Schedule Viewer
Last schedule upload: D3-R25005-00-RPL10 — 9281 activities — 06/03/2026 08:35 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260524.xer
· Uploaded Jun 03, 2026 01:35 PM
· 9281 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
0
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.EY.EF2.01630 |
RPL10.EY.EF2 - Install Remaining Electrical Tie-ins | Tie-ins | Not Started | 06/10/26 | 06/16/26 | 6.2 | 6.2 |
|
158.8 |
RPL10.EY.NS1.01340 |
RPL10.EY.NS1 - Install Lighting | Hardscape and Landscape | Not Started | 06/10/26 | 06/23/26 | 12.5 | 12.5 |
|
168.8 |
RPL10.EY.NS2.01340 |
RPL10.EY.NS2 - Install Lighting | Hardscape and Landscape | Not Started | 06/10/26 | 06/23/26 | 12.5 | 12.5 |
|
180.0 |
RPL10.INT.NS3.01060 |
RPL10.Interior.NS3 - OFE - LV Skids and TopHat - Set / Place / Anchor (04.30.26) (Rev-05.11.26) | OFE | Not Started | 06/10/26 | 07/08/26 | 25.0 | 25.0 |
|
33.8 |
RPL10.INT.NS3.01160 |
RPL10.Interior.NS3 - Tie-ins - Control Fault Domain 1 SQ7.2 - WBS Summary | Tie-Ins NS3 Control Fault Domain 1 | Not Started | 06/10/26 | 10/16/26 | 113.8 | 113.8 |
|
66.2 |
RPL10.INT.NS3.03120 |
RPL10.Interior.NS3 - Control Fault Domain 1 SQ7.2 - Install HAC Busway and Cable Tray Tie-In | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/10/26 | 07/08/26 | 25.0 | 25.0 |
|
148.8 |
RPL10.INT.NS4.01390 |
RPL10.Interior.NS4 - Control Fault Domain 2 SQ8.1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 06/10/26 | 06/15/26 | 5.0 | 5.0 |
|
140.0 |
RPL10.SSBC.BB.1180 |
RPL10.Int.Build Back.SSB-Corr - LO #2,3,4 - Final Clean | Build Back Interior Leave Out Wall #2 #3 #4 (SSB Corr) | Not Started | 06/10/26 | 06/15/26 | 5.0 | 5.0 |
|
170.0 |
RPL10.WP4.NS1.01040 |
RPL10.Conn NS1.CFD6 Infrastructure - WBS Summary | Infrastructure | Not Started | 06/10/26 | 06/15/26 | 5.0 | 5.0 |
|
71.2 |
RPL10.WP4.NS1.01060 |
RPL10.Conn NS1.CFD6 Infrastructure | Infrastructure | Not Started | 06/10/26 | 06/15/26 | 5.0 | 5.0 |
|
71.2 |
GCD.RPL10.5745 |
[RPL10] TC Ready: All General Services [RPL10-Exterior IDFs] | TC Ready: General Services | Not Started | 06/11/26 | 06/11/26 | 0.0 | 0.0 |
|
208.8 |
ICM.B10.2530 |
[NWB] L3/L4 Start EY - NS1 | Commissioning | Not Started | 06/11/26 | 06/11/26 | 0.0 | 0.0 |
|
166.2 |
RPL.GF.D.N0100.XG |
GS.EF1 Infrastructure Ready RPL10 | Give Milestones (XREFs) | Not Started | 06/11/26 | 06/11/26 | 0.0 | 0.0 |
|
841.2 |
RPL.GF.D.N0290.XR |
Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to AI2 | Connectivity (XREFs) | Not Started | 06/11/26 | 06/11/26 | 0.0 | 0.0 |
|
156.2 |
RPL.GF.D.N0610.XG |
GS.IDF Hut Install Complete (03, 04, 08, 09, 10) | Give Milestones (XREFs) | Not Started | 06/11/26 | 06/11/26 | 0.0 | 0.0 |
|
841.2 |
RPL10.CTRC.BB.3395 |
