Schedule Viewer

Last schedule upload: D3-R25005-00-RPL10 — 9281 activities — 06/03/2026 08:35 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260524.xer · Uploaded Jun 03, 2026 01:35 PM · 9281 activities
Experimental Auto-populate checklist dates from schedule:
Clear
100
Activities Shown
61
Completed
38
In Progress
62
Critical
Activity ID Activity Name WBS Status Start Finish Dur (d) Rem (d) % Comp Float (d)
RPL10.INT.ENDC.01110 RPL10.Interior.End-Corridor - BoW - Install Fire Life Safety Lowside OH and In-wall Balance of Walls & Overhead Complete 05/04/26 05/08/26 8.8 0.0
100%
0.0
RPL10.INT.NS1.01230 RPL10.Interior.NS1 - Control Fault Domain 6 SQ1.1 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Active 05/04/26 06/08/26 25.0 12.5
0%
11.2
RPL10.INT.NS1.01360 RPL10.Interior.NS1 - Control Fault Domain 5 SQ2.1 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Active 05/04/26 06/08/26 25.0 12.5
0%
37.5
RPL10.INT.NS2.01210 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install LV Side Aisle Cable Tray LV Side Tie-ins Complete 05/04/26 05/20/26 6.2 0.0
100%
0.0
RPL10.INT.NS2.01680 RPL10.Interior.NS2 - Control Fault Domain 2 SQ5.2 - Install Duct (LV Side) LV Side Tie-ins Complete 05/04/26 05/04/26 5.0 0.0
100%
0.0
RPL10.INT.NS2.01710 RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 2 SQ5.2 - WBS Summary Tie-Ins NS2 Control Fault Domain 2 Active 05/04/26 08/14/26 91.2 72.5
0%
58.8
RPL10.INT.NS2.01820 RPL10.Interior.NS2 - Control Fault Domain 1 SQ6.2 - Install Duct (LV Side) LV Side Tie-ins Complete 05/04/26 05/04/26 5.0 0.0
100%
0.0
RPL10.INT.NS2.01850 RPL10.Interior.NS2 - Tie-ins - Control Fault Domain 1 SQ6.2 - WBS Summary Tie-Ins NS2 Control Fault Domain 1 Active 05/04/26 09/04/26 105.0 91.2
0%
30.0
RPL10.INT.NS2.02525 RPL10.Interior.NS2 - OFE - Control Fault Domain 5 SQ2.2 (HAC) OFE NS2 Control Fault Domain 5 Complete 05/04/26 05/11/26 18.8 0.0
100%
0.0
RPL10.INT.NS3.01100 RPL10.Interior.NS3 - Tie-ins - WBS Summary Tie-Ins Active 05/04/26 12/22/26 201.2 182.5
0%
147.5
RPL10.INT.NS3.01112 RPL10.Interior.NS3 - MES Skids - Final Piping Tie-Ins & Inspections NS3 - MES Skids Active 05/04/26 06/24/26 30.0 27.5
0%
126.2
RPL10.INT.NS4.01060 RPL10.Interior.NS4 - OFE - LV Skids and TopHat - Set / Place / Anchor (04.22.26) (LOE) OFE Active 05/04/26 06/11/26 25.0 16.2
0%
95.0
RPL10.INT.NS4.01065 RPL10.Interior.NS4 - OFE - Electrical Panels (ATS) - Set / Anchor OFE Complete 05/04/26 05/08/26 6.2 0.0
100%
0.0
RPL10.INT.NS4.01100 RPL10.Interior.NS4 - Tie-ins - WBS Summary Tie-Ins Active 05/04/26 11/30/26 181.2 162.5
0%
155.0
RPL10.INT.NS4.01110 RPL10.Interior.NS4 - MES Skids Tie-ins (LOE) NS4 - MES Skids Active 05/04/26 07/28/26 75.0 56.2
0%
232.5
RPL10.INT.NS4.01111 RPL10.Interior.NS4 - MES Skids - Set & Anchor Interconnects NS4 - MES Skids Active 05/04/26 06/05/26 30.0 11.2
0%
130.0
RPL10.INT.NS4.01112 RPL10.Interior.NS4 - MES Skids - Final Piping Tie-Ins & Inspections NS4 - MES Skids Active 05/04/26 06/19/26 30.0 23.8
0%
130.0
RPL10.INT.NS4.03240 RPL10.Interior.NS4 - OFE - LV Skids and TopHat - Set / Place / Anchor (04.22.26) (Rev-05.04.26) (Installed First 7) OFE Complete 05/04/26 05/20/26 25.0 0.0
