Schedule Viewer
Last schedule upload: D3-R25005-00-RPL10 — 9281 activities — 06/03/2026 08:35 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260524.xer
· Uploaded Jun 03, 2026 01:35 PM
· 9281 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
91
Completed
9
In Progress
91
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.INT.SSB.01800 |
RPL10.Interior.SSB - BoW - Install VAV's/ Duct Branches | Balance of Walls and OverHead | Complete | 03/09/26 | 04/20/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02580 |
RPL10.Interior.SSB-Corridor - Priority - Install FA (Highside OH space) *No Scope | Priority Walls & OverHead | Complete | 03/09/26 | 03/09/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.03100 |
RPL10.Interior.SSB-Corridor - Priority - P2 Wall Tape Finish Paint | Priority Wall (P2) - Grid Line 10-38 | Complete | 03/09/26 | 03/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1320 |
RPL10.MCUP.Loop 2 - Set mCUPs #6 (1 per 5 days) | OFE | Complete | 03/09/26 | 03/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.NS43.01000 |
RPL10.SKIN.NS43 - Install Temp Doors | Glazing, Doors and Ext Devices | Complete | 03/09/26 | 03/10/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.NS43.01020 |
RPL10.SKIN.NS43 - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Active | 03/09/26 | 12/23/26 | 251.2 | 158.8 |
|
105.0 |
RPL10.SKN.S.01100 |
RPL10.SKIN.South - Secure All Exterior Mounted Boxes and Devices on Skin | South | Complete | 03/09/26 | 03/11/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.SKN.W.01040 |
RPL10.SKIN.West - Secure All Exterior Mounted Boxes and Devices on Skin | West | Complete | 03/09/26 | 03/11/26 | 6.2 | 0.0 |
|
0.0 |
ICM.B10.1855 |
[NWB] Delivery of MES - Multi Trade Rack (First Delivery) - RPL10 | Construction | Complete | 03/10/26 | 03/10/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.01090 |
RPL10.Interior.Center-Corridor - OFE - NS1 (1x Optical Splice) (03.04.26) (Rev-03.09.26) | OFE | Complete | 03/10/26 | 05/08/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07500 |
RPL10.Interior.Center-Corridor - Priority - Perimeter Wall Tape, Float and Paint (Outside) (EF1 & EF2) | EF Perimeter Walls | Complete | 03/10/26 | 03/13/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02320 |
RPL10.Interior.NS4 - Priority - Install Drywall at Exterior Wall | OverHead | Complete | 03/10/26 | 03/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01220 |
RPL10.Interior.SSB - BoW - Install Security Lowside OH and In-wall | Balance of Walls and OverHead | Complete | 03/10/26 | 03/25/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01240 |
RPL10.Interior.SSB - BoW - Install Plumbing Lowside OH and In-wall | Balance of Walls and OverHead | Complete | 03/10/26 | 03/30/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.SSB.03480 |
RPL10.Interior.SSB - Priority - P0 & P1 Wall Tape Float Paint (East Sides) | Priority Wall (P0&P1) - Grid Line 10-41/40 | Complete | 03/10/26 | 04/10/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04240 |
RPL10.Interior.SSB - Priority - P5 Tape Float Paint One Side Remaining Wall (South) | Priority Wall (P5) - Grid Line 10-C | Complete | 03/10/26 | 03/13/26 | 8.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.04280 |
RPL10.Interior.SSB - Priority - P5 Tape Float Paint Two Side Remaining Wall (South) | Priority Wall (P5) - Grid Line 10-C | Complete | 03/10/26 | 03/13/26 | 8.0 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.04100 |