RPL10.Int.Build Back.Center-Corr - LO #6 - Install Remaining Hilti Steel | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 06/11/26 | 06/15/26 | 3.8 | 3.8 |
|
151.2 |
RPL10.CTRC.BB.3435 |
RPL10.Int.Build Back.Center-Corr - LO #8 - Frame | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 06/11/26 | 06/12/26 | 2.5 | 2.5 |
|
142.5 |
RPL10.CX.MCUP.01040 |
RPL10.CX.mCup Loop 1 - L3/L4 - mCUP - FWM | mCup Loop 1 (mCup #1,#3,#5,#7) | Not Started | 06/11/26 | 06/24/26 | 12.5 | 12.5 |
|
26.2 |
RPL10.CX.NS1.01020 |
RPL10.CX.NS1 - L3/L4 - MV Skids (8) Loop 2 | NS1 ELECTRICAL | Not Started | 06/11/26 | 06/22/26 | 10.0 | 10.0 |
|
18.8 |
RPL10.INT.CTRC.01350 |
RPL10.Interior.Center-Corridor - BoW - Final Paint | Balance of Walls & OverHead | Not Started | 06/11/26 | 06/17/26 | 6.2 | 6.2 |
|
86.2 |
RPL10.INT.EF1.01230 |
RPL10.Interior.EF1 - North CRAH Gallery - Leak Detection / Heat Trace | North CRAH Gallery | Not Started | 06/11/26 | 06/17/26 | 6.2 | 6.2 |
|
101.2 |
RPL10.INT.EF1.01470 |
RPL10.Interior.EF1 - EF1 East - Set Passive Panels / Racks | East EF-1 | Not Started | 06/11/26 | 06/17/26 | 6.2 | 6.2 |
|
175.0 |
RPL10.INT.EF1.01630 |
RPL10.Interior.EF1 - South CRAH Gallery - Piping Tie-ins FW (In Gallery #3 CRAH Units) | South CRAH Gallery | Not Started | 06/11/26 | 06/23/26 | 11.2 | 11.2 |
|
96.2 |
RPL10.INT.EF2.01240 |
RPL10.Interior.EF2 - North CRAH Gallery - Leak Detection / Heat Trace | North CRAH Gallery | Not Started | 06/11/26 | 06/17/26 | 6.2 | 6.2 |
|
118.8 |
RPL10.INT.NS2.01800 |
RPL10.Interior.NS2 - Control Fault Domain 2 SQ5.2 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 06/11/26 | 06/16/26 | 5.0 | 5.0 |
|
66.2 |
RPL10.INT.NS4.01410 |
RPL10.Interior.NS4 - Control Fault Domain 3 SQ9.1 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 06/11/26 | 06/16/26 | 5.0 | 5.0 |
|
138.8 |
RPL10.INT.NS4.01860 |
RPL10.Interior.NS4 - Tie-ins - Control Fault Domain 6 SQ12.1 - WBS Summary | Tie-Ins NS4 Control Fault Domain 6 | Not Started | 06/11/26 | 11/25/26 | 146.2 | 146.2 |
|
103.8 |
RPL10.INT.NS4.03200 |
RPL10.Interior.NS4 - Control Fault Domain 6 SQ12.1 - Install HAC Busway and Cable Tray Tie-In | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/11/26 | 07/09/26 | 25.0 | 25.0 |
|
216.2 |
RPL10.WP2.GSIDF.4040 |
RPL10.Conn GSIDFNX01 - CorpNet Live | Network | Not Started | 06/11/26 | 06/11/26 | 0.0 | 0.0 |
|
670.0 |
RPL10.WP2.GSIDF.4180 |
RPL10.Conn GSIDFNX02 - CorpNet Live | Network | Not Started | 06/11/26 | 06/11/26 | 0.0 | 0.0 |
|
670.0 |
RPL10.WP2.GSIDF.4740 |
RPL10.Conn GSIDFNX06 - CorpNet Live | Network | Not Started | 06/11/26 | 06/11/26 | 0.0 | 0.0 |
|
670.0 |
RPL10.WP2.GSIDF.4880 |
RPL10.Conn GSIDFNX07 - CorpNet Live | Network | Not Started | 06/11/26 | 06/11/26 | 0.0 | 0.0 |
|
670.0 |
GCD.RPL10.3985 |
MCUP Ready for Energization - (MCUPs Loop 2) | mCup | Not Started | 06/12/26 | 06/12/26 | 0.0 | 0.0 |
