Schedule Viewer
Last schedule upload: D3-R25005-00-RPL10 — 9281 activities — 06/03/2026 08:35 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260524.xer
· Uploaded Jun 03, 2026 01:35 PM
· 9281 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
1
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.WP2.EF2.1020 |
RPL10.Conn GS.EF2 Install Cabling (Pull, Splice & Terminate) | Cabling | Not Started | 05/26/26 | 05/29/26 | 5.0 | 5.0 |
|
186.2 |
RPL10.WP2.EF2.1040 |
RPL10.Conn GS.EF2 Install Cabling for Path1 from (CAV 1/4) MMH to GS.EF (Pull, Splice & Terminate) | Cabling | Not Started | 05/26/26 | 05/29/26 | 5.0 | 5.0 |
|
156.2 |
RPL10.WP2.GSIDF.1180 |
RPL10.Conn GSIDFNE1 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/02/26 | 7.5 | 7.5 |
|
130.0 |
RPL10.WP2.GSIDF.1340 |
RPL10.Conn GSIDFN13 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
37.5 |
RPL10.WP2.GSIDF.1480 |
RPL10.Conn GSIDFN23 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
47.5 |
RPL10.WP2.GSIDF.1560 |
RPL10.Conn GSIDFN41 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/08/26 | 12.5 | 12.5 |
|
170.0 |
RPL10.WP2.GSIDF.1720 |
RPL10.Conn GSIDFN43 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/08/26 | 12.5 | 12.5 |
|
208.8 |
RPL10.WP2.GSIDF.1800 |
RPL10.Conn GSIDFN31 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/08/26 | 12.5 | 12.5 |
|
182.5 |
RPL10.WP2.GSIDF.1960 |
RPL10.Conn GSIDFN33 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/08/26 | 12.5 | 12.5 |
|
208.8 |
RPL10.WP2.GSIDF.2060 |
RPL10.Conn GSIDFNX01 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
215.0 |
RPL10.WP2.GSIDF.2140 |
RPL10.Conn GSIDFNX02 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
215.0 |
RPL10.WP2.GSIDF.2460 |
RPL10.Conn GSIDFNX06 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
215.0 |
RPL10.WP2.GSIDF.2540 |
RPL10.Conn GSIDFNX07 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/01/26 | 6.2 | 6.2 |
|
215.0 |
RPL10.WP2.GSIDF.2840 |
RPL10.Conn GSIDFNX11 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/15/26 | 18.8 | 18.8 |
|
202.5 |
RPL10.WP2.GSIDF.2920 |
RPL10.Conn GSIDFNX12 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/15/26 | 18.8 | 18.8 |
|
202.5 |
RPL10.WP2.GSIDF.2980 |
RPL10.Conn GSIDFNX13 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/26/26 | 06/02/26 | 7.5 | 7.5 |
|
213.8 |
RPL10.WP2.MDF1.1180 |
RPL10.Conn GSMDF1<>GSMDF2 - Pull, Splice, Terminate & Test | Cabling | Not Started | 05/26/26 | 05/29/26 | 5.0 | 5.0 |
|
57.5 |
RPL10.WP2.MDF1.1200 |
RPL10.Conn GSMDF1 - Install, Copper & WAPs | Cabling | Not Started | 05/26/26 | 05/29/26 | 5.0 | 5.0 |
|
57.5 |
RPL10.WP2.MDF1.1220 |