RPL10.Interior.SSB-Corridor - Priority - Tape Finish Paint Exterior Wall (Remaining Work) | Priority Walls & OverHead | Complete | 03/10/26 | 03/13/26 | 6.2 | 0.0 |
|
0.0 |
GCD.RPL10.1655 |
Start MES Installation - RPL10 | Construction Milestones | Complete | 03/11/26 | 03/11/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01280 |
RPL10.EY.EF2 - Install Electrical Tie-ins (include penetration detail) | Tie-ins | Complete | 03/11/26 | 04/06/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01290 |
RPL10.EY.EF2 - Tie-ins - WBS Summary | Tie-ins | Active | 03/11/26 | 06/26/26 | 95.0 | 30.0 |
|
155.0 |
RPL10.INT.CTRC.01830 |
RPL10.Interior.Center-Corridor - Priority - Install FA/ Linear Heat Detection (Highside OH space) | Priority Walls & OverHead | Complete | 03/11/26 | 03/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07160 |
RPL10.Interior.Center-Corridor - Priority - Install Partial IMP Panel Wall ~50ft (EF1) | EF Perimeter Walls | Complete | 03/11/26 | 03/16/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07620 |
RPL10.Interior.Center-Corridor - Priority - MEP In-Wall Rough Ins/Backing (EF2 UPS Gallery, Lighting Inverter Room) | Priority Wall (P4) - Grid Line 10-D | Complete | 03/11/26 | 03/20/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6220 |
RPL10.Interior.End-Corridor - Priority - P7 Wall MEP In-Wall Rough Ins | Priority Wall (P7) - Grid Line 10-02 | Complete | 03/11/26 | 03/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.6380 |
RPL10.Interior.End-Corridor - Priority - P7 Wall Backing | Priority Wall (P7) - Grid Line 10-02 | Complete | 03/11/26 | 04/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01150 |
RPL10.Interior.NS1 - OFE - MES Skids - Set / Place / Anchor **03/12 | OFE | Complete | 03/11/26 | 04/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.INT.NS3.02320 |
RPL10.Interior.NS3 - Priority - Install Drywall at Exterior Wall | OverHead | Complete | 03/11/26 | 03/17/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.01251 |
RPL10.Interior.SSB-Corridor - Install Electrical - SSB Electrical Room (10.S2.06) | Balance of Walls & OverHead | Complete | 03/11/26 | 03/19/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02240 |
RPL10.Interior.SSB-Corridor - BoW - Install Electrical GS MDF Electrical (10.N1.08) | Balance of Walls & OverHead | Complete | 03/11/26 | 03/31/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02620 |
RPL10.Interior.SSB-Corridor - BoW - Install Mechanical Piping Lowside OH and In-Wall | Balance of Walls & OverHead | Complete | 03/11/26 | 03/20/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.INT.SSBC.02680 |
RPL10.Interior.SSB-Corridor - BoW - Install VAV's | Balance of Walls & OverHead | Complete | 03/11/26 | 03/30/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.MCUP.LP2.1360 |
RPL10.MCUP.Loop 2 - Set mCUPs #8 (1 per 5 days) | OFE | Complete | 03/11/26 | 03/13/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.SKN.SSB.01140 |
RPL10.SKIN.SSB - Install Roof System - Install EJ Grid lines 10-31/30 | Expansion Joint | Complete | 03/11/26 | 03/13/26 | 5.0 | 0.0 |
|
0.0 |
FR01.1020 |
FR01: PSI HAC Delays - NS1 - LV Side Aisle - First Delivery (Benchmark) ((1)) | FR01: NS1 LV Side Aisle HAC Delays | Complete | 03/12/26 | 03/12/26 | 1.2 | 0.0 |
|
0.0 |
FR01.1040 |
FR01: PSI HAC Delays - NS1 - LV Side Aisle - Second Delivery (2,3) | FR01: NS1 LV Side Aisle HAC Delays | Complete | 03/12/26 | 03/12/26 | 1.2 | 0.0 |
|
0.0 |
FR02.1120 |
