Schedule Viewer

Last schedule upload: D3-R25005-00-RPL10 — 9281 activities — 06/03/2026 08:35 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260524.xer · Uploaded Jun 03, 2026 01:35 PM · 9281 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
78
Completed
22
In Progress
79
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.SKN.SSB.01370 RPL10.SKIN.BLDG - RFI1103 Parapet Coping PVC Termication Incompatible material Skin Complete 03/31/26 05/04/26 5.0 0.0
100%
0.0
RPL.CM.D.N5690.XR Bridge at LA 583 ( META GIVE MILESTONE) Logistics - Off-Site Receive XREF Milsetones Complete 04/01/26 04/01/26 0.0 0.0
100%
0.0
RPL10.CFCI.4830 RPL10 - Prep / Submit for Review - Carpet (CFCI) Div. 09 - Carpet Complete 04/01/26 04/08/26 25.0 0.0
100%
0.0
RPL10.CFCI.4880 RPL10 - Submittal Rvw/App'l - Epoxy Flooring (Spec 09 67 23) (CFCI) Div. 09 - Epoxy Flooring Complete 04/01/26 04/06/26 25.0 0.0
100%
0.0
RPL10.EY.EF2.01100 RPL10.EY.EF2 - Install FSP - WBS Summary Fiber Support Platform Active 04/01/26 12/24/26 231.2 185.0
0%
108.8
RPL10.EY.EF2.01790 RPL10.EY.EF2 - Trade Partner Mobilization from North to South Fiber Support Platform Complete 04/01/26 04/03/26 6.2 0.0
100%
0.0
RPL10.EY.NS2.01200 RPL10.EY.NS2 - Tent Temp Conditioning Startup and Available (Including Acclimation) (03/13/26) Tent and Temp Conditions Complete 04/01/26 04/03/26 7.5 0.0
100%
0.0
RPL10.INT.CTRC.07660 RPL10.Interior.Center-Corridor - BoW - Install EZ Path Balance of Walls & OverHead Complete 04/01/26 04/10/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.6090 RPL10.Interior.End-Corridor - Priority - Install FA (Highside OH space) Priority Walls & OverHead Complete 04/01/26 04/06/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.02420 RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (HAC) OFE NS1 Control Fault Domain 6 Complete 04/01/26 04/20/26 25.0 0.0
100%
0.0
RPL10.INT.NS2.01110 RPL10.Interior.NS2 - MES Skids Tie-ins (LOE) NS2 - MES Skids Active 04/01/26 07/07/26 75.0 37.5
0%
148.8
RPL10.INT.NS2.01111 RPL10.Interior.NS2 - MES Skids - Set & Anchor Interconnects NS2 - MES Skids Complete 04/01/26 04/07/26 30.0 0.0
100%
0.0
RPL10.INT.NS3.01080 RPL10.Interior.NS3 - OFE - WBS Summary OFE Active 04/01/26 11/02/26 187.5 141.2
0%
55.0
RPL10.INT.NS3.02480 RPL10.Interior.NS3 - OFE - MES Skids - Pre Set 30"" Piping OFE Complete 04/01/26 04/17/26 12.5 0.0
100%
0.0
RPL10.INT.NS4.01080 RPL10.Interior.NS4 - OFE - WBS Summary OFE Active 04/01/26 10/06/26 163.8 117.5
0%
113.8
RPL10.INT.NS4.02425 RPL10.Interior.NS4 - OFE - MES Skids - Pre Set 30"" Piping OFE Complete 04/01/26 04/17/26 12.5 0.0
100%
0.0
RPL10.INT.EF1.01090 RPL10.Interior.EF1 - Priority OH - Security OverHead Complete 04/02/26 05/04/26 2.5 0.0
100%
0.0
RPL10.INT.EF1.01160 RPL10.Interior.EF1 - CFCI - WBS Summary OFE Active 04/02/26 06/05/26 48.8 11.2
0%
100.0
RPL10.INT.EF1.01190 RPL10.Interior.EF1 - CFCI - Install CFCI Prefab Cable Rack - EF1 East OFE Complete 04/02/26 05/15/26 12.5 0.0
100%
0.0
RPL10.INT.NS1.01720 RPL10.Interior.NS1 - OFE - Control Fault Domain 2 SQ5.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS1 Control Fault Domain 2 Active 04/02/26 06/11/26 61.2 16.2
