Schedule Viewer
Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer
· Uploaded Apr 16, 2026 01:19 PM
· 6139 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
5
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL06.CON.WP4.01800 |
RPL06.Conn WP4 FENW DHB CFD5 Infrastructure | Infrastructure | Not Started | 12/09/26 | 01/07/27 | 25.0 | 25.0 |
|
91.2 |
RPL06.CX.DHA.01500 |
RPL06.CX.DHA - L3/L4 - Control Fault Domain 05 - FW Flush and Fill | Control Fault Domain 5 | Not Started | 12/09/26 | 12/17/26 | 8.8 | 8.8 |
|
50.0 |
RPL06.INT.CTRC.07060 |
RPL06.Interior.Center-Corridor - Final Finishes & Fixtures - Flooring | Restrooms | Not Started | 12/09/26 | 12/17/26 | 8.8 | 8.8 |
|
37.5 |
RPL06.INT.CTRC.3300 |
RPL06.Interior.Center-Corridor LO #10 & #12 - Plumbing Trim Out | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 12/09/26 | 12/09/26 | 1.2 | 1.2 |
|
5.0 |
RPL06.INT.CTRC.3320 |
RPL06.Interior.Center-Corridor LO #10 & #12 - Fire Life Safety Trim Out | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 12/09/26 | 12/09/26 | 1.2 | 1.2 |
|
5.0 |
RPL06.INT.CTRC.3380 |
RPL06.Interior.Center-Corridor LO #10 & #12 - Install Asset Tags | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 12/09/26 | 12/11/26 | 3.8 | 3.8 |
|
2.5 |
RPL06.INT.CTRC.8140 |
RPL06.Interior.Center-Corridor LO #10 - Install Door (Verify with Trades before installation) | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 12/09/26 | 12/10/26 | 2.5 | 2.5 |
|
65.0 |
RPL06.INT.CTRC.8540 |
RPL06.Interior.Center-Corridor LO #11 - QC | Remaining of LO Wall #11 (Spoke Parts) | Not Started | 12/09/26 | 12/09/26 | 1.2 | 1.2 |
|
48.8 |
RPL06.INT.CTRC.8780 |
RPL06.Interior.Center-Corridor LO #11 - Fire Safing/ Wall Finishes | Remaining of LO Wall #11 (Spoke Parts) | Not Started | 12/09/26 | 12/10/26 | 2.5 | 2.5 |
|
55.0 |
RPL06.INT.DHA.01900 |
RPL06.Interior.DHA - Control Fault Domain 5 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 12/09/26 | 12/30/26 | 18.8 | 18.8 |
|
33.8 |
RPL06.INT.DHB.01840 |
RPL06.Conn DHB - CFD5 - Set Passive Racks for WP#3b (16) | Infrastructure | Not Started | 12/09/26 | 12/11/26 | 3.8 | 3.8 |
|
38.8 |
RPL06.INT.DHB.02050 |
RPL06.Interior.DHB - Final Clean | Tie-Ins | Not Started | 12/09/26 | 12/14/26 | 5.0 | 5.0 |
|
115.0 |
RPL06.INT.DHB.02880 |
RPL06.Conn DHB - CFD5 - Set Passive Racks for PON (16) | Infrastructure | Not Started | 12/09/26 | 12/11/26 | 3.8 | 3.8 |
|
88.8 |
RPL06.INT.DHC.01170 |
RPL06.Interior.DHC - Control Fault Domain 1 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 12/09/26 | 01/07/27 | 25.0 | 25.0 |
|
52.5 |
RPL06.INT.DHC.01180 |
RPL06.Interior.DHC - Control Fault Domain 1 - Pull EPMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 12/09/26 | 01/07/27 | 25.0 | 25.0 |
