Schedule Viewer
Last schedule upload: D3-R25005-00-RPL10 — 9281 activities — 06/03/2026 08:35 AM CT
RPL10 - GC LIVE SCHEDULE - Data Date 20260524.xer
· Uploaded Jun 03, 2026 01:35 PM
· 9281 activities
Experimental
Auto-populate checklist dates from schedule:
100
Activities Shown
0
Completed
0
In Progress
2
Critical
| Activity ID | Activity Name | WBS | Status | Start | Finish | Dur (d) | Rem (d) | % Comp | Float (d) |
|---|---|---|---|---|---|---|---|---|---|
RPL10.WP2.GSIDF.4100 |
RPL10.Conn GSIDFNX01 - Network Deployment | Network | Not Started | 06/19/26 | 06/25/26 | 5.0 | 5.0 |
|
670.0 |
RPL10.WP2.GSIDF.4240 |
RPL10.Conn GSIDFNX02 - Network Deployment | Network | Not Started | 06/19/26 | 06/25/26 | 5.0 | 5.0 |
|
670.0 |
RPL10.WP2.GSIDF.4800 |
RPL10.Conn GSIDFNX06 - Network Deployment | Network | Not Started | 06/19/26 | 06/25/26 | 5.0 | 5.0 |
|
670.0 |
RPL10.WP2.GSIDF.4940 |
RPL10.Conn GSIDFNX07 - Network Deployment | Network | Not Started | 06/19/26 | 06/25/26 | 5.0 | 5.0 |
|
670.0 |
RPL10.WP2.GSIDF.5420 |
RPL10.Conn GSIDFNX11 - CorpNet Deployment | Network | Not Started | 06/19/26 | 06/25/26 | 5.0 | 5.0 |
|
660.0 |
RPL10.WP4.027240 |
RPL10.Conn NS1.CFD6.48<>06-10 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/19/26 | 06/23/26 | 3.8 | 3.8 |
|
110.0 |
RPL10.WP4.NS1.01120 |
RPL10.Conn NS1.CFD6 Network Suite [JXSW<>MA] Multi Drop Cable | Pre ORv3 Rack | Not Started | 06/19/26 | 06/23/26 | 3.8 | 3.8 |
|
71.2 |
DCC.B10.3557 |
[NWB] Cabling Start : Front End Production Cabling [NWS 4] | Connectivity | Not Started | 06/22/26 | 06/22/26 | 0.0 | 0.0 |
|
833.8 |
DCC.B10.3559 |
[NWB] Cabling Start : Back End Production Cabling [NWS 4] | Connectivity | Not Started | 06/22/26 | 06/22/26 | 0.0 | 0.0 |
|
833.8 |
FR03.1320 |
FR03: PSI - NS1 - PCX H01 & H02 - 3rd Party Inspections | FR03: House Power Skid Missing Panel Delay | Not Started | 06/22/26 | 06/23/26 | 2.5 | 2.5 |
|
40.0 |
FR03.1440 |
FR03: PSI - NS2 - PCX H01 & H02 - 3rd Party Inspections | FR03: House Power Skid Missing Panel Delay | Not Started | 06/22/26 | 06/23/26 | 2.5 | 2.5 |
|
53.8 |
GCD.RPL10.3528 |
[RPL10] TC Ready: Production Cabling Pathways Complete [NS1 Rows 9-16] | TC Ready: Production Cabling - NS1 | Not Started | 06/22/26 | 06/22/26 | 0.0 | 0.0 |
|
25.0 |
RPL10.CTRC.BB.3515 |
RPL10.Int.Build Back.Center-Corr - LO #7 - Install Remaining Hilti Steel | Build Back Interior Leave Out Wall #7, #7B #9 (Center Corr) | Not Started | 06/22/26 | 06/24/26 | 3.8 | 3.8 |
|
142.5 |
RPL10.EY.EF1.01250 |
RPL10.EY.EF1 - Install Sleeves MEPL | Hardscape and Landscape | Not Started | 06/22/26 | 06/26/26 | 6.2 | 6.2 |
|
416.2 |
RPL10.EY.EF1.01260 |
RPL10.EY.EF1 - Install Hardscape and Landscape - WBS Summary | Hardscape and Landscape | Not Started | 06/22/26 | 08/11/26 | 45.0 | 45.0 |
|
415.0 |