0%
38.8
RPL10.INT.NS1.02640 RPL10.Interior.NS1 - OFE - Control Fault Domain 2 SQ5.1 (LV Side Aisle) OFE NS1 Control Fault Domain 2 Complete 04/02/26 04/06/26 5.0 0.0
100%
0.0
RPL10.CBL.1160 RPL10.Conn BLDG - Install GS and Production Cabling - WBS Summary Connectivity Active 04/06/26 02/23/29 901.2 857.5
0%
0.0
RPL10.EY.NS1.01250 RPL10.EY.NS1 - Install Electrical Tie-ins (include penetration detail) Tie-ins Complete 04/06/26 05/13/26 12.5 0.0
100%
0.0
RPL10.EY.NS1.01260 RPL10.EY.NS1 - Tie-ins - WBS Summary Tie-ins Active 04/06/26 06/02/26 50.0 7.5
0%
26.2
RPL10.INT.CTRC.01120 RPL10.Interior.Center-Corridor - BoW - Install Fire Alarm Lowside OH and In-wall Balance of Walls & OverHead Complete 04/06/26 05/04/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.01240 RPL10.Interior.Center-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls & OverHead Complete 04/06/26 05/04/26 8.8 0.0
100%
0.0
RPL10.INT.CTRC.02480 RPL10.Interior.Center-Corridor - Priority - Hang Drywall (EF2 UPS Gallery, Lighting Inverter Room) Priority Wall (P4) - Grid Line 10-D Complete 04/06/26 04/09/26 5.0 0.0
100%
0.0
RPL10.INT.CTRC.06960 RPL10.Interior.Center-Corridor - Priority - P6 Wall Hang Drywall (West Side) Priority Wall (P6) - Grid Line 10-16 Complete 04/06/26 04/09/26 5.0 0.0
100%
0.0
RPL10.INT.EF2.01100 RPL10.Interior.EF2 - Priority OH - Electrical OverHead Complete 04/06/26 04/10/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.6240 RPL10.Interior.End-Corridor - Priority - QC Exterior Wall - Backing/In-Wall Priority Walls & OverHead Complete 04/06/26 04/07/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01350 RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install Duct (LV SIde) LV Side Tie-ins Complete 04/06/26 04/06/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01380 RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 5 SQ2.1 - WBS Summary Tie-Ins NS1 Control Fault Domain 5 Active 04/06/26 07/07/26 81.2 37.5
0%
31.2
RPL10.INT.NS1.02440 RPL10.Interior.NS1 - OFE - Control Fault Domain 6 SQ1.1 - (Mech Side Aisle) OFE NS1 Control Fault Domain 6 Complete 04/06/26 04/20/26 22.5 0.0
100%
0.0
RPL10.INT.NS2.01093 RPL10.Interior.NS2 - LV Skids and TopHat - Top Hat Busway NS2 - LV Skids and TopHat Complete 04/06/26 04/24/26 18.8 0.0
100%
0.0
RPL10.INT.SSB.01320 RPL10.Interior.SSB - BoW - Hang Drywall (Remaining) Balance of Walls and OverHead Complete 04/06/26 04/16/26 3.8 0.0
100%
0.0
RPL10.INT.SSB.07040 RPL10.Interior.SSB - Priority - P5 Tape Float Paint Two Side Remaining Wall (North) Priority Wall (P5) - Grid Line 10-C Complete 04/06/26 04/14/26 8.0 0.0
100%
0.0
RPL10.INT.SSBC.02380 RPL10.Interior.SSB-Corridor - BoW - Install Electrical Tie-Ins Balance of Walls & OverHead Complete 04/06/26 04/20/26 8.8 0.0
100%
0.0
RPL10.INT.SSBC.02940 RPL10.Interior.SSB-Corridor - BoW - F/R/P Pads / Curbs Balance of Walls & OverHead Complete 04/06/26 04/07/26 3.8 0.0
100%
0.0
RPL10.SKN.SSB.01050 RPL10.SKIN.SSB - Install Lighting Glazing, Doors and Ext Devices Complete 04/06/26 04/17/26 5.0 0.0
100%
0.0