RPL10.Conn GSMDF1 - Includes Rack/ Stack/ Patch | Network | Not Started | 05/26/26 | 05/29/26 | 5.0 | 5.0 |
|
21.2 |
RPL10.WP2.MDF1.1240 |
RPL10.Conn C.MDF1 <> GS.MDF1 - Pull, Splice, Terminate & Test | Cabling | Not Started | 05/26/26 | 05/29/26 | 5.0 | 5.0 |
|
57.5 |
RPL10.WP2.MDF1.1260 |
RPL10.Conn GS.EF1 <> GS.MDF1 - Pull, Splice, Terminate & Test | Cabling | Not Started | 05/26/26 | 05/29/26 | 5.0 | 5.0 |
|
21.2 |
RPL10.WP2.MDF2.1180 |
RPL10.Conn GSMDF2 - Install, Copper & WAPs | Cabling | Not Started | 05/26/26 | 05/29/26 | 5.0 | 5.0 |
|
57.5 |
RPL10.WP2.MDF2.1220 |
RPL10.Conn GSMDF2 - Includes Rack/ Stack/ Patch | Network | Not Started | 05/26/26 | 05/29/26 | 5.0 | 5.0 |
|
21.2 |
RPL10.WP2.MDF2.1240 |
RPL10.Conn C.MDF2 <> GS.MDF2 - Pull, Splice, Terminate & Test | Cabling | Not Started | 05/26/26 | 05/29/26 | 5.0 | 5.0 |
|
57.5 |
RPL10.WP2.MDF2.1260 |
RPL10.Conn GS.EF2 <> GS.MDF2 - Pull, Splice, Terminate & Test | Cabling | Not Started | 05/26/26 | 05/29/26 | 5.0 | 5.0 |
|
21.2 |
RPL10.WP4.08400 |
RPL10.Conn 10GSMDF1 Pull/Install Fanout (MMC<>UPC) [PON] | Pre ORv3 Rack | Not Started | 05/26/26 | 05/29/26 | 5.0 | 5.0 |
|
153.8 |
GCD.RPL10.1116 |
RPL10 EY Ready for Energization | Construction Milestones | Not Started | 05/27/26 | 05/27/26 | 0.0 | 0.0 |
|
180.0 |
JCL.C.1400 |
RPL10 - Cost Risk LOE-19 Connectivity Package 3B - Front End Cabling (ISP) | Cost LOEs | Not Started | 05/27/26 | 03/05/27 | 242.5 | 242.5 |
|
80.0 |
RPL.10.D.X3810.XR |
100MW (40 MW Initial , 60 MW later) Cx Temp Power to MV Skids RPL10 NS1 Available (DPR Want 05.20.25) | Power (XREFs) | Not Started | 05/27/26 | 05/27/26 | 0.0 | 0.0 |
|
32.5 |
RPL.GF.D.N0125.XR |
4 of 4 Fiber Test Complete CAV2/3 to GS.EF2/ Prod.EF2B | Connectivity (XREFs) | Not Started | 05/27/26 | 05/27/26 | 0.0 | 0.0 |
|
151.2 |
RPL10.CFCI.5070 |
RPL10 - Submittal Rvw/App'l - Bathroom Accessories | (CFCI) Div. 10 - Specialities | Not Started | 05/27/26 | 06/09/26 | 12.5 | 12.5 |
|
132.5 |
RPL10.CFCI.5290 |
RPL10 - Fabricate / Deliver - Carpet Tile | (CFCI) Div. 09 - Carpet | Not Started | 05/27/26 | 07/13/26 | 41.2 | 41.2 |
|
157.5 |
RPL10.CFCI.5690 |
RPL10 - Fabricate / Deliver - Glass / Frames | Glass & Glazing (Alum. Entrances & Curtainwall) | Not Started | 05/27/26 | 06/16/26 | 18.8 | 18.8 |
|
432.5 |
RPL10.EY.NS1.01290 |
RPL10.EY.NS1 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
168.8 |
RPL10.EY.NS1.01320 |
RPL10.EY.NS1 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 05/27/26 | 09/17/26 | 100.0 | 100.0 |
|
382.5 |
RPL10.EY.NS2.01300 |
RPL10.EY.NS2 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
180.0 |
RPL10.EY.NS2.01310 |