RPL10.EY.EF2.01650 |
RPL10.EY.EF2 - Remaining L2 Checklist Completion | Tie-ins | Not Started | 06/22/26 | 06/26/26 | 6.2 | 6.2 |
|
155.0 |
RPL10.INT.EF1.01270 |
RPL10.Interior.EF1 - North CRAH Gallery - Pull EPMS / BMS from panel to devices | North CRAH Gallery | Not Started | 06/22/26 | 06/26/26 | 6.2 | 6.2 |
|
98.8 |
RPL10.INT.EF1.01280 |
RPL10.Interior.EF1 - North CRAH Gallery - Fire Life Safety | North CRAH Gallery | Not Started | 06/22/26 | 06/26/26 | 6.2 | 6.2 |
|
166.2 |
RPL10.INT.EF1.01290 |
RPL10.Interior.EF1 - North CRAH Gallery - Install copper from GS.IDF to BMS and EPMS panels | North CRAH Gallery | Not Started | 06/22/26 | 06/26/26 | 6.2 | 6.2 |
|
98.8 |
RPL10.INT.EF1.01340 |
RPL10.Interior.EF1 - South CRAH Gallery - Pull EPMS / BMS from panel to devices | South CRAH Gallery | Not Started | 06/22/26 | 06/26/26 | 6.2 | 6.2 |
|
98.8 |
RPL10.INT.EF1.01350 |
RPL10.Interior.EF1 - South CRAH Gallery - Fire Life Safety | South CRAH Gallery | Not Started | 06/22/26 | 06/26/26 | 6.2 | 6.2 |
|
166.2 |
RPL10.INT.EF1.01360 |
RPL10.Interior.EF1 - South CRAH Gallery - Install copper from GS.IDF to BMS and EPMS panels | South CRAH Gallery | Not Started | 06/22/26 | 06/26/26 | 6.2 | 6.2 |
|
98.8 |
RPL10.INT.EF1.01520 |
RPL10.Interior.EF1 - EF1 West - Pull EPMS / BMS from panel to devices | West EF-1 | Not Started | 06/22/26 | 06/26/26 | 6.2 | 6.2 |
|
98.8 |
RPL10.INT.EF1.01530 |
RPL10.Interior.EF1 - EF1 West - Install copper from GS.IDF to BMS and EPMS panels | West EF-1 | Not Started | 06/22/26 | 06/26/26 | 6.2 | 6.2 |
|
98.8 |
RPL10.INT.EF1.01540 |
RPL10.Interior.EF1 - EF1 West - Fire Life Safety | West EF-1 | Not Started | 06/22/26 | 06/30/26 | 8.8 | 8.8 |
|
163.8 |
RPL10.INT.ENDC.01290 |
RPL10.Interior.End-Corridor - BoW - Install Battery | Balance of Walls & Overhead | Not Started | 06/22/26 | 07/06/26 | 12.5 | 12.5 |
|
185.0 |
RPL10.INT.ENDC.1660 |
RPL10.Interior.End-Corridor - BoW - Final Paint | Balance of Walls & Overhead | Not Started | 06/22/26 | 07/01/26 | 10.0 | 10.0 |
|
202.5 |
RPL10.INT.NS2.02705 |
RPL10.Interior.NS2 - OFE - Control Fault Domain 2 SQ5.2 (HAC) | OFE NS2 Control Fault Domain 2 | Not Started | 06/22/26 | 07/13/26 | 18.8 | 18.8 |
|
0.0 |
RPL10.INT.NS3.01092 |
RPL10.Interior.NS3 - LV Skids and TopHat - Maintenance and Reserve Busways | NS3 - LV Skids and TopHat | Not Started | 06/22/26 | 07/13/26 | 18.8 | 18.8 |
|
146.2 |
RPL10.INT.NS3.01440 |
RPL10.Interior.NS3 - Tie-ins - Control Fault Domain 3 SQ9.2 (including IDF) - WBS Summary | Tie-Ins NS3 Control Fault Domain 3 | Not Started | 06/22/26 | 10/28/26 | 113.8 | 113.8 |
|
81.2 |
RPL10.INT.NS3.03160 |
RPL10.Interior.NS3 - Control Fault Domain 3 SQ9.2 - Install HAC Busway and Cable Tray Tie-In | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/22/26 | 07/20/26 | 25.0 | 25.0 |