RPL10.WP2.01080 RPL10.Conn Int IDF Huts - Install GS Cabling Pull/Term/Test (13x GS.IDF) ~5275 LF - WBS Summary Interior Active 04/06/26 12/16/26 221.2 177.5
0%
680.0
RPL10.WP2.EF1.1000 RPL10.Conn GS.EF1 Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Complete 04/06/26 04/08/26 3.8 0.0
100%
0.0
RPL10.WP2.EF2.1000 RPL10.Conn GS.EF2 Set Infrastructure (Wall mounting enclousres, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Complete 04/06/26 04/08/26 3.8 0.0
100%
0.0
RPL10.CFCI.5140 RPL10- Fabricate / Deliver - Epoxy Flooring / Resinous (Spec 09 67 23) (CFCI) Div. 09 - Epoxy Flooring Complete 04/07/26 04/30/26 25.0 0.0
100%
0.0
RPL10.CFCI.7140 RPL10- Fabricate / Deliver - Cabinets / Casework (CFCI) Div. 09 - Epoxy Flooring Active 04/07/26 09/24/26 25.0 107.5
0%
50.0
RPL10.EY.EF2.01090 RPL10.EY.EF2 - Install RPL-3 FSP Deep Foundation ((TCCO est Release 27-Jul-26)) Fiber Support Platform - RPL-3 Complete 04/07/26 04/16/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.6140 RPL10.Interior.End-Corridor - Priority - Install Drywall at IMP Exterior Wall Priority Walls & OverHead Complete 04/07/26 04/09/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01880 RPL10.Interior.NS1 - OFE - Control Fault Domain 1 SQ6.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS1 Control Fault Domain 1 Active 04/07/26 06/24/26 70.0 20.0
0%
31.2
RPL10.INT.NS1.02700 RPL10.Interior.NS1 - OFE - Control Fault Domain 1 SQ6.1 (LV Side Aisle) OFE NS1 Control Fault Domain 1 Complete 04/07/26 04/08/26 2.5 0.0
100%
0.0
RPL10.INT.NS2.01120 RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS2 Control Fault Domain 6 Complete 04/07/26 05/08/26 36.2 0.0
100%
0.0
RPL10.INT.NS2.02445 RPL10.Interior.NS2 - OFE - Control Fault Domain 6 SQ1.2 - (LV Side Aisle) OFE NS2 Control Fault Domain 6 Complete 04/07/26 04/10/26 6.2 0.0
100%
0.0
RPL10.INT.NS3.02000 RPL10.Interior.NS3 - Priority - Install Draft Curtains (#4 - 6 Days Each * 2 crew) OverHead Complete 04/07/26 04/17/26 15.0 0.0
100%
0.0
RPL10.INT.NS4.02000 RPL10.Interior.NS4 - Priority - Install Draft Curtains (#4 - 6 Days Each* 2 crew) OverHead Complete 04/07/26 04/17/26 15.0 0.0
100%
0.0
RPL10.EY.EF1.01090 RPL10.EY.EF1 - Install RPL-1 FSP Columns F/R/P Fiber Support Platform - RPL-1 Complete 04/08/26 04/15/26 6.2 0.0
100%
0.0
RPL10.EY.EF2.01170 RPL10.EY.EF2 - Install RPL-5 FSP Deep Foundation (TCCO est Release 21-Oct-26) Fiber Support Platform - RPL-5 Complete 04/08/26 04/17/26 6.2 0.0
100%
0.0
RPL10.EY.ENDC.01110 RPL10.EY.End - Install AHU (4) - CFCI OFE Complete 04/08/26 04/10/26 8.8 0.0
100%
0.0
RPL10.EY.NS1.01240 RPL10.EY.NS1 - Install GS.IDF Hut (1x GS.IDF) NX01 (04.08.26) OFE Complete 04/08/26 04/15/26 6.2 0.0
100%
0.0
RPL10.EY.NS1.01270 RPL10.EY.NS1 - Install GS.IDF Hut (1x GS.IDF) NX02 (04.08.26) OFE Complete 04/08/26 04/15/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.01120 RPL10.Interior.SSB - BoW - Tape Finish Paint (Finish Out) Balance of Walls and OverHead Complete 04/08/26 04/17/26 8.8 0.0
100%
0.0
RPL10.CFCI.5110 RPL10 - Submittal Rvw/App'l - Carpet (CFCI) Div. 09 - Carpet Active 04/09/26 05/26/26 25.0 1.2
0%
157.5
RPL10.CFCI.7120 RPL10 - Fabricate / Deliver - Coping Fixed Louvers Active 04/09/26 06/08/26 6.2 12.5
