Schedule Viewer

Last schedule upload: D3-R25005-00-RPL06 — 6139 activities — 04/16/2026 08:19 AM CT
RPL06 - GC LIVE SCHEDULE - Data Date 2026.04.12.xer · Uploaded Apr 16, 2026 01:19 PM · 6139 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
0
Completed
0
In Progress
4
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL06.INT.EC.LO.9520 RPL06.Interior.EC LO #15 - Duct Drops / Trim out Interior Leave Out Wall #15 DHC/EC for DHA&C HACs Not Started 03/04/27 03/05/27 2.5 2.5
0%
7.5
RPL06.INT.EC.LO.9540 RPL06.Interior.EC LO #15 - Fire Safing / Wall Finishes Interior Leave Out Wall #15 DHC/EC for DHA&C HACs Not Started 03/04/27 03/05/27 2.5 2.5
0%
60.0
RPL06.INT.EC.LO.9600 RPL06.Interior.EC LO #15 - Install Flooring Tiles/Resinous Flooring in specific rooms **?? Interior Leave Out Wall #15 DHC/EC for DHA&C HACs Not Started 03/04/27 03/08/27 3.8 3.8
0%
58.8
RPL06.INT.EC.LO.9660 RPL06.Interior.EC LO #15 - Install Remaining Lights Interior Leave Out Wall #15 DHC/EC for DHA&C HACs Not Started 03/04/27 03/09/27 5.0 5.0
0%
1.2
RPL06.INT.ENDC.1660 RPL06.Interior.End-Corridor - BoW - Final Paint and Tube Steel Paint (IFP Add) Balance of Walls & Overhead Not Started 03/04/27 03/10/27 6.2 6.2
0%
52.5
RPL06.WP3B.012360 RPL06.Conn EF2<>DHC.28 Pull Pigtails (384F) P2&3 (MES) EF2<>DHC.28 Not Started 03/04/27 03/05/27 2.5 2.5
0%
127.5
RPL06.WP3B.013780 RPL06.Conn EF2<>DHC.27 Install (A-End) Pigtails (384F) P2&3 (MES) EF2<>DHC.27 Not Started 03/04/27 03/04/27 1.2 1.2
0%
60.0
RPL06.WP3B.014500 RPL06.Conn EF1<>DHC.27 Splice (A-End) Pigtails (384F) P1&4 (LV) EF1<>DHC.27 Not Started 03/04/27 03/11/27 7.5 7.5
0%
61.2
RPL06.WP3B.015940 RPL06.Conn EF1<>DHC.27 Install (Z-End) Pigtails (384F) P1&4 (LV) EF1<>DHC.27 Not Started 03/04/27 03/04/27 1.2 1.2
0%
61.2
RPL06.WP4.037420 RPL06.Conn DHC.27 Pull Trunk (384F) [RSW<>FSW] Trunks Not Started 03/04/27 03/04/27 1.2 1.2
0%
72.5
RPL06.WP4.037440 RPL06.Conn DHC.28 Pull Trunk (384F) [RSW<>FSW] Trunks Not Started 03/04/27 03/04/27 1.2 1.2
0%
142.5
RPL06.WP4.037480 RPL06.Conn DHA.07.25<>25 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 03/04/27 03/04/27 1.2 1.2
0%
55.0
RPL06.WP4.037500 RPL06.Conn DHA.08.29<>29 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 03/04/27 03/04/27 1.2 1.2
0%
55.0
RPL06.WP4.037520 RPL06.Conn DHB.20.37<>37 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 03/04/27 03/04/27 1.2 1.2
0%
42.5
RPL06.WP4.037540 RPL06.Conn DHB.19.34<>33 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] In-Row Not Started 03/04/27 03/04/27 1.2 1.2
0%
42.5
RPL06.WP4.037760 RPL06.Conn DHA.07 Install (Z-End) Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 03/04/27 03/05/27 2.5 2.5
0%
50.0
RPL06.WP4.037780 RPL06.Conn DHA.08 Install (Z-End) Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 03/04/27 03/05/27 2.5 2.5
0%
50.0
RPL06.WP4.037800 RPL06.Conn DHB.19 Install (Z-End) Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 03/04/27 03/05/27 2.5 2.5
0%
-6.2
RPL06.WP4.037820 RPL06.Conn DHB.20 Install (Z-End) Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 03/04/27 03/05/27 2.5 2.5