RPL10.EY.NS2 - MV Loop 2 - L2 Checklist Completion | Tie-ins | Not Started | 05/27/26 | 06/09/26 | 12.5 | 12.5 |
|
61.2 |
RPL10.EY.NS2.01320 |
RPL10.EY.NS2 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 05/27/26 | 10/19/26 | 127.5 | 127.5 |
|
355.0 |
RPL10.INT.CTRC.01260 |
RPL10.Interior.Center-Corridor - BoW - Remaining Electrical OFE Tie In | Balance of Walls & OverHead | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
111.2 |
RPL10.INT.CTRC.01420 |
RPL10.Interior.Center-Corridor - BoW - Install Battery | Balance of Walls & OverHead | Not Started | 05/27/26 | 06/09/26 | 12.5 | 12.5 |
|
108.8 |
RPL10.INT.EF2.01390 |
RPL10.Interior.EF2 - CFCI - Install CFCI Prefab Cable Rack - EF2 West | OFE | Not Started | 05/27/26 | 06/16/26 | 18.8 | 18.8 |
|
20.0 |
RPL10.INT.ENDC.1460 |
RPL10.Interior.End-Corridor - BoW - Frame Hard Lid | Balance of Walls & Overhead | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
185.0 |
RPL10.INT.ENDC.1600 |
RPL10.Interior.End-Corridor - BoW - Electrical Trim Out (incl Lights) | Balance of Walls & Overhead | Not Started | 05/27/26 | 06/05/26 | 10.0 | 10.0 |
|
222.5 |
RPL10.INT.ENDC.1620 |
RPL10.Interior.End-Corridor - BoW - Security Trim Out | Balance of Walls & Overhead | Not Started | 05/27/26 | 06/05/26 | 10.0 | 10.0 |
|
222.5 |
RPL10.INT.ENDC.1900 |
RPL10.Interior.End-Corridor - BoW - F/R/P Pads | Balance of Walls & Overhead | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
185.0 |
RPL10.INT.ENDC.6200 |
RPL10.Interior.End-Corridor - BoW - Install Fire Safing/ Seal all Penetrations (Lowside space) | Balance of Walls & Overhead | Not Started | 05/27/26 | 06/01/26 | 5.0 | 5.0 |
|
220.0 |
RPL10.INT.ENDC.6460 |
RPL10.Interior.End-Corridor - BoW - Install Fire Alarm Panel | Balance of Walls & Overhead | Not Started | 05/27/26 | 05/28/26 | 2.5 | 2.5 |
|
282.5 |
RPL10.INT.NS1.01290 |
RPL10.Conn NS1.CFD6 - Set Passive Racks for WP3B | Infrastructure | Not Started | 05/27/26 | 05/29/26 | 3.8 | 3.8 |
|
37.5 |
RPL10.INT.NS1.02840 |
RPL10.Conn NS1.CFD6 - Set Passive Racks for PON | Infrastructure | Not Started | 05/27/26 | 05/29/26 | 3.8 | 3.8 |
|
158.8 |
RPL10.INT.NS4.01120 |
RPL10.Interior.NS4 - OFE - Control Fault Domain 1 SQ7.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS4 Control Fault Domain 1 | Not Started | 05/27/26 | 07/27/26 | 53.8 | 53.8 |
|
68.8 |
RPL10.INT.NS4.02480 |
RPL10.Interior.NS4 - OFE - Control Fault Domain 1 SQ7.1 (LV Side Aisle) | OFE NS4 Control Fault Domain 1 | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
103.8 |
RPL10.SSBC.BB.1000 |
RPL10.Int.Build Back.SSB-Corr - LO #2,3,4 - MEPF Trim Out | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Not Started | 05/27/26 | 06/09/26 | 12.5 | 12.5 |