|
52.5 |
RPL06.INT.DHC.01190 |
RPL06.Interior.DHC - Control Fault Domain 1 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 12/09/26 | 01/07/27 | 25.0 | 25.0 |
|
40.0 |
RPL06.INT.DHD.01240 |
RPL06.Interior.DHD - Control Fault Domain 1 - Install copper from GS.IDF to BMS and EPMS panels | Remaining Tie-ins post Mech Side Aisle install | Not Started | 12/09/26 | 01/07/27 | 25.0 | 25.0 |
|
36.2 |
RPL06.WP3B.011300 |
RPL06.Conn EF1<>DHB.11 Pull Pigtails (384F) P1&4 (MES) | EF1<>DHB.11 | Not Started | 12/09/26 | 12/10/26 | 2.5 | 2.5 |
|
17.5 |
RPL06.WP3B.012680 |
RPL06.Conn EF1<>DHA.08 Install (A-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.08 | Not Started | 12/09/26 | 12/09/26 | 1.2 | 1.2 |
|
105.0 |
RPL06.WP3B.014100 |
RPL06.Conn EF1<>DHA.07 Splice (A-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.07 | Not Started | 12/09/26 | 12/16/26 | 7.5 | 7.5 |
|
106.2 |
RPL06.WP3B.015540 |
RPL06.Conn EF1<>DHA.07 Install (Z-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.07 | Not Started | 12/09/26 | 12/09/26 | 1.2 | 1.2 |
|
106.2 |
RPL06.WP4.018940 |
RPL06.Conn DHA.07 Pull Trunk (384F) [RSW<>FSW] | Trunks | Not Started | 12/09/26 | 12/10/26 | 2.5 | 2.5 |
|
116.2 |
RPL06.WP4.018960 |
RPL06.Conn DHA.08 Pull Trunk (384F) [RSW<>FSW] | Trunks | Not Started | 12/09/26 | 12/10/26 | 2.5 | 2.5 |
|
116.2 |
RPL06.WP4.019300 |
RPL06.Conn DHA.05.20<>19 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 12/09/26 | 12/09/26 | 1.2 | 1.2 |
|
123.8 |
RPL06.WP4.019320 |
RPL06.Conn DHA.06.24<>23 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 12/09/26 | 12/09/26 | 1.2 | 1.2 |
|
123.8 |
RPL06.WP4.019760 |
RPL06.Conn DHB.18.29<>29 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 12/09/26 | 12/09/26 | 1.2 | 1.2 |
|
110.0 |
RPL06.WP4.019840 |
RPL06.Conn DHB.18.31<>31 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 12/09/26 | 12/11/26 | 3.8 | 3.8 |
|
107.5 |
GCD.RPL06.4685 |
L3/L4 Start - DHA Rows 25-32 | DH | Not Started | 12/10/26 | 12/10/26 | 0.0 | 0.0 |
|
111.2 |
GCD.RPL06.4805 |
L3/L4 Start - DHA Rows 33-40 | DH | Not Started | 12/10/26 | 12/10/26 | 0.0 | 0.0 |
|
111.2 |
RPL06.CX.DHA.01140 |
RPL06.CX.DHA - L3/L4 - Elec. Domain 07/08 | DHA ELECTRICAL | Not Started | 12/10/26 | 12/15/26 | 5.0 | 5.0 |
|
42.5 |
RPL06.INT.CTRC.3700 |
RPL06.Interior.Center-Corridor LO #11 & #13 - Install Door Frames | Interior Leave Out Wall #11, #13 (DHA/CC) | Not Started | 12/10/26 | 12/11/26 | 2.5 | 2.5 |
|
-10.0 |
RPL06.INT.CTRC.8560 |
RPL06.Interior.Center-Corridor LO #11 - Hang Drywall | Remaining of LO Wall #11 (Spoke Parts) | Not Started | 12/10/26 | 12/15/26 | 5.0 | 5.0 |
|
48.8 |
RPL06.INT.SBC.04040 |
RPL06.Interior.SSB-Corridor - BoW - Final Clean | Balance of Walls & Overhead | Not Started | 12/10/26 | 12/15/26 | 5.0 | 5.0 |