0%
-10.0
GCD.RPL06.5405 L3/L4 Start - DHC Rows 25-32 DH Not Started 03/05/27 03/05/27 0.0 0.0
0%
136.2
RPL06.CX.DHC.01140 RPL06.CX.DHC - L3/L4 - Elec. Domain 07/08 DHC ELECTRICAL Not Started 03/05/27 03/10/27 5.0 5.0
0%
47.5
RPL06.INT.EC.9640 RPL06.Interior.EC LO #15 - Hang Drywall Remaining of LO #15 (Ancillary, Elec Room, Humidifier Room & IDF) Not Started 03/05/27 03/10/27 5.0 5.0
0%
63.8
RPL06.WP3B.013080 RPL06.Conn EF1<>DHC.28 Install (A-End) Pigtails (384F) P1&4 (LV) EF1<>DHC.28 Not Started 03/05/27 03/05/27 1.2 1.2
0%
128.8
RPL06.WP3B.015220 RPL06.Conn EF2<>DHC.27 Splice (A-End) Pigtails (384F) P2&3 (MES) EF2<>DHC.27 Not Started 03/05/27 03/12/27 7.5 7.5
0%
60.0
RPL06.WP3B.016660 RPL06.Conn EF2<>DHC.27 Install (Z-End) Pigtails (384F) P2&3 (MES) EF2<>DHC.27 Not Started 03/05/27 03/05/27 1.2 1.2
0%
60.0
RPL06.WP4.032780 RPL06.Conn DHC.26 Install (A-End) Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 03/05/27 03/08/27 2.5 2.5
0%
140.0
RPL06.WP4.033320 RPL06.Conn DHC.26 Install (A-End) Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 03/05/27 03/08/27 2.5 2.5
0%
142.5
RPL06.WP4.033360 RPL06.Conn DHD.36 Install (A-End) Ext. Trunk (384F) [SSW<>JXSW] SSW<>JXSW Not Started 03/05/27 03/08/27 2.5 2.5
0%
127.5
RPL06.WP4.033860 RPL06.Conn DHD.36 Install (A-End) Trunk (192F) [FSW<>SSW] FSW<>SSW Not Started 03/05/27 03/08/27 2.5 2.5
0%
130.0
RPL06.WP4.033960 RPL06.Conn DHC.26 Install (A-End) Trunk (384F) [RSW<>FSW] Trunks Not Started 03/05/27 03/10/27 5.0 5.0
0%
142.5
RPL06.WP4.034600 RPL06.Conn DHD.36 Install (A-End) Trunk (384F) [RSW<>FSW] Trunks Not Started 03/05/27 03/10/27 5.0 5.0
0%
130.0
RPL06.WP4.036380 RPL06.Conn DHC.26.21 Install (A-End) Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 03/05/27 03/08/27 2.5 2.5
0%
150.0
RPL06.WP4.037200 RPL06.Conn DHD.36.29 Install (A-End) Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 03/05/27 03/08/27 2.5 2.5
0%
137.5
RPL06.WP4.037880 RPL06.Conn DHA.07.27<>27 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 03/05/27 03/05/27 1.2 1.2
0%
55.0
RPL06.WP4.037900 RPL06.Conn DHA.08.31<>31 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 03/05/27 03/05/27 1.2 1.2
0%
55.0
RPL06.WP4.037920 RPL06.Conn DHB.20.39<>39 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] In-Row Not Started 03/05/27 03/05/27 1.2 1.2
0%
42.5
RPL06.WP4.037940 RPL06.Conn DHB.19.36<>35 Install (Z-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] In-Row Not Started 03/05/27 03/05/27 1.2 1.2
0%
42.5
RPL06.WP4.037960 RPL06.Conn DHC.21.03 Install (A-End) Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 03/05/27 03/08/27 2.5 2.5
0%
150.0
RPL06.WP4.037980 RPL06.Conn DHC.22.07 Install (A-End) Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 03/05/27 03/08/27 2.5 2.5
0%
150.0
RPL06.WP4.038140 RPL06.Conn DHC.21.04 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 03/05/27 03/18/27 12.5 12.5
0%
137.5
RPL06.WP4.038160 RPL06.Conn DHC.22.08 Pull Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 03/05/27 03/18/27 12.5 12.5
0%
137.5