100%
301.2
RPL10.INT.EF1.01210 RPL10.Interior.EF1 - Tie-ins - WBS Summary Tie-Ins Active 04/09/26 07/27/26 86.2 55.0
0%
157.5
RPL10.INT.EF1.01380 RPL10.Interior.EF1 - EF1 East - Install Upper Trays East EF-1 Complete 04/09/26 05/18/26 6.2 0.0
100%
0.0
RPL10.INT.EF1.01400 RPL10.Interior.EF1 - Tie-ins - EF1 East - WBS Summary East EF-1 Active 04/09/26 06/23/26 32.5 26.2
0%
180.0
RPL10.INT.EF2.01160 RPL10.Interior.EF2 - CFCI - WBS Summary OFE Active 04/09/26 06/16/26 75.0 20.0
0%
108.8
RPL10.INT.EF2.01190 RPL10.Interior.EF2 - CFCI - Install CFCI Prefab Cable Rack - EF2 East OFE Active 04/09/26 05/29/26 25.0 5.0
0%
20.0
RPL10.INT.ENDC.01060 RPL10.Interior.End-Corridor - Balance of Walls & Overhead (Restroom, Janitor, Fire Riser, Humidifier) - WBS Summary Balance of Walls & Overhead Active 04/09/26 08/21/26 118.8 78.8
0%
226.2
RPL10.INT.ENDC.6420 RPL10.Interior.End-Corridor - BoW - BoW Frame Priority Soffit and Hang Drywall Balance of Walls & Overhead Complete 04/09/26 04/14/26 5.0 0.0
100%
0.0
RPL10.MCUP.LP1.1860 RPL10.MCUP.Loop 1 - Tie-in Electrical #5 Tie-Ins Electrical Complete 04/09/26 05/22/26 8.8 0.0
100%
0.0
RPL10.MCUP.LP1.1960 RPL10.MCUP.Loop 1 - Tie-in Electrical #7 Tie-Ins Electrical Complete 04/09/26 05/22/26 11.2 0.0
100%
0.0
RPL.10.D.X3720.XG RMUs/MV Skids Set (Loop 1) - RPL10 NS2 Give Milestones (XREFs) Complete 04/10/26 04/10/26 0.0 0.0
100%
0.0
RPL.10.D.X3725.XG RMUs/MV Skids Set (Loop 2) - RPL10 NS2 Give Milestones (XREFs) Complete 04/10/26 04/10/26 0.0 0.0
100%
0.0
RPL10.INT.CTRC.02500 RPL10.Interior.Center-Corridor - Priority - Tape, Float and Paint (EF2 UPS Gallery, Lighting Inverter Room) Priority Wall (P4) - Grid Line 10-D Complete 04/10/26 04/17/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07020 RPL10.Interior.Center-Corridor - Priority - P6 Wall Tape, Float and Paint (West Side) Priority Wall (P6) - Grid Line 10-16 Complete 04/10/26 04/20/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.07060 RPL10.Interior.Center-Corridor - BoW - Install Mechanical Piping Lowside OH and On-Wall Balance of Walls & OverHead Complete 04/10/26 04/27/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.01050 RPL10.Interior.End-Corridor - BoW - Frame Balance of Wall Balance of Walls & Overhead Complete 04/10/26 04/13/26 5.0 0.0
100%
0.0
RPL10.INT.ENDC.6360 RPL10.Interior.End-Corridor - Priority - Tape Finish Paint Exterior Wall Priority Walls & OverHead Complete 04/10/26 04/15/26 10.0 0.0
100%
0.0
RPL10.MCUP.LP1.1720 RPL10.MCUP.Loop 1 - Tie-in EPMS #3 Tie-Ins EPMS Complete 04/10/26 05/22/26 7.5 0.0
100%
0.0
RPL10.MCUP.LP1.1740 RPL10.MCUP.Loop 1 - Tie-in BMS #3 Tie-Ins BMS Complete 04/10/26 05/22/26 8.8 0.0
100%
0.0
RPL10.MCUP.LP2.1440 RPL10.MCUP.Loop 2 - Set Electrical Skids #2 OFE Complete 04/10/26 04/13/26 2.5 0.0
100%
0.0
RPL10.MCUP.LP2.1460 RPL10.MCUP.Loop 2 - Set Electrical Skids #4 OFE Complete 04/10/26 04/13/26 2.5 0.0
100%
0.0
RPL10.STR.NS43.01160 RPL10.Structure.NS43 - SOG Sealant Cure F/R/P Complete 04/10/26 04/10/26 1.2 0.0
100%
0.0