|
170.0 |
RPL10.WP2.CMDF1.1010 |
RPL10.Conn CMDF1 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/27/26 | 06/01/26 | 5.0 | 5.0 |
|
152.5 |
RPL10.WP2.CMDF2.1020 |
RPL10.Conn CMDF2 Install Cabling (Pull, Splice & terminate) | Cabling | Not Started | 05/27/26 | 06/02/26 | 6.2 | 6.2 |
|
151.2 |
RPL10.WP4.08800 |
RPL10.Conn NS1.CFD6 Pull/Install Ext. Trunk (384F) [JXSW<>MA] | [MA<>JXSW] | Not Started | 05/27/26 | 06/03/26 | 7.5 | 7.5 |
|
188.8 |
RPL10.WP4.NS1.01760 |
RPL10.Conn NS1.CFD6 Infrastructure - WBS Summary | Infrastructure | Not Started | 05/27/26 | 06/09/26 | 12.5 | 12.5 |
|
71.2 |
RPL10.WP4.NS1.01780 |
RPL10.Conn NS1.CFD6 Infrastructure | Infrastructure | Not Started | 05/27/26 | 06/09/26 | 12.5 | 12.5 |
|
71.2 |
RPL10.WP4.NS1.01800 |
RPL10.Conn NS1.CFD6 Network - WBS Summary | Network | Not Started | 05/27/26 | 10/21/26 | 130.0 | 130.0 |
|
647.5 |
RPL10.INT.SSB.01380 |
RPL10.Interior.SSB - BoW - Security Trim Out | Balance of Walls and OverHead | Not Started | 05/28/26 | 06/05/26 | 8.8 | 8.8 |
|
156.2 |
RPL10.INT.SSB.01530 |
RPL10.Interior.SSB - Loading Dock and Storage - Install OverHead Doors (Mob 1) | Loading Dock and Storage | Not Started | 05/28/26 | 05/29/26 | 2.5 | 2.5 |
|
153.8 |
RPL10.INT.SSB.01840 |
RPL10.Interior.SSB - BoW - Install Split Systems/Humidifiers | Balance of Walls and OverHead | Not Started | 05/28/26 | 06/03/26 | 6.2 | 6.2 |
|
186.2 |
RPL10.INT.SSBC.03020 |
RPL10.Interior.SSB-Corridor - BoW - Plumbing Trim Out | Balance of Walls & OverHead | Not Started | 05/28/26 | 06/05/26 | 8.8 | 8.8 |
|
122.5 |
RPL10.MCUP.LP2.2040 |
RPL10.MCUP.Loop 2 - Tie-in - MV Loop L2 Checklist Completion | Tie-Ins Electrical | Not Started | 05/28/26 | 06/10/26 | 12.5 | 12.5 |
|
131.2 |
DCC.B10.3155 |
[NWB] GS Gear Delivered [NWS 4] | Connectivity | Not Started | 05/29/26 | 05/29/26 | 0.0 | 0.0 |
|
853.8 |
RPL.GF.D.N0520.XG |
Ready for Mortenson to Test CAV1 to GS.EF1 | Give Milestones (XREFs) | Not Started | 05/29/26 | 05/29/26 | 0.0 | 0.0 |
|
852.5 |
RPL.GF.D.N0530.XG |
Ready for Mortenson to Test CAV4 to EF1F | Give Milestones (XREFs) | Not Started | 05/29/26 | 05/29/26 | 0.0 | 0.0 |
|
852.5 |
RPL10.CTRC.BB.3275 |
RPL10.Int.Build Back.Center-Corr - LO #13 - P6 Frame Remaining Wall & MEP In-Wall/Backing (Around 30"" Mech Pipe) | Build Back Interior Leave Out Wall #12 #13 @ 30"" Mech Piping (Center Corr) | Not Started | 05/29/26 | 06/01/26 | 2.5 | 2.5 |
|
86.2 |
RPL10.EY.NS4.01240 |
RPL10.EY.NS4 - Install GS.IDF Hut (1x GS.IDF) NX03 (05.29.26) | OFE | Not Started | 05/29/26 | 06/04/26 | 6.2 | 6.2 |
|
123.8 |
RPL10.EY.NS4.01270 |