FR02: PSI HAC Delays - NS2 - LV Side Aisle - First Delivery (Row 1) | FR02: NS2 LV Side Aisle HAC Delays | Complete | 03/12/26 | 04/07/26 | 2.5 | 0.0 |
|
0.0 |
FR02.1140 |
FR02: PSI HAC Delays - NS2 - LV Side Aisle - Second Delivery (Row 2) | FR02: NS2 LV Side Aisle HAC Delays | Complete | 03/12/26 | 04/07/26 | 1.2 | 0.0 |
|
0.0 |
FR02.1160 |
FR02: PSI HAC Delays - NS2 - LV Side Aisle - Third Delivery (Row 3,4,5) | FR02: NS2 LV Side Aisle HAC Delays | Complete | 03/12/26 | 04/09/26 | 1.2 | 0.0 |
|
0.0 |
FR02.1180 |
FR02: PSI HAC Delays - NS2 - LV Side Aisle - Fourth Delivery (Row 6,7,8) | FR02: NS2 LV Side Aisle HAC Delays | Complete | 03/12/26 | 04/10/26 | 2.5 | 0.0 |
|
0.0 |
FR02.1200 |
FR02: PSI HAC Delays - NS2 - LV Side Aisle - Fourth Delivery (Row 9) | FR02: NS2 LV Side Aisle HAC Delays | Complete | 03/12/26 | 04/10/26 | 2.5 | 0.0 |
|
0.0 |
NW.2140 |
031226 - Non Weather Impact #3 - Power Outage Due to Severe Weather 031226 | Project Impacts | Complete | 03/12/26 | 03/12/26 | 1.2 | 0.0 |
|
0.0 |
RPL10.INT.NS4.01050 |
RPL10.Interior.NS4 - Priority - Install FA / Linear heat detection | OverHead | Complete | 03/12/26 | 03/18/26 | 2.5 | 0.0 |
|
0.0 |
RPL.10.D.X1410.XR |
Ready for Fiber Support Platform Construction - AI 1 (TCCO est Release 09-Feb-26) | Connectivity (XREFs) | Complete | 03/13/26 | 03/13/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01130 |
RPL10.EY.EF1 - Install UPS-CU (2) | OFE | Complete | 03/13/26 | 03/13/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.ENDC.01080 |
RPL10.EY.End - Cure (High Early Mix) | Foundations | Complete | 03/13/26 | 03/19/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.EY.NS1.01200 |
RPL10.EY.NS1 - Tent Temp Conditioning Startup and Available (Including Acclimation) (02/23/26) | Tent and Temp Conditions | Complete | 03/13/26 | 03/20/26 | 7.5 | 0.0 |
|
0.0 |
RPL10.EY.NS3.01080 |
RPL10.EY.NS3 - Tent SOG Cure | Tent and Temp Conditions | Complete | 03/13/26 | 03/20/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01070 |
RPL10.Interior.NS2 - OFE - MES Skids - Set / Place / Anchor | OFE | Complete | 03/13/26 | 04/06/26 | 25.0 | 0.0 |
|
0.0 |
RPL10.SKN.EF12.01120 |
RPL10.SKIN.EF12 - Install Roof System - Final Roof (Grid 10-20 / 10-10) | Roofing | Complete | 03/13/26 | 03/27/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.STR.EF12.01180 |
RPL10.Structure.EF12 - Install SOG Joint Sealant & Floor Sealer | F/R/P | Complete | 03/13/26 | 03/19/26 | 6.2 | 0.0 |
|
0.0 |
RPL.CM.D.C5520.XR |
Burn Road East | Logistics - Onsite Receive XREF Milestones | Complete | 03/16/26 | 03/16/26 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5540.XR |
Chewy Court ( Around RPL10 & Admin) | Logistics - Onsite Receive XREF Milestones | Complete | 03/16/26 | 03/16/26 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5840.XR |
R2 Road | Logistics - Onsite Receive XREF Milestones | Complete | 03/16/26 | 03/16/26 | 0.0 | 0.0 |
|
0.0 |
RPL.CM.D.C5860.XR |
D2 Pass | Logistics - Onsite Receive XREF Milestones | Complete | 03/16/26 | 03/16/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01050 |
RPL10.EY.EF1 - Install Fiber Support Platform (FSP) - WBS Summary | Fiber Support Platform | Active | 03/16/26 | 07/24/26 | 115.0 | 53.8 |
|
227.5 |
RPL10.EY.EF1.01580 |
RPL10.EY.EF1 - Install RPL FSP Trade Partner Mobilization | Fiber Support Platform | Complete | 03/16/26 | 03/16/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.EY.EF1.01600 |
RPL10.EY.EF1 - Install RPL FSP Trade Partner Mobilization & Setup | Fiber Support Platform | Complete | 03/16/26 | 03/18/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.EF2.01610 |