|
63.8 |
RPL06.WP3B.014120 |
RPL06.Conn EF1<>DHA.08 Splice (A-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.08 | Not Started | 12/10/26 | 12/17/26 | 7.5 | 7.5 |
|
105.0 |
RPL06.WP3B.015560 |
RPL06.Conn EF1<>DHA.08 Install (Z-End) Pigtails (384F) P1&4 (LV) | EF1<>DHA.08 | Not Started | 12/10/26 | 12/10/26 | 1.2 | 1.2 |
|
105.0 |
RPL06.CON.WP3B.01060 |
RPL06.Conn EF1<>DHB12 - WBS Summary | EF1<>DHB.12 | Not Started | 12/11/26 | 12/28/26 | 13.8 | 13.8 |
|
87.5 |
RPL06.CON.WP3B.01120 |
RPL06.Conn EF2<>DHB11 - WBS Summary | EF1<>DHB.12 | Not Started | 12/11/26 | 12/28/26 | 13.8 | 13.8 |
|
87.5 |
RPL06.EY.SSB.01300 |
RPL06.EY.SSB - Install Temp Paving | Hardscape and Landscape | Not Started | 12/11/26 | 12/24/26 | 12.5 | 12.5 |
|
68.8 |
RPL06.INT.CTRC.01500 |
RPL06.Interior.Center-Corridor (N) - Mechanical L2 Checklist Completion | Fit out (North) | Not Started | 12/11/26 | 12/24/26 | 12.5 | 12.5 |
|
57.5 |
RPL06.INT.CTRC.1840 |
RPL06.Interior.Center-Corridor - BoW - Mechanical L2 Checklist Completion | Balance of Walls & Overhead | Not Started | 12/11/26 | 12/24/26 | 12.5 | 12.5 |
|
50.0 |
RPL06.INT.CTRC.8040 |
RPL06.Interior.Center-Corridor LO #10 - Electrical Trim Out | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 12/11/26 | 12/15/26 | 3.8 | 3.8 |
|
58.8 |
RPL06.INT.CTRC.8060 |
RPL06.Interior.Center-Corridor LO #10 - Security Trim Out | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 12/11/26 | 12/15/26 | 3.8 | 3.8 |
|
58.8 |
RPL06.INT.CTRC.8160 |
RPL06.Interior.Center-Corridor LO #10 - Install Remaining Refrigerant Line | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 12/11/26 | 12/15/26 | 3.8 | 3.8 |
|
62.5 |
RPL06.INT.CTRC.8760 |
RPL06.Interior.Center-Corridor LO #11 - Install Flooring Tiles/Resinous Flooring in specific rooms **?? | Remaining of LO Wall #11 (Spoke Parts) | Not Started | 12/11/26 | 12/15/26 | 3.8 | 3.8 |
|
55.0 |
RPL06.INT.DHC.02370 |
RPL06.Interior.DHC - OFE - Control Fault Domain 2 (Mech Side Aisle) | Control Fault Domain 2 | Not Started | 12/11/26 | 12/22/26 | 10.0 | 10.0 |
|
6.2 |
RPL06.INT.DHD.01310 |
RPL06.Interior.DHD - Control Fault Domain 2 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 12/11/26 | 01/04/27 | 18.8 | 18.8 |
|
52.5 |
RPL06.INT.DHD.01320 |
RPL06.Interior.DHD - Control Fault Domain 2 - Pull EPMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 12/11/26 | 01/04/27 | 18.8 | 18.8 |
|
52.5 |
RPL06.INT.DHD.01330 |
RPL06.Interior.DHD - Control Fault Domain 2 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 12/11/26 | 01/04/27 | 18.8 | 18.8 |
|
40.0 |
RPL06.INT.DHD.02430 |
RPL06.Interior.DHD - OFE - Control Fault Domain 3 (Mech Side Aisle) | Control Fault Domain 3 | Not Started | 12/11/26 | 12/22/26 | 10.0 | 10.0 |