|
137.5 |
RPL10.Conn.MS.02210 |
FacNet Ready @ NS1-EY IDFs | Connectivity Milestones | Not Started | 06/12/26 | 06/12/26 | 0.0 | 0.0 |
|
207.5 |
RPL10.Conn.MS.02230 |
FacNet Ready @ NS2-EY IDFs | Connectivity Milestones | Not Started | 06/12/26 | 06/12/26 | 0.0 | 0.0 |
|
207.5 |
RPL10.INT.EF2.01110 |
RPL10.Interior.EF2 - Priority OH - Controls / EPMS / BMS | OverHead | Not Started | 06/12/26 | 06/17/26 | 5.0 | 5.0 |
|
131.2 |
RPL10.INT.EF2.01180 |
RPL10.Interior.EF2 - North CRAH Gallery - Install Upper Trays Interconnects | North CRAH Gallery | Not Started | 06/12/26 | 06/18/26 | 6.2 | 6.2 |
|
20.0 |
RPL10.INT.EF2.01220 |
RPL10.Interior.EF2 - South CRAH Gallery - Install Upper Trays Interconnects | South CRAH Gallery | Not Started | 06/12/26 | 06/18/26 | 6.2 | 6.2 |
|
20.0 |
RPL10.INT.EF2.01230 |
RPL10.Interior.EF2 - North CRAH Gallery - Install Lower Trays Interconnects | North CRAH Gallery | Not Started | 06/12/26 | 06/18/26 | 6.2 | 6.2 |
|
20.0 |
RPL10.INT.EF2.01260 |
RPL10.Interior.EF2 - Tie-ins - South CRAH Gallery - WBS Summary | South CRAH Gallery | Not Started | 06/12/26 | 06/25/26 | 12.5 | 12.5 |
|
178.8 |
RPL10.INT.EF2.01270 |
RPL10.Interior.EF2 - South CRAH Gallery - Install Lower Trays Interconnects | South CRAH Gallery | Not Started | 06/12/26 | 06/18/26 | 6.2 | 6.2 |
|
20.0 |
RPL10.INT.EF2.01480 |
RPL10.Interior.EF2 - EF2 West - Install Upper Trays | West EF-2 | Not Started | 06/12/26 | 06/18/26 | 6.2 | 6.2 |
|
20.0 |
RPL10.INT.EF2.01490 |
RPL10.Interior.EF2 - Tie-ins - EF2 West - WBS Summary | West EF-2 | Not Started | 06/12/26 | 08/24/26 | 63.8 | 63.8 |
|
145.0 |
RPL10.INT.EF2.01500 |
RPL10.Interior.EF2 - EF2 West - Install Lower Trays | West EF-2 | Not Started | 06/12/26 | 06/18/26 | 6.2 | 6.2 |
|
20.0 |
RPL10.INT.EF2.01750 |
RPL10.Interior.EF2 - South CRAH Gallery - Piping Tie-ins FW (In Gallery #3 CRAH Units) | South CRAH Gallery | Not Started | 06/12/26 | 06/24/26 | 11.2 | 11.2 |
|
112.5 |
RPL10.INT.ENDC.01320 |
RPL10.Interior.End-Corridor - BoW - Install Toilet Accessories | Balance of Walls & Overhead | Not Started | 06/12/26 | 06/22/26 | 8.8 | 8.8 |
|
202.5 |
RPL10.INT.NS1.02040 |
RPL10.Interior.NS1 - Control Fault Domain 1 SQ6.1 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/12/26 | 07/10/26 | 25.0 | 25.0 |
|
67.5 |
RPL10.INT.NS2.01580 |
RPL10.Interior.NS2 - Control Fault Domain 3 SQ4.2 - Pull BMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/12/26 | 07/10/26 | 25.0 | 25.0 |
|
35.0 |
RPL10.INT.NS2.01590 |
RPL10.Interior.NS2 - Control Fault Domain 3 SQ4.2 - Pull EPMS from panel to devices | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/12/26 | 07/10/26 | 25.0 | 25.0 |
|
35.0 |
RPL10.INT.NS2.01600 |