RPL10.EY.NS4 - Install GS.IDF Hut (1x GS.IDF) NX04 (05.29.26) | OFE | Not Started | 05/29/26 | 06/04/26 | 6.2 | 6.2 |
|
123.8 |
RPL10.EY.NS4.01590 |
RPL10.EY.NS4 - Install MV, RMUs & Electrical Panels (Delayed RVCD: 05.28 - Remaining 10) | OFE | Not Started | 05/29/26 | 06/25/26 | 25.0 | 25.0 |
|
92.5 |
RPL10.INT.EF1.01170 |
RPL10.Interior.EF1 - CFCI - Set South CRAH Units | OFE | Not Started | 05/29/26 | 06/04/26 | 6.2 | 6.2 |
|
101.2 |
RPL10.INT.EF1.01200 |
RPL10.Interior.EF1 - Tie-ins - North CRAH Gallery - WBS Summary | North CRAH Gallery | Not Started | 05/29/26 | 06/26/26 | 26.2 | 26.2 |
|
166.2 |
RPL10.INT.EF1.01610 |
RPL10.Interior.EF1 - North CRAH Gallery - Piping Tie-ins FW (In Gallery #3 CRAH Units) | North CRAH Gallery | Not Started | 05/29/26 | 06/10/26 | 11.2 | 11.2 |
|
96.2 |
RPL10.INT.EF2.01150 |
RPL10.Interior.EF2 - CFCI - Set North CRAH Units | OFE | Not Started | 05/29/26 | 06/04/26 | 6.2 | 6.2 |
|
112.5 |
RPL10.INT.NS1.01890 |
RPL10.Interior.NS1 - Control Fault Domain 2 SQ5.1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 05/29/26 | 06/03/26 | 5.0 | 5.0 |
|
83.8 |
RPL10.INT.NS1.01920 |
RPL10.Interior.NS1 - Control Fault Domain 1 SQ6.1 - Install Vesda / FA | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/29/26 | 06/25/26 | 25.0 | 25.0 |
|
67.5 |
RPL10.INT.NS1.01930 |
RPL10.Interior.NS1 - Control Fault Domain 1 SQ6.1 - Install FW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/29/26 | 06/25/26 | 25.0 | 25.0 |
|
67.5 |
RPL10.INT.NS1.01970 |
RPL10.Interior.NS1 - Control Fault Domain 1 SQ6.1 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/29/26 | 06/25/26 | 25.0 | 25.0 |
|
67.5 |
RPL10.INT.NS1.02300 |
RPL10.Interior.NS1 - Control Fault Domain 1 SQ6.1 - Install TW | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/29/26 | 06/25/26 | 25.0 | 25.0 |
|
67.5 |
RPL10.INT.NS1.02820 |
RPL10.Interior.NS1 - Control Fault Domain 1 SQ6.1 - Install Duct (MES Side) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/29/26 | 06/25/26 | 25.0 | 25.0 |
|
67.5 |
RPL10.INT.NS4.01130 |
RPL10.Interior.NS4 - Control Fault Domain 1 SQ7.1 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 05/29/26 | 06/04/26 | 6.2 | 6.2 |
|
116.2 |
RPL10.INT.NS4.01580 |
RPL10.Interior.NS4 - Tie-ins - Control Fault Domain 4 SQ10.1 - WBS Summary | Tie-Ins NS4 Control Fault Domain 4 | Not Started | 05/29/26 | 10/15/26 | 122.5 | 122.5 |
|
103.8 |
RPL10.INT.NS4.03160 |
RPL10.Interior.NS4 - Control Fault Domain 4 SQ10.1 - Install HAC Busway and Cable Tray Tie-In | Remaining Tie-ins post Mech Side Aisle install | Not Started | 05/29/26 | 06/25/26 | 25.0 | 25.0 |
|
195.0 |
RPL10.INT.NS4.03220 |