|
15.0 |
RPL06.WP3B.011320 |
RPL06.Conn EF1<>DHB.12 Pull Pigtails (384F) P1&4 (MES) | EF1<>DHB.12 | Not Started | 12/11/26 | 12/14/26 | 2.5 | 2.5 |
|
22.5 |
RPL06.WP3B.012740 |
RPL06.Conn EF1<>DHB.11 Install (A-End) Pigtails (384F) P1&4 (MES) | EF1<>DHB.11 | Not Started | 12/11/26 | 12/11/26 | 1.2 | 1.2 |
|
17.5 |
RPL06.WP4.019740 |
RPL06.Conn DHA.07.25<>25 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 12/11/26 | 12/11/26 | 1.2 | 1.2 |
|
122.5 |
RPL06.WP4.019820 |
RPL06.Conn DHA.07.27<>27 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 12/11/26 | 12/15/26 | 3.8 | 3.8 |
|
107.5 |
RPL06.WP4.019980 |
RPL06.Conn DHA.08.29<>29 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 12/11/26 | 12/11/26 | 1.2 | 1.2 |
|
122.5 |
RPL06.WP4.020080 |
RPL06.Conn DHA.08.31<>31 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 12/11/26 | 12/15/26 | 3.8 | 3.8 |
|
107.5 |
GCD.RPL06.4005 |
[RPL06] TC-C Ready : Production Cabling Start [DHB Rows 33-40] | TC-C Ready: Production Cabling - DHB | Not Started | 12/14/26 | 12/14/26 | 0.0 | 0.0 |
|
298.8 |
RPL06.CON.WP2.11100 |
RPL06.Conn - GSMDF1(South)<>DH B - CFD5 Rack #01 Pull, Install & Test PON Trunks | MDF1 <> DH B - Rack#01 MES side | Not Started | 12/14/26 | 12/16/26 | 3.8 | 3.8 |
|
108.8 |
RPL06.CON.WP2.12100 |
RPL06.Conn - GSMDF2(North)<>DH B - CFD5 Rack #50 Pull, Install & Test PON Trunks | MDF2 <> DH B - Rack#50 LV side | Not Started | 12/14/26 | 12/16/26 | 3.8 | 3.8 |
|
108.8 |
RPL06.CON.WP3B.01440 |
RPL06.Conn EF2<>DHB.19 - WBS Summary | EF2<>DHB.19 | Not Started | 12/14/26 | 12/28/26 | 12.5 | 12.5 |
|
43.8 |
RPL06.INT.CTRC.3400 |
RPL06.Interior.Center-Corridor LO #10 & #12 - Install Door (Verify with Trades before installation) | Interior Leave Out Wall #10, #12 (DHB/CC) | Not Started | 12/14/26 | 12/15/26 | 2.5 | 2.5 |
|
2.5 |
RPL06.INT.CTRC.3740 |
RPL06.Interior.Center-Corridor LO #11 & #13 - Fire Safing OH and | Interior Leave Out Wall #11, #13 (DHA/CC) | Not Started | 12/14/26 | 12/15/26 | 2.5 | 2.5 |
|
-10.0 |
RPL06.OFCI.7020 |
OFCI Delivery: FE Fiber for CFD D.1 (ROJ ) (RVCD ) | Data Hall D | Not Started | 12/14/26 | 01/05/27 | 18.8 | 18.8 |
|
56.2 |
RPL06.WP3B.012180 |
RPL06.Conn EF2<>DHB.19 Pull Pigtails (384F) P2&3 (LV) | EF2<>DHB.19 | Not Started | 12/14/26 | 12/14/26 | 1.2 | 1.2 |
|
38.8 |
RPL06.WP3B.014180 |
RPL06.Conn EF1<>DHB.11 Splice (A-End) Pigtails (384F) P1&4 (MES) | EF1<>DHB.11 | Not Started | 12/14/26 | 12/21/26 | 7.5 | 7.5 |
|
17.5 |
RPL06.WP3B.015620 |
RPL06.Conn EF1<>DHB.11 Install (Z-End) Pigtails (384F) P1&4 (MES) | EF1<>DHB.11 | Not Started | 12/14/26 | 12/14/26 | 1.2 | 1.2 |
|
17.5 |
RPL06.WP4.019660 |