RPL10.Interior.NS2 - Control Fault Domain 3 SQ4.2 - Set UPS and Panel (2) | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/12/26 | 07/10/26 | 25.0 | 25.0 |
|
28.8 |
RPL10.INT.NS3.01090 |
RPL10.Interior.NS3 - LV Skids and TopHat Tie-ins (LOE) | NS3 - LV Skids and TopHat | Not Started | 06/12/26 | 07/20/26 | 32.5 | 32.5 |
|
146.2 |
RPL10.INT.NS3.01091 |
RPL10.Interior.NS3 - LV Skids and TopHat - Set & Anchor Interconnects | NS3 - LV Skids and TopHat | Not Started | 06/12/26 | 07/08/26 | 22.5 | 22.5 |
|
146.2 |
RPL10.INT.NS4.01093 |
RPL10.Interior.NS4 - LV Skids and TopHat - Top Hat Busway | NS4 - LV Skids and TopHat | Not Started | 06/12/26 | 07/02/26 | 18.8 | 18.8 |
|
147.5 |
RPL10.INT.NS4.01114 |
RPL10.Interior.NS4 - MES Skids - BMS Tie-Ins | NS4 - MES Skids | Not Started | 06/12/26 | 07/16/26 | 30.0 | 30.0 |
|
232.5 |
RPL10.WP2.GSIDF.4060 |
RPL10.Conn GSIDFNX01 - Security Deployment | Network | Not Started | 06/12/26 | 06/18/26 | 5.0 | 5.0 |
|
670.0 |
RPL10.WP2.GSIDF.4200 |
RPL10.Conn GSIDFNX02 - Security Deployment | Network | Not Started | 06/12/26 | 06/18/26 | 5.0 | 5.0 |
|
670.0 |
RPL10.WP2.GSIDF.4760 |
RPL10.Conn GSIDFNX06 - Security Deployment | Network | Not Started | 06/12/26 | 06/18/26 | 5.0 | 5.0 |
|
670.0 |
RPL10.WP2.GSIDF.4900 |
RPL10.Conn GSIDFNX07 - Security Deployment | Network | Not Started | 06/12/26 | 06/18/26 | 5.0 | 5.0 |
|
670.0 |
RPL10.WP2.GSIDF.7580 |
RPL10.Conn GSMDF2 - Security Live | Network | Not Started | 06/12/26 | 06/12/26 | 0.0 | 0.0 |
|
46.0 |
RPL10.WP2.GSIDF.7720 |
RPL10.Conn GSMDF1 - Security Live | Network | Not Started | 06/12/26 | 06/12/26 | 0.0 | 0.0 |
|
46.0 |
FR03.1280 |
FR03: PSI - NS1 - PCX H01 & H02 - FTI Quality Checks | FR03: House Power Skid Missing Panel Delay | Not Started | 06/15/26 | 06/16/26 | 2.5 | 2.5 |
|
40.0 |
FR03.1400 |
FR03: PSI - NS2 - PCX H01 & H02 - FTI Quality Checks | FR03: House Power Skid Missing Panel Delay | Not Started | 06/15/26 | 06/16/26 | 2.5 | 2.5 |
|
53.8 |
RPL.10.D.X38X1.XR |
100MW (40 MW Initial , 60 MW later) Cx Temp Power to MV Skids RPL10 mCUPs (South)Available | Power (XREFs) | Not Started | 06/15/26 | 06/15/26 | 0.0 | 0.0 |
|
130.0 |
RPL10.CTRC.BB.3455 |
RPL10.Int.Build Back.Center-Corr - LO #8 - MEPF - In Wall | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 06/15/26 | 06/17/26 | 3.8 | 3.8 |
|
142.5 |
RPL10.Conn.MS.02290 |
FacNet Ready @ MCUP IDFs | Connectivity Milestones | Not Started | 06/15/26 | 06/15/26 | 0.0 | 0.0 |
|
206.2 |
RPL10.INT.EF1.01220 |
RPL10.Interior.EF1 - North CRAH Gallery - Install Lower Trays Interconnects | North CRAH Gallery | Not Started | 06/15/26 | 06/19/26 | 6.2 | 6.2 |
|
18.8 |
RPL10.INT.EF1.01300 |
RPL10.Interior.EF1 - South CRAH Gallery - Install Lower Trays Interconnects | South CRAH Gallery | Not Started | 06/15/26 | 06/19/26 | 6.2 | 6.2 |
|
18.8 |
RPL10.INT.EF1.01500 |
