |
|
51.2 |
RPL06.INT.CTRC.1720 |
RPL06.Interior.Center-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out | Balance of Walls & Overhead | Not Started | 10/30/26 | 11/09/26 | 8.8 | 8.8 |
|
51.2 |
RPL06.INT.CTRC.2540 |
RPL06.Interior.Center-Corridor LO #10 & #12 - Tie In MEPF with IMP Wall buildback | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 10/30/26 | 11/04/26 | 5.0 | 5.0 |
|
2.5 |
RPL06.INT.DHA.01580 |
RPL06.Interior.DHA - Control Fault Domain 4 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/30/26 | 11/20/26 | 18.8 | 18.8 |
|
48.8 |
RPL06.INT.DHA.01590 |
RPL06.Interior.DHA - Control Fault Domain 4 - Pull EPMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/30/26 | 11/20/26 | 18.8 | 18.8 |
|
48.8 |
RPL06.INT.DHA.01600 |
RPL06.Interior.DHA - Control Fault Domain 4 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/30/26 | 11/20/26 | 18.8 | 18.8 |
|
42.5 |
RPL06.INT.DHB.01780 |
RPL06.Interior.DHB - Control Fault Domain 5 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/30/26 | 11/20/26 | 18.8 | 18.8 |
|
32.5 |
RPL06.INT.DHB.01790 |
RPL06.Interior.DHB - Control Fault Domain 5 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/30/26 | 11/20/26 | 18.8 | 18.8 |
|
17.5 |
RPL06.INT.DHB.01850 |
RPL06.Interior.DHB - Control Fault Domain 4 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/30/26 | 11/20/26 | 18.8 | 18.8 |
|
35.0 |
RPL06.INT.DHB.02280 |
RPL06.Interior.DHB - Control Fault Domain 5 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/30/26 | 11/20/26 | 18.8 | 18.8 |
|
17.5 |
RPL06.INT.DHB.02780 |
RPL06.Interior.DHB - Control Fault Domain 5 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 10/30/26 | 11/20/26 | 18.8 | 18.8 |
|
17.5 |
RPL06.INT.SSB.01520 |
RPL06.Interior.SSB - Loading Dock and Storage - Install Shelving | Loading Dock and Storage | Not Started | 10/30/26 | 11/04/26 | 5.0 | 5.0 |
|
138.8 |
RPL06.WP3B.011160 |
RPL06.Conn EF1<>DHA.04 Pull Pigtails (384F) P1&4 (LV) | EF1<>DHA.04 | Not Started | 10/30/26 | 10/30/26 | 1.2 | 1.2 |
|
86.2 |
RPL06.WP3B.012100 |
RPL06.Conn EF2<>DHB.15 Pull Pigtails (384F) P2&3 (LV) | EF2<>DHB.15 | Not Started | 10/30/26 | 11/02/26 | 2.5 | 2.5 |
|
66.2 |
RPL06.WP3B.012580 |
RPL06.Conn EF1<>DHA.03 Install (A-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.03 | Not Started | 10/30/26 | 10/30/26 | 1.2 | 1.2 |
|
72.5 |
RPL06.WP4.013640 |
RPL06.Conn DHA.03 Pull Trunk (384F) [RSW<>FSW] | Trunks | Not Started | 10/30/26 | 11/02/26 | 2.5 | 2.5 |
|
83.8 |
RPL06.WP4.013660 |
RPL06.Conn DHA.04 Pull Trunk (384F) [RSW<>FSW] | Trunks | Not Started | 10/30/26 | 11/02/26 | 2.5 | 2.5 |
|
147.5 |
RPL06.WP4.013760 |
RPL06.Conn DHB.15 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 10/30/26 | 10/30/26 | 1.2 | 1.2 |
|
88.8 |
RPL06.WP4.013780 |
RPL06.Conn DHB.16 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 10/30/26 | 10/30/26 | 1.2 | 1.2 |
|
133.8 |
RPL06.WP4.014120 |
RPL06.Conn DHB.15.17 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 10/30/26 | 11/13/26 | 12.5 | 12.5 |
|
95.0 |
RPL06.WP4.014140 |
RPL06.Conn DHB.16.21 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 10/30/26 | 11/13/26 | 12.5 | 12.5 |
|
95.0 |
RPL06.WP4.014400 |
RPL06.Conn DHB.15 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 10/30/26 | 10/30/26 | 1.2 | 1.2 |
|
123.8 |
RPL06.WP4.014420 |
RPL06.Conn DHB.16 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 10/30/26 | 10/30/26 | 1.2 | 1.2 |
|
123.8 |
RPL06.WP4.014440 |
RPL06.Conn DHB.13.12<>11 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 10/30/26 | 10/30/26 | 1.2 | 1.2 |
|
142.5 |
RPL06.WP4.014460 |
RPL06.Conn DHB.14.16<>15 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Jumpers | Not Started | 10/30/26 | 10/30/26 | 1.2 | 1.2 |