RPL06.Conn DHA.03.12 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 12/14/26 | 12/28/26 | 12.5 | 12.5 |
|
110.0 |
RPL06.WP4.019680 |
RPL06.Conn DHA.04.16 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 12/14/26 | 12/28/26 | 12.5 | 12.5 |
|
110.0 |
RPL06.WP4.019700 |
RPL06.Conn DHB.19 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 12/14/26 | 12/14/26 | 1.2 | 1.2 |
|
55.0 |
RPL06.WP4.019720 |
RPL06.Conn DHB.20 Pull Ext. Trunk (384F) [SSW<>JXSW] | SSW<>JXSW | Not Started | 12/14/26 | 12/14/26 | 1.2 | 1.2 |
|
51.2 |
RPL06.WP4.019900 |
RPL06.Conn DHB.19.33 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 12/14/26 | 12/28/26 | 12.5 | 12.5 |
|
60.0 |
RPL06.WP4.019920 |
RPL06.Conn DHB.20.37 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] | Jumpers (AI Confirmed) | Not Started | 12/14/26 | 12/28/26 | 12.5 | 12.5 |
|
60.0 |
RPL06.WP4.020400 |
RPL06.Conn DHB.18.31<>31 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Jumpers | Not Started | 12/14/26 | 12/14/26 | 1.2 | 1.2 |
|
107.5 |
RPL06.WP4.020420 |
RPL06.Conn DHB.17.28<>27 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 12/14/26 | 12/14/26 | 1.2 | 1.2 |
|
107.5 |
RPL06.WP4.020660 |
RPL06.Conn DHB.19 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 12/14/26 | 12/14/26 | 1.2 | 1.2 |
|
88.8 |
RPL06.WP4.020680 |
RPL06.Conn DHB.20 Pull Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 12/14/26 | 12/14/26 | 1.2 | 1.2 |
|
88.8 |
RPL06.CON.WP3B.01400 |
RPL06.Conn EF2<>DHB.20 - WBS Summary | EF2<>DHB.20 | Not Started | 12/15/26 | 12/29/26 | 12.5 | 12.5 |
|
38.8 |
RPL06.INT.CTRC.8080 |
RPL06.Interior.Center-Corridor LO #10 - Plumbing Trim Out | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 12/15/26 | 12/17/26 | 3.8 | 3.8 |
|
58.8 |
RPL06.INT.CTRC.8100 |
RPL06.Interior.Center-Corridor LO #10 - Fire Life Safety Trim Out | Remaining of LO Wall #10 (Spoke Parts & Spoke Tech) | Not Started | 12/15/26 | 12/17/26 | 3.8 | 3.8 |
|
58.8 |
RPL06.INT.DHB.02060 |
RPL06.Interior.DHB - Final Punch Walk | Tie-Ins | Not Started | 12/15/26 | 12/16/26 | 2.5 | 2.5 |
|
115.0 |
RPL06.INT.SSBC.01530 |
RPL06.Interior.SSB-Corridor - Remaining DHB L2 Checklist Completion | Fit out | Not Started | 12/15/26 | 12/21/26 | 6.2 | 6.2 |
|
105.0 |
RPL06.WP3B.011340 |
RPL06.Conn EF1<>DHB.13 Pull Pigtails (384F) P1&4 (MES) | EF1<>DHB.13 | Not Started | 12/15/26 | 12/16/26 | 2.5 | 2.5 |
|
22.5 |
RPL06.WP3B.012200 |
RPL06.Conn EF2<>DHB.20 Pull Pigtails (384F) P2&3 (LV) | EF2<>DHB.20 | Not Started | 12/15/26 | 12/15/26 | 1.2 | 1.2 |
|
38.8 |
RPL06.WP3B.012760 |
RPL06.Conn EF1<>DHB.12 Install (A-End) Pigtails (384F) P1&4 (MES) | EF1<>DHB.12 | Not Started | 12/15/26 | 12/15/26 | 1.2 | 1.2 |
|
87.5 |
RPL06.WP3B.013620 |
RPL06.Conn EF2<>DHB.19 Install (A-End) Pigtails (384F) P2&3 (LV) | EF2<>DHB.19 | Not Started | 12/15/26 | 12/15/26 | 1.2 | 1.2 |