RPL10.EY.EF1.01740 RPL10.EY.EF1 - FSP2 - Install Steel Delivery & Assembly (Logistic #7 Install) Fiber Support Platform - RPL-2 Complete 04/13/26 05/04/26 12.5 0.0
100%
0.0
RPL10.EY.ENDC.01140 RPL10.EY.End - Install Mechanical Main (include penetration detail) Tie-ins Complete 04/13/26 04/27/26 18.8 0.0
100%
0.0
RPL10.EY.ENDC.01150 RPL10.EY.End - Tie-ins - WBS Summary Tie-ins Active 04/13/26 07/07/26 68.8 37.5
0%
243.8
RPL10.EY.NS2.01210 RPL10.EY.NS2 - HAC Prefab prior to install Tent and Temp Conditions Complete 04/13/26 04/17/26 7.5 0.0
100%
0.0
RPL10.EY.SSB.01160 RPL10.EY.SSB - Install Electrical Tie-ins (include penetration detail) Tie-ins Complete 04/13/26 05/22/26 25.0 0.0
100%
0.0
RPL10.INT.CTRC.07760 RPL10.Interior.Center-Corridor - BoW - Install Mechanical Piping Lowside On Hilti Steel (North) Priority Walls & OverHead Complete 04/13/26 04/20/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.6440 RPL10.Interior.End-Corridor - BoW - BoW Soffit Tape, Float and Paint Priority, Fire Safing Both Sides Balance of Walls & Overhead Complete 04/13/26 04/24/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01240 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install TW Remaining Tie-ins post Mech Side Aisle install Complete 04/13/26 05/12/26 25.0 0.0
100%
0.0
RPL10.INT.NS1.01310 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Complete 04/13/26 04/21/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01490 RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install Duct (LV Side) LV Side Tie-ins Complete 04/13/26 04/13/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01520 RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 4 SQ3.1 (including IDF) - WBS Summary Tie-Ins NS1 Control Fault Domain 4 Active 04/13/26 07/14/26 81.2 43.8
0%
35.0
RPL10.INT.NS1.01630 RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - Install Duct (LV Side) LV Side Tie-ins Complete 04/13/26 04/13/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.01660 RPL10.Interior.NS1 - Tie-ins - Control Fault Domain 3 SQ4.1 - WBS Summary Tie-Ins NS1 Control Fault Domain 3 Active 04/13/26 07/14/26 81.2 43.8
0%
56.2
RPL10.INT.NS1.02120 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install FW Remaining Tie-ins post Mech Side Aisle install Complete 04/13/26 05/12/26 25.0 0.0
100%
0.0
RPL10.INT.NS2.01230 RPL10.Interior.NS2 - OFE - Control Fault Domain 5 SQ2.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary OFE NS2 Control Fault Domain 5 Complete 04/13/26 05/15/26 40.0 0.0
100%
0.0
RPL10.INT.NS2.02505 RPL10.Interior.NS2 - OFE - Control Fault Domain 5 SQ2.2 (LV Side Aisle) Upto Row 9 OFE NS2 Control Fault Domain 5 Complete 04/13/26 04/15/26 5.0 0.0
100%
0.0
RPL10.INT.NS3.02340 RPL10.Interior.NS3 - Priority - Install Electrical (Exterior Drywall mounted Branch) OverHead Complete 04/13/26 04/17/26 6.2 0.0
100%
0.0
RPL10.INT.NS4.02340 RPL10.Interior.NS4 - Priority - Install Electrical (Exterior Drywall mounted Branch) OverHead Complete 04/13/26 04/17/26 6.2 0.0
100%
0.0
RPL10.INT.SSB.03320 RPL10.Interior.SSB - BoW - Install Fire Safing/ Seal all Penetrations (Lowside space) Balance of Walls and OverHead Complete 04/13/26 04/21/26 6.2 0.0
100%
0.0