RPL10.Interior.EF1 - EF1 West - Install Lower Trays | West EF-1 | Not Started | 06/15/26 | 06/19/26 | 6.2 | 6.2 |
|
18.8 |
RPL10.INT.EF1.01510 |
RPL10.Interior.EF1 - EF1 West - Install Lighting | West EF-1 | Not Started | 06/15/26 | 06/30/26 | 15.0 | 15.0 |
|
96.2 |
RPL10.INT.EF2.01430 |
RPL10.Interior.EF2 - EF2 East - Pull EPMS / BMS from panel to devices | East EF-2 | Not Started | 06/15/26 | 06/19/26 | 6.2 | 6.2 |
|
116.2 |
RPL10.INT.EF2.01440 |
RPL10.Interior.EF2 - EF2 East - Install copper from GS.IDF to BMS and EPMS panels | East EF-2 | Not Started | 06/15/26 | 06/19/26 | 6.2 | 6.2 |
|
116.2 |
RPL10.INT.EF2.01450 |
RPL10.Interior.EF2 - EF2 East - Fire Life Safety | East EF-2 | Not Started | 06/15/26 | 06/23/26 | 8.8 | 8.8 |
|
181.2 |
RPL10.INT.ENDC.01250 |
RPL10.Interior.End-Corridor - BoW - Set Equipment / Interior | Balance of Walls & Overhead | Not Started | 06/15/26 | 06/19/26 | 6.2 | 6.2 |
|
185.0 |
RPL10.INT.NS4.01490 |
RPL10.Interior.NS4 - OFE - Control Fault Domain 4 SQ10.1 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS4 Control Fault Domain 4 | Not Started | 06/15/26 | 09/08/26 | 75.0 | 75.0 |
|
93.8 |
RPL10.INT.NS4.01510 |
RPL10.Interior.NS4 - Control Fault Domain 3 SQ9.1 - Install LV Side Aisle HAC Busway | LV Side Tie-ins | Not Started | 06/15/26 | 06/18/26 | 5.0 | 5.0 |
|
170.0 |
RPL10.INT.NS4.02660 |
RPL10.Interior.NS4 - OFE - Control Fault Domain 4 SQ10.1 (LV Side Aisle) | OFE NS4 Control Fault Domain 4 | Not Started | 06/15/26 | 06/18/26 | 5.0 | 5.0 |
|
151.2 |
RPL10.MCUP.LP1.2000 |
RPL10.MCUP.Loop 1 - Install Lighting | Hardscape and Landscape | Not Started | 06/15/26 | 06/26/26 | 12.5 | 12.5 |
|
441.2 |
RPL10.MCUP.LP1.2500 |
RPL10.MCUP.Loop 1 - Install Bollards | Hardscape and Landscape | Not Started | 06/15/26 | 06/26/26 | 12.5 | 12.5 |
|
430.0 |
RPL10.WP2.GSIDF.7600 |
RPL10.Conn GSMDF2 - Network Deployment | Network | Not Started | 06/15/26 | 06/26/26 | 10.0 | 10.0 |
|
46.0 |
RPL10.WP2.GSIDF.7740 |
RPL10.Conn GSMDF1 - Network Deployment | Network | Not Started | 06/15/26 | 06/26/26 | 10.0 | 10.0 |
|
46.0 |
RPL10.CTRC.BB.3415 |
RPL10.Int.Build Back.Center-Corr - LO #6 - Install Remaining Cable Tray on Hilti Steel | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 06/16/26 | 06/18/26 | 3.8 | 3.8 |
|
151.2 |
RPL10.EY.EF1.01370 |
RPL10.EY.EF1 - FSP2 - Install Final Roof (Standing Seam Panels) Phase 1 | Fiber Support Platform - RPL-2 | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
227.5 |
RPL10.EY.EF1.01800 |
RPL10.EY.EF1 - FSP1 - Install Louvers Phase 2 | Fiber Support Platform - RPL-1 | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
240.0 |
RPL10.EY.ENDC.01170 |
RPL10.EY.End - Install Lighting | Hardscape and Landscape | Not Started | 06/16/26 | 07/07/26 | 18.8 | 18.8 |
|
408.8 |