|
163.8 |
RPL10.INT.NS4.01670 |
RPL10.Interior.NS4 - Control Fault Domain 4 SQ10.1 - Install LV Side Aisle Cable Tray | LV Side Tie-ins | Not Started | 06/22/26 | 06/25/26 | 5.0 | 5.0 |
|
188.8 |
RPL10.W3B.FE.011161 |
RPL10.Conn EF1B<>NS1.CFD6 (P2-3) Pull Fiber Trunk (384F) [EF<>SSW] | EF1B<>NS1.1 (P2-3) [EF<>SSW] | Not Started | 06/22/26 | 06/24/26 | 3.8 | 3.8 |
|
26.2 |
RPL10.W3B.FE.011281 |
RPL10.Conn EF2B<>NS1.CFD6 (P1-4) Pull Fiber Trunk (384F) [EF<>SSW] | EF2B<>NS1.1 (P1-4) [EF<>SSW] | Not Started | 06/22/26 | 06/24/26 | 3.8 | 3.8 |
|
18.8 |
RPL10.WP3A.EF.03000 |
RPL10.Conn EF1B Infrastructure - WBS Summary | Infrastructure & Cabling | Not Started | 06/22/26 | 08/03/26 | 37.5 | 37.5 |
|
172.5 |
RPL10.WP3A.EF.03020 |
RPL10.Conn EF1B Infrasturcture 1 (Racks & Vertical Cable Manager,Ladder Racks) | Infrastructure & Cabling | Not Started | 06/22/26 | 07/20/26 | 25.0 | 25.0 |
|
110.0 |
RPL10.WP3A.EF.04000 |
RPL10.Conn EF1B OSP Pathway - WBS Summary | Infrastructure & Cabling | Not Started | 06/22/26 | 08/03/26 | 37.5 | 37.5 |
|
172.5 |
RPL10.WP3B.FE.01020 |
RPL10.Conn NS1.CFD6 (FE) ISP Cabling - WBS Summary | FENW (Front End Network) | Not Started | 06/22/26 | 07/10/26 | 17.5 | 17.5 |
|
41.2 |
RPL10.WP3B.FE.01115 |
RPL10.Conn EF2B<>NS1.CFD6 (P1-4) Pull/Install/Test - WBS Summary | EF2B<>NS1.1 (P1-4) [EF<>SSW] | Not Started | 06/22/26 | 06/30/26 | 8.8 | 8.8 |
|
42.5 |
RPL10.WP3B.FE.01125 |
RPL10.Conn EF1B<>NS1.CFD6 (P2-3) Pull/Install/Test - WBS Summary | EF1B<>NS1.1 (P2-3) [EF<>SSW] | Not Started | 06/22/26 | 07/08/26 | 15.0 | 15.0 |
|
41.2 |
RPL10.CTRC.BB.3495 |
RPL10.Int.Build Back.Center-Corr - LO #8 - Tape, Float and Paint | Build Back Interior Leave Out Wall #6 #8 (Center Corr) | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
142.5 |
RPL10.EY.EF1.01230 |
RPL10.EY.EF1 - FSP2 - Install Grounding Wire | Fiber Support Platform - RPL-2 | Not Started | 06/23/26 | 06/24/26 | 2.5 | 2.5 |
|
243.8 |
RPL10.EY.EF1.01420 |
RPL10.EY.EF1 - FSP2 - Install Interior Hilti Support | Fiber Support Platform - RPL-2 | Not Started | 06/23/26 | 06/30/26 | 7.5 | 7.5 |
|
231.2 |
RPL10.EY.EF1.01720 |
RPL10.EY.EF1 - FSP2 - Install Final Roof (Standing Seam Panels) Phase 2 | Fiber Support Platform - RPL-2 | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
227.5 |
RPL10.EY.EF1.01820 |
RPL10.EY.EF1 - FSP1 - Install Insect Screen Phase 2 | Fiber Support Platform - RPL-1 | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
240.0 |
RPL10.EY.EF1.01840 |
RPL10.EY.EF1 - FSP2 - Install Louvers Phase 1 | Fiber Support Platform - RPL-2 | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
227.5 |
RPL10.EY.NS4.01200 |
RPL10.EY.NS4 - HAC Prefab prior to install | Tent and Temp Conditions | Not Started | 06/23/26 | 07/07/26 | 12.5 | 12.5 |
|
68.8 |