100%
0.0
RPL10.INT.SSBC.01252 RPL10.Interior.SSB-Corridor - BoW - Install Electrical - Lighitng Inverter Room (10.S2.07) Balance of Walls & OverHead Complete 05/04/26 05/18/26 8.8 0.0
100%
0.0
RPL10.WP2.01160 RPL10.Conn IDF Huts - (GSMDF to GSIDF) EF1 NE1 WBS Summary GSIDFNE1 Active 05/04/26 06/23/26 45.0 26.2
0%
457.5
RPL10.WP2.GSIDF.1160 RPL10.Conn GSIDFNE1 Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 05/04/26 05/08/26 6.2 0.0
100%
0.0
RPL10.WP2.GSIDF.1520 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS4 N41 WBS Summary GSIDFN41 Active 05/04/26 07/16/26 65.0 46.2
0%
811.2
RPL10.WP2.GSIDF.1540 RPL10.Conn GSIDFN41 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 05/04/26 05/08/26 6.2 0.0
100%
0.0
RPL10.WP2.GSIDF.1680 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS4 N43 WBS Summary GSIDFN43 Active 05/04/26 07/16/26 65.0 46.2
0%
208.8
RPL10.WP2.GSIDF.1700 RPL10.Conn GSIDFN43 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 05/04/26 05/08/26 6.2 0.0
100%
0.0
RPL10.WP2.GSIDF.1760 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS3 N31 WBS Summary GSIDFN31 Active 05/04/26 07/16/26 65.0 46.2
0%
811.2
RPL10.WP2.GSIDF.1780 RPL10.Conn GSIDFN31 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 05/04/26 05/08/26 6.2 0.0
100%
0.0
RPL10.WP2.GSIDF.1920 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS3 N33 WBS Summary GSIDFN33 Active 05/04/26 07/16/26 65.0 46.2
0%
208.8
RPL10.WP2.GSIDF.1940 RPL10.Conn GSIDFN33 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 05/04/26 05/08/26 6.2 0.0
100%
0.0
RPL10.WP2.GSIDF.2020 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS1 NX01 WBS Summary GSIDFNX01 Active 05/04/26 06/26/26 48.8 30.0
0%
827.5
RPL10.WP2.GSIDF.2040 RPL10.Conn GSIDFNX01 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 05/04/26 05/08/26 6.2 0.0
100%
0.0
RPL10.WP2.GSIDF.2100 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS1 NX02 WBS Summary GSIDFNX02 Active 05/04/26 06/26/26 48.8 30.0
0%
827.5
RPL10.WP2.GSIDF.2120 RPL10.Conn GSIDFNX02 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 05/04/26 05/08/26 6.2 0.0
100%
0.0
RPL10.WP2.GSIDF.2420 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS2 NX06 WBS Summary GSIDFNX06 Active 05/04/26 06/26/26 48.8 30.0
0%
827.5
RPL10.WP2.GSIDF.2440 RPL10.Conn GSIDFNX06 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 05/04/26 05/08/26 6.2 0.0
100%
0.0
RPL10.WP2.GSIDF.2500 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS2 NX07 WBS Summary GSIDFNX07 Active 05/04/26 06/26/26 48.8 30.0
0%
827.5
RPL10.WP2.GSIDF.2520 RPL10.Conn GSIDFNX07 Set Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 05/04/26 05/08/26 6.2 0.0
100%
0.0
RPL10.WP2.MDF1.1000 RPL10.Conn GSMDF1 Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Complete 05/04/26 05/06/26 3.8 0.0
100%
0.0
RPL10.WP2.MDF2.1000 RPL10.Conn GSMDF2 Set Infrastructure (Wall mounting enclosures, Tier1 Basket Tray, Waterfalls etc.) Infrastructure Complete 05/04/26 05/06/26 3.8 0.0
100%
0.0