RPL10.INT.EF2.01525 |
RPL10.Interior.EF2 - EF2 West - Install Wall Mounted Ladder Racks on Full Height EF Walls | West EF-2 | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
193.8 |
RPL10.INT.NS1.01710 |
RPL10.Interior.NS1 - Control Fault Domain 4 SQ3.1 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/16/26 | 07/14/26 | 25.0 | 25.0 |
|
35.0 |
RPL10.INT.NS1.01850 |
RPL10.Interior.NS1 - Control Fault Domain 3 SQ4.1 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/16/26 | 07/14/26 | 25.0 | 25.0 |
|
45.0 |
RPL10.INT.NS1.01990 |
RPL10.Interior.NS1 - Control Fault Domain 2 SQ5.1 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/16/26 | 07/14/26 | 25.0 | 25.0 |
|
55.0 |
RPL10.INT.NS2.01290 |
RPL10.Interior.NS2 - Control Fault Domain 6 SQ1.2 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/16/26 | 07/14/26 | 25.0 | 25.0 |
|
8.8 |
RPL10.INT.NS2.01390 |
RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - Install Copper from GS.IDF to BMS and EPMS panels | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/16/26 | 07/14/26 | 25.0 | 25.0 |
|
12.5 |
RPL10.INT.NS2.01620 |
RPL10.Interior.NS2 - Control Fault Domain 4 SQ3.2 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/16/26 | 07/14/26 | 25.0 | 25.0 |
|
28.8 |
RPL10.INT.NS3.01300 |
RPL10.Interior.NS3 - Tie-ins - Control Fault Domain 2 SQ8.2 - WBS Summary | Tie-Ins NS3 Control Fault Domain 2 | Not Started | 06/16/26 | 10/21/26 | 112.5 | 112.5 |
|
72.5 |
RPL10.INT.NS3.03140 |
RPL10.Interior.NS3 - Control Fault Domain 2 SQ8.2 - Install HAC Busway and Cable Tray Tie-In | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/16/26 | 07/14/26 | 25.0 | 25.0 |
|
153.8 |
RPL10.INT.NS4.01530 |
RPL10.Interior.NS4 - Control Fault Domain 3 SQ9.1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 06/16/26 | 06/19/26 | 5.0 | 5.0 |
|
170.0 |
RPL10.INT.SSBC.01440 |
RPL10.Interior.SSB-Corridor - BoW - Electrical L2 Checklist Completion | Balance of Walls & OverHead | Not Started | 06/16/26 | 06/29/26 | 12.5 | 12.5 |
|
102.5 |
RPL10.INT.SSBC.01470 |
RPL10.Interior.SSB-Corridor - BoW - Mechanical L2 Checklist Completion | Balance of Walls & OverHead | Not Started | 06/16/26 | 06/29/26 | 12.5 | 12.5 |
|
102.5 |
RPL10.SKN.EF12.01030 |
RPL10.SKIN.EF12 - Install Awning over Doors | Glazing, Doors and Ext Devices | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
241.2 |
RPL10.SKN.NS12.01040 |
RPL10.SKIN.NS12 - Install Louvers | Glazing, Doors and Ext Devices | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
137.5 |
RPL10.SKN.NS12.01110 |
RPL10.SKIN.NS12 - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 06/16/26 | 06/22/26 | 6.2 | 6.2 |
|
145.0 |
RPL10.SKN.SSB.01170 |
RPL10.SKIN.SSB - QC | Glazing, Doors and Ext Devices | Not Started | 06/16/26 | 06/17/26 | 2.5 | 2.5 |
|
151.2 |