RPL10.EY.EF2 - Install Remaining UPS-CU (2) | OFE | Complete | 03/16/26 | 03/16/26 | 3.8 | 0.0 |
|
0.0 |
RPL10.EY.SSB.01540 |
RPL10.EY.SSB - Install AHU Duct Stands & Ducts | OFE | Complete | 03/16/26 | 03/26/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07560 |
RPL10.Interior.Center-Corridor - Priority - P3 Wall Frame Wall (Post Optical Splice) | Priority Wall (P3) - Grid Line 10-25 | Complete | 03/16/26 | 03/18/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.EF1.01000 |
RPL10.Interior.EF1 - Priority OH - Install Duct (Highside OH space) | OverHead | Complete | 03/16/26 | 03/16/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.INT.EF1.01120 |
RPL10.Interior.EF1 - Priority OH - Fire Life Safety (Sprinkler Drops) | OverHead | Complete | 03/16/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01000 |
RPL10.Interior.EF2 - Priority OH - Install Duct (Highside OH space) | OverHead | Complete | 03/16/26 | 03/16/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.INT.EF2.01120 |
RPL10.Interior.EF2 - Priority OH - Fire Life Safety (Sprinkler Drops) | OverHead | Complete | 03/16/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01130 |
RPL10.Interior.NS1 - Priority - Install Controls / EPMS / BMS | OverHead | Complete | 03/16/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01180 |
RPL10.Interior.NS1 - LV Skids and TopHat Tie-ins (LOE) | NS1 - LV Skids and TopHat | Complete | 03/16/26 | 03/27/26 | 32.5 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01181 |
RPL10.Interior.NS1 - LV Skids and TopHat - Set & Anchor Interconnects | NS1 - LV Skids and TopHat | Complete | 03/16/26 | 03/25/26 | 22.5 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01182 |
RPL10.Interior.NS1 - LV Skids and TopHat - Maintenance and Reserve Busways | NS1 - LV Skids and TopHat | Complete | 03/16/26 | 03/25/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.NS1.01190 |
RPL10.Interior.NS1 - Tie-ins - WBS Summary | Tie-Ins | Active | 03/16/26 | 07/15/26 | 108.8 | 45.0 |
|
158.8 |
RPL10.INT.NS1.01200 |
RPL10.Interior.NS1 - MES Skids Tie-ins (LOE) | NS1 - MES Skids | Active | 03/16/26 | 07/10/26 | 97.5 | 41.2 |
|
133.8 |
RPL10.INT.NS1.01201 |
RPL10.Interior.NS1 - MES Skids - Set & Anchor Interconnects | NS1 - MES Skids | Complete | 03/16/26 | 04/07/26 | 30.0 | 0.0 |
|
0.0 |
RPL10.INT.NS2.02380 |
RPL10.Interior.NS2 - Priority - Install Controls / EPMS / BMS | OverHead | Complete | 03/16/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS3.01010 |
RPL10.Interior.NS3 - Priority - Install Duct | OverHead | Complete | 03/16/26 | 04/16/26 | 18.8 | 0.0 |
|
0.0 |
RPL10.INT.NS3.01050 |
RPL10.Interior.NS3 - Priority - Install FA / Linear heat detection | OverHead | Complete | 03/16/26 | 03/20/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.NS3.02380 |
RPL10.Interior.NS3 - Priority - Install Controls / EPMS / BMS | OverHead | Complete | 03/16/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS3.02400 |
RPL10.Interior.NS3 - Priority - Install Fire Life Safety (Sprinkler Drops) | OverHead | Complete | 03/16/26 | 04/06/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02380 |
RPL10.Interior.NS4 - Priority - Install Controls / EPMS / BMS | OverHead | Complete | 03/16/26 | 03/16/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.NS4.02400 |
RPL10.Interior.NS4 - Priority - Install Fire Life Safety (Sprinkler Drops) | OverHead | Complete | 03/16/26 | 03/30/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.01100 |