|
142.5 |
GCD.RPL06.1735 |
Start FSHAC set in place - RPL06 - DHC&D | Construction Milestones | Not Started | 11/02/26 | 11/02/26 | 0.0 | 0.0 |
|
260.0 |
RPL06.EY.DHA.01480 |
RPL06.EY.DHA - Install Landscaping | Hardscape and Landscape | Not Started | 11/02/26 | 11/16/26 | 12.5 | 12.5 |
|
320.0 |
RPL06.EY.DHC.01340 |
RPL06.EY.DHC - Install Lighting | Hardscape and Landscape | Not Started | 11/02/26 | 11/16/26 | 12.5 | 12.5 |
|
240.0 |
RPL06.INT.CTRC.2530 |
RPL06.Interior.Center-Corridor LO #10 & #12 - Install IMP Wall at Leave Out (DH D) | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 11/02/26 | 11/04/26 | 3.8 | 3.8 |
|
2.5 |
RPL06.INT.DHD.02290 |
RPL06.Interior.DHD - OFE - Control Fault Domain 1 (HAC) | Control Fault Domain 1 | Not Started | 11/02/26 | 11/19/26 | 16.2 | 16.2 |
|
12.5 |
RPL06.INT.SSB.02460 |
RPL06.Interior.SSB - BoW - Install Flooring Tiles/Resinous Flooring in specific rooms **?? | Balance of Walls and OverHead | Not Started | 11/02/26 | 11/06/26 | 6.2 | 6.2 |
|
120.0 |
RPL06.INT.SSB.06440 |
RPL06.Interior.SSB LO #16 - Final Paint | Leave Out Wall #16 (SSB - North of Loading Dock) | Not Started | 11/02/26 | 11/10/26 | 8.8 | 8.8 |
|
68.8 |
RPL06.INT.SSB.06960 |
RPL06.Interior.SSB - BoW - QC | Balance of Walls and OverHead | Not Started | 11/02/26 | 11/06/26 | 6.2 | 6.2 |
|
120.0 |
RPL06.WP3B.012600 |
RPL06.Conn EF1<>DHA.04 Install (A-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.04 | Not Started | 11/02/26 | 11/02/26 | 1.2 | 1.2 |
|
135.0 |
RPL06.WP3B.014020 |
RPL06.Conn EF1<>DHA.03 Splice (A-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.03 | Not Started | 11/02/26 | 11/09/26 | 7.5 | 7.5 |
|
72.5 |
RPL06.WP3B.015460 |
RPL06.Conn EF1<>DHA.03 Install (Z-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.03 | Not Started | 11/02/26 | 11/02/26 | 1.2 | 1.2 |
|
72.5 |
RPL06.WP4.014160 |
RPL06.Conn DHB.15 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 11/02/26 | 11/02/26 | 1.2 | 1.2 |
|
88.8 |
RPL06.WP4.014180 |
RPL06.Conn DHB.16 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 11/02/26 | 11/02/26 | 1.2 | 1.2 |
|
133.8 |
RPL06.WP4.014800 |
RPL06.Conn DHB.15.17<>17 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 11/02/26 | 11/04/26 | 3.8 | 3.8 |
|
123.8 |
RPL06.WP4.014820 |
RPL06.Conn DHB.16.21<>21 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 11/02/26 | 11/04/26 | 3.8 | 3.8 |
|
123.8 |
RPL06.WP4.014840 |
RPL06.Conn DHB.15 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 11/02/26 | 11/04/26 | 3.8 | 3.8 |
|
142.5 |
RPL06.WP4.014860 |
RPL06.Conn DHB.16 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 11/02/26 | 11/04/26 | 3.8 | 3.8 |
|
142.5 |
DCC.B6.3165 |
[SSDCB1] PortMaps Delivered : GS | Connectivity | Not Started | 11/03/26 | 11/03/26 | 0.0 | 0.0 |
|
331.2 |
DCC.B6.3170 |
[SSDCB1] PortMaps Delivered : Elevations & Cabling | Connectivity | Not Started | 11/03/26 | 11/03/26 | 0.0 | 0.0 |
|
331.2 |
DCC.B6.3175 |
[SSDCB1] PortMaps Delivered : Backbone | Connectivity | Not Started | 11/03/26 | 11/03/26 | 0.0 | 0.0 |
|
331.2 |
DCC.B6.3180 |
[SSDCB1] PortMaps Delivered : Front End | Connectivity | Not Started | 11/03/26 | 11/03/26 | 0.0 | 0.0 |
|
331.2 |
DCC.B6.3460 |
[SSDCB1] Production Dark Fiber Path 1 - Circuit Delivered **Pred?? only for RPL10?? | Connectivity | Not Started | 11/03/26 | 11/03/26 | 0.0 | 0.0 |
|
331.2 |
RPL06.CON.WP2.08780 |
RPL06.Conn - GSIDF/DH B1 - Install & Test Network (FIM) | Network | Not Started | 11/03/26 | 11/04/26 | 2.5 | 2.5 |
|
328.8 |
RPL06.CON.WP2.08820 |
RPL06.Conn - GSIDF/DH A1 - WBS Summary | Int. IDF Stick Built - GSIDF6A1 | Not Started | 11/03/26 | 11/20/26 | 16.2 | 16.2 |
|
315.0 |