RPL06.WP4.038220 RPL06.Conn DHD.29.04 Install (A-End) Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 03/05/27 03/08/27 2.5 2.5
0%
137.5
RPL06.WP4.038240 RPL06.Conn DHD.30.08 Install (A-End) Duplex Jumper (LC<>LC) [RSW<>FSW (AI Confirmed)] Jumpers (AI Confirmed) Not Started 03/05/27 03/08/27 2.5 2.5
0%
137.5
RPL06.WP4.039140 RPL06.Conn DHC.25.20<>19 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 03/05/27 03/05/27 1.2 1.2
0%
147.5
RPL06.WP4.039500 RPL06.Conn DHC.26.24<>23 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 03/05/27 03/05/27 1.2 1.2
0%
147.5
RPL06.WP4.039800 RPL06.Conn DHD.35.28<>27 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 03/05/27 03/05/27 1.2 1.2
0%
135.0
RPL06.WP4.039820 RPL06.Conn DHD.36.32<>31 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, Across-Row)] Across-Row Not Started 03/05/27 03/05/27 1.2 1.2
0%
135.0
GCD.RPL06.2002 L3 Finish - DHB DH Not Started 03/08/27 03/08/27 0.0 0.0
0%
25.0
GCD.RPL06.3905 L3/L4 Finish - DHB Rows 33-40 DH Not Started 03/08/27 03/08/27 0.0 0.0
0%
25.0
RPL06.EY.DHC.01450 RPL06.EY.DHC - Install Remaining Electrical Tie-ins Tie-ins Not Started 03/08/27 03/12/27 6.2 6.2
0%
116.2
RPL06.EY.DHC.01510 RPL06.EY.DHC - Install Floor Mounted Outdoor Split AC Units (Qty4) OFE Not Started 03/08/27 03/09/27 2.5 2.5
0%
113.8
RPL06.EY.DHD.01440 RPL06.EY.DHD - Install Remaining Mechanical/ refrigerant Tie-ins Tie-ins Not Started 03/08/27 03/12/27 6.2 6.2
0%
103.8
RPL06.EY.ENDC.01120 RPL06.EY.End - Install Perm Paving Hardscape and Landscape Not Started 03/08/27 03/12/27 6.2 6.2
0%
166.2
RPL06.EY.ENDC.01130 RPL06.EY.End - Install Electrical Tie-ins (include penetration detail) Tie-ins Not Started 03/08/27 04/05/27 25.0 25.0
0%
51.2
RPL06.EY.ENDC.01160 RPL06.EY.End - Install Hardscape and Landscape - WBS Summary Hardscape and Landscape Not Started 03/08/27 05/17/27 62.5 62.5
0%
166.2
RPL06.EY.ENDC.02120 RPL06.EY.End - Install Remaining Permanent Duct with insulation to AHU Units Temp Conditions Not Started 03/08/27 03/17/27 10.0 10.0
0%
66.2
RPL06.INT.EC.9280 RPL06.Interior.ECr LO #14 - Plumbing Trim Out Remaining of LO Wall #14 (Ancillary, Elec Room, Humidifier Room & IDF) Not Started 03/08/27 03/12/27 6.2 6.2
0%
71.2
RPL06.INT.EC.9300 RPL06.Interior.ECr LO #14 - Fire Life Safety Trim Out Remaining of LO Wall #14 (Ancillary, Elec Room, Humidifier Room & IDF) Not Started 03/08/27 03/12/27 6.2 6.2
0%
71.2
RPL06.INT.EC.9680 RPL06.Interior.EC LO #15 - Install Flooring Tiles/Resinous Flooring in specific rooms **?? Remaining of LO #15 (Ancillary, Elec Room, Humidifier Room & IDF) Not Started 03/08/27 03/10/27 3.8 3.8
0%
73.8
RPL06.INT.ENDC.6140 RPL06.Interior.EC Ext. Leave Out #18 - Drop Remaining Duct Exterior Leave Out Wall #18 EC - North for DHB&D HACs Not Started 03/08/27 03/09/27 2.5 2.5
0%
101.2
RPL06.WP3B.013800 RPL06.Conn EF2<>DHC.28 Install (A-End) Pigtails (384F) P2&3 (MES) EF2<>DHC.28 Not Started 03/08/27 03/08/27 1.2 1.2
0%
127.5
RPL06.WP3B.014520 RPL06.Conn EF1<>DHC.28 Splice (A-End) Pigtails (384F) P1&4 (LV) EF1<>DHC.28 Not Started 03/08/27 03/15/27 7.5 7.5