RPL10.INT.ENDC.1700 |
RPL10.Interior.End-Corridor - BoW - Plumbing Trim Out | Balance of Walls & Overhead | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
202.5 |
RPL10.INT.ENDC.1720 |
RPL10.Interior.SSB-Corridor - BoW - Fire Life Safety Trim Out / Fire Alarm Trim Out | Balance of Walls & Overhead | Not Started | 06/23/26 | 07/02/26 | 10.0 | 10.0 |
|
261.2 |
RPL10.INT.NS1.01420 |
RPL10.Conn NS1.CFD5 - Set Passive Racks for WP3B | Infrastructure | Not Started | 06/23/26 | 06/25/26 | 3.8 | 3.8 |
|
21.2 |
RPL10.INT.NS1.02860 |
RPL10.Conn NS1.CFD5 - Set Passive Racks for PON | Infrastructure | Not Started | 06/23/26 | 06/25/26 | 3.8 | 3.8 |
|
137.5 |
RPL10.INT.NS2.01480 |
RPL10.Interior.NS2 - Control Fault Domain 5 SQ2.2 - L2 Checklist Completion | Remaining Tie-ins post Mech Side Aisle install | Not Started | 06/23/26 | 07/21/26 | 25.0 | 25.0 |
|
12.5 |
RPL10.INT.NS4.01690 |
RPL10.Interior.NS4 - Control Fault Domain 5 SQ11.1 - Install Duct (LV Side) | LV Side Tie-ins | Not Started | 06/23/26 | 06/26/26 | 5.0 | 5.0 |
|
171.2 |
RPL10.INT.SSB.01430 |
RPL10.Interior.SSB - Loading Dock and Storage - Electrical Trim Out | Loading Dock and Storage | Not Started | 06/23/26 | 07/01/26 | 8.8 | 8.8 |
|
153.8 |
RPL10.INT.SSB.01460 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Lighting and Devices | Loading Dock and Storage | Not Started | 06/23/26 | 07/01/26 | 8.8 | 8.8 |
|
153.8 |
RPL10.INT.SSB.01470 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Unit Heaters | Loading Dock and Storage | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
162.5 |
RPL10.INT.SSB.01480 |
RPL10.Interior.SSB - Loading Dock and Storage - Security Trim Out | Loading Dock and Storage | Not Started | 06/23/26 | 07/01/26 | 8.8 | 8.8 |
|
153.8 |
RPL10.INT.SSB.01540 |
RPL10.Interior.SSB - Loading Dock and Storage - Fire Life Safety Trim Out / Fire Alarm Trim Out | Loading Dock and Storage | Not Started | 06/23/26 | 07/01/26 | 8.8 | 8.8 |
|
153.8 |
RPL10.INT.SSB.01780 |
RPL10.Interior.SSB - Loading Dock and Storage - Install Split Systems/Humidifiers | Loading Dock and Storage | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
162.5 |
RPL10.INT.SSB.06040 |
RPL10.Interior.SSB - Loading Dock Area - Electrical Panels | Loading Dock and Storage | Not Started | 06/23/26 | 07/01/26 | 8.8 | 8.8 |
|
153.8 |
RPL10.SKN.EF12.01040 |
RPL10.SKIN.EF12 - Install Louvers | Glazing, Doors and Ext Devices | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
247.5 |
RPL10.SKN.EF12.01110 |
RPL10.SKIN.EF12 - Install Scupper and Downspouts | Glazing, Doors and Ext Devices | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
251.2 |
RPL10.SKN.NS12.01050 |
RPL10.SKIN.NS12 - Install Lighting | Glazing, Doors and Ext Devices | Not Started | 06/23/26 | 06/26/26 | 5.0 | 5.0 |
|
137.5 |