|
43.8 |
RPL06.WP4.019940 |
RPL06.Conn DHB.19 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 12/15/26 | 12/15/26 | 1.2 | 1.2 |
|
55.0 |
RPL06.WP4.019960 |
RPL06.Conn DHB.20 Pull Trunk (192F) [FSW<>SSW] | FSW<>SSW | Not Started | 12/15/26 | 12/15/26 | 1.2 | 1.2 |
|
51.2 |
RPL06.WP4.020940 |
RPL06.Conn DHB.20.37<>37 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] | Across-Row | Not Started | 12/15/26 | 12/17/26 | 3.8 | 3.8 |
|
88.8 |
RPL06.WP4.020960 |
RPL06.Conn DHB.19 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 12/15/26 | 12/17/26 | 3.8 | 3.8 |
|
107.5 |
RPL06.WP4.020980 |
RPL06.Conn DHB.20 Install Ext. Trunk (24F) [PON (Passive, In-Rack)] | In-Rack | Not Started | 12/15/26 | 12/17/26 | 3.8 | 3.8 |
|
107.5 |
RPL06.WP4.021000 |
RPL06.Conn DHB.19.34<>33 Pull Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] | Across-Row | Not Started | 12/15/26 | 12/18/26 | 5.0 | 5.0 |
|
88.8 |
GCD.RPL06.4705 |
L3/L4 Finish - DHA Rows 01-08 | DH | Not Started | 12/16/26 | 12/16/26 | 0.0 | 0.0 |
|
105.0 |
RPL06.CX.DHA.01580 |
RPL06.CX.DHA - L3/L4 - Control Fault Domain 04 - TW Flush and Fill | Control Fault Domain 4 | Not Started | 12/16/26 | 12/28/26 | 10.0 | 10.0 |
|
42.5 |
RPL06.CX.DHD.01080 |
RPL06.CX.DHD - L4 - WBS Summary (Mechanical) | DHD MECHANICAL | Not Started | 12/16/26 | 06/08/27 | 148.8 | 148.8 |
|
41.2 |
RPL06.CX.DHD.01260 |
RPL06.CX.DHD - L3/L4 - Control Fault Domain 01 - FW Flush and Fill | Control Fault Domain 1 | Not Started | 12/16/26 | 12/24/26 | 8.8 | 8.8 |
|
58.8 |
RPL06.INT.CTRC.01950 |
RPL06.Interior.Center-Corridor (S) - Install Lighting | Fit out (South) | Not Started | 12/16/26 | 12/24/26 | 8.8 | 8.8 |
|
30.0 |
RPL06.INT.CTRC.02050 |
RPL06.Interior.Center-Corridor (S) - Final Paint and Tube Steel Paint (IFP Add) | Fit out (South) | Not Started | 12/16/26 | 12/30/26 | 12.5 | 12.5 |
|
46.2 |
RPL06.INT.CTRC.3980 |
RPL06.Interior.Center-Corridor LO #11 & #13 - Duct Drops / Trim out | Interior Leave Out Wall #11, #13 (DHA/CC) | Not Started | 12/16/26 | 12/17/26 | 2.5 | 2.5 |
|
-8.8 |
RPL06.INT.CTRC.4080 |
RPL06.Interior.Center-Corridor LO #11 & #13 - Install Remaining Lights | Interior Leave Out Wall #11, #13 (DHA/CC) | Not Started | 12/16/26 | 12/21/26 | 5.0 | 5.0 |
|
-8.8 |
RPL06.INT.CTRC.4100 |
RPL06.Interior.Center-Corridor LO #11 & #13 - Install Flooring Tiles/Resinous Flooring in specific rooms **?? | Interior Leave Out Wall #11, #13 (DHA/CC) | Not Started | 12/16/26 | 12/18/26 | 3.8 | 3.8 |
|
27.5 |
RPL06.INT.CTRC.4240 |
RPL06.Interior.Center-Corridor LO #11 & #13 - Fire Safing / Wall Finishes | Interior Leave Out Wall #11, #13 (DHA/CC) | Not Started | 12/16/26 | 12/17/26 | 2.5 | 2.5 |
|
-10.0 |