0%
128.8
RPL06.WP3B.015960 RPL06.Conn EF1<>DHC.28 Install (Z-End) Pigtails (384F) P1&4 (LV) EF1<>DHC.28 Not Started 03/08/27 03/08/27 1.2 1.2
0%
128.8
RPL06.WP4.038460 RPL06.Conn DHA.07 Install (Z-End) Trunk (384F) [RSW<>FSW] Trunks Not Started 03/08/27 03/11/27 5.0 5.0
0%
50.0
RPL06.WP4.038480 RPL06.Conn DHA.08 Install (Z-End) Trunk (384F) [RSW<>FSW] Trunks Not Started 03/08/27 03/11/27 5.0 5.0
0%
50.0
RPL06.WP4.038500 RPL06.Conn DHB.19 Install (Z-End) Trunk (384F) [RSW<>FSW] Trunks Not Started 03/08/27 03/11/27 5.0 5.0
0%
-6.2
RPL06.WP4.038520 RPL06.Conn DHB.20 Install (Z-End) Trunk (384F) [RSW<>FSW] Trunks Not Started 03/08/27 03/11/27 5.0 5.0
0%
-10.0
RPL06.WP4.039760 RPL06.Conn DHC.27.25<>25 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 03/08/27 03/08/27 1.2 1.2
0%
147.5
RPL06.WP4.039780 RPL06.Conn DHC.28.29<>29 Install (A-End) Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 03/08/27 03/08/27 1.2 1.2
0%
147.5
RPL06.WP4.040120 RPL06.Conn DHC.27.27<>27 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 03/08/27 03/10/27 3.8 3.8
0%
135.0
RPL06.WP4.040140 RPL06.Conn DHC.28.31<>31 Pull Simplex Jumper (SC<>LC) [PON (Active, In-Row)] Jumpers Not Started 03/08/27 03/10/27 3.8 3.8
0%
135.0
RPL06.WP4.047640 RPL06.Conn BE ISP DHA.CFD2 (RSL) FTSW > STSW EX384f [Across-Row] Across-Row Not Started 03/08/27 03/19/27 12.5 12.5
0%
3.8
RPL06.CX.DHB.01220 RPL06.CX.DHB - TAB Verification DHB DATA HALL LEVEL TESTING Not Started 03/09/27 03/15/27 6.2 6.2
0%
18.8
RPL06.CX.DHD.01090 RPL06.CX.DHD - L3/L4 - Control Fault Domain 01 Control Fault Domain 1 Not Started 03/09/27 03/31/27 20.0 20.0
0%
41.2
RPL06.INT.EC.LO.9560 RPL06.Interior.EC LO #15 - Electrical Trim Out Interior Leave Out Wall #15 DHC/EC for DHA&C HACs Not Started 03/09/27 03/09/27 1.2 1.2
0%
58.8
RPL06.INT.EC.LO.9580 RPL06.Interior.EC LO #15 - Security Trim Out Interior Leave Out Wall #15 DHC/EC for DHA&C HACs Not Started 03/09/27 03/09/27 1.2 1.2
0%
58.8
RPL06.INT.EC.LO.9780 RPL06.Interior.EC LO #15 - Install Remaining Refrigerant Line Interior Leave Out Wall #15 DHC/EC for DHA&C HACs Not Started 03/09/27 03/10/27 2.5 2.5
0%
66.2
RPL06.INT.ENDC.5100 RPL06.Interior.EC Ext. Leave Out #19 - Install Electrical Lowside OH Exterior Leave Out Wall #19 EC - South for DHA&C HACs Not Started 03/09/27 03/12/27 5.0 5.0
0%
42.5
RPL06.INT.ENDC.5120 RPL06.Interior.EC Ext. Leave Out #19 - Install Plumbing Lowside OH Exterior Leave Out Wall #19 EC - South for DHA&C HACs Not Started 03/09/27 03/12/27 5.0 5.0
0%
42.5
RPL06.INT.ENDC.5140 RPL06.Interior.EC Ext. Leave Out #19 - Install Fire Life Safety Lowside OH Exterior Leave Out Wall #19 EC - South for DHA&C HACs Not Started 03/09/27 03/12/27 5.0 5.0
0%
42.5
RPL06.INT.ENDC.5160 RPL06.Interior.EC Ext. Leave Out #19 - Install Security Lowside OH Exterior Leave Out Wall #19 EC - South for DHA&C HACs Not Started 03/09/27 03/12/27 5.0 5.0
0%
42.5
RPL06.INT.ENDC.5180 RPL06.Interior.EC Ext. Leave Out #19 - Install Controls / EPMS / BMS OH Exterior Leave Out Wall #19 EC - South for DHA&C HACs Not Started 03/09/27 03/15/27 6.2 6.2