RPL10.SKN.NS43.01030 |
RPL10.SKIN.NS43 - Install Awning over Doors | Glazing, Doors and Ext Devices | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
241.2 |
RPL10.SSB.BB.1980 |
RPL10.Ext.Build Back.SSB - LO #5 - Install Doors, Hardware | Build Back Exterior Leave Out Wall #5 (East SSB) | Not Started | 06/23/26 | 06/24/26 | 2.5 | 2.5 |
|
405.0 |
RPL10.WP2.GSIDF.2400 |
RPL10.Conn GSIDFNX05 Install & Test Network (FIM) | Network | Not Started | 06/23/26 | 06/25/26 | 3.8 | 3.8 |
|
196.2 |
RPL10.WP2.GSIDF.3360 |
RPL10.Conn GSIDFNX05 Install Copper, WAPs, Security Camera & Access Control | Cabling | Not Started | 06/23/26 | 06/25/26 | 3.8 | 3.8 |
|
455.0 |
RPL10.WP2.GSIDF.5720 |
RPL10.Conn GSIDFNX13 - CorpNet Live | Network | Not Started | 06/23/26 | 06/23/26 | 0.0 | 0.0 |
|
662.0 |
RPL10.WP4.01220 |
RPL10.Conn NS1.CFD5.09 Pull Duplex Jumper (LC<>LC) [MA<>JXSW] | Pull Duplex Jumper [MA<>JXSW] | Not Started | 06/23/26 | 06/25/26 | 3.8 | 3.8 |
|
135.0 |
RPL10.WP4.027460 |
RPL10.Conn NS1.CFD5.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
111.2 |
RPL10.WP4.027660 |
RPL10.Conn NS1.CFD4.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
111.2 |
RPL10.WP4.027860 |
RPL10.Conn NS1.CFD3.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
111.2 |
RPL10.WP4.028060 |
RPL10.Conn NS1.CFD2.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
111.2 |
RPL10.WP4.028260 |
RPL10.Conn NS1.CFD1.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
111.2 |
RPL10.WP4.028460 |
RPL10.Conn NS2.CFD6.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
122.5 |
RPL10.WP4.028660 |
RPL10.Conn NS2.CFD5.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
122.5 |
RPL10.WP4.028860 |
RPL10.Conn NS2.CFD4.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
122.5 |
RPL10.WP4.029060 |
RPL10.Conn NS2.CFD3.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
122.5 |
RPL10.WP4.029260 |
RPL10.Conn NS2.CFD2.48<>11-15 Prefab Duplex Jumper (LC<>LC) [RSW<>FSW] | Prefab | Not Started | 06/23/26 | 06/29/26 | 6.2 | 6.2 |
|
122.5 |
RPL10.WP4.NS1.02440 |
RPL10.Conn NS1.CFD5 Infrastructure - WBS Summary | Infrastructure | Not Started | 06/23/26 | 06/26/26 | 5.0 | 5.0 |
|
40.0 |
RPL10.WP4.NS1.02460 |
RPL10.Conn NS1.CFD5 Infrastructure | Infrastructure | Not Started | 06/23/26 | 06/26/26 | 5.0 | 5.0 |
|
40.0 |
FR03.1340 |
FR03: PSI - NS1 - PCX H01 & H02 - Issue Resolution | FR03: House Power Skid Missing Panel Delay | Not Started | 06/24/26 | 06/25/26 | 2.5 | 2.5 |
|
40.0 |
FR03.1460 |
FR03: PSI - NS2 - PCX H01 & H02 - Issue Resolution | FR03: House Power Skid Missing Panel Delay | Not Started | 06/24/26 | 06/25/26 | 2.5 | 2.5 |
|
53.8 |
RPL.10.D.X35X0.XR |
Substation Perm Power Cutover - RPL10 NS & mCUPs (Potential for remaining provisioning) | Power (XREFs) | Not Started | 06/24/26 | 06/24/26 | 0.0 | 0.0 |