RPL10.EY.EF1.01160 RPL10.EY.EF1 - FSP1 - Install Steel Span Structure Modules Fiber Support Platform - RPL-1 Complete 05/05/26 05/15/26 13.8 0.0
100%
0.0
RPL10.EY.EF1.01680 RPL10.EY.EF1 - FSP2 - Columns Cap Cure Fiber Support Platform - RPL-2 Complete 05/05/26 05/11/26 8.8 0.0
100%
0.0
RPL10.INT.CTRC.01170 RPL10.Interior.Center-Corridor - BoW - Install Doors Frame Balance of Walls & OverHead Complete 05/05/26 05/11/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01600 RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install LV Side Aisle HAC Busway LV Side Tie-ins Complete 05/05/26 05/18/26 5.0 0.0
100%
0.0
RPL10.INT.NS2.01370 RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Install LV Side Aisle HAC Busway LV Side Tie-ins Complete 05/05/26 05/14/26 5.0 0.0
100%
0.0
RPL10.INT.NS3.01070 RPL10.Interior.NS3 - OFE - MES Skids - Set / Place / Anchor OFE Active 05/05/26 05/28/26 25.0 3.8
0%
86.2
RPL10.INT.NS3.02020 RPL10.Interior.NS3 - OFE - Ancillary Skids - Set / Place / Anchor (04.29.26) OFE Complete 05/05/26 05/08/26 5.0 0.0
100%
0.0
RPL10.INT.SSB.02560 RPL10.Interior.SSB - BoW - ACT - Device Tiles Balance of Walls and OverHead Complete 05/05/26 05/13/26 8.8 0.0
100%
0.0
RPL10.INT.SSB.02580 RPL10.Interior.SSB - BoW - ACT - MEP Devices Balance of Walls and OverHead Complete 05/05/26 05/13/26 8.8 0.0
100%
0.0
RPL10.INT.SSBC.02920 RPL10.Interior.SSB-Corridor - BoW - Install Resinous Flooring in specific rooms Balance of Walls & OverHead Complete 05/05/26 05/11/26 6.2 0.0
100%
0.0
RPL10.INT.SSBC.03460 RPL10.Interior.Center-Corridor - BoW - Bed Tape Paint (OFE Room Closing) Balance of Walls & OverHead Complete 05/05/26 05/13/26 8.8 0.0
100%
0.0
RPL10.SSB.BB.1130 RPL10.Ext.Build Back.SSB - LO #5 - Tape Finish Paint Build Back Exterior Leave Out Wall #5 (East SSB) Complete 05/05/26 05/07/26 6.2 0.0
100%
0.0
RPL10.INT.NS3.01065 RPL10.Interior.NS3 - OFE - Electrical Panels (ATS,SB House,MCB,MLO, Transformer) - Set / Anchor OFE Complete 05/06/26 05/08/26 6.2 0.0
100%
0.0
RPL10.MCUP.LP2.1640 RPL10.MCUP.Loop 2 - Install Site Grading for Paving *Start 05/08 Hardscape and Landscape Active 05/06/26 07/20/26 18.8 48.8
0%
411.2
RPL.GF.D.G4620.XG Rack & Cabinets Complete - DHB - RPL6 Give Milestones (XREFs) Not Started 05/07/26 05/07/26 0.0 0.0
0%
455.0
RPL10.INT.NS3.01110 RPL10.Interior.NS3 - MES Skids Tie-ins (LOE) NS3 - MES Skids Active 05/07/26 07/31/26 95.0 60.0
0%
242.5
RPL10.INT.NS3.01111 RPL10.Interior.NS3 - MES Skids - Set & Anchor Interconnects NS3 - MES Skids Active 05/07/26 06/10/26 30.0 15.0
0%
126.2
RPL10.CTRC.BB.2040 RPL10.Int.Build Back.Center-Corr - LO #12 - P3 Tape, Float and Paint (Around 30"" Mech Pipe) Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) Complete 05/08/26 05/14/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.02600 RPL10.Interior.NS1 - OFE - Control Fault Domain 3 SQ4.1 (HAC) OFE NS1 Control Fault Domain 3 Complete 05/08/26 05/22/26 18.8 0.0
100%
0.0
RPL10.INT.NS2.02545 RPL10.Interior.NS2 - OFE - Control Fault Domain 5 SQ2.2 (Mech Side Aisle) OFE NS2 Control Fault Domain 5 Complete 05/08/26 05/15/26 16.2 0.0
100%
0.0