RPL10.Interior.NS4 - OFE - LV Skids and TopHat - Set / Place / Anchor (Delayed - RVCD-05.28.26) Remaining 8) | OFE | Not Started | 05/29/26 | 06/11/26 | 12.5 | 12.5 |
|
95.0 |
RPL10.MCUP.LP2.2060 |
RPL10.MCUP.Loop 2 - Tie-in - Electrical L2 Checklist Completion | Tie-Ins Electrical | Not Started | 05/29/26 | 06/11/26 | 12.5 | 12.5 |
|
131.2 |
RPL10.WP2.GSIDF.7500 |
RPL10.Conn GSMDF2 - CorpNet/FacNet Ready (Rack & Stack Active Gear Complete) | Network | Not Started | 05/29/26 | 05/29/26 | 0.0 | 0.0 |
|
46.0 |
RPL10.WP2.GSIDF.7640 |
RPL10.Conn GSMDF1 - CorpNet/FacNet Ready (Rack & Stack Active Gear Complete) | Network | Not Started | 05/29/26 | 05/29/26 | 0.0 | 0.0 |
|
46.0 |
RPL.CM.D.C5480.XR |
Leia Lane | Logistics - Onsite Receive XREF Milestones | Not Started | 06/01/26 | 06/01/26 | 0.0 | 0.0 |
|
852.5 |
RPL10.INT.EF2.01370 |
RPL10.Interior.EF2 - EF2 East - Install Upper Trays | East EF-2 | Not Started | 06/01/26 | 06/05/26 | 6.2 | 6.2 |
|
25.0 |
RPL10.INT.EF2.01400 |
RPL10.Interior.EF2 - Tie-ins - EF2 East - WBS Summary | East EF-2 | Not Started | 06/01/26 | 08/10/26 | 62.5 | 62.5 |
|
151.2 |
RPL10.INT.NS1.02010 |
RPL10.Interior.NS1 - Control Fault Domain 1 SQ6.1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 06/01/26 | 06/04/26 | 5.0 | 5.0 |
|
91.2 |
RPL10.INT.NS2.01520 |
RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 06/01/26 | 06/04/26 | 5.0 | 5.0 |
|
56.2 |
RPL10.INT.NS2.01650 |
RPL10.Interior.NS2 - Control Fault Domain 3 SQ4.2 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 06/01/26 | 06/04/26 | 5.0 | 5.0 |
|
65.0 |
RPL10.INT.NS2.02645 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 3 SQ4.2 (HAC) | OFE NS2 Control Fault Domain 3 | Not Started | 06/01/26 | 06/19/26 | 18.8 | 18.8 |
|
0.0 |
RPL10.INT.SSB.01390 |
RPL10.Interior.SSB - BoW - Plumbing Trim Out | Balance of Walls and OverHead | Not Started | 06/01/26 | 06/05/26 | 6.2 | 6.2 |
|
196.2 |
RPL10.INT.SSB.07080 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Dock Levelers, Pads, Exterior lights and Lock (Mob 2) | Loading Dock and Storage | Not Started | 06/01/26 | 06/05/26 | 6.2 | 6.2 |
|
153.8 |
RPL10.WP2.CMDF1.1100 |
RPL10.Conn CMDF1 Includes Rack/ Stack/ Patch | Network | Not Started | 06/01/26 | 06/03/26 | 3.8 | 3.8 |
|
152.5 |
RPL10.WP2.GSIDF.7520 |
RPL10.Conn GSMDF2 - CorpNet Deployment | Network | Not Started | 06/01/26 | 06/05/26 | 5.0 | 5.0 |
|
46.0 |
RPL10.WP2.GSIDF.7660 |
RPL10.Conn GSMDF1 - CorpNet Deployment | Network | Not Started | 06/01/26 | 06/05/26 | 5.0 | 5.0 |
|
46.0 |
RPL10.WP4.08420 |
RPL10.Conn 10GSMDF2 Pull/Install Fanout (MMC<>UPC) [PON] | Pre ORv3 Rack | Not Started | 06/01/26 | 06/04/26 | 5.0 | 5.0 |
|
153.8 |