0%
41.2
RPL06.INT.ENDC.5200 RPL06.Interior.EC Ext. Leave Out #19 - Fire Safing OH Exterior Leave Out Wall #19 EC - South for DHA&C HACs Not Started 03/09/27 03/10/27 2.5 2.5
0%
45.0
RPL06.INT.ENDC.5520 RPL06.Interior.EC Ext. Leave Out #19 - Install Remaining Refrigerant Line Exterior Leave Out Wall #19 EC - South for DHA&C HACs Not Started 03/09/27 03/11/27 3.8 3.8
0%
98.8
RPL06.PR.DHA.FE.0035 RPL06.PR.DHA FENW PZ2 (Row 09-24) - ENS Ready for PZ2 FENW Not Started 03/09/27 03/09/27 0.0 0.0
0%
60.0
RPL06.PR.DHA.FE.0040 RPL06.PR.DHA FENW PZ2 (Row 09-24) - Provisioning, Auditing, Issue Remediation (FSW, SSW) FENW Not Started 03/09/27 04/13/27 31.2 31.2
0%
165.0
RPL06.WP3B.015240 RPL06.Conn EF2<>DHC.28 Splice (A-End) Pigtails (384F) P2&3 (MES) EF2<>DHC.28 Not Started 03/09/27 03/16/27 7.5 7.5
0%
127.5
RPL06.WP3B.016680 RPL06.Conn EF2<>DHC.28 Install (Z-End) Pigtails (384F) P2&3 (MES) EF2<>DHC.28 Not Started 03/09/27 03/09/27 1.2 1.2
0%
127.5
RPL06.EY.DHC.01440 RPL06.EY.DHC - Install Remaining Mechanical/ refrigerant Tie-ins Tie-ins Not Started 03/10/27 03/16/27 6.2 6.2
0%
113.8
RPL06.EY.ENDC.01180 RPL06.EY.End - Install BMS/EPMS Tie-ins Tie-ins Not Started 03/10/27 03/31/27 18.8 18.8
0%
55.0
RPL06.INT.EC.9320 RPL06.Interior.ECr LO #14 - Install Door (Verify with Trades before installation) Remaining of LO Wall #14 (Ancillary, Elec Room, Humidifier Room & IDF) Not Started 03/10/27 03/16/27 6.2 6.2
0%
68.8
RPL06.INT.EC.LO.9680 RPL06.Interior.EC LO #15 - Install Asset Tags Interior Leave Out Wall #15 DHC/EC for DHA&C HACs Not Started 03/10/27 03/12/27 3.8 3.8
0%
1.2
RPL06.INT.ENDC.4020 RPL06.Interior.EC Ext. Leave Out #18 - Install Remaining Vertical Tube Steel Support for Cable Tray (IFP Add) Exterior Leave Out Wall #18 EC - North for DHB&D HACs Not Started 03/10/27 03/10/27 1.2 1.2
0%
110.0
RPL06.INT.ENDC.5800 RPL06.Interior.EC Ext. Leave Out #18 - Install Remaining Lights Exterior Leave Out Wall #18 EC - North for DHB&D HACs Not Started 03/10/27 03/23/27 12.5 12.5
0%
40.0
RPL06.INT.ENDC.5980 RPL06.Interior.EC Ext. Leave Out #18 - Mechanical L2 Checklist Completion Exterior Leave Out Wall #18 EC - North for DHB&D HACs Not Started 03/10/27 03/23/27 12.5 12.5
0%
101.2
RPL06.EY.ENDC.01140 RPL06.EY.End - Install Mechanical Main (include penetration detail) Tie-ins Not Started 03/11/27 04/01/27 18.8 18.8
0%
41.2
RPL06.INT.EC.9700 RPL06.Interior.EC LO #15 - Install Remaining Lights Remaining of LO #15 (Ancillary, Elec Room, Humidifier Room & IDF) Not Started 03/11/27 03/16/27 5.0 5.0
0%
66.2
RPL06.INT.EC.9720 RPL06.Interior.EC LO #15 - Tape Finish Paint Remaining of LO #15 (Ancillary, Elec Room, Humidifier Room & IDF) Not Started 03/11/27 03/17/27 6.2 6.2
0%
63.8
RPL06.INT.EC.LO.9620 RPL06.Interior.EC LO #15 - Plumbing Trim Out Interior Leave Out Wall #15 DHC/EC for DHA&C HACs Not Started 03/11/27 03/11/27 1.2 1.2
0%
58.8
RPL06.INT.EC.LO.9640 RPL06.Interior.EC LO #15 - Fire Life Safety Trim Out Interior Leave Out Wall #15 DHC/EC for DHA&C HACs Not Started 03/11/27 03/11/27 1.2 1.2
0%
58.8