RPL10.INT.SSBC.02780 RPL10.Interior.SSB-Corridor - BoW - Duct Drops Trim out Balance of Walls & OverHead Complete 05/08/26 05/19/26 5.0 0.0
100%
0.0
RPL10.INT.SSBC.02960 RPL10.Interior.SSB-Corridor - BoW - Electrical Trim Out Balance of Walls & OverHead Active 05/08/26 05/26/26 8.8 1.2
0%
80.0
GCD.RPL10.1827 Delivery of RMU - (First Delivery) - RPL10 - NS43 Construction Milestones Complete 05/11/26 05/11/26 0.0 0.0
100%
0.0
RPL10.EY.EF1.01270 RPL10.EY.EF1 - FSP1 - Install Floor Grating Fiber Support Platform - RPL-1 Complete 05/11/26 05/22/26 12.5 0.0
100%
0.0
RPL10.EY.EF1.01350 RPL10.EY.EF1 - FSP2 - Install Roofing Z Purlin (Logistic #7 Install) Fiber Support Platform - RPL-2 Complete 05/11/26 05/22/26 12.5 0.0
100%
0.0
RPL10.EY.EF2.01890 RPL10.EY.EF2 - FSP3 - Install Columns Cap Erect Shoring & Decking & F/R/P (Center & Turner Side) Fiber Support Platform - RPL-3 Complete 05/11/26 05/14/26 3.8 0.0
100%
0.0
RPL10.EY.EF2.01910 RPL10.EY.EF2 - FSP5 - Install Columns Cap Erect Shoring & Decking & F/R/P (Center & Turner Side) Fiber Support Platform - RPL-5 Complete 05/11/26 05/14/26 3.8 0.0
100%
0.0
RPL10.EY.ENDC.01130 RPL10.EY.End - Install Electrical Tie-ins (include penetration detail) Tie-ins Active 05/11/26 06/08/26 25.0 12.5
0%
165.0
RPL10.EY.NS4.01220 RPL10.EY.NS4 - Install MV, RMUs & Electrical Panels (15) (LOE) OFE Active 05/11/26 06/25/26 25.0 28.8
0%
92.5
RPL10.EY.NS4.01230 RPL10.EY.NS4 - OFE - MV - WBS Summary OFE Active 05/11/26 06/25/26 41.2 28.8
0%
105.0
RPL10.EY.NS4.01610 RPL10.EY.NS4 - Install MV, RMUs & Electrical Panels (15) (Installed First 5) OFE Complete 05/11/26 05/18/26 25.0 0.0
100%
0.0
RPL10.INT.EF1.01650 RPL10.Interior.EF1 - North CRAH Gallery - Install Duct work OBSOLETE Obsolete Complete 05/11/26 05/12/26 6.2 0.0
100%
0.0
RPL10.INT.EF1.01670 RPL10.Interior.EF1 - North CRAH Gallery - Install Duct Drops & GRD's OBSOLETE Obsolete Complete 05/11/26 05/12/26 6.2 0.0
100%
0.0
RPL10.INT.EF1.01690 RPL10.Interior.EF1 - South CRAH Gallery - Install Duct work OBSOLETE Obsolete Complete 05/11/26 05/12/26 6.2 0.0
100%
0.0
RPL10.INT.EF1.01710 RPL10.Interior.EF1 - South CRAH Gallery - Install Duct Drops & GRD's OBSOLETE Obsolete Complete 05/11/26 05/12/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.01260 RPL10.Interior.End-Corridor - BoW - Install Cable Tray OBSOLETE Obsolete Complete 05/11/26 05/12/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.1340 RPL10.Interior.End-Corridor - BoW - Install VAV's/Duct Branches OBSOLETE Obsolete Complete 05/11/26 05/12/26 6.2 0.0
100%
0.0
RPL10.INT.NS1.01610 RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - Install LV Side Aisle Cable Tray LV Side Tie-ins Complete 05/11/26 05/20/26 5.0 0.0
100%
0.0
RPL10.INT.NS1.02560 RPL10.Interior.NS1 - OFE - Control Fault Domain 4 SQ3.1 (Mech Side Aisle) OFE NS1 Control Fault Domain 4 Complete 05/11/26 05/15/26 16.2 0.0
100%
0.0
RPL10.INT.NS2.01113 RPL10.Interior.NS2 - MES Skids - CDU Tie-Ins ( 2 per day) NS2 - MES Skids Active 05/11/26 06/12/26 30.0 17.5
0%
148.8
RPL10.INT.NS2.01140 RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - Install Vesda / FA Remaining Tie-ins post Mech Side Aisle install Active 05/11/26 06/08/26 25.0 12.5