RPL10.Interior.SSB - BoW - Install Controls / EPMS / BMS and In-wall | Balance of Walls and OverHead | Complete | 03/16/26 | 03/19/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.SSB.03360 |
RPL10.Interior.SSB - BoW - Install Backings | Balance of Walls and OverHead | Complete | 03/16/26 | 03/20/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.SSB.07000 |
RPL10.Interior.SSB - Priority - P5 MEP In-Wall Remaining Wall (North) | Priority Wall (P5) - Grid Line 10-C | Complete | 03/16/26 | 03/19/26 | 4.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1540 |
RPL10.MCUP.Loop 1 - Tie-in BMS (LOE) | Tie-Ins BMS | Complete | 03/16/26 | 05/22/26 | 50.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1560 |
RPL10.MCUP.Loop 1 - Tie-in BMS #1 | Tie-Ins BMS | Complete | 03/16/26 | 05/22/26 | 10.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1580 |
RPL10.MCUP.Loop 1 - Tie-in EPMS (LOE) | Tie-Ins EPMS | Complete | 03/16/26 | 05/22/26 | 50.0 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1600 |
RPL10.MCUP.Loop 1 - Tie-in EPMS #1 | Tie-Ins EPMS | Complete | 03/16/26 | 05/22/26 | 8.8 | 0.0 |
|
0.0 |
RPL10.MCUP.LP1.1660 |
RPL10.MCUP.Loop 1 - Tie-in SD, DW **Confirm Scope | Tie-Ins Mechanical | Complete | 03/16/26 | 03/17/26 | 15.0 | 0.0 |
|
0.0 |
RPL10.SKN.EF12.01000 |
RPL10.SKIN.EF12 - Install Temp Doors | Glazing, Doors and Ext Devices | Complete | 03/16/26 | 03/17/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.SKN.EF12.01020 |
RPL10.SKIN.EF12 - Install Windows, Doors, Louvers and Ext Devices - WBS Summary | Glazing, Doors and Ext Devices | Active | 03/16/26 | 07/10/26 | 102.5 | 22.5 |
|
247.5 |
RPL10.INT.CTRC.01140 |
RPL10.Interior.Center-Corridor - OFE - NS2 (1x Optical Splice) (03.10.26) (Rev-03.16.26) | OFE | Complete | 03/17/26 | 05/08/26 | 12.5 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07000 |
RPL10.Interior.Center-Corridor - Priority - P6 Wall Hang Drywall (East Side) | Priority Wall (P6) - Grid Line 10-16 | Complete | 03/17/26 | 03/20/26 | 5.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.07640 |
RPL10.Interior.Center-Corridor - Priority - Install Partial IMP Panel Wall ~50ft (EF2) | EF Perimeter Walls | Complete | 03/17/26 | 03/18/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.ENDC.01030 |
RPL10.Interior.End-Corridor - Priority - Install Fire Sprinkler (Highside OH Space) | Priority Walls & OverHead | Complete | 03/17/26 | 03/23/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.INT.NS2.01060 |
RPL10.Interior.NS2 - OFE - LV Skids and TopHat - Set / Place / Anchor (03.18.26) | OFE | Complete | 03/17/26 | 03/30/26 | 25.0 | 0.0 |
|
0.0 |
GCD.RPL10.1020 |
Weather tight SSB and NS12 | Construction Milestones | Complete | 03/18/26 | 03/18/26 | 0.0 | 0.0 |
|
0.0 |
RPL10.INT.CTRC.06980 |
RPL10.Interior.Center-Corridor - Priority - QC - P6 Wall - Backing/Wall | Priority Wall (P6) - Grid Line 10-16 | Complete | 03/18/26 | 03/19/26 | 2.5 | 0.0 |
|
0.0 |
RPL10.INT.SSB.06720 |
RPL10.Interior.SSB - BoW - Install Remaining Unistruts & Hangers | Balance of Walls and OverHead | Complete | 03/18/26 | 03/30/26 | 6.2 | 0.0 |
|
0.0 |
RPL10.CFCI.7060 |
RPL10 - Fabricate / Deliver - Scuppers & Downspouts | Fixed Louvers | Active | 03/19/26 | 06/08/26 | 6.2 | 12.5 |
|
145.0 |
RPL10.CFCI.7100 |
RPL10 - Fabricate / Deliver - Metal Canopy | Fixed Louvers | Active | 03/19/26 | 06/01/26 | 6.2 | 6.2 |
|
161.2 |
RPL10.CFCI.7160 |
RPL10 - Fabricate / Deliver - Awning over Doors | Fixed Louvers | Active | 03/19/26 | 06/01/26 | 6.2 | 6.2 |
|
137.5 |