|
301.2 |
RPL.GF.D.N0270.XR |
Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to RPL8 | Connectivity (XREFs) | Not Started | 06/24/26 | 06/24/26 | 0.0 | 0.0 |
|
202.5 |
RPL.GF.D.N0300.XR |
Fiber Pulls, Test & Term All Prod EF to EF Complete RPL 10 to AI3 | Connectivity (XREFs) | Not Started | 06/24/26 | 06/24/26 | 0.0 | 0.0 |
|
145.0 |
RPL10.CTRC.BB.3675 |
RPL10.Int.Build Back.Center-Corr - LO #9 - Hang Drywall | Build Back Interior Leave Out Wall #7, #7B #9 (Center Corr) | Not Started | 06/24/26 | 06/26/26 | 3.8 | 3.8 |
|
137.5 |
RPL10.INT.CTRC.01070 |
RPL10.Interior.Center-Corridor - BoW - Install Doors (Verify with Trades Before Installation) | Balance of Walls & OverHead | Not Started | 06/24/26 | 06/26/26 | 3.8 | 3.8 |
|
86.2 |
RPL10.INT.CTRC.01100 |
RPL10.Interior.Center-Corridor - BoW - Security Trim Out (Both Side of Corridor Wall) | Balance of Walls & OverHead | Not Started | 06/24/26 | 06/25/26 | 2.5 | 2.5 |
|
162.5 |
RPL10.INT.EF1.01310 |
RPL10.Interior.EF1 - South CRAH Gallery - Leak Detection / Heat Trace | South CRAH Gallery | Not Started | 06/24/26 | 06/30/26 | 6.2 | 6.2 |
|
96.2 |
RPL10.INT.EF2.01460 |
RPL10.Interior.EF2 - EF2 East - Set Passive Panels / Racks | East EF-2 | Not Started | 06/24/26 | 06/30/26 | 6.2 | 6.2 |
|
175.0 |
RPL10.INT.NS3.01120 |
RPL10.Interior.NS3 - OFE - Control Fault Domain 1 SQ7.2 (LV Side Aisle, HAC, Mech Side Aisle) - WBS Summary | OFE NS3 Control Fault Domain 1 | Not Started | 06/24/26 | 08/21/26 | 52.5 | 52.5 |
|
0.0 |
RPL10.INT.NS3.02500 |
RPL10.Interior.NS3 - OFE - Control Fault Domain 1 SQ7.2 (LV Side Aisle) | OFE NS3 Control Fault Domain 1 | Not Started | 06/24/26 | 06/30/26 | 6.2 | 6.2 |
|
33.8 |
RPL10.INT.NS4.01115 |
RPL10.Interior.NS4 - MES Skids - EPMS Tie-In | NS4 - MES Skids | Not Started | 06/24/26 | 07/28/26 | 30.0 | 30.0 |
|
232.5 |
RPL10.INT.SSB.02720 |
RPL10.Interior.SSB - BoW - Install Acoustic Baffle Ceiling Walls in specific rooms | Balance of Walls and OverHead | Not Started | 06/24/26 | 07/02/26 | 8.8 | 8.8 |
|
177.5 |
RPL10.INT.SSB.07140 |
RPL10.Interior.SSB - BoW - Install Bathroon Flooring and Wall Tile | Balance of Walls and OverHead | Not Started | 06/24/26 | 06/30/26 | 6.2 | 6.2 |
|
132.5 |
RPL10.WP2.GSIDF.5740 |
RPL10.Conn GSIDFNX13 - Security Deployment | Network | Not Started | 06/24/26 | 06/30/26 | 5.0 | 5.0 |
|
662.0 |
RPL10.WP2.GSIDF.6000 |
RPL10.Conn GSIDFN13 - CorpNet Live | Network | Not Started | 06/24/26 | 06/24/26 | 0.0 | 0.0 |
|
661.0 |
RPL10.WP2.GSIDF.6420 |
RPL10.Conn GSIDFN23 - CorpNet Live | Network | Not Started | 06/24/26 | 06/24/26 | 0.0 | 0.0 |
|
661.0 |
RPL10.WP2.GSIDF.6660 |
RPL10.Conn GSIDFN33 - CorpNet/FacNet Ready (Rack & Stack Active Gear Complete) | Network | Not Started | 06/24/26 | 06/24/26 | 0.0 | 0.0 |
|
168.0 |