0%
21.2
RPL10.INT.NS4.01090 RPL10.Interior.NS4 - LV Skids and TopHat Tie-ins (LOE) NS4 - LV Skids and TopHat Active 05/11/26 07/02/26 32.5 35.0
0%
147.5
RPL10.INT.NS4.01091 RPL10.Interior.NS4 - LV Skids and TopHat - Set & Anchor Interconnects NS4 - LV Skids and TopHat Active 05/11/26 06/11/26 22.5 6.2
0%
147.5
RPL10.INT.SSB.01280 RPL10.Interior.SSB - BoW - Duct Drops / Trim out Balance of Walls and OverHead Complete 05/11/26 05/19/26 8.8 0.0
100%
0.0
RPL10.INT.SSB.01300 RPL10.Interior.SSB - Loading Dock and Storage - Install Fire Life Safety / Fire Alarm OBSOLETE Obsolete Complete 05/11/26 05/12/26 8.8 0.0
100%
0.0
RPL10.INT.SSB.02460 RPL10.Interior.SSB - BoW - Install Resinous Flooring in specific rooms Balance of Walls and OverHead Complete 05/11/26 05/13/26 8.8 0.0
100%
0.0
RPL10.MCUP.LP1.2020 RPL10.MCUP.Loop 1 - Tie-in - MV Loop L2 Checklist Completion Tie-Ins Electrical Active 05/11/26 05/26/26 11.2 1.2
0%
22.5
RPL10.SSB.BB.1360 RPL10.Ext.Build Back.SSB - LO #5 - Install Frame Build Back Exterior Leave Out Wall #5 (East SSB) Complete 05/11/26 05/11/26 2.5 0.0
100%
0.0
RPL10.WP2.CMDF2.1000 RPL10.Conn CMDF2 Install Infrastructure Racks, Tier1 Infrastructure Complete 05/11/26 05/15/26 6.2 0.0
100%
0.0
RPL10.WP2.GSIDF.1300 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS1 N13 WBS Summary GSIDFN13 Active 05/11/26 07/09/26 52.5 40.0
0%
817.5
RPL10.WP2.GSIDF.1320 RPL10.Conn GSIDFN13 Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 05/11/26 05/15/26 6.2 0.0
100%
0.0
RPL10.WP2.GSIDF.1440 RPL10.Conn IDF Huts - (GSMDF to GSIDF) NS2 N23 WBS Summary GSIDFN23 Active 05/11/26 07/09/26 52.5 40.0
0%
817.5
RPL10.WP2.GSIDF.1460 RPL10.Conn GSIDFN23 Install Infrastructure (Racks, Waterfalls etc.) Infrastructure Complete 05/11/26 05/15/26 6.2 0.0
100%
0.0
RPL10.INT.CTRC.01320 RPL10.Interior.Center-Corridor - BoW - MEPF Frame Hard Lid Rough In/Close of Inspection Balance of Walls & OverHead Complete 05/12/26 05/18/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.01160 RPL10.Interior.End-Corridor - OFE - NS4 (1x GS.IDF) N43 (04.24.26) (RVCD 05.12.26) OFE Complete 05/12/26 05/19/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.01190 RPL10.Interior.End-Corridor - OFE - NS3 (1x GS.IDF) N33 (04.24.26) (RVCD 05.12.26) OFE Complete 05/12/26 05/19/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.1540 RPL10.Interior.End-Corridor - BoW - QC BoW Backing/In-Wall Balance of Walls & Overhead Complete 05/12/26 05/13/26 6.2 0.0
100%
0.0
RPL10.INT.ENDC.1560 RPL10.Interior.End-Corridor - BoW - Hang Drywall BoW Balance of Walls & Overhead Complete 05/12/26 05/22/26 10.0 0.0
100%
0.0
RPL10.INT.NS1.02660 RPL10.Interior.NS1 - OFE - Control Fault Domain 2 SQ5.1 (HAC) OFE NS1 Control Fault Domain 2 Active 05/12/26 06/02/26 18.8 7.5
0%
31.2
RPL10.INT.NS2.02585 RPL10.Interior.NS2 - OFE - Control Fault Domain 4 SQ3.2 (HAC) OFE NS2 Control Fault Domain 4 Active 05/12/26 05/29/26 18.8 5.0
0%
0.0
RPL10.INT.NS4.01092 RPL10.Interior.NS4 - LV Skids and TopHat - Maintenance and Reserve Busways NS4 - LV Skids and TopHat Active 05/12/26 06/16/26 18.8 3.